Loading...
2018-30660 Resolution RESOLUTION NO. 2018-30660 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, ACCEPTING THE RECOMMENDATION OF THE FINANCE AND CITYWIDE PROJECTS COMMITTEE AT ITS NOVEMBER 30, 2018 MEETING, TO NEGOTIATE AND ENTER INTO A CHANGE ORDER(CHANGE ORDER NO. 2) WITH SHORELINE FOUNDATION, INC., WITH THE CITY'S COST FOR SAME NOT TO EXCEED THE AMOUNT OF $529,570, FOR THE RELOCATION OF SEGMENTS OF THE INDIAN CREEK SEAWALL, WHICH RELOCATION WILL AID THE CITY IN RESOLVING U.S. ARMY CORPS OF ENGINEERS (USAGE), FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP), SOUTH FLORIDA WATER MANAGEMENT (SFWMD), AND MIAMI-DADE COUNTY DEPARTMENT OF ENVIRONMENTAL RESOURCE MANAGEMENT (DERM) REGULATORY CONCERNS. WHEREAS, the Indian Creek Seawall Project (Project) started in 2016 in an effort to protect the existing corridor against frequent flooding and sea level rise; WHEREAS, the contract was awarded to Shoreline Foundation, Inc. (Shoreline), and the Project scope extended from 25th Street to 41st Street along Indian Creek Drive and a portion of Collins Avenue; and WHEREAS, during the first year of the Project, construction of the seawall only took place within City owned street ends or previously deeded properties; and WHEREAS, thereafter, as the Project progressed, the City was able to extend its construction into additional properties via quit claim deeds or easements; and WHEREAS, Change Order No. 1 was issued to extend the seawall to these additional areas, so there would be a continuous seawall to provide uniform protection from extreme tides and storm surge with the co-benefit that the upland area could be transformed into a greenway; and WHEREAS, on December 18, 2017, problems related to the Project construction were identified and the City met in the field with the United States Army Corps of Engineers (USACE), Florida Department of Environmental Protection (FDEP), South Florida Water Management District (SFWMD), the Miami-Dade County Department of Environmental Resources Management (DERM), [jointly the "Regulatory Agencies'] and regarding the construction of the Project; and WHEREAS, the Regulatory Agencies identified deficiencies that include lack of Federal authorization for construction north of 27th Street; and construction of the seawall westerly of where permitted, within the State's submerged lands in the vicinity of 29th Street, 30th Street to 31st Street, and 37th Street to 38th Street; and WHEREAS, the City immediately issued a stop work order to Shoreline and assigned a new City Project Manager to oversee the Project; and WHEREAS, since December 2017, there have been numerous meetings with the Regulatory Agencies, both in the office and in the field, where the issues related to seawall construction have been reviewed in great detail and the areas of concern distilled to the three main areas: (1) the vicinity of 29th Street; (2) 30th Street to 31st Street; and (3) 37th Street to 38th Street; and WHEREAS, the underlying permits for the Project shall require modification to allow for removal of the problematic seawalls that encroach more than 18 inches onto submerged lands, and re-construction of the seawall in appropriate locations, without said encroachment; and WHEREAS, the resulting consensus of the Regulatory Agencies is to require the seawall in the three above referenced locations to be removed and relocated, consisting of a total of 650 feet of seawall; and WHEREAS, in addition to the above plan, the Florida Division of State Lands will require mitigation for the encroachment onto the submerged lands; and WHEREAS, the City and the Regulatory Agencies are working on a mitigation plan, which may include the City donating similar submerged lands to the State, and other possible options of habitat restoration, or water quality improvements; and WHEREAS, the total seawall length along Indian Creek, between 25th Street and 41st Street, is approximately 4,700 linear feet; and WHEREAS, Shoreline has constructed approximately 2,600 linear feet of the 4,700 linear feet, and 650 feet of the new seawall is to be removed and reinstalled as identified above; and WHEREAS, the total cost of the 2,600 linear feet of seawall is contracted for $3.7 million; and WHEREAS, the total cost for relocating the 650 linear feet of seawall required by the Regulatory Agencies will cost approximately $1 million; and WHEREAS, the City and Shoreline have discussed the construction and cost issues relating to the Project and the parties are seeking a change order, to cover the cost of removing and re-constructing the 650 linear feet, which cost would be borne by both parties; and WHEREAS, the Administration is recommending approval of Change Order No. 2, which would include the removal and reconstruction/relocation of the 650 linear feet of seawall, in the three locations identified above, with the City's total maximum cost not to exceed $529,570; and WHEREAS, at its November 30, 2018 meeting, the Finance and Citywide Projects Committee accepted the request for a Change Order for the relocation of the segments of the Indian Creek seawall to resolve the regulatory issues, with the City's cost not to exceed amount of$529,570. NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND THE CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, the Mayor and City Commission accepting the recommendation of the Finance and Citywide Projects Committee (FCWPC) from its November 30, 2018 meeting, to negotiate, and enter into Change Order No. 2 with Shoreline Foundation, Inc., with the City's cost for same not to exceed amount of $529,570, for the relocation of segments of the Indian Creek Seawall, which relocation will aid the City in resolving U.S. Army Corps of Engineers (USACE), Florida Department of Environmental Protection (DEP), South Florida Water Management, and Miami-Dade County Department Of Environmental Resource Management regulatory concerns. PASSED and ADOPTED this 7a- day of December, 2018. ATTEST: an e till Ira' Raf el E. nado, Cit Clerk APPROVED AS TO FORM& LANGUAGE &F E ELUTION IZQlB City Attorney Date PMS g �c 1* i oTrOltf,TtD * €3 fin' 1� Resolutions-R7 T MIAMI BEACH COMMISSION MEMORANDUM TO: Honorable Mayor and Members of the City Commission FROM: Jimmy L. Morales, City Manager DATE: December 12, 2018 SUBJECT:A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, ACCEPTING THE RECOMMENDATION OF THE FINANCE AND CITYWIDE PROJECTS COMMITTEE AT ITS NOVEMBER 30, 2018 MEETING, TO NEGOTIATE AND ENTER INTO A CHANGE ORDER (CHANGE ORDER NO. 2) WITH SHORELINE FOUNDATION, INC., WITH THE CITY'S COST FOR SAME NOT TO EXCEED THE AMOUNT OF $529,570, FOR THE RELOCATION OF SEGMENTS OF THE INDIAN CREEK SEAWALL, WHICH RELOCATION WILL AID THE CITY IN RESOLVING U.S. ARMY CORPS OF ENGINEERS (USAGE), FLORIDA DEPARTMENT OF ENVIRONMENTAL PROTECTION (DEP), SOUTH FLORIDA WATER MANAGEMENT (SFWMD), AND MIAMI-DADE COUNTY DEPARTMENT OF ENVIRONMENTAL RESOURCE MANAGEMENT(DERM) REGULATORY CONCERNS. RECOMMENDATION The Adrdnistration recommends approving the Resolution. ANALYSIS The Indian Creek Seawall Project(Project)started in 2016 in an effort to protect the existing corridor against frequent flooding and sea level rise.The contract was awarded to Shoreline Foundation, Inc. (Shoreline), and the Project scope extended from 25th Street to 41st Street along Indian Creek Drive and a portion of Collins Avenue. During the first year of the Project, construction of the seawall only took place within City owned street ends or previously deeded properties. Thereafter,as the Project progressed,the City was able to extend its construction into additional properties via quit claim deeds or easements. Change Order No. 1 was issued to extend seawall to these additional areas, so there would be a continuous seawall to provide uniform protection from extreme tides and storm surge with the co-benefit that the upland area could be transformed into a greenway. On December 18,2017,problems related to the Project construction were identified and the City met in the field with the United States Army Corps of Engineers (USAGE), Florida Department of Environmental Protection (FDEP), South Florida Water Management District (SFWMD), the Mian-Dade County Department of Environmental Resources Management (DERM), [jointly the"Regulatory Agencies")regarding the construction of the Project. The Regulatory Agencies identified deficiencies that include lack of Federal authorization for construction north of 27th Street; construction of the seawall westerly of where permitted, within the State's submerged lands in the vicinity of 29th Street, 30th Street to 31st Street,and 37th Street to 38th Street.The City immediately issued a stop work order to the contractor,Shoreline, and assigned a new City Project Manager to oversee the construction. Since December 2017, there have been numerous meetings with the Regulatory Agencies, both in the office and in the field, where the issues related to seawall construction have been reviewed in great detail and the areas of concern distilled to the three nein areas:(1)the vicinity of 29th Street,(2)30th Street to 31st Street,and(3)37th Street to 38th Street. The underlying permits for the Project shall require modification to allow for removal of the problematic seawalls that encroach more than 18 inches onto submerged lands, and re-construction of the seawall in appropriate locations, without said encroachment.Resulting consensus of the Regulatory Agencies is to require the seawall in the three above referenced locations to be removed and relocated,consisting of a total of 650 feet of seawall. In addition to the above plan,the Florida Division of State Lands will require rrtigation for the encroachment onto the submerged lands.The City and the Regulatory Agencies are working on a rritigation plan, which may include the City donating similar submerged lands to the State,and other possible options of habitat restoration,or water quality improvements. The total seawall length along Indian Creek, between 25th Street and 41st Street, is approximately 4,700 linear feet.Shoreline has constructed approximately 2,600 linear feet of the 4,700 linear feet, and 650 feet of the new seawall is to be removed and reinstalled as identified above.The total cost of the 2,600 linear feet of seawall is contracted for$3.7 Trillion. The total cost for relocating the 650 linear feet of seawall required by the Regulatory Agencies will cost approximately$1 million. The City and Shoreline have discussed the construction and cost issues relating to the Project and the parties are seeking a change order to cover the cost of removing and re-constructing the 650 linear feet,which cost would be borne by both parties. The Administration is recommending approval of Change Order No. 2, which would include the removal and reconstruction/relocation of the 650 linear feet of seawall. in the three locations identified above.with the City's total maximum cost not to exceed$529,570. At its November 30, 2018 meeting, the Finance and Citywide Projects Committee accepted the request for a Change Order for the relocation of the segments of the Indian Creek seawall to resolve the regulatory issues,with the City's cost for same not to exceed the amount of$529,570 CONCLUSION The Administration recommends approving the Resolution. Amount 1 $529,570 Account 1 389-0810-069357-29-410-564-00-00-00- 21220 7 aaislative Tracking Public Works ATTACHMENTSi Description d Final Reso o Shoreline Settlement Proposal Carpenter, Eric From: Tony Royo <tony@shorelinefoundation.com> Sent: Monday, October 15, 2018 9:29 AM To: Carpenter, Eric Cc: Coley, Roy;Soto, Luis Subject RE:Indian Creek Follow Up Flag: Follow up Flag Status: Completed Eric, we will agree to following;See below Respectfully, James"Tony"Royo President SF,= SHORELINE FOUNDATION,INC. 2781 S.W. 56 Avenue Pembroke Park,Florida 33023-4166 Ph: (954) 985-0460 Fax: (954) 985-0462 www.shorelincfoundation.corn From: Carpenter, Eric [mailto:EricCaroenter(amiamibeachfl.Qov] Sent:Thursday, October 11, 2018 7:08 PM To: Tony Royo' Cc: Coley, Roy; Soto, Luis Subject: RE: Indian Creek Tony, I am conceptually ok with this proposal if we agree to 5%retainage Agreed. Just to be transparent, I have only identified $2.5 Million for additional seawalls on Indian Creek at this time. I do not think that takes us all the way to 41' Street so I cannot commit to that end point but I am willing to continue north from 32"°Street toward 41st Street as long as funding is available. I am optimistic that additional money will become available but it is not there today. My agreement is contingent upon the agreed upon change order amount and terms we have discussed that cap the City's expense for relocation of 650 feet of seawall at$477,505. This amount was for 560 LF please add$76,741 to increase to 650 LE. New total of change order would be$554,245 As we have discussed all of this is subject to Commission approval. I hope that we can agree on this to be able to move forward with the permitting and resolution of this matter. Also we will need to he paid the follow within 30 days; • $138,783.54 for invoice 2914-RI dated 8/15/2018 • $403,794.18 of completed work as agreed 1 • $142,087.00 5% retainage Total paid to shoreline now = $684,664.72 Respectfully, Eric 1'.Carpenter,P.E. Assistant City Manager MIAMIBEACH 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:305-673-7080 / www.miamibeachtRov We are commMed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,histone community From:Tony Royo [mailto:tonv(tshorelinefoundation.com7 Sent:Thursday, October 11, 2018 5:56 PM To: Carpenter, Eric Subject: FW: Indian Creek Eric; We have had numerous conversations with Luis regarding moving forward with payment for the Indian Creek,as it relates to work completed. It appears that we are close to mutual agreement. Therefore, please consider the following; 1. While we don't fully agree to the quantities depicted within the attached DRAFT payment spread sheet generated by Luis,we will agree to accept payment in the amount of $403,794.19 if the following are also agreed to by the COMB and come to fruition; 2. The COMB pays 5FI's invoice$139,783.54 for the piles and panels fabricated pursuant to the directive given by Bruce. 3. The COMB releases all but 2.5%of retainage owed to SFI. 4. The COMB issues the Change Order to move the previously installed seawalls. 5. The COMB issues 5FI the PO for the remaining seawall work along Indian Creek to complete the seawall up to 41"St. Respectfully, James "Tony"Royo President misaia SHORELINE FOUNDATION, INC. 2781 S.W. 56 Avenue Pembroke Park,Florida 33023-4166 Ph: (954) 985-0460 Fax: (954) 985-0462 www.chottlinefoundation.com 2 Carpenter, Eric From: Tony Royo <tony@shorelinefoundationcom> Sent: Friday, September 28, 2018 8:02 AM To: Carpenter, Eric Subject: FW:settlement Proposal Attachments: SFI Indian Creek Seawall Realignment Proposal 9 11_2018.pdf '.. Eric,when can we begin the process to get our agreement to move forward, I think it would be advantageous to everything ready so when the permits are ready we immediately go to work,thoughts? Respectfully, James "Tony"Royo President aiNat SHORELINE FOUNDATION, INC. 2781 S.W. 56 Avenue Pembroke Park,Florida 33023-4166 Ph: (954) 985-0460 Fax; (954) 985-0462 www.shotelinefoundation.com From:Tony Royo [mailto:tonv(Ishorelinefoundation.coml Sent: Sunday, September 23, 2018 1:21 PM To: Carpenter, Eric <EricCamenteremiamibeachfl.gov> ( ricCar nteralmiamibeachfI.gov) Cc: 'John McGee'; Charles Diveto; 'Mark Osburn' Subject: settlement Proposal Settlement Proposal Eric, after consideration of the City's proposal, SFI does not believe we have any actual responsibility for the cost to relocate the seawall, but in spirit of cooperation and in an effort to put this issue behind all of us we would be willing to accept the following: 1) 1) As you know, there are several City jobs that have been completed and or invoices the have not been paid. The City will pay SFI the following within 30 days: • $27,192.28 for CPM-15-532 Maurice Gibb Park Seawall P.O. # 20171018 • $138,783.54 for invoice 2914-R1 dated 8/15/2018 • $ 333,377.24 pay request November 2017 • $ 101,588.40 pay request December 2017 • $284,174.00 Retainage earned through December 2017 Total $885,115.46 We have broken out the seawall work into 3 areas (see attached for a detailed breakdown of costs and values) 2) SFI will relocate 100 L.F. of seawall in area 2 at its expense 3) SFI will locate 180L.F. of seawall in area 3 at its expense 4) Shoreline will waive all interest and attorney fees Total value of SFI work and waiver is approximately $591,377.00 [$ 348,610.00 relocation work plus add the value of the waiver of interest $110,000.00 and attorney's fees/Administrative cost $ 132,767.00 to provide the biggest value possible. 5) The City of Miami Beach will issue a Change Order to SFI in the amount of$689,505.00 to relocate appx 220 L.F. of existing seawall in area 1 and 60 L.F. of existing seawall in area 2. Note: The city of Miami beach cost per L.F. is higher than SFI is due the fact area 1 has a cap poured, therefore more demo is involved, and the material cannot be reused, along with the cost of mobilization. 6) The City would likewise waive any attorney's fees or potential claims against SFI. 7) The City of Miami Beach will issue a notice to proceed and Purchase order to finish the work on the balance of Shoreline's existing contract within 30 days and SFI will proceed with any work that has all required permits and will complete the balance of the work as soon as all of the permits for that work are completed. If you agree we can proceed to prepare the necessary papers and approvals Respectfully, James"Tony"Royo President gamst SHORELINE FOUNDATION,INC. 2781 S.W. 56 Avenue Pembroke Park, Florida 33023-4166 Ph:(954)985-0460 Fax: (954)985-0462 wwwshorelinefoundation.com 2 E . +w. _ 1 tyyrT� I' . aril C YY • Riir:j2. '.•... ..-" N'.'+y am. . fur. -.;:• n.}. v �— =:" Seawall h: c. 9lknal.2:,•4,°Lt { .: 1✓ :':.: 'eawa1114'heightBW'•los 210 IF $1,15700 $ 242,970.000 Allowance for Trench Safety EA $ 25.00 $ 25.00 _': Dram' '9±rt_ .i...:- -14: .. _4 ' rr... `...i : : , �.rfai i 'tr.:;. . ::'S`.17.:.'v :,.s?..; � . .:.5" dal:,./fir ',w''rt1t5 seawall UV height SW'plus 10 fl $1,157.00 $ 115700.00 _ Allowance for Trench Safet 1 0 $ 2500 $ 25.00 E. a. ".arf.. ::EFEf�rp.». 'i:^ip' : i ::'.;-:,ae�1:17'.?G..i 1111.1 Sectional Barges 1 Months $ 26.500.0 - _ MOT 129th to 38th Street) 1 Months $ 4,500.0 - Demo Enisting Concrete Cap o IF $ 100.00 Remove and Reinstall 14"King Pile 11 Each $ 2,280.0 _ Remove and Reinstall 144 Batter Pile 11 Each $ 2,280.00 - Remove and Reinstall Seawall Panels 10 Each $ 1,520.00 - _ Remove and Dls.ose 14"Batter Elan $ 1,190.00 - - Su.ply and Install 14"Batter Pile 2 Each $ 1,810.0 - Vibration Monitoring 5 Day $ 750.00 $ 0750.0 - Pile Logs 5 Day $ 750.0 $ 3,750.00 MEM Concrete Testing 1 EA $ 150.00 $ 150.00 - IIMIIIIIIIIIIIIIIIIIIIIIIM rilliraTeS ''' v l ____ 1!R' ^' 18Oi. v_c' 1�l__.0 >.i laeX�0. Seawall l4'height 500 plus 180 LF $1,157.00 $ 208,260.0 Allowance for Trench Safet a0 $ 25.00J $ 25.0 tsc r an .. L — Sectional Barges 1 Months $ 2050.0 - - MOT(29th to 38th Street) 1 Months $ 4,50.00 - Remove and Reinstall 14(King Pile 19 Each $ 2,280.00 - - Remove and Reinstall 14"Batter Pile 19 Each $ 152000 Remove and Reinstall Seawall Panels 18 Each $ 15200 - Vibration Monitoring 11 Day $ 750.00 $ 8,250.00 _ Pile Logs it Day $ 750.00 $ 8,25000 Concrete Testing 3 EA $ 150.00 $ 450.00 IS 111311111111=1.1 "lityli :atlial ? ,a.,i.':14.LUCIF 5. 41,4, iiritait . . "t%Viti:Mtaa.L.3i1113 giliaSIWORairifirMillniM Total Value of Realignment $ 1,038,115.00 THIS PAGE INTENTIONALLY LEFT BLANK