Resolution 2019-30684 RESOLUTION Na 2019-30684
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR
AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO THE
AGREEMENT BETWEEN THE CITY AND BERGERON LAND DEVELOPMENT
INC. FOR DESIGN BUILD SERVICES FOR THE WEST AVENUE BRIDGE AND
PEDESTRIAN BRIDGE OVER COLLINS CANAL (RFP NO. 2016-062-KB) (THE
'AGREEMENT"), WITH SUCH CHANGE ORDER NO. 1 IN THE NOT-TO -
EXCEED AMOUNT OF $355,142.04, PLUS A 10% OWNER'S CONTINGENCY
IN THE AMOUNT OF $35,514.20, TO PROVIDE FOR ACCESSIBILITY
IMPROVEMENTS AND ADDITIONAL ENHANCEMENTS TO THE AESTHETICS
OF THE PEDESTRIAN BRIDGE, INCLUDING ARCHITECTURAL PANELS,
RAMPS AND STEPS, TO BE FUNDED WITH $330,000 IN PREVIOUSLY
APPROPRIATED FUNDS, AND SUBJECT TO A CAPITAL BUDGET
AMENDMENT FOR THE$60,657 REMAINING BALANCE REQUIRED TO FUND
CHANGE ORDER NO. 1.
WHEREAS, on April 27, 2016, the City Commission awarded the contract for design build
service for the West Avenue Bridge and Pedestrian Bridge over Collins Canal Project (RFP No.
2016-062-KB) ("the Project") to Bergeron Land Development Inc., in the amount of $9,930,000;
and
yVHEREAS, the scope of work for the Project included street lighting, pedestrian lighting,
signage and pavement markings, new vehicular and pedestrian signals on Dade Boulevard and
West Avenue, utility relocation and/or adjustments, and drainage; and
WHEREAS, after several meetings, members of the community requested that the overall
aesthetics of the pedestrian bridge be enhanced. The enhancements included aluminum paneling,
powder coating, and LED lighting; and
WHEREAS, on January 17, 2018, the Mayor and City Commission approved a capital
budget amendment that included for$440,000 to the Project, from which $350,000 was allocated
for the requested aesthetic improvements of architectural panels, powder coating and decorative
lighting for an enclosed aluminum pedestrian bridge, and $90,000.00 was allocated for landscape
enhancements along Dade Boulevard; and
WHEREAS, on February 14, 2018, the Mayor and City Commission rejected a proposed
change order with respect to the pedestrian bridge enhancements, and instead directed City staff
to design a simple truss bridge, and the Planning Director noted that a simple bridge like the one
over the Indian Creek Waterway(which is a sidewalk with handrails)would most likely not have to
go to the Design Review Board ("DRB") unless the City Commission directed staff to obtain
approval from the DRB; and
WHEREAS, on February 14, 2018, the City Commission also requested that the Sunset
Harbour and WAVNA associations be afforded the opportunity to provide input before a final design
is approved; and
IVHEREAS, on May 3, 2018, the City conducted a public meeting for the Project, with the
participation of Public Works staff and Commissioner Mark Samuelian, to to present residents with
five (5) pedestrian bridge renderings showing the aesthetic options for the proposed bridge; and
WHEREAS, Option 4A, a "Venetian Bubble" architectural side panel, had the most votes
and was the aesthetic option selected. City staff explained that if the cost of Option 4A exceeded
the funds previously approved by the City Commission, the request for additional funds would
require City Commission approval; and
WHEREAS, on October 2, 2018, the DRB approved the proposed decorative "Venetian
Bubble",panels for the pedestrian bridge,with the recommendation that the panel design be further
refined and more articulately coordinated with the structural truss system of the bridge; and
WHEREAS, the method of installation of the "Venetian Bubble" panels would be further
developied and would be installed on the outside of the bridge support systems. Further, the panels
would extend along the ramping and approach walkways, subject to City approval;
WHEREAS, the Design-Builder for the Project, Bergeron Land Development, Inc., has
submitted a cost proposal to implement the foregoing enhancements, including costs for the re-
design fees, powder coated panels and changes to the ramps; and
WHEREAS, City staff has reviewed the cost proposal and finds it to be fair and reasonable,
and is (therefore requesting approval of Change Order No. 1, in the maximum amount of
$355,142.04, plus a 10% Owner's Contingency in the amount of$35,514.20, to permit final design
and fabrication of the bridge to commence as soon as possible; and
WHEREAS, of the $440,000 previously appropriated on January 17, 2018 for
enhancements and landscaping for the Project, $110,000 has been spent on landscaping;
accordingly, Change Order No. 1 would be funded with $330,000 in previously appropriated funds,
and shall be subject to a capital budget amendment in the amount of $60,657 for the remaining
balance required to fund Change Order No. 1.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission
hereby 'approve and authorize the Mayor and City Clerk to execute Change Order No. 1 to the
Agreement between the City and Bergeron Land Development Inc. for Design Build Services for
the West Avenue Bridge and Pedestrian Bridge Over Collins Canal (RFP No. 2016-062-KB), with
such Change Order No. 1 in the not to exceed amount of $355,142.04, plus a 10% Owner's
Contingency in the amount of$35,514.20, to provide for accessibility improvements and additional
enhancements to the aesthetics of the pedestrian bridge, including architectural panels, ramps and
steps, to be funded with$330,000 in previously appropriated funds, and subject to a Capital Budget
Amendment for the $60,657 remaining balance required to fund Change Order No. 1.
PASSED and ADOPTED this 16th day of January, 201
ATTEST:
/,a4f "' � A tan Gelber, r or
a"i ilk %'\ .. •
Rafael E. Granado, Oity , Le .:,, ,F j'.- . , APPROVED AS TO
FORM&LANGUAGE
..�a ' &FOR EXECUTION
° .INCORP ORATED: 0
2-< '‘` oft-t_Ogv; f if(((i
CRY AttomeY (e0c) Date
o
Agenda Item RrI F
Date 1—I6-II
i\A o ! BEACH
City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov
COM ISSION MEMORANDUM
J
TO: Honorable Mayor and Members of the City Com ission
FROM: Jimmy L. Morales, City Manager
1'
DATE: January 16, 2019
SUBJECT: A RESOLUTION OF THE MAYO- AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND
CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO THE AGREEMENT
BETWEEN THE CITY AND BERGERON LAND DEVELOPMENT INC. FOR DESIGN
BUILD SERVICES FOR THE WEST AVENUE BRIDGE AND PEDESTRIAN BRIDGE
OVER COLLINS CANAL (RFP NO. 2016-062-KB) (THE "AGREEMENT"), WITH
SUCH CHANGE ORDER NO. 1 IN THE NOT-TO - EXCEED AMOUNT OF
$355,142.04, PLUS A 10% OWNER'S CONTINGENCY IN THE AMOUNT OF
$35,514.20, TO PROVIDE FOR ACCESSIBILITY IMPROVEMENTS AND
ADDITIONAL ENHANCEMENTS TO THE AESTHETICS OF THE PEDESTRIAN
BRIDGE, INCLUDING ARCHITECTURAL PANELS, RAMPS AND STEPS, TO BE
FUNDED WITH $330,000 IN PREVIOUSLY APPROPRIATED FUNDS, AND
SUBJECT TO A CAPITAL BUDGET AMENDMENT FOR THE $60,657 REMAINING
BALANCE REQUIRED TO FUND CHANGE ORDER NO. 1.
RECOMMENDATION
The Administration recommends that the Mayor and City Commission of the City of Miami Beach, Florida
accept the recommendation of the City Manager to authorize Change Order No. 1, to expand the scope
of the current Contract for Design Build Services for the West Avenue Bridge and Pedestrian Bridge over
Collins Canal (RFP No. 2016-062-KB) to Bergeron Land Development Inc., in the maximum amount of
$355,142.04 plus a 10% owner contingency in the amount of$35,514.20.
i
BACKGROUND
On April 27, 2016, the City Commission awarded the contract for design build services for the West
Avenue Bridge and Pedestrian Bridge over Collins Canal (RFP No. 2016-062-KB) to Bergeron Land
Development Inc, in the amount of $9,930,000. The scope of work also included street lighting,
pedestrian lighting, signage and pavement markings, new vehicular and pedestrian signals on Dade
Boulevard and West Avenue, utility relocation and/or adjustments, and drainage.
After several meetings, members of the community requested that the overall aesthetics of the pedestrian
bridge be lenhanced. The enhancements included aluminum paneling, powder coating, and LED lighting.
On January 17, 2018, a capital budget amendment was approved and included an item for $440,000 to
the project from which $350,000 was allocated for the requested aesthetic improvements of architectural
panels, powder coating and decorative lighting for an enclosed aluminum pedestrian bridge. At the same
time, a total of$90,000.00 was allocated for landscape enhancements along Dade Boulevard using City's
inhouse farces as a cost savings measure.
On February 14, 2018, Change Order No. 1 was presented to the Commission for approval. The
Commission made a motion to reject the change order and instead instructed City staff to design a simple
truss bridge. It was requested that the Sunset Harbor and WAvNA associations' input be taken into
consideration before a final design was placed into production. Thomas Mooney, Planning Department
Director stated that a simple bridge like the one over the Indian Creek Waterway (which is a sidewalk with
handrails) would most likely not have to go to the Design Review Board (DRB) unless the City
Commission directed staff to get approved from DRB.
On May 3,; 2018, the City conducted a public meeting for the West Avenue Bridge Project. Participants
included Public Works staff and Commissioner Mark Samuelian. The purpose of the meeting was to
present residents with five (5) pedestrian bridge renderings showing the aesthetic options for the bridge.
Option 4A; a bubble architectural side panel had the most votes and was the aesthetic option selected.
City staff explained that if Option 4A exceeded the funds the Commission had previously approved, the
request would need to go back to Commission for a change order.
On October 2, 2018, City staff presented the Pedestrian Bridge's decorative 'venetian bubble' panels to
the DRB, where the Board approved the bridge plans with the recommendation that the panel design
shall be further refined and more articulately coordinated with the structural truss system of the bridge.
The method of installation of the "Venetian Bubble" panels shall be further developed and installed on the
outside of.the bridge support systems. Further, the panels shall extend along the ramping and approach
walkways, in a manner to be reviewed and approved by staff consistent with the Design Review Criteria
and/or the'directions from the Board.
Currently, ithe cost proposal for the re-design fees, powder coated panels and changes to the ramps has
been provided by the contractor. City staff is requesting the Commission to authorize the Mayor and City
Clerk to execute a Change Order No. 1 in the maximum amount of $355,142.04 plus a 10% owner
contingency in the amount of $35,514.20. Approval is being requested at this time so final design and
fabrication of the bridge can commence as soon as possible.
Since the capital budget was approved approximately one year ago, $110,000 has been spent on
landscaping which is now complete. That leaves $330,000 available for this change order. $60,656.24
will be needed in a future capital budget amendment to fund this work
CONCLUSION
The Administration recommends that the Mayor and City Commission of the City of Miami Beach, Florida
accept the recommendation of the City Manager to authorize Change Order No. 1, to expand the scope
of the current Contract for Design Build Services for the West Avenue Bridge and Pedestrian Bridge over
Collins Canal (RFP No. 2016-062-KB) to Bergeron Land Development Inc., in the maximum amount of
$355,142.04 plus a 10% owner contingency in the amount of$35,514.20.
JLM/ / RWC/JJF/NNN
Legislative Tracking
Public Works
ATTACHMENTS:
Description
❑ 645 Lincoln Ct Pedestrian Ramps Proposal - REVISED 1-3-19 (2)
❑ DRAFT Reso
Page 1075 of 1648
1
_....
t n)
---,,\\ !,:'
: {ir )/ ,,r-s)
�' I , IC < I f J "
1 ! ._,) ,__LA.L. „ ,-:,..,_. , J_L_A.L__ \:). ,.._,..,, ,,, \i,
LAND DEVELOPMENT, INC.
January 3rd, 2019
ATTN: Luis Soto, P.E., Sent Via: Email
City Engineer LuisSoto@miamibeachfl.gov
City of Miami Beach, Public Works Department
Re: West Ave Bridge Project& Dade Reconstruction, Miami Beach
BLD Job No. 645
Change Order: Pedestrian Bridge&Lincoln Ct Access Ramps-FINAL
Dear Mr. Soto,
Per our conference call on December 21st and further discussions which followed, please refer to the
REVISED proposal on page 2 for the services requested, and page 3 for General Notes and Exclusions.
I
Sincerely
BERGERON LAND DEVELOPMENT,INC.
Yandy Fuentes
Project Manager
Attachments: Exhibits A, B, &C.
cc: Brian Thomason, Daniel Irion, Giancarlo Pena, Eric Carpenter
Bergeron Land Development Inc.
19612 SW 69th Place
Ft.Lauderdale,FL 33332
Phone: (9541 680-6100
Page 1076 of 1648
2
Description Quantity UoM Unit Price Total
Gatorbridge-additional work
Powder Coating-Grey 1 LS $32,500.00 $32,500.00
Panels& Engineering Design (additional panels&
1 LS $54,500.00 $54,500.00
design, review&stamping fees)
Ballarena-south ramp
Mobilization 1 LS $5,000.00 $5,000.00
M.O.T. (device&installation), exclude drawings& 1 LS $1,500.00 $1,500.00
permits
Clearing& Grubbing 1 LS $2,800.00 $2,800.00
Embankment(backfill on ramps) 1 LS $3,500.00 $3,500.00
Concrete Glass NS, Gravity Wall 187 LF $240.00 $44,880.00
4"Sidewalks 68 SY $45.00 $3,060.00
Type F-Cub Gutter 53 LF $44.64 $2,366.04
Manhole Adjustment 1 EA $3,500.00 $3,500.00
Inlet P-9 2 EA $7,500.00 $15,000.00
Pipe Culvert, HDPE Material, Round, 18"S/CD 54.00 LF $180.00 $9,720.00
Grass Area(exclude irrigation), including 4"top soil- 100 SY $25.00 $2,500.00
minimum of 100 SY
Moz Designs. Inc.
LaserCut Bubbles Dbl Sided No grain Grey Powder
Coat `- 30 EA $960.00 $28,800.00
Crating&Handling 1 LS $575.00 $575.00
Ground SOpping-Standard Delivery to 33139 1 LS $1,500.00 $1,500.00
Keith&Schnars-design
Lincoln Ct Access Ramps Redesign Fees 1 LS $26,780.00 $26,780.00
Bergeron Land Development
Unforeseen Conditions(i.e.harmonization, ramp 1 LS $60,000.00 $60,000.00
panels we,ding, QC,pavement markings)
Mobilization&Demobilization 1 LS $22,567.00 $22,567.00
Panels& Engineering Design (Original Design before 1 L5 $47,433.00 $47,433.00
DRB Meeting)
Original Pedestrian Bridge
PrecastArCh Fascia Deduct 1 LS -$70,000.00 -$70,000.00
Giralt Enterprises
Aluminum,Handrail-Index 862 208.43 LF $49.60 $10,338.13
Subtotal: $308,819.17
Bergeron 15%M/U: $46,322.88
Total: $355,142.04
Bergeron Land Development Inc.
19612 SW 69th Place
Ft.Lauderdale,FL 33332
Phone: (9541 680-6100
Page 1077 of 1648
3
General Notes:
*Gatorbridge pricing is based on latest round of comments made by DRB as communicated by the city on 10/11/18.Exhibit B and
detailed in Exhibit C.
*This proposal�Jdoes not include lighting for the Pedestrian Bridge or Access Ramps due to insufficient information at the time of
submittal.PVo plans or details.
*Laser cut panels are produced to size and cannot be cut once produced.
*Lead time for panels are 4-6 weeks plus transit time
Excluded:
Permits
Bergeron Land Development Inc.
19612 SW 69th Place
Ft.Lauderdale,FL 33332
Phone: (9541 680-6100
Page 1078 of 1648
EXHIBIT A
B-B
A
9 9.
A-A i q
cz ''''
® 9 n A, ®9E.9E.zE.++9 6 B, 9113,.nE�x, 6.6 46
aE E5
9e.E L9. NaAXb E eE GSE 51,9SEAWALL
IxtEr rre nos slmT moulillEo R+n Et.s3o waxkr.
ecX sos son [OLEINS CANAL 1e PIPE ...-- — - _
ex°
rxl _ , /
XlaNl ecX NI
rsv)-z as eaP EL 19 ..__-..- .. _ _ - 1
Eae EL r9 IA I ISE)sas Ix +3�5 w, - .
IxvEA!(NE)-1.15 ExIST.INVERT(51 3.a6 •Exlsi IrvvENr lxl-1 a5_ • BEGINrvwat rip:IxDAalti ..,...-*LI
YXax wag CROSS SECTION A-A
IAGR Pirmuros F�
\YIN/LINE •
N r U
Xaxoxal WI camEt.T.sT t.3.90
ik
XAMIAIL LANDING N El..;00.
EXIST.EOP Mg.. / 'j=gam .5. /TOIPENaIM (TYPICu�t, D I
Mg.. ,1,50
—KZ
cOli6177 I/
if
El.ibOpr+\/ Et. Et el9 V //` NAY Ix/
,w uxE�% 660 l/rv,wt oi'"""" \IeterrPE Ig---,1 ! �EAV`OSAIL //// ,z 1,
96
fig LANDING eE� LANDING T, /
as
/`% t.19 I`O,�\W .19 Ic Pl II
2
99.s lal EL.r•
eulLDrx
��� � \� .td'LWI►.. ` � t.I,E Et.I.TE / I`
." - ,..111
;Lf �EGAxsGGT,EA Et LEE T� ,I� •
\� Las
3',s, x� o 0 174 ►E:r3r 07,ir ' I
EL 9la e MIN
•
EXIST.EGPED.
,5
Pr A'.-,I Ira ?AVM MA) ,� rA Dta xtv0.EExrRIN 0E IM 7
CROSS SECTION B-B
6-29-I8®NEW ACCESS RASP DETAIL SHEET
1 o3 0 j..
ENGINEER OF RECORD
®M I AMI REACH �� " = ENGINEER OF RECORD: 5- File name
XXXXXXXXXXXXXXXXXXXXXXXXXX CRY MANAGER: JIMMY L.HOYCOLEY LES DESIGNER ENGINEER: A RLMetl Plan L•yaatEp
DIRECTOR: ROY COLEY ESSWN BY: 9 •
FIeIE Book:N/A Page: .JILL Job Oder: N/A
® TffLE: CITY ENGINEER: LUIS SOTO,RE. CHECKER: Dare 1 8/2018
PUBLIC WORKS DEPARTMEN XXXXXXXXXXXXXXXXXXXXXXXXXX )
..,„,�.....,,,,n„n..,..,n.M,..,......,..,..,, - _.__ --._._.. o DreNrO&
EXHIBIT B
From: Pena, Giancarlo <GiancarloPena@miamibeachfl.gov>
Sent: Thursday, October 11, 2018 3:56 PM
To: Yandy Fuentes
Cc: Soto, Luis; Brian Thomason; Daniel Veillette
Subject: RE: DRB meeting on Ped-Bridge
Attachments: A0029_N3-1.jpg; maximus2-1.jpg; Panels.pdf
Yandy,
Below Please find recommendation from the design review board.
The method of installation of the "Venetian Bubble" panels shall be further developed and installed on
the ouiside of the bridge support systems. Further,the panels shall extend along the ramping and
approach walkways.
Attached please find exhibit.
Thank Jou,
MIAM .
1,7 E Ac
Giancarlo Pena, P.E., CGC.,Civil engineer III
PUBLIC1WORKS DEPARTMENT
1700 Convention Center Drive,Miami Beach,FL 33139
Tel:305;673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov
We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community.
Before you print this email,consider the negative environmental impacts associated with
printing. •
From: Pena, Giancarlo
Sent:\Vednesday, October 10, 2018 3:40 PM
To: 'Yacndy Fuentes'<yfuentes@bergeroninc.com>
Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason <bthomason@bergeroninc.com>; Daniel
Veillette<dveillette@bergeroninc.com>
Subject: RE: DRB meeting on Ped-Bridge
Ok
Thank you
M1AMEACH
Giancarlo Pena, P.E., CGC.,Civil engineer Ill
PUBLIC WORKS DEPARTMENT
1700 Convention Center Drive,Miami Beach,FL 33139
Tel:3051673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov
Page 1080 of 1648
We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community.
4 Before you print this email,consider the negative environmental impacts associated with
printing.
From:Pandy Fuentes<yfuentes@bergeroninc.com>
Sent:Wednesday, October 10, 2018 3:38 PM
To: Pena, Giancarlo<GiancarloPena@miamibeachfl.gov>
Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason<bthomason@bergeroninc.com>; Daniel
Veillette<dveillette@bergeroninc.com>
Subject: Re: DRB meeting on Ped-Bridge
Giancarlo,
It looks like Rick is out of the office until next week. I would recommend to work on the
recommendations by the DRB and if Gatorbridge has any questions, we could coordinate a
conference call.
Sincerely,
Yandy Fuentes
Project Manager
Bergeron Land Development Inc.
19612 SW 69th Place
Fort Lauderdale, Florida 33332
Cell: (954) 658-6775
Phone: (954) 680-6100
Fax: (954) 680-0666
Website: www.bergeronlanddev.com
Email: yfuentes@bergeroninc.com
This message and any and all attachments are intended only for the recipients as named above
and may contain confidential,proprietary, and/or privileged information. Unauthorized use,
distribution, or reliance upon such information is not allowed. If you have received this message
by mistake,please contact the sender and destroy all digital and hard copies.
Sent from my iPhone
On Oct 10, 2018, at 3:18 PM, Pena, Giancarlo <GiancarloPena@miamibeachfl.gov>wrote:
Yandy,
I am working on getting all the required information, but can we schedule a conference
call for tomorrow 11:00 AM or Friday at 10:00 AM.
Thank you,
Page 1081 of 1648
MIAMBEACH
Giancarlo Pena,P.E., CGC.,Civil engineer Ill
PUBLIC WORKS DEPARTMENT
1700 Convention Center Drive,Miami Beach,FL 33139
Tel:305-673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov
We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,
historic community.
Before you print this email,consider the negative environmental impacts
associated with printing.
From:Yandy Fuentes<yfuentes@bergeroninc.com>
Sent:Wednesday, October 10, 2018 1:03 PM
To: Pena, Giancarlo<GiancarloPena@miamibeachfl.gov>
Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason
<bthomason@bergeroninc.com>; Daniel Veillette<dveillette@bergeroninc.com>
Subject: RE: DRB meeting on Ped-Bridge
Hi Giancarlo,
Any update on the request below?
Sincerely,
Yandy y Fae wte4
Project Manager
Bergeron Land Development Inc.
19612 SW 69th Place
Fort Lauderdale, Florida 33332
ell: (954) 658-6775
Phone: (954) 680-6100
Fax: (954) 680-0666
Website: www.bergeronlanddev.com
Email: yfuentes(abergeroninc.com
y y"*�t t i
-,�.) r['�, c14}�9 1. i�s .t4
LAND i)rVEL'M N1_i:NC_
f?k \\4.
EA
,:, t )
BERGRO
Aso ,- .„. ,, 204
- <image006.jpg>
Page 1082 of 1648
This message and any and all attachments are intended only for the recipients as named
above and may contain confidential,proprietary, and/or privileged
information. Unauthorized use, distribution, or reliance upon such information is not
allowed. If you have received this message by mistake,please contact the sender and
destroy all digital and hard copies.
From:Yandy Fuentes
Sent:Thursday, October 4, 2018 8:58 AM
To:Giancarlo (Inspector) Pena<GiancarloPena@miamibeachfl.gov>
Cc: LuisSoto@miamibeachfl.gov; Brian Thomason<bthomason@bergeroninc.com>;
Daniel Veillette<dveillette@bergeroninc.com>
Subject: Fwd: DRB meeting on Ped-Bridge
Good morning Giancarlo,
Please see below from Gatorbridge. Can you accommodate their request. Thank
you.
Sincerely,
Yandy Fuentes
Project Manager
Bergeron Land Development Inc.
19612 SW 69th Place
Fort Lauderdale, Florida 33332
Cell: (954) 658-6775
Phone: (954) 680-6100
Fax: (954) 680-0666
Website: www.bergeronlanddev.com
Email: yfuentes@bergeroninc.com
This message and any and all attachments are intended only for the recipients as
named above and may contain confidential,proprietary, and/or privileged
information. Unauthorized use, distribution, or reliance upon such information is
not allowed. If you have received this message by mistake,please contact the
sender and destroy all digital and hard copies.
Sent from my iPhone
Begin forwarded message:
From: Rick Cawston<rcawston@cmilc.com>
Date: October 4, 2018 at 8:35:00 AM EDT
To: Yandy Fuentes <yfuentes@bergeroninc.com>
Cc: Brian Thomason<bthomason@bergeroninc.com>, Daniel
Page 1083 of 1648
Veillette<dveillette@bergeroninc.com>
Subject: RE: DRB meeting on Ped-Bridge
Yandy,
Thanks for the update. It sounds like we may be inching closer to an
approved design.
Two quick things to help move this along.
1. Can you please have them note their comments on the
drawings to help ensure we make the proper revisions in the
correct places?
2. Can you confirm these are the final review comments from all
reviewers?
From there we can have our engineers review and complete the
changes.
Thanks, Rick
Rick Cawston
Director of Sales
GatorDock&GatorBridge
Direct:770-933-8148 Mobile:404-229-7589
qatordock.com I gatorbridge.com I cmilc.com
Marine Access Solutions \/ Prefabricated Aluminum Bridges
From:Yandy Fuentes<vfuentes@bergeroninc.com>
Sent:Wednesday, October 3, 2018 5:52 PM
To: Rick Cawston<rcawston@cmilc.com>
Cc: Brian Thomason<bthomason@bergeroninc.com>; Daniel Veillette
<dveillette@bergeroninc.com>
Subject: Fwd: DRB meeting on Ped-Bridge
Hi Rick,
Please see below comments from Giancarlo following yesterday's
DRB meeting.
Please call me tomorrow to discuss at your earliest convenience.
Thank you.
Page 1084 of 1648
Sincerely,
Yandy Fuentes
Project Manager
Bergeron Land Development Inc.
19612 SW 69th Place
Fort Lauderdale,Florida 33332
Cell: (954) 658-6775
Phone: (954) 680-6100
Fax: (954) 680-0666
Website: www.bergeronlanddev.com
Email: yfuentes@bergeroninc.com
This message and any and all attachments are intended only for
the recipients as named above and may contain confidential,
proprietary, and/or privileged information. Unauthorized use,
distribution, or reliance upon such information is not allowed. If
you have received this message by mistake,please contact the
sender and destroy all digital and hard copies.
Sent from my iPhone
Begin forwarded message:
From: "Pena, Giancarlo"
<GiancarloPena@miamibeachfl.gov>
Date: October 3, 2018 at 8:52:57 AM EDT
To: Yandy Fuentes <yfuentes@bergeroninc.com>
Cc: "Soto, Luis" <LuisSoto@miamibeachfl.gov>
Subject: RE: DRB meeting on Ped-Bridge
Yandy,
As per our conversation,the city received approval for
the bridge, but DRB requested that the panels to be
move in front of the frame and to integrate the panels
along the north ramp. Please let me know when can we
have a conference call to discuss.
Thank you,
AM1 E CH
Page 1085 of 1648
Giancarlo Pena, P.E.,CGC.,Civil engineer 111
PUBLIC WORKS DEPARTMENT
1700 Convention Center Drive,Miami Beach,FL 33139
Tel:305-673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028
/www.miamibeachfl.gov
We are committed to providing excellent public service and safety to all who
live,work and play in our vibrant,tropical,historic community.
ip,4 Before you print this email,consider the
negative environmental impacts associated with
printing.
From:Soto, Luis
Sent:Tuesday, October 02, 2018 9:44 PM
To: Pena, Giancarlo
<GiancarloPena@miamibeachfl.gov>
Cc:Yandy Fuentes<yfuentes@bergeroninc.com>
Subject: FW: DRB meeting on Ped-Bridge
Giancarlo, please request a cost proposal from
Bergeron.We may have to meet with Yandy specifics.
Thanks
From:Carpenter, Eric
Sent:Tuesday, October 02, 2018 1:21 PM
I was able to confirm that we did get DRB approval
conditioned on the modifications they requested. We
are reaching out to the Design/Builder today to request
a change order for the modifications so that can be
presented to Commission. Unfortunately I think we are
going to be too late for the October Commission
meeting but we will push to try to get the item on as
soon as possible.
Respectfully,
Eric T. Carpenter,P.E.
Assistant City Manager
MIAMIf EACH
1700 Convention Center Drive,Miami Beach,FL 33139
Tel:305-673-7080 / www.miamibeachfl.gov
We are committed to providing excellent public service and safety to all who
live,work and play in our vibrant,tropical,historic community.
Page 1086 of 1648
91791.10 L801. 068d
.4
, A
, ,
,
, 014
$ •I
I } 11 Pi .
I f i
I,
, 1 # . ;1
. .
0
,
#
0 • ..
, ' ,. , I
# •
• di # 0 1 ' I' Ii
# # , 1 . .Ai 1
.
v
Or / iiii1 il
40
I
'1 II f i
4 ' r
I, i1
11"
. ..„
' .0 I ,
, a
Irfir •
.11 1 III.
•., ' ,,
$ 0 1/ 01
A i I
I Al f #
F i
' • li 1
• , i I ,
I
11 i • l
# " . ,'
t
4
# If:
t
0 1 "
I . 1
. ,
. 11 •
#1 t
, .
...
• I°
) ,
II
I ,
11 it .
Ili j
i 1
/ r,
f II
r i
r --..- - -N--
i ' 1 - ,• -•,...
-. - ....
rif / r
i
r if ./
, :.
.. / . .,
.,._
.,
, ..„
I
1 r -,
KN. ----',-
-i . ,!.... ,,,•-_,,
i . s
r ,
# .
c , — _
..‘.._ A 4._.,,,,i*It ' I -
l-- y 1 v
f ner� —'� w.tl I• 1Et I 471 , 'I
1�n ,r i4ils whir i ier.111lP'°ka11111 ' 1
Y •I -III••I 1 ks:_41 fr r4iisd11i1'llitll�rl,iMRiiilr1a1114 o 11111x'. I1. I '.1
• t .,fi p t,k ail twi.ul,.t 71.„,„,„1U1Ur,7 SLjI W. ,:11j11e 11 r• I I
-r-. _ - ° ;II i ( •'l - e1tY1 '.1�d11,a tkl :r1iup°�4111tr11111{lu',111111w;,1jrlUlrtt'•°- Ir ll 1 .I II
'I.t '',I; 11, r 4jk' '.. Mk uifrgk W+rr r1111w'i itithrr:j111'!r•'n'lllk$lillpil,.'�r1111u,,°:iP11»+,..rii II1
(- , it I rnhk•'fir kxll+r 1111af°11111rr1°i 111,..'rtRI rtlii :i u+ltatr:riull 117;.:•S:yr_111+::•ii`:tiiNillii 1
r. ' 1,. ' i! itll l ;:i11U{' alvialu;
EXHIBIT C
From: Rick Cawston<rcawston@cmilc.com>
Sent: Tuesday, November 27, 2018 7:59 AM
To: Yandy Fuentes
Cc: Brian Thomason
Subject: RE: DRB meeting on Ped-Bridge
Yandy,
My ap logies but it took some time to get updated pricing on the larger panels. Below is a summary of
the proposed changes and associated costs.
Upgrade Panel Dimension to a 5'tall continuous on length of bridge- $16,000
Increase Truss Height by 1'with increased profile and wind load - $19,500
Add framing to support panels (previous design utilized existing truss)- $14,000
Engineering Redesign of Truss, panels,frames with review and analysis- $5,000
Total cost of requested changes- $54,500
This does not affect the cost of powder coating at this time, however we have been notified by our
powder coater of an increase effective January 1, 2019.
Given that the current design meets the spirit and intent of the rendering provided,along with the cost
of the design modifications, our recommendation would be to move forward with the current design
and take advantage of 2018 powder coating prices.
Please let us know how your client would like to proceed.
Thanks, Rick
From: I andy Fuentes<yfuentes@bergeroninc.com>
Sent:Wednesday, November 7, 2018 8:11 PM
To: Rick Cawston<rcawston@cmilc.com>
Cc: Marta Banister<MBanister@cmilc.com>;Tom Hauer<THauer@gatordock.com>; Brian Thomason
<bthorhason@bergeroninc.com>
Subject: Re: DRB meeting on Ped-Bridge
Thank you for the fast response.
Sincerely,
Yandy Fuentes
Project Manager
Bergeron Land Development Inc.
19612 SW 69th Place
Fort Lauderdale, Florida 33332
Cell: (954) 658-6775
Page 1089 of 1648
Phone. (954) 680-6100
Fax: (954) 680-0666
Website:www.bergeronlanddev.com
Email: fuentes@bergeroninc.com
This message and any and all attachments are intended only for the recipients as named above and may
contain confidential,proprietary, and/or privileged information. Unauthorized use, distribution, or
reliance upon such information is not allowed. If you have received this message by mistake,please
contact the sender and destroy all digital and hard copies.
Sent fr m my iPhone
On Nov 7, 2018, at 7:30 PM, Rick Cawston<rcawston@cmilc.com>wrote:
We can do grey as a custom color for the $32,500 quoted. Standard colors are black,
white, brown,green and blue are the standard colors that can be done for$26,000.
Either option would include powder coating the entire bridge structure (excluding
decking) but including the panels.
•