Loading...
2003-25162 Reso RESOLUTION NO. 2003-25162 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROPRIATING FUNDING, IN THE AMOUNT OF $200,000, FROM MID-BEACH QUALITY OF LIFE FUNDS, TO THE SCOTT RAKOW YOUTH CENTER PROJECT, FOR ADDITIONAL CHANGE ORDERS NECESSARY TO COMPLETE THE PROJECT AND FOR A CONTINGENCY FOR PHASE II OF THE PROJECT. WHEREAS, on June 19, 1996, the Mayor and City Commission approved the Master Plan for the improvements to the City's Parks and Recreation facilities of which the Scott Rakow Youth Center (Project) was a component, and an Agreement with the firm of Carr Smith Corradino (Corradino) was executed on July 16th, 1996 for design, bidding and construction administration for the Project; and WHEREAS, bids for the Project were received on October 13, 2000, with seven responsive, responsible bidders and on January 31, 2001, the Administration recommended the firm of International Builders Latin America, Inc. (IBLA) as the best and lowest bidder and requested award of a contract to IBLA, in the amount of $2,893,000, which included $47,300 in additive alternates and $258,700 for contingency; and WHEREAS, Notice to Proceed was given to IBLA on April 9, 2001, and construction began on April 24, 2001; and WHEREAS, a contingency allowance was included as part of the Construction Agreement (Agreement) executed with IBLA and IBLA argued that this amount was to be used by IBLA at its discretion; and WHEREAS, the City argued that the contingency allowance was to be used by the City at its discretion for additional scope of work or to account for unforeseen conditions; and WHEREAS, the dispute exacerbated the cash flow problems faced by IBLA and led to negotiations between both parties because the language in the Agreement was not definitive on the use of the contingency and, in addition, the Agreement showed the amount of the contingency as part of the lump sum bid amount; and WHEREAS, the negotiations were not successful in defining the use of the contingency between the two parties without reducing the original scope of Phase II of the Project, and therefore, the City had established the use of the contingency with IBLA as part of the Agreement and identified additional change orders needed to complete the Project for which new funding would be needed; and WHEREAS, because the contingency was not available to the City to be used for unforeseen conditions or changes to the scope, additional funding was required to pay for identified change orders; and WHEREAS, On September 11, 2002, the City Commission appropriated $250,000 for change orders that required funding; and WHEREAS, additional change orders are now necessary to complete the Project as designed, in the amount of approximately $77,500, beyond the $250,000 previously anticipated, for work already performed by IBLA; and WHEREAS, there are additional proposed change orders, in the amount of $22,300, which are currently under review and for which a final cost has not been established; and WHEREAS, the total expected change orders amount is $99,881 and an additional contingency of approximately $100,000 is required for Phase II of the Project. NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION OF THECITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission appropriate funds, in the amount of $200,000, from Mid-Beach Quality of Life Funds, for the Scott Rakow Youth Center Project, for additional change orders necessary to complete the Project and for a contingency for Phase II of the Project. PASSED and ADOPTED this ATTEST: ~ CITY CLERK T:\AGENDA\2003\apr0903\regularlScottRakowAppropriationReso.doc APPROVED AS TO FORM & LANGUAGE .. fOR EXECUTION ft<- y)s.'-/oJ u. CITY OF MIAMI BEACH COMMISSION ITEM SUMMARY ~ Condensed Title: A resolution appropriating funding, in the amount of $200,000 for the Project, for additional change orders necessary to complete the Project. Scott Rakow Youth Center Issue: Shall the City Commission authorize appropriation of additional funding in order to complete the Project as was originally intended and pay for additional change orders required during construction? Item Summary/Recommendation: A Notice to Proceed was given to International Builders Latin America, Inc. (IBLA) on April 9, 2001 and construction began on April 24, 2001. On September 11,2002, the City Commission approved a resolution appropriating funds in the amount of $250,000 for additional change orders which required funding such as sanitary pipe re-routing, electrical relocations, new electrical installations related to existing conditions, additional fire alarm devices, water main repairs, modifications to the HV AC system, code related changes and additional painting of existing spaces. To date, change orders in the amount of $206,000 have been executed with IBLA for Phase I of the project. Additionally, other costs not previously budgeted have been approved. Some of these have included geotechnical testing, threshold inspections, and FPL and Bell South charges. Proposed change orders in the amount of approximately $77,500 have been negotiated for such items as louver & ductwork relocation at existing mechanical room; additional electrical relocations due to the phasing of the project; additional emergency exit lights, strobes and panic devices requested by the Fire Department; modification of new sanitary sewer line due to existing elevation conflicts; new wall rail at entrance due to ADA; and other miscellaneous items. Other proposed change orders, in the approximate amount of $22,300, are still being reviewed. Total expected change orders amount is $99,881. The requested amount of $200,000 includes a contingency of approximately $100,000 in case any additional unforeseen conditions occur during the renovation of the existing building in Phase II. At this time, the Administration recommends that the additional funding be approved in order to complete the Project expeditiouslv. Advisory Board Recommendation: I N/A Financiallnfonnation: Approved City Clerk's Office Legislative TraCking: I Jorge E. Chartrand n-Offs: D partment Director City Manager T:\AGENDA\2003\apr0903\regular\Scott Rakow Appropriation Cover.doc AGENDA ITEM DATE c7B r- ~-O3 CITY OF MIAMI BEACH CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139 www.miamibeachfl.gov COMMISSION MEMORANDUM From: Mayor David Dermer and Members of the City Commission Jorge M. Gonzale~. r------.r- City Manager ~v-' - rJ A RESOLUTIO OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROPRIATING FUNDING IN THE AMOUNT OF $200,000, FROM THE MID-BEACH QUALITY OF LIFE FUNDS, TO THE SCOTT RAKOW YOUTH CENTER PROJECT, FOR ADDITIONAL CHANGE ORDERS AND CONTINGENCY NECESSARY TO COMPLETE THE PROJECT. Date: April 9, 2003 To: Subject: ADMINISTRATION RECOMMENDATION Adopt the Resolution. FUNDING Funding is available from Mid-Beach Quality of Life Funds. ANALYSIS The Scott Rakow Youth Center Improvements Project was initiated by the Mayor and City Commission in 1994 and was a part of the original $15 million Parks Bond issue. The original scope called for the expansion and renovation of the ice rink and other improvements to the Center. On June 19, 1996, the Mayor and City Commission approved the Master Plan for the improvements to the City's Parks and Recreation facilities of which the Scott Rakow Youth Center (Project) was a component. An Agreement with the firm of Carr Smith Corradino (Corradino) was executed on July 16th, 1996 for design, bidding and construction administration for the Project. The firm of Corradino was given direction to proceed with the design and completion of the construction documents on the basis of an adopted Resolution to design the largest ice rink possible within the available property. Bids for the Project were received on October 13,2000 with seven responsive, responsible bidders. On January 31,2001, after review and .evaluation of the bids, the Administration recommended the firm of International Builders Latin America, Inc. (IBLA) as the best and lowest bidder and requested award of a contract to IBLA, in the amount of $2,893,000. The award included $47,300 in additive alternates and $258,700 for contingency. Funds were previously appropriated from different funding sources such as the Parks Bond Fund, the General Obligation Bond Series 2000, Safe Neighborhood Parks Bond Fund and the City's Capital Projects Bond Fund. Commission Memorandum Scott Rakow Youth Center April 9, 2003 Page 2 Notice to proceed was given to IBLA on April 9, 2001 and construction began on April 24, 2001. Several unforeseen conditions arose as well as other issues, which delayed portions of the construction and added costs to the Project. In addition, IBLA has had cash flow problems that also generated delays to the prompt completion of the Project. The most significant problem has been the use of the contingency allowance included in the award of the Project to IBLA. The contingency allowance was included as part of the Agreement executed with IBLA and their contention was that the allowance amount was to be used by IBLA at their discretion. The City argued that the contingency allowance was to be used by the City at its discretion for additional scope of work or to account for unforeseen conditions. After many unsuccessful negotiations, the City accepted the use ofthe contingency with IBLA as part of the construction Agreement and identified additional change orders needed to complete the Project for which new funding was needed. On September 11, 2002, the City Commission approved a Resolution appropriating funds in the amount of $250,000 for additional change orders such as sanitary pipe re-routing, electrical relocations, new electrical installations related to existing conditions, additional fire alarm devices, water main repairs, modifications to the HVAC system, code related changes and additional painting of existing spaces. Some of the change orders are due to unforeseen conditions, some are attributed to requests by the Building Department related to code interpretations and others are due to, in the City's consideration, errors and omissions by the consultant, Corradino. The City intends to ask Corradino to reimburse the City for the costs of those change orders. Negotiations on this matter will commence at the completion of the Project. Phase I work, which includes the construction of the new ice rink and related facilities such as the new locker rooms and restrooms, the skate rental and pro shop, the new ticket booth, new ice rink equipment and offices is approximately ninety five percent complete. Phase II of the Project, which includes construction of the multi-purpose room, installation of auger piles, new First Floor Restrooms, removal of existing ice rink equipment, installation of HV AC equipment, irrigation and landscaping, elevator upgrades, additional renovation of the existing 2nd Floor, some additional offices and storage rooms, new restrooms in the existing building, a portion of the asbestos abatement, and some other minor renovations may begin as soon as Phase I is completed. To date, change orders in the amount of $206,000 have been executed with IBLA for Phase I of the project. Some of these change orders have included modifications to electrical, fire alarm, and ammonia connections to satisfy additional Building Department requirements. Additionally, geotechnical testing, threshold inspections, FPL charges, and Bell South charges, in the amount of $46,000, which were not previously budgeted, have had an impact on the Project's funding. The above costs have exhausted the $250,000 previously appropriated. Commission Memorandum Scott Rakow Youth Center April 9, 2003 Page 3 Proposed change orders, in the amount of approximately $77,500, have been negotiated for such items as louver & ductwork relocation at existing mechanical room; additional electrical relocations due to the phasing of the project; emergency exit lights, strobes and panic devices to satisfy additional Fire Department comments; modification of a new sanitary sewer line due to existing elevation conditions; new wall rail at entrance requested for ADA compliance; additional interconnections between the ammonia system and the fire alarm system requested by the Fire department ;and other miscellaneous items. Most of the above work has already been performed by ISLA. There are proposed change orders, in the amount of $22,300, which are currently under review and a final cost has not been established. Total expected change orders amount is $99,881 (See Attachment). ISLA has provided an updated construction schedule to complete the current scope of work, the Phase II scope and the additional change order work. Some time extensions have been granted to ISLA through previous change orders. Expected completion at this time is the end of May 2003 for Phase I and October 2003 for the remainder of the project. However, the contractor continues to experience internal cash flow problems. This has affected their relationship with their sub-contractors and subsequent completion of the final components of Phase 1. The City has contacted the bonding company and has put the contractor on notice for these delays. The bonding company is currently assisting the City in making payments to the contractor and their sub-contractors in order to ensure that ISLA uses the Project funds appropriately and in a timely fashion. The City and the bonding company intend to continue making payments in this fashion until the completion of the Project. The requested amount of $200,000 includes a contingency of approximately $100,000 in case any additional unforeseen conditions occur during the renovation of the existing building in Phase II. At this time, the Administration recommends that the additional funding be approved in order to complete the Project expeditiously. T:IAGENDA12003lapr0903\regular\ScottRakowAppropriation .doc PROJECT NAME: SCOTT RAKOW YOUTH CENTER - Additions and Renovations Project Outstandina Chanae Order Reauest Status ReDort PROPOSED C.O. C.O.R. SCOPE OF WORK AMOUNT TIME(Days) Class. No. No. 71R New Louver and Ductwork Modifications at Existing $ 26,780.92 0 Mechanical RoomlWater Tower 74 Optional sand layer for new ice rink Floor $ 13,442.42 0 77 New Emergency/Exit Lights $ 6,419.26 0 5 90 Labor for Ice Rink Floor Watering $ 470.40 0 92 RemovelReplace Existing Curb on Sheridan Ave $ 7,795.00 0 3 93 New Sidewalk Continuation at ADA Ramp (RFI#207) $ 3,668.00 0 3 94 Modifications to sanitary 6" line (RFI#209) $ 10,404.00 0 96 42" Wall Rail @ New Ramp Landing $ 647.00 0 97 Relocate lights at new ramp $ 1,591.00 0 98 Interconnection of ammonia Discharge fan switch with $ 3,336.00 0 Ammonia Panel 99 New Louvers for Locker Room doors $ 586.00 0 100 Additional Horn Strobes requested by Electrical Plan $ 454.00 0 5 Reviewer at FA Plans 2/2003 Connection of Exhaust Fan controls at Ice Rink Room to 101 Fire Alarm Panel (Requested by Fire Department $ 3,397.00 0 5 Inspector 2/2003) CMS New Interior Signage $ 6,000.00 0 3 CMS Connection of new HVAC units to existing EMS. $ 14,890.00 0 CLASSIFICATIONS: 1. ERRORS & OMMISSIONS 2. UNFORESEEN CONDITIONS 3. OWNER REQUESTED CHANGE 4. CONTRACTOR REQUESTED CHANGE 5. BUILDING DEPARTMENT CHANGES: PERMITTING/INSPECTIONS