LTC 358-2018 CIP Monthly Construction Projects UpdateMIAMIBEACH
OFFICE OF THE CITY MANAGER
NO. LTC# 358-2018
LETTER TO COMMISSION
TO: Mayor Dan Gelber and Members of the City Co ission
FROM: Jimmy L. Morales, City Manager
DATE: June 21, 2018
SUBJECT: CIP Monthly Construction Project Update
Below please find the monthly update for active City of Miami Beach construction projects under
the purview of the Office of Capital Improvement Projects.
Altos Del Mar Park
Scope: Park Improvements include new landscape, irrigation, site lighting, volleyball
courts, walkways, terraced lawn, accessible playground, restroom, and storage facility.
Status: Commission approved award to West Construction on October 18, 2017.
Construction began April 2018. Project completion anticipated October 2018.
Beach Lifeguard Towers Replacement
Scope: Construction of 35 lifeguard towers.
Status: Construction began March 2015. Twenty-two towers have been completed and
placed at their permanent location. Seven additional towers are currently under
construction. Five of the towers are scheduled to be placed at their permanent location •
late June 2018 and the remaining two in July 2018.
Beachwalk II — Phase 2
Scope: Construction of an on -grade ADA compliant pedestrian paver walkway running
from 3rd ST to 5th ST, with turtle friendly lighting, landscaping and irrigation.
Status: Construction began March 2018 and is scheduled for completion December
2018.
Biscayne Point Island Entry
Scope: Beautification project of the neighborhood entryway to Biscayne Point Island.
Status: Concrete curbs and sidewalks have been completed. Landscaping and
guardhouse renovation is ongoing. Request for additional services was approved at the
March 7 Commission Meeting. Project is 87% complete and scheduled for completion
July 2018.
Collins Park Parking Garage
Scope: The project, located at 300-340 23rd Street, consists of a six (6) level parking
garage with 513 parking spaces and approximately 15,000 SF of retail spaces at the
ground level.
Status: Project is a design build and has been awarded. Notice to Proceed #1 was
issued March 2018. Project was heard at the Historic Preservation Board on June 11,
2018 where the demolition waiver was approved and the remainder of the project was
continued to the July meeting. Project is scheduled for completion October 2019.
Central Bayshore South Neighborhood Improvements
Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to
the east, 28 St. to the south and Prairie Ave to the west and Meridian Ave from 28 St. to
Dade Blvd.
Status: Water main installation is complete. Drainage design is currently at 75%. The
Urban Land Institute Advisory Services Panel has recently completed a review of the
City's stormwater management program. The project will continue to move forward
following direction from the City Commission based on the panel's recommendations
and best practices.
Espanola Way Bollards
Scope: Installation of protective bollards at each end of Espanola Way (Washington
Avenue and Drexel Avenue).
Status: Commission approved a supplemental work order for construction on October
18, 2017. Construction began June 11, 2018. Project is scheduled for completion
September 2018.
Fleet Management Seawall
Scope: Complete replacement of approximately 200 feet of seawall, concrete slab,
staircase with railing and a small portion of fence to protect upland structures.
Status: Construction began late June 2017 as an emergency repair. Anticipated
completion date is late June 2018.
Middle Beach Recreational Corridor Ph. 2 - Section 1 (Beachwalk)
Scope: Construction of an on -grade pedestrian walkway encompassing eleven (11) City
blocks from 53 St to 64 St.
Status: Construction began July 2017. Contractor continues installation of lime rock base
and commenced paver path installation. Project is 50% complete and is scheduled for
completion October 2018.
Middle Beach Recreational Corridor Ph. 2 — Section 2 (Beachwalk)
Scope: Construction of an on -grade pedestrian walkway encompassing eight (8) City
blocks from 46 St to 53 St.
Status: Construction began March 2018. Project is scheduled for completion January
2019.
North Shore Park Tennis Center Renovation
Scope: Renovation/expansion of the North Shore Tennis Center Building. The current
building will be enclosed to create a dedicated entrance and indoor space.
Status: Construction began June 18, 2018. Project is scheduled for completion
September 2018.
Palm & Hibiscus Island Neighborhood Improvements
Scope: Neighborhood improvements on Palm and Hibiscus Islands.
Status: Construction began January 2016. Project is 87% complete and scheduled for
completion September 2018.
Stormwater Pump Station at 19th Street
Scope: Installation of a stormwater pump station, including an emergency generator and
seawall reconstruction along Collins canal.
Status: Construction of the pump station and seawall began January 2018. Project is
scheduled for completion late November 2018.
Sunset Islands 3 & 4 Neighborhood Improvements
Scope: Neighborhood improvements on Sunset Islands 3 & 4.
Status: Construction began June 2015. Project is 97% complete and scheduled for
completion July 2018.
Surface Parking Lot P2 — Nikki Beach (Penrods)
Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting,
improvements to storm water drainage, irrigation, paving and signage, and infrastructure
for future electric car charging stations.
Status: Contract for construction services was awarded to West Construction at the
December 2017 commission meeting. Construction began May 1, 2018 and is
scheduled for completion November 2018.
Venetian Islands Neighborhood Improvements
Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands.
Status: Construction began May 2013. Project is 90% complete. San Marino Island
anticipated completion July 2018; Dilido Island anticipated completion July 2018; and
Rivo Alto Island anticipated completion September 2018.
West Avenue Phase II Improvements - North of 14th Street
Scope: Neighborhood Right of Way improvements north of 14th Street to Lincoln Lane.
Status: Notice to Proceed #1 was issued July 31, 2017. Currently design is at 60%
development. The Urban Land Institute Advisory Services Panel has recently completed
a review of the City's stormwater management program. The project will continue to
move forward following direction from the City Commission based on the panel's
recommendations and best practices. Additionally, the project was selected by a
partnership between 100 Resilient Cities and Columbia University, to be included in the
Resilience Accelerator program. The Resilience Accelerator is a workshop that will focus
on strategy, design, stakeholder engagement, and costs and benefits to the project. The
workshop will be held in August, for a duration of 3 days.
West Avenue Phase II Improvements - South of 14th Street
Scope: Neighborhood Right of Way improvements south of 14th Street to 6th Street.
Status: Notice to Proceed #1 was issued July 31, 2017. Currently design is at 60%
development. The Urban Land Institute Advisory Services Panel has recently completed
a review of the City's stormwater management program. The project will continue to
move forward following direction from the City Commission based on the panel's
recommendations and best practices. Additionally, the project was selected by a
partnership between 100 Resilient Cities and Columbia University, to be included in the
Resilience Accelerator program. The Resilience Accelerator is a workshop that will focus
on strategy, design, stakeholder engagement, and costs and benefits to the project. The
workshop will be held in August, for a duration of 3 days.
JLM/EC/DM