446-2003 RDA ResoRESOLUTION NO. 446-2003
A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE
MIAMI BEACH REDEVELOPMENT AGENCY APPROPRIATING
FUNDS, IN THE AMOUNT OF $887,290, FROM SOUTH POINTE
TAX INCREMENT FUNDS, WITH RESPECT TO CONSTRUCTION
COSTS ASSOCIATED TO (A) SSDI-NORTH SEAWALL REPAIR;
(B) SSDI-NORTH EMBAYMENT FILL-IN; (C) SSDI-NORTH
SEAWALL NORTH PIER A (D) CONSTRUCTION STAGING
COSTS; AND (E) STORM SEWER RELOCATION; IN
ACCORDANCE WITH THE SETTLEMENT AGREEMENT
AMONGST THE CITY OF MIAMI BEACH, THE MIAMI BEACH
REDEVELOPMENT AGENCY, AND WEST SIDE PARTNERS
LIMITED, AND IN ACCORDANCE WITH THE PROVISIONS OF THE
GRANT OF BAYWALK EASEMENT.
WHEREAS, in November 1995, the City of Miami Beach, the Miami Beach
Redevelopment Agency and the Portoflno Group entered into a Development Agreement
that was terminated in June 1997; and
WHEREAS, in October 1998, the parties entered into a Settlement Agreement that
transferred the deed to SSDI-North (which was held in escrow) to West Side Partners,
Limited and sets forth the obligations of the parties with respect to the Development of
SSDI-North and SSDI-South parcels; and
WHEREAS, as part of the Settlement Agreement between the City of Miami Beach,
the Miami Beach Redevelopment Agency and West Side Partners, Limited, it was
contemplated that West Side Partners would develop the SSDI-North parcel in two stages;
and
WHEREAS, the developer, The Related Companies (TRG), has purchased the
property from West Side Partners, Limited and is proceeding to develop the SSDI-North
parcel; construction was initiated in September 2001; and
WHEREAS, construction on SSDI-North consists of two high rise residential towers
and related amenities, as approved and reflected in the concept plan, modified by
Resolution No. 2001-24349 adopted by the City Commission on April 18, 2001; and
WHEREAS, construction on Murano Grande, the project located along the southerly
portion of SSDI-North, was initiated in September 2001, and the Settlement Agreement
requires that only one project be completed at a time and that the first SSDI-North project
and its required parking spaces be completed prior to initiating the second project; and
WHEREAS, in connection with this construction commencement, several
construction activities must occur on the northerly portion of SSDI-North, and adjacent
properties to support the proposed Murano Grande and ICON projects; and
WHEREAS, on June 27, 2001, July 18, 2001, January 9, 2002, and July 10, 2002,
respectively, the RDA appropriated a total of approximately $6,074,910 for its various
obligations as identified in the Settlement/Lease Agreements; and
WHEREAS, the City/RDA has certain continuing financial obligations pursuant to the
Settlement Agreement for the construction activities; and
WHEREAS, the City/RDA's obligations in connection with SSDI-North consists of
SSDI-North Seawall Repair ($338,000); SSDI-North Embayment Fill-in ($240,700); SSDI-
North Pier A North 40 ($140,000); Construction Staging ($60,000); and Storm Water Utility
Relocation ($379,250); for a total of $1,157,950; and
WHEREAS, a total of $270,660.53 in savings from previous appropriations is
available for a net amount of $887,290 needed to complete construction obligations.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE CHAIRMAN AND
MEMBERS OF THE MIAMI BEACH REDEVELOPMENT AGENCY that the Chairman and
Members herein authorize the appropriation of $887,290, from the South Pointe Tax
Increment Funds a Resolution of the Chairman and Members of the Miami Beach
Redevelopment Agency appropriating funds, in the amount of $887,290, from South Pointe
Tax Increment Funds, with respect to construction costs associated to (a) SSDI-North
Seawall Repair; (b) SSDI-North Embayment fill-in; (c) SSDI-North Seawall North PierA (d)
Construction Staging Costs; and (e) Storm Sewer Relocation; in accordance with the
Settlement Agreement amongst the City of Miami Beach, the Miami Beach Redevelopment
Agency, and West Side Partners Limited, and in accordance with the provisions of the
grant of Baywalk Easement.
PASSED and ADOPTED this 19th
ATTEST:
SECRETARY
T:~AGENDA~2003~mar1903~I'da~)3-19-03 Final Version Corem Memo SSDI North.res.doc
day of March
CHAIRMAN
,2003
FORM & LANGUAG~
& FOR EXECAJI1ON
5'l:h STRF'£T '
IV.B
SSDI NORTH
III
TEMP. CURB CUT
II
ALTON ROAD STAGING AREA
(RE-AUGNMENT)
V.C
U.G. STORAGE
TANK FARM
ELECTRICAL
RELOCATION
VI.B
~A'~R MAIN
RELOCATION
VI.C
FDOT
STORM SEWER
RELOCATION
SEAWALL WORK
SSDI NORTH
VII.A
SEAWAE. WORK
SSDI SOUTH
III - TENI'OP, N~ CUmC~
IK)RiH LOT
IV -- 1EMPORAR~ P&ql(l~3 LOTS
IV.A - ALASI~N PARCEL
IV.B - SSOl NOR'nJ
IV.C -- BLOC~ 51, LO~ 5 TO g
V.A .-NEF- 1
V.B .-..NEF - 2
V.C ,-U~. STORAOE TANK FAI~
B. EC'TI~.N.
WATI~ klNN
~.C -- U~ F~LOCAIION8
FOOT 8TOI~ SE~
VII.A -- SEAWALL WOrK ~ ~OUTH
~I.B - ~EAWALL WOFK 8~DI F, oITn-I
8O
IV.C
BLOCK 51
LOTS 5
iRiAPHIC SCALE~ 1' =
CITY
GODDMAN
;,H. LUll
HINSDN
PDINTE
CITY OF
MIAMI ~EACH
SOUTH PDINTE
PARK
EXHIBIT B ~
MURAND GRANDE
DF MIAMI BEACH
CI'IY OF MIAMI BEACH
CONMISSlON ITEM SUMMARY
Condensed Title:
A Resolution appropriating funds in the amount of $887,290 from South Pointe Tax Increment Funds, with
respect to construction costs associated to (a) SSDI-North Seawall Repair; (b) SSDI-North Embayment Fill-
in; (c) SSDI-North Seawall North Pier A (d) Construction Staging Costs; and (e) Storm Sewer Relocation; in
accordance with the Settlement Agreement amongst the City of Miami Beach, the Miami Beach
Redevelopment Agency, and West Side Partners Limited and in accordance with the provisions of the grant
of Baywalk Easement.
~ssue:
Should the Chair and Board approve the appropriation requested for the additional costs/expenses
required pursuant to the settlement agreement between the City of Miami Beach, the Miami Beach
Redevelopment Acjency and West Side Partners?
Item Summary/Recommendation:
The Administration recommends appropriating $887,290 from the South Pointe Tax Increment Funds in
accordance with the Settlement Agreement amongst the City of Miami Beach, the Miami Beach
Redevelopment Agency and West Side partners, Limited and in accordance with the surviving provisions of
the 1995 Development Agreement and in accordance with the provisions of the Grant of Baywalk
Easement.
Advisory Board Recommendation:
I N/A
Financial Information:
Source of Amount Account Approved
Funds: I $887,290
2
3
4
Finance Dept. Total $887,290
City Clerk's Office Legislative Tracking:
I Christina M. Cuervo/Alexandra Rolandelli
Sign-Offs:
Department Director AssiStant CitY Manager
d. tc
T:~.GENDA~2003\rnarlO03\rda\03-19-03 Final Version Comm Memo S~DI Nodh.sum,doc
City Manager
AGENDA ITEM v~~
DATE
COMMISSION MEMORANDUM
To:
From:
Subject:
Date: March 19, 2003
Mayor David Dermer and
Members of the City Commission
Jorge M. Gonzalez ~ p~
City Manager
A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE MIAMI
BEACH REDEVELOPMENT AGENCY APPROPRIATING FUNDS IN THE
AMOUNT OF $887,290 FROM SOUTH POINTE TAX INCREMENT FUNDS,
WITH RESPECT TO CONSTRUCTION COSTS ASSOCIATED TO (A) SSDI-
NORTH SEAWALL REPAIR; (B) SSDI-NORTH EMBAYMENT FILL-IN; (C)
SSDI-NORTH SEAWALL NORTH PIER A (D) CONSTRUCTION STAGING
COSTS; AND (E) STORM SEWER RELOCATION; IN ACCORDANCE WITH
THE SETTLEMENT AGREEMENT AMONGST THE CITY OF MIAMI BEACH,
THE MIAMI BEACH REDEVELOPMENT AGENCY, AND WEST SIDE
PARTNERS LIMITED AND IN ACCORDANCE WITH THE PROVISIONS OF
THE GRANT OF BAYWALK EASEMENT.
ADMINISTRATION RECOMMENDATION
Adopt the resolution.
ANALYSIS
In November 1995, the City of Miami Beach, the Miami Beach Redevelopment Agency and
the Portofino Group entered into a Development Agreement that was terminated in June
1997. In October 1998, the parties entered into a Settlement Agreement that transferred
the deed to SSDl-North (which was held in escrow) to West Side Partners, Limited and
sets forth the obligations of the parties with respect to the Development of SSDl-North and
SSDl-South parcels.
As part of the Settlement Agreement between the City of Miami Beach, the Miami Beach
Redevelopment Agency and West Side Partners, Limited, it was contemplated that West
Side Partners would develop the SSDI-North parcel in two stages. The developer, The
Related Companies (TRG), has purchased the property from West Side Partners, Limited
and provided notice that it intended to develop the SSDI-North parcel. Construction on
said parcel was initiated in September 2001.
Construction on SSDI-North consists of two high rise residential towers and related
amenities as approved and reflected in the concept plan, modified by Resolution No.
2001-24349 adopted by the City Commission on April 18, 2001. Construction on Murano
Grande, the project located along the southerly portion of SSDI-North, was initiated in
September 2001. The Settlement Agreement requires that only one project be completed
at a time and that the first SSDI-North project and its required parking spaces be
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-North Appropriations
Page 2
completed prior to initiating the second project. In connection with this construction
commencement, several construction activities must occur on the northerly portion of
SSDI-North and adjacent properties to support the proposed Murano Grande and ICON
projects.
On June 27, 2001, July 18, 2001, on January 9, 2002, and on July 10, 2002 the RDA
appropriated approximately $6,074,910 for its various obligations as identified in the
Settlement / Lease Agreements. Exhibit ^ identifies the original cost estimated for the
City's obligation in 1995 and the costs incurred to date.
Construction Scope and Estimated Costs
Pursuant to the Settlement Agreement, TRG is to coordinate and construct the City's
construction obligations, such as, contaminated soil remediation, utility relocations, seawall
repairs / construction, Alton J~oad staging areas and temporary parking areas. TRG has
retained the services of various professionals to design, permit and construct the numerous
improvements. Detail design efforts for certain project elements are approximately 95
percent complete. In an effort to obtain budget level cost estimates for the various
improvements, TRG requested its Contractor, KVC Constructors, Inc. (KVC), to obtain bids
for certain sub-trades with specialties in certain areas of work. The estimates presented
herein include the costs and certain allowances to perform the scope of work and its
ancillary items. It is noted that permitting requirements as well as existing site conditions
may alter the character of the work to be implemented, thereby increasing / decreasing the
associated construction costs. It is anticipated that upon completion of the detail design
efforts, the following procedure will be utilized to develop final construction costs:
· Performance of a constructability review by a third party, Hazen and Sawyer
· Submittal of the plans to a minimum of three qualified contractors for each sub-trade or
project element
· The lowest, qualified bidder(s) (as determined by the City / RDA and TRG) will be
retained to perform the work
Hazen and Sawyer shall serve, as the City's coordinator with respect to the City's
obligations. TRG / KVC will provide Agreements prior to their execution for the City's
review and comment, as well as provide the actual bids obtained from each contractor(s).
Hazen and Sawyer and City staff shall review bids obtained by TRG as they relate to the
Settlement Agreement construction. Progress payment requisitions prepared by KVC to
TRG will be reviewed by Hazen and Sawyer and recommended for payments to the City /
RDA.
The estimates presented herein are for appropriation purposes only and are not intended
to be final construction cost estimates.
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-North Appropriations
Page 3
The City / RDA has certain financial obligations pursuant to the Settlement Agreement for
the construction activities. A description of each construction activity is presented herein.
The City / RDA's obligations in connection with SSDI-North are as follows:
Table 1
Appropriation Description Summary
Previous Total City / RDA City / RDA
Work Item Description Appropriation Estimated Obligation Cost
Costs
SSDI-North Seawall Repair Yes
SSDI-North Embayment Fill-in No
SSDI-North Pier A North 40 No
Construction Staging Costs No
Storm Water Utility Relocation Yes
Totals
$338,000 100% $338,000
$240,700 100% $240,700
$140,000 100% $140,000
$180,000 33% $60,000
$379,250 100% $379,250
$1,277,950 $1,157,950
(A) SSDI-North Seawall Repair
As part of the Settlement Agreement, the parties entered into a Grant of Baywalk
Easement that grants the City a permanent and irrevocable non-exclusive easement along
the Baywalk. The City is obligated, at its sole cost and expense, to restore, maintain,
repair and, as required, replace the bulkheads and seawall, in a first class condition.
Approximately 790 linear feet of deteriorated seawall exists along the SSDI-North property.
The deteriorated seawall from just north of the existing Pier E to Pier A must be repaired /
rehabilitated per the Settlement Agreement. TRG prepared three (3) alternative designs
for the repair of the seawall. More than one seawall repair section will be utilized in the
performance of the work to add ress field requirements. During the previous summer 2002,
the implemented alternative comprised a retaining wall anchored to the root of the existing
steel sheet pile wall system. Preliminary budget estimates for the previously implemented
seawall repair section have been obtained for the future summer 2003 seawall work. The
seawall subcontractor has recently provided revised budget estimates for the
implementation of new sheet piling and has determined that the cost to implement the new
steel sheet piling is more cost effective than the implemented repair section. Therefore, It
is anticipated that new steel sheet piling will be installed along the remaining work limits
during summer 2003 and this work can be performed almost entirely from an upland
location thereby reducing costs.
At the request of the Marina operator, the City and TRG entered into a Second
Supplemental agreement to construct the SSDI - North seawall repairs. This Agreement
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-North Appropriations
Page 4
identifies a timeframe during the summer of calendar years 2002, 2003 and 2004 to
perform the seawall construction work. One of the conditions required by the City and
accepted by TRG and the Marina operator, was the waiver of all previous and future claims
against the City. The seawall repair schedule was divided into two phases to correlate with
the Second Supplemental Agreement. Phase I consisted of the work between Piers A and
B, Piers D to E and the installation of new steel sheeting along the face of the two
embayments between Piers B and C. This Phase I work was completed during the period
of August to October 2002. Phase II work will consist of the repairs between Piers D and B
and will be completed during the period of August to October 2003. Should any of this
work not be completed during this period, the remaining work will have to be completed
during the summer 2004. It is important to note that the permits for this work are required
from the United States Army Corps of Engineers, State of Florida Department of
Environmental Protection and the Miami-Dade Department of Environmental Resources
Management. The following is the status of the permit applications:
Table 2
SSDI - North Seawall Repair Permitting Status
Permit Application Permit Issuance
Permitting Entity Submittal Date Date
United States Army Corps of Engineers
State of Florida Department of Environmental
Protection
Miami-Dade Department of Environmental
Resources Management
June 22,2001
June 22,2001
June 22,2001
July 9, 2001
November 19, 2001
April 30, 2002
On July 18, 2001, the City / RDA appropriated budgetary funds for portions of this work.
Since the appropriation of July 18, 2001, additional requirements have been identified that
were not previously identified in the budget presented to the City / RDA. They are as
follows:
During the permitting effort, the Miami-Dade Department of Environmental Resources
(M-DDERM) identified the requirement to perform a coral survey. Corals were identified
to be present along the existing seawall and required that a coral relocation plan be
submitted. Once approved, the corals were relocated and quarterly monitoring reports
were required to monitor the sustainability of the relocated corals. This requirement
has been addressed in subsequent planning efforts. The costs are estimated at
approximately $34,500.
The permitting fee allowance for the M-DDERM and the City of Miami Beach Building
Department was underestimated. The required permit fee allowance must be
increased by an additional $49,500.
· During the prosecution of the seawall work along SSDI - South, holes were discovered
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-North Appropriations
Page 5
along the face of the sheet piling below the proposed concrete cap section. The design
modifications implemented along the SSDI - South were incorporated into the proposed
repair section for the SSDI - North sections to accommodate the anticipated conditions
of the sheeting. This work requires the placement of shallow steel sheeting on the
landward side of the seawall to form and pour the area behind the existing seawall to
encapsulate the anticipated holes in the existing steel sheets below the bottom of the
proposed repair section. This repair was previously performed along the SSDI-South
seawall and was utilized along SSDI-North, Piers A to B and D to E. This work was
implemented during summer 2002. Additional costs associated with the revised design
section represent an additional $254,000.
The total additional appropriation for this work approximates $338,000. The limits of the
seawall repair are identified in Exhibit B, Area VII. A.
(B) SSDI-North Embayment Fill-In
The Settlement Agreement required the parties to enter into a Grant of Baywalk Easement
that grants the City a permanent and irrevocable non-exclusive easement along the
Baywalk. The City is obligated, at its sole cost and expense, to restore, maintain, repair
and, as required, replace the bulkheads and seawall, in a first class condition. The existing
seawall within the SSDI-North area consists of two embayment areas that must be
backfilled to allow for the construction of the Baywalk (located between Piers B and C).
Construction activities include the installation of approximately 60 linear feet of new steel
sheet piles in conjunction with a tie rod / dead man system to structurally support the sheet
piles along the front of the embayments. Construction activities also include the
implementation of the recommended seawall repair section along approximately 103 linear
feet of deteriorated seawall to complete the repairs to the seawall north of Pier E and
backfilling of the existing embayment area to support future Baywalk construction by
others. The responsibility to construct the Baywalk in this vicinity lies with the developer,
TRG. The City has the ongoing obligation to maintain and restore the Baywalk. The City/
RDA has separately entered into a Baywalk maintenance and operating agreement as a
result of the City's Fourth Amendment to the Marina lease agreement with the Marina
Lessee.
Permitting activities have been summarized in the previous Table 2. This work was
partially completed during the August to October 2002 timeframe. The balance of the work
will be completed during the period of August through October 2003. Total expenditures
associated with this item are approximated at $240,700 and its location is identified in
Exhibit B, Area VII. A.
(C) SSDI-North Seawall North of Pier A
The Grant of Baywalk Easement granted the City a permanent and irrevocable non-
exclusive easement along the Baywalk. The City is obligated, at its sole cost and expense,
to restore, maintain, repair and, as required, replace the bulkheads and seawall, in a first
class condition. Approximately 125 linear feet of the seawall north of Pier A must be
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-NorIh Appropriations
Page 6
rehabilitated. This represents the northern boundary of the SSDI North property. This
portion of the work was not previously appropriated in fiscal years 2000 / 2001. This work
requires that the tenants of the Junior's Building be relocated to the first floor office space
located in the Murano Grande. This is anticipated to occur during the March / April 2003
timeframe to coincide with the temporary certificate of occupancy (TCO) for the Murano
Grande garage / south tower. Upon obtaining the TCO, TRG will temporarily relocate the
Junior's Building tenants to the office space located in the Murano Grande garage / south
tower. This will allow TRG to remove the Junior's Building structure, thereby providing
access to the seawall north of Pier A. The Baywalk will be constructed by TRG prior to
ICON project completion. Work will be performed during the period of March through
August 2003. Permitting status is as referenced in the previous table 2.
The limits of the SSDI-North seawall north of Pier A are identified in Exhibit B, Area VII. A.
Costs are anticipated to approximate $140,000.
(D) Construction Sta.qinR Costs
A Staging Area License Agreement was approved and entered into on May 24, 1999 as
part of the Settlement Agreement between the City of Miami Beach, the Miami Beach
Redevelopment Agency and West Side Partners, LTD. The Staging Area License
Agreement requires the City to grant West Side Partners a license to close off the
contiguous sidewalk and the westernmost lane of Alton Road to support construction
activities. The limits of the Staging Area License include that area contiguous to the SSDI-
North construction parcel as illustrated in Exhibit B Area II. The construction staging area
may consist of the following:
· Closure of the westernmost lane of Alton Road
· Closure of the sidewalk along the west Alton Road right-of-way
· Removal of the existing median along the centerline of Alton Road
· Roadway base construction and pavement to provide for two lanes of traffic in each
direction
· Temporary street lighting
The construction staging area will extend to the south limits of the Fifth Street right-of-way
and will be utilized by KVC and its subcontractors to stage, store and construct the
improvements required within the northerly portion of SSDl-North. The City is to bear one-
third of the costs associated with the construction of these temporary improvements. West
Side Partners and the Marina Lessee will pay the remaining two-thirds of the costs.
The estimated budget to realign Alton Road to accommodate the Murano Grande Phase 2
and 3 construction staging areas is approximately $180,000, of which the City / RDA is
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-Notth Approprfations
Page 7
responsible for one-third, or $60,000. The City is also obligated to share in the costs
associated with the restoration of Alton Road to comply with the South Pointe Streetscape
Master Plan design section. The City's obligation is one-third of the costs. The City's
obligation to restore Alton Road to comply with the South Pointe Streetscape Master Plan
will be provided and appropriated at a future date.
(E) Storm Sewer Relocation
As part of the Settlement Agreement, the parties entered into a Grant of Baywalk
Easement that grants the City a permanent and irrevocable non-exclusive easement along
the Baywalk. The Grant of Baywalk Easement also obligates the City / RDA to fund the
costs and expenses associated with the physical relocation of the utilities within the SSDI-
North property. This project component consists of the relocation of the existing FDOT
Storm Drainage 54" diameter pipe. This pipe provides for the disposal of collected storm
water runoff from the Fifth Street right-of-way and a portion of the Alton Road right-of-way
between Fifth and Third Streets. This pipe is located underneath the proposed ICON
property and must be relocated around the proposed structure footprint so that the pipe
may be maintained by the FDOT and to allow for the construction of the ICON project.
The South Pointe Streetscape Master Plan identified the need for a future 24-inch diameter
outfall during the implementation of Phase 5. The location of the outfall was not identified
and it was determined that due to the development of the SSDI-South and North
properties, the identification of a corridor for a future outfall would become very difficult, if
not impossible, in the future. Therefore, it was determined that additional engineering
analyses was required to identify the additional volume of storm water runoff to be
disposed of via the proposed outfall. The evaluation determined thatthe proposed 72-inch
diameter outfall had sufficient hydraulic capacity to accommodate a portion of the South
Pointe Phase 5 drainage element. Due to the additional relocated outfall length and
additional proposed flow volumes, the pipe diameter must be increased from its existing
size to a 72-inch diameter pipe to overcome the additional frictional / minor losses
associated with the new alignment. The work consists of furnishing and installing
approximately 365 linear feet of 72" diameter pipe. The installation will require alignment
changes and will be facilitated with the construction of three (3) below grade structures at
the alignment changes. Construction of the new pipe will require that the existing 54-inch
diameter pipe be maintained in service so that the Fifth Street and Alton Road drainage
systems continue with their intended service.
Site conditions are complicated due to the presence of the high water table, elevated levels
of contamination and the proximity of existing utilities to the proposed alignment. The
elevated levels of Arsenic in the groundwater pose a concern to the project team since any
waters removed during the excavation effort cannot be discharged directly to Biscayne Bay
without being treated. Various options were considered such as treating the dewatering
effluent prior to its discharge to Biscayne Bay, discharging the dewatering effluent via
recharge galleries on - site, discharge to the sanitary sewer system or to install the pipe
and its appurtenances with industrial divers. The contract documents were structured to
require installation with no trench dewatering, therefore the 72-inch diameter pipe will be
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-Not~h Appropriations
Page 8
installed in a wet trench.
This project component was previously appropriated based upon budgetary estimates
prepared by TRG / KVC. Ten contractors were requested to provide budgetary estimates
for the City's consideration. Of the ten contractors contacted, four proposals were provided
to TRG / KVC. A review of the proposals and a more thorough understanding of the
project have resulted in a net increase of $379,250 (project scope modifications have also
resulted in price decreases and the net increase reflects the additional costs required to
complete this project) and are itemized below:
Additional professional services were required since the original budget appropriation
did not include professional services for the design, permitting and construction
management services. Services to address drawing revisions to accommodate
underground utility relocations, staging area requirements, hydraulic analyses to
accommodate future South Pointe drainage and construction administration services
are required. Additional professional services for this effort approximate $73,500.
During the detail design phase, additional underground utility verification services
were authorized to identify the location and depth of certain utilities. This investigative
effort verified the location and depth of the City's two (2) 20-inch diameter water
mains parallel to the Fifth Street corridor and adjacent to the project area. The
additional cost associated with the utility verification effort approximated $2,300.
On March 15, 2002, TRG received an engineering report from its consultant entitled
Evaluation of Arsenic Concentrations in Soil, Murano Phases 2 and 3, prepared by
Universal Engineering Sciences. This report identified the presence of elevated
levels of arsenic at the project site. It is estimated that approximately 1,200 cubic
yards of contaminated soils would have to be characterized, stockpiled, loaded,
transported and disposed of at a landfill. The costs associated with this item
approximate $117,000 (approx. 1,560 tons) and do not include any efforts to
remediate the environmental conditionsof the site.
· Soil characterization and analyses of the excavated soils will be required during
construction to characterize the level of contamination in an effort to determine
whether the material can be disposed of at a landfill or is suitable for use as backfill at
an off-site location. Soil characterization and analyses expenses approximate
$7,100.
· An increase in the allowance for permit fees is requested in the amount of $14,200.
This line item is an allowance to be authorized at a later date.
During the detail design effort, it was determined that underground
telecommunications equipment owned by BellSouth and MCI were located in the
alignment of the proposed 72-inch diameter pipe relocation corridor. Construction of
the 72-inch diameter pipe will require that BellSouth and MCI facilities be relocated to
accommodate the proposed construction. BellSouth facilities are active fiber optic
March 19, 2003
Miami Beach Redevelopment Agency
SSDI-North Appropriations
Page 9
lines and have to be relocated prior to the installation of the 72-inch diameter pipe
work being performed. This work was valued at $44,400 and was performed by
BellSouth directly.
MCI's facilities also require relocation, although MCI's facilities are not in service and
consist of an empty manhole and conduit. At the completion of the 72-inch diameter
pipe installation, MCI's facilities will be relocated and made available for service as
previously intended. The value of MCI relocation work is estimated at $50,000.
New seawall Repair and outfall section is required since the existing outfall section
cannot be utilized. Additional costs associated with this item are $102,000.
The limits of the storm water relocation are identified in Exhibit B, Area VI. C.
SUMMARY
In summary, an appropriation is requested for the additional costs / expenses identified
during the course of the work, as follows:
Table 3
Summary of Appropriation Request
Item Description Appropriation Amount
Items to be Appropriated
SSDI-North Seawall Repair
SSDI-North Embayment Fill-in
SSDI-North Pier A North 40
Construction Staging Costs
Storm Water Utility Relocation
Sub-total Appropriation Request
$338,000
$240,7OO
$140,000
$60,000
$379,250
$1,15~950
Savings from Previous Appropriations
Replacement Parking on Portofino Parcels
SSDI North Electrical Utility Relocation
Environmental Indemnity - Sheet Pile Cut Off Wall
Environmental Indemnity - Appropriation of 100%
of the cost when City/RDA's obligation was only
50%
Total Savings from Previous Appropriations
($10,983.03)
($21,852.50)
($66,129.00)
($171,696.00)
($270, 660. 53)
Total Appropriation Requested $887,290
March 19, 2003
Miami Beach Redevelopment Agency
$$DI-Nor~h Approp#ations
Page 10
RECOMMENDATIONS
The Administration recommends appropriating $887,290 from the South Pointe Tax
Increment Funds in accordance with the Settlement Agreement amongst the City of Miami
Beach, the Miami Beach Redevelopment Agency and West Side partners, Limited and in
accordance with the surviving provisions of the 1995 Development Agreement and in
accordance with the provisions of the Grant of Baywalk Easement.
JMG/~/AR
T:~AGENDA~003~ar 1903¥da\03-19-03 Final Version Corem Memo SSDI North.doc