Resolution 2019-30684 RESOLUTION Na 2019-30684 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO THE AGREEMENT BETWEEN THE CITY AND BERGERON LAND DEVELOPMENT INC. FOR DESIGN BUILD SERVICES FOR THE WEST AVENUE BRIDGE AND PEDESTRIAN BRIDGE OVER COLLINS CANAL (RFP NO. 2016-062-KB) (THE 'AGREEMENT"), WITH SUCH CHANGE ORDER NO. 1 IN THE NOT-TO - EXCEED AMOUNT OF $355,142.04, PLUS A 10% OWNER'S CONTINGENCY IN THE AMOUNT OF $35,514.20, TO PROVIDE FOR ACCESSIBILITY IMPROVEMENTS AND ADDITIONAL ENHANCEMENTS TO THE AESTHETICS OF THE PEDESTRIAN BRIDGE, INCLUDING ARCHITECTURAL PANELS, RAMPS AND STEPS, TO BE FUNDED WITH $330,000 IN PREVIOUSLY APPROPRIATED FUNDS, AND SUBJECT TO A CAPITAL BUDGET AMENDMENT FOR THE$60,657 REMAINING BALANCE REQUIRED TO FUND CHANGE ORDER NO. 1. WHEREAS, on April 27, 2016, the City Commission awarded the contract for design build service for the West Avenue Bridge and Pedestrian Bridge over Collins Canal Project (RFP No. 2016-062-KB) ("the Project") to Bergeron Land Development Inc., in the amount of $9,930,000; and yVHEREAS, the scope of work for the Project included street lighting, pedestrian lighting, signage and pavement markings, new vehicular and pedestrian signals on Dade Boulevard and West Avenue, utility relocation and/or adjustments, and drainage; and WHEREAS, after several meetings, members of the community requested that the overall aesthetics of the pedestrian bridge be enhanced. The enhancements included aluminum paneling, powder coating, and LED lighting; and WHEREAS, on January 17, 2018, the Mayor and City Commission approved a capital budget amendment that included for$440,000 to the Project, from which $350,000 was allocated for the requested aesthetic improvements of architectural panels, powder coating and decorative lighting for an enclosed aluminum pedestrian bridge, and $90,000.00 was allocated for landscape enhancements along Dade Boulevard; and WHEREAS, on February 14, 2018, the Mayor and City Commission rejected a proposed change order with respect to the pedestrian bridge enhancements, and instead directed City staff to design a simple truss bridge, and the Planning Director noted that a simple bridge like the one over the Indian Creek Waterway(which is a sidewalk with handrails)would most likely not have to go to the Design Review Board ("DRB") unless the City Commission directed staff to obtain approval from the DRB; and WHEREAS, on February 14, 2018, the City Commission also requested that the Sunset Harbour and WAVNA associations be afforded the opportunity to provide input before a final design is approved; and IVHEREAS, on May 3, 2018, the City conducted a public meeting for the Project, with the participation of Public Works staff and Commissioner Mark Samuelian, to to present residents with five (5) pedestrian bridge renderings showing the aesthetic options for the proposed bridge; and WHEREAS, Option 4A, a "Venetian Bubble" architectural side panel, had the most votes and was the aesthetic option selected. City staff explained that if the cost of Option 4A exceeded the funds previously approved by the City Commission, the request for additional funds would require City Commission approval; and WHEREAS, on October 2, 2018, the DRB approved the proposed decorative "Venetian Bubble",panels for the pedestrian bridge,with the recommendation that the panel design be further refined and more articulately coordinated with the structural truss system of the bridge; and WHEREAS, the method of installation of the "Venetian Bubble" panels would be further developied and would be installed on the outside of the bridge support systems. Further, the panels would extend along the ramping and approach walkways, subject to City approval; WHEREAS, the Design-Builder for the Project, Bergeron Land Development, Inc., has submitted a cost proposal to implement the foregoing enhancements, including costs for the re- design fees, powder coated panels and changes to the ramps; and WHEREAS, City staff has reviewed the cost proposal and finds it to be fair and reasonable, and is (therefore requesting approval of Change Order No. 1, in the maximum amount of $355,142.04, plus a 10% Owner's Contingency in the amount of$35,514.20, to permit final design and fabrication of the bridge to commence as soon as possible; and WHEREAS, of the $440,000 previously appropriated on January 17, 2018 for enhancements and landscaping for the Project, $110,000 has been spent on landscaping; accordingly, Change Order No. 1 would be funded with $330,000 in previously appropriated funds, and shall be subject to a capital budget amendment in the amount of $60,657 for the remaining balance required to fund Change Order No. 1. NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission hereby 'approve and authorize the Mayor and City Clerk to execute Change Order No. 1 to the Agreement between the City and Bergeron Land Development Inc. for Design Build Services for the West Avenue Bridge and Pedestrian Bridge Over Collins Canal (RFP No. 2016-062-KB), with such Change Order No. 1 in the not to exceed amount of $355,142.04, plus a 10% Owner's Contingency in the amount of$35,514.20, to provide for accessibility improvements and additional enhancements to the aesthetics of the pedestrian bridge, including architectural panels, ramps and steps, to be funded with$330,000 in previously appropriated funds, and subject to a Capital Budget Amendment for the $60,657 remaining balance required to fund Change Order No. 1. PASSED and ADOPTED this 16th day of January, 201 ATTEST: /,a4f "' � A tan Gelber, r or a"i ilk %'\ .. • Rafael E. Granado, Oity , Le .:,, ,F j'.- . , APPROVED AS TO FORM&LANGUAGE ..�a ' &FOR EXECUTION ° .INCORP ORATED: 0 2-< '‘` oft-t_Ogv; f if(((i CRY AttomeY (e0c) Date o Agenda Item RrI F Date 1—I6-II i\A o ! BEACH City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov COM ISSION MEMORANDUM J TO: Honorable Mayor and Members of the City Com ission FROM: Jimmy L. Morales, City Manager 1' DATE: January 16, 2019 SUBJECT: A RESOLUTION OF THE MAYO- AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO THE AGREEMENT BETWEEN THE CITY AND BERGERON LAND DEVELOPMENT INC. FOR DESIGN BUILD SERVICES FOR THE WEST AVENUE BRIDGE AND PEDESTRIAN BRIDGE OVER COLLINS CANAL (RFP NO. 2016-062-KB) (THE "AGREEMENT"), WITH SUCH CHANGE ORDER NO. 1 IN THE NOT-TO - EXCEED AMOUNT OF $355,142.04, PLUS A 10% OWNER'S CONTINGENCY IN THE AMOUNT OF $35,514.20, TO PROVIDE FOR ACCESSIBILITY IMPROVEMENTS AND ADDITIONAL ENHANCEMENTS TO THE AESTHETICS OF THE PEDESTRIAN BRIDGE, INCLUDING ARCHITECTURAL PANELS, RAMPS AND STEPS, TO BE FUNDED WITH $330,000 IN PREVIOUSLY APPROPRIATED FUNDS, AND SUBJECT TO A CAPITAL BUDGET AMENDMENT FOR THE $60,657 REMAINING BALANCE REQUIRED TO FUND CHANGE ORDER NO. 1. RECOMMENDATION The Administration recommends that the Mayor and City Commission of the City of Miami Beach, Florida accept the recommendation of the City Manager to authorize Change Order No. 1, to expand the scope of the current Contract for Design Build Services for the West Avenue Bridge and Pedestrian Bridge over Collins Canal (RFP No. 2016-062-KB) to Bergeron Land Development Inc., in the maximum amount of $355,142.04 plus a 10% owner contingency in the amount of$35,514.20. i BACKGROUND On April 27, 2016, the City Commission awarded the contract for design build services for the West Avenue Bridge and Pedestrian Bridge over Collins Canal (RFP No. 2016-062-KB) to Bergeron Land Development Inc, in the amount of $9,930,000. The scope of work also included street lighting, pedestrian lighting, signage and pavement markings, new vehicular and pedestrian signals on Dade Boulevard and West Avenue, utility relocation and/or adjustments, and drainage. After several meetings, members of the community requested that the overall aesthetics of the pedestrian bridge be lenhanced. The enhancements included aluminum paneling, powder coating, and LED lighting. On January 17, 2018, a capital budget amendment was approved and included an item for $440,000 to the project from which $350,000 was allocated for the requested aesthetic improvements of architectural panels, powder coating and decorative lighting for an enclosed aluminum pedestrian bridge. At the same time, a total of$90,000.00 was allocated for landscape enhancements along Dade Boulevard using City's inhouse farces as a cost savings measure. On February 14, 2018, Change Order No. 1 was presented to the Commission for approval. The Commission made a motion to reject the change order and instead instructed City staff to design a simple truss bridge. It was requested that the Sunset Harbor and WAvNA associations' input be taken into consideration before a final design was placed into production. Thomas Mooney, Planning Department Director stated that a simple bridge like the one over the Indian Creek Waterway (which is a sidewalk with handrails) would most likely not have to go to the Design Review Board (DRB) unless the City Commission directed staff to get approved from DRB. On May 3,; 2018, the City conducted a public meeting for the West Avenue Bridge Project. Participants included Public Works staff and Commissioner Mark Samuelian. The purpose of the meeting was to present residents with five (5) pedestrian bridge renderings showing the aesthetic options for the bridge. Option 4A; a bubble architectural side panel had the most votes and was the aesthetic option selected. City staff explained that if Option 4A exceeded the funds the Commission had previously approved, the request would need to go back to Commission for a change order. On October 2, 2018, City staff presented the Pedestrian Bridge's decorative 'venetian bubble' panels to the DRB, where the Board approved the bridge plans with the recommendation that the panel design shall be further refined and more articulately coordinated with the structural truss system of the bridge. The method of installation of the "Venetian Bubble" panels shall be further developed and installed on the outside of.the bridge support systems. Further, the panels shall extend along the ramping and approach walkways, in a manner to be reviewed and approved by staff consistent with the Design Review Criteria and/or the'directions from the Board. Currently, ithe cost proposal for the re-design fees, powder coated panels and changes to the ramps has been provided by the contractor. City staff is requesting the Commission to authorize the Mayor and City Clerk to execute a Change Order No. 1 in the maximum amount of $355,142.04 plus a 10% owner contingency in the amount of $35,514.20. Approval is being requested at this time so final design and fabrication of the bridge can commence as soon as possible. Since the capital budget was approved approximately one year ago, $110,000 has been spent on landscaping which is now complete. That leaves $330,000 available for this change order. $60,656.24 will be needed in a future capital budget amendment to fund this work CONCLUSION The Administration recommends that the Mayor and City Commission of the City of Miami Beach, Florida accept the recommendation of the City Manager to authorize Change Order No. 1, to expand the scope of the current Contract for Design Build Services for the West Avenue Bridge and Pedestrian Bridge over Collins Canal (RFP No. 2016-062-KB) to Bergeron Land Development Inc., in the maximum amount of $355,142.04 plus a 10% owner contingency in the amount of$35,514.20. JLM/ / RWC/JJF/NNN Legislative Tracking Public Works ATTACHMENTS: Description ❑ 645 Lincoln Ct Pedestrian Ramps Proposal - REVISED 1-3-19 (2) ❑ DRAFT Reso Page 1075 of 1648 1 _.... t n) ---,,\\ !,:' : {ir )/ ,,r-s) �' I , IC < I f J " 1 ! ._,) ,__LA.L. „ ,-:,..,_. , J_L_A.L__ \:). ,.._,..,, ,,, \i, LAND DEVELOPMENT, INC. January 3rd, 2019 ATTN: Luis Soto, P.E., Sent Via: Email City Engineer LuisSoto@miamibeachfl.gov City of Miami Beach, Public Works Department Re: West Ave Bridge Project& Dade Reconstruction, Miami Beach BLD Job No. 645 Change Order: Pedestrian Bridge&Lincoln Ct Access Ramps-FINAL Dear Mr. Soto, Per our conference call on December 21st and further discussions which followed, please refer to the REVISED proposal on page 2 for the services requested, and page 3 for General Notes and Exclusions. I Sincerely BERGERON LAND DEVELOPMENT,INC. Yandy Fuentes Project Manager Attachments: Exhibits A, B, &C. cc: Brian Thomason, Daniel Irion, Giancarlo Pena, Eric Carpenter Bergeron Land Development Inc. 19612 SW 69th Place Ft.Lauderdale,FL 33332 Phone: (9541 680-6100 Page 1076 of 1648 2 Description Quantity UoM Unit Price Total Gatorbridge-additional work Powder Coating-Grey 1 LS $32,500.00 $32,500.00 Panels& Engineering Design (additional panels& 1 LS $54,500.00 $54,500.00 design, review&stamping fees) Ballarena-south ramp Mobilization 1 LS $5,000.00 $5,000.00 M.O.T. (device&installation), exclude drawings& 1 LS $1,500.00 $1,500.00 permits Clearing& Grubbing 1 LS $2,800.00 $2,800.00 Embankment(backfill on ramps) 1 LS $3,500.00 $3,500.00 Concrete Glass NS, Gravity Wall 187 LF $240.00 $44,880.00 4"Sidewalks 68 SY $45.00 $3,060.00 Type F-Cub Gutter 53 LF $44.64 $2,366.04 Manhole Adjustment 1 EA $3,500.00 $3,500.00 Inlet P-9 2 EA $7,500.00 $15,000.00 Pipe Culvert, HDPE Material, Round, 18"S/CD 54.00 LF $180.00 $9,720.00 Grass Area(exclude irrigation), including 4"top soil- 100 SY $25.00 $2,500.00 minimum of 100 SY Moz Designs. Inc. LaserCut Bubbles Dbl Sided No grain Grey Powder Coat `- 30 EA $960.00 $28,800.00 Crating&Handling 1 LS $575.00 $575.00 Ground SOpping-Standard Delivery to 33139 1 LS $1,500.00 $1,500.00 Keith&Schnars-design Lincoln Ct Access Ramps Redesign Fees 1 LS $26,780.00 $26,780.00 Bergeron Land Development Unforeseen Conditions(i.e.harmonization, ramp 1 LS $60,000.00 $60,000.00 panels we,ding, QC,pavement markings) Mobilization&Demobilization 1 LS $22,567.00 $22,567.00 Panels& Engineering Design (Original Design before 1 L5 $47,433.00 $47,433.00 DRB Meeting) Original Pedestrian Bridge PrecastArCh Fascia Deduct 1 LS -$70,000.00 -$70,000.00 Giralt Enterprises Aluminum,Handrail-Index 862 208.43 LF $49.60 $10,338.13 Subtotal: $308,819.17 Bergeron 15%M/U: $46,322.88 Total: $355,142.04 Bergeron Land Development Inc. 19612 SW 69th Place Ft.Lauderdale,FL 33332 Phone: (9541 680-6100 Page 1077 of 1648 3 General Notes: *Gatorbridge pricing is based on latest round of comments made by DRB as communicated by the city on 10/11/18.Exhibit B and detailed in Exhibit C. *This proposal�Jdoes not include lighting for the Pedestrian Bridge or Access Ramps due to insufficient information at the time of submittal.PVo plans or details. *Laser cut panels are produced to size and cannot be cut once produced. *Lead time for panels are 4-6 weeks plus transit time Excluded: Permits Bergeron Land Development Inc. 19612 SW 69th Place Ft.Lauderdale,FL 33332 Phone: (9541 680-6100 Page 1078 of 1648 EXHIBIT A B-B A 9 9. A-A i q cz '''' ® 9 n A, ®9E.9E.zE.++9 6 B, 9113,.nE�x, 6.6 46 aE E5 9e.E L9. NaAXb E eE GSE 51,9SEAWALL IxtEr rre nos slmT moulillEo R+n Et.s3o waxkr. ecX sos son [OLEINS CANAL 1e PIPE ...-- — - _ ex° rxl _ , / XlaNl ecX NI rsv)-z as eaP EL 19 ..__-..- .. _ _ - 1 Eae EL r9 IA I ISE)sas Ix +3�5 w, - . IxvEA!(NE)-1.15 ExIST.INVERT(51 3.a6 •Exlsi IrvvENr lxl-1 a5_ • BEGINrvwat rip:IxDAalti ..,...-*LI YXax wag CROSS SECTION A-A IAGR Pirmuros F� \YIN/LINE • N r U Xaxoxal WI camEt.T.sT t.3.90 ik XAMIAIL LANDING N El..;00. EXIST.EOP Mg.. / 'j=gam .5. /TOIPENaIM (TYPICu�t, D I Mg.. ,1,50 —KZ cOli6177 I/ if El.ibOpr+\/ Et. Et el9 V //` NAY Ix/ ,w uxE�% 660 l/rv,wt oi'"""" \IeterrPE Ig---,1 ! �EAV`OSAIL //// ,z 1, 96 fig LANDING eE� LANDING T, / as /`% t.19 I`O,�\W .19 Ic Pl II 2 99.s lal EL.r• eulLDrx ��� � \� .td'LWI►.. ` � t.I,E Et.I.TE / I` ." - ,..111 ;Lf �EGAxsGGT,EA Et LEE T� ,I� • \� Las 3',s, x� o 0 174 ►E:r3r 07,ir ' I EL 9la e MIN • EXIST.EGPED. ,5 Pr A'.-,I Ira ?AVM MA) ,� rA Dta xtv0.EExrRIN 0E IM 7 CROSS SECTION B-B 6-29-I8®NEW ACCESS RASP DETAIL SHEET 1 o3 0 j.. ENGINEER OF RECORD ®M I AMI REACH �� " = ENGINEER OF RECORD: 5- File name XXXXXXXXXXXXXXXXXXXXXXXXXX CRY MANAGER: JIMMY L.HOYCOLEY LES DESIGNER ENGINEER: A RLMetl Plan L•yaatEp DIRECTOR: ROY COLEY ESSWN BY: 9 • FIeIE Book:N/A Page: .JILL Job Oder: N/A ® TffLE: CITY ENGINEER: LUIS SOTO,RE. CHECKER: Dare 1 8/2018 PUBLIC WORKS DEPARTMEN XXXXXXXXXXXXXXXXXXXXXXXXXX ) ..,„,�.....,,,,n„n..,..,n.M,..,......,..,..,, - _.__ --._._.. o DreNrO& EXHIBIT B From: Pena, Giancarlo <GiancarloPena@miamibeachfl.gov> Sent: Thursday, October 11, 2018 3:56 PM To: Yandy Fuentes Cc: Soto, Luis; Brian Thomason; Daniel Veillette Subject: RE: DRB meeting on Ped-Bridge Attachments: A0029_N3-1.jpg; maximus2-1.jpg; Panels.pdf Yandy, Below Please find recommendation from the design review board. The method of installation of the "Venetian Bubble" panels shall be further developed and installed on the ouiside of the bridge support systems. Further,the panels shall extend along the ramping and approach walkways. Attached please find exhibit. Thank Jou, MIAM . 1,7 E Ac Giancarlo Pena, P.E., CGC.,Civil engineer III PUBLIC1WORKS DEPARTMENT 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:305;673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community. Before you print this email,consider the negative environmental impacts associated with printing. • From: Pena, Giancarlo Sent:\Vednesday, October 10, 2018 3:40 PM To: 'Yacndy Fuentes'<yfuentes@bergeroninc.com> Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason <bthomason@bergeroninc.com>; Daniel Veillette<dveillette@bergeroninc.com> Subject: RE: DRB meeting on Ped-Bridge Ok Thank you M1AMEACH Giancarlo Pena, P.E., CGC.,Civil engineer Ill PUBLIC WORKS DEPARTMENT 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:3051673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov Page 1080 of 1648 We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community. 4 Before you print this email,consider the negative environmental impacts associated with printing. From:Pandy Fuentes<yfuentes@bergeroninc.com> Sent:Wednesday, October 10, 2018 3:38 PM To: Pena, Giancarlo<GiancarloPena@miamibeachfl.gov> Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason<bthomason@bergeroninc.com>; Daniel Veillette<dveillette@bergeroninc.com> Subject: Re: DRB meeting on Ped-Bridge Giancarlo, It looks like Rick is out of the office until next week. I would recommend to work on the recommendations by the DRB and if Gatorbridge has any questions, we could coordinate a conference call. Sincerely, Yandy Fuentes Project Manager Bergeron Land Development Inc. 19612 SW 69th Place Fort Lauderdale, Florida 33332 Cell: (954) 658-6775 Phone: (954) 680-6100 Fax: (954) 680-0666 Website: www.bergeronlanddev.com Email: yfuentes@bergeroninc.com This message and any and all attachments are intended only for the recipients as named above and may contain confidential,proprietary, and/or privileged information. Unauthorized use, distribution, or reliance upon such information is not allowed. If you have received this message by mistake,please contact the sender and destroy all digital and hard copies. Sent from my iPhone On Oct 10, 2018, at 3:18 PM, Pena, Giancarlo <GiancarloPena@miamibeachfl.gov>wrote: Yandy, I am working on getting all the required information, but can we schedule a conference call for tomorrow 11:00 AM or Friday at 10:00 AM. Thank you, Page 1081 of 1648 MIAMBEACH Giancarlo Pena,P.E., CGC.,Civil engineer Ill PUBLIC WORKS DEPARTMENT 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:305-673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028/www.miamibeachfl.gov We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical, historic community. Before you print this email,consider the negative environmental impacts associated with printing. From:Yandy Fuentes<yfuentes@bergeroninc.com> Sent:Wednesday, October 10, 2018 1:03 PM To: Pena, Giancarlo<GiancarloPena@miamibeachfl.gov> Cc:Soto, Luis<LuisSoto@miamibeachfl.gov>; Brian Thomason <bthomason@bergeroninc.com>; Daniel Veillette<dveillette@bergeroninc.com> Subject: RE: DRB meeting on Ped-Bridge Hi Giancarlo, Any update on the request below? Sincerely, Yandy y Fae wte4 Project Manager Bergeron Land Development Inc. 19612 SW 69th Place Fort Lauderdale, Florida 33332 ell: (954) 658-6775 Phone: (954) 680-6100 Fax: (954) 680-0666 Website: www.bergeronlanddev.com Email: yfuentes(abergeroninc.com y y"*�t t i -,�.) r['�, c14}�9 1. i�s .t4 LAND i)rVEL'M N1_i:NC_ f?k \\4. EA ,:, t ) BERGRO Aso ,- .„. ,, 204 - <image006.jpg> Page 1082 of 1648 This message and any and all attachments are intended only for the recipients as named above and may contain confidential,proprietary, and/or privileged information. Unauthorized use, distribution, or reliance upon such information is not allowed. If you have received this message by mistake,please contact the sender and destroy all digital and hard copies. From:Yandy Fuentes Sent:Thursday, October 4, 2018 8:58 AM To:Giancarlo (Inspector) Pena<GiancarloPena@miamibeachfl.gov> Cc: LuisSoto@miamibeachfl.gov; Brian Thomason<bthomason@bergeroninc.com>; Daniel Veillette<dveillette@bergeroninc.com> Subject: Fwd: DRB meeting on Ped-Bridge Good morning Giancarlo, Please see below from Gatorbridge. Can you accommodate their request. Thank you. Sincerely, Yandy Fuentes Project Manager Bergeron Land Development Inc. 19612 SW 69th Place Fort Lauderdale, Florida 33332 Cell: (954) 658-6775 Phone: (954) 680-6100 Fax: (954) 680-0666 Website: www.bergeronlanddev.com Email: yfuentes@bergeroninc.com This message and any and all attachments are intended only for the recipients as named above and may contain confidential,proprietary, and/or privileged information. Unauthorized use, distribution, or reliance upon such information is not allowed. If you have received this message by mistake,please contact the sender and destroy all digital and hard copies. Sent from my iPhone Begin forwarded message: From: Rick Cawston<rcawston@cmilc.com> Date: October 4, 2018 at 8:35:00 AM EDT To: Yandy Fuentes <yfuentes@bergeroninc.com> Cc: Brian Thomason<bthomason@bergeroninc.com>, Daniel Page 1083 of 1648 Veillette<dveillette@bergeroninc.com> Subject: RE: DRB meeting on Ped-Bridge Yandy, Thanks for the update. It sounds like we may be inching closer to an approved design. Two quick things to help move this along. 1. Can you please have them note their comments on the drawings to help ensure we make the proper revisions in the correct places? 2. Can you confirm these are the final review comments from all reviewers? From there we can have our engineers review and complete the changes. Thanks, Rick Rick Cawston Director of Sales GatorDock&GatorBridge Direct:770-933-8148 Mobile:404-229-7589 qatordock.com I gatorbridge.com I cmilc.com Marine Access Solutions \/ Prefabricated Aluminum Bridges From:Yandy Fuentes<vfuentes@bergeroninc.com> Sent:Wednesday, October 3, 2018 5:52 PM To: Rick Cawston<rcawston@cmilc.com> Cc: Brian Thomason<bthomason@bergeroninc.com>; Daniel Veillette <dveillette@bergeroninc.com> Subject: Fwd: DRB meeting on Ped-Bridge Hi Rick, Please see below comments from Giancarlo following yesterday's DRB meeting. Please call me tomorrow to discuss at your earliest convenience. Thank you. Page 1084 of 1648 Sincerely, Yandy Fuentes Project Manager Bergeron Land Development Inc. 19612 SW 69th Place Fort Lauderdale,Florida 33332 Cell: (954) 658-6775 Phone: (954) 680-6100 Fax: (954) 680-0666 Website: www.bergeronlanddev.com Email: yfuentes@bergeroninc.com This message and any and all attachments are intended only for the recipients as named above and may contain confidential, proprietary, and/or privileged information. Unauthorized use, distribution, or reliance upon such information is not allowed. If you have received this message by mistake,please contact the sender and destroy all digital and hard copies. Sent from my iPhone Begin forwarded message: From: "Pena, Giancarlo" <GiancarloPena@miamibeachfl.gov> Date: October 3, 2018 at 8:52:57 AM EDT To: Yandy Fuentes <yfuentes@bergeroninc.com> Cc: "Soto, Luis" <LuisSoto@miamibeachfl.gov> Subject: RE: DRB meeting on Ped-Bridge Yandy, As per our conversation,the city received approval for the bridge, but DRB requested that the panels to be move in front of the frame and to integrate the panels along the north ramp. Please let me know when can we have a conference call to discuss. Thank you, AM1 E CH Page 1085 of 1648 Giancarlo Pena, P.E.,CGC.,Civil engineer 111 PUBLIC WORKS DEPARTMENT 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:305-673-7000 x6343/Cell:305-546-2943 Fax:305-673-7028 /www.miamibeachfl.gov We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community. ip,4 Before you print this email,consider the negative environmental impacts associated with printing. From:Soto, Luis Sent:Tuesday, October 02, 2018 9:44 PM To: Pena, Giancarlo <GiancarloPena@miamibeachfl.gov> Cc:Yandy Fuentes<yfuentes@bergeroninc.com> Subject: FW: DRB meeting on Ped-Bridge Giancarlo, please request a cost proposal from Bergeron.We may have to meet with Yandy specifics. Thanks From:Carpenter, Eric Sent:Tuesday, October 02, 2018 1:21 PM I was able to confirm that we did get DRB approval conditioned on the modifications they requested. We are reaching out to the Design/Builder today to request a change order for the modifications so that can be presented to Commission. Unfortunately I think we are going to be too late for the October Commission meeting but we will push to try to get the item on as soon as possible. Respectfully, Eric T. Carpenter,P.E. Assistant City Manager MIAMIf EACH 1700 Convention Center Drive,Miami Beach,FL 33139 Tel:305-673-7080 / www.miamibeachfl.gov We are committed to providing excellent public service and safety to all who live,work and play in our vibrant,tropical,historic community. Page 1086 of 1648 91791.10 L801. 068d .4 , A , , , , 014 $ •I I } 11 Pi . I f i I, , 1 # . ;1 . . 0 , # 0 • .. , ' ,. , I # • • di # 0 1 ' I' Ii # # , 1 . .Ai 1 . v Or / iiii1 il 40 I '1 II f i 4 ' r I, i1 11" . ..„ ' .0 I , , a Irfir • .11 1 III. •., ' ,, $ 0 1/ 01 A i I I Al f # F i ' • li 1 • , i I , I 11 i • l # " . ,' t 4 # If: t 0 1 " I . 1 . , . 11 • #1 t , . ... • I° ) , II I , 11 it . Ili j i 1 / r, f II r i r --..- - -N-- i ' 1 - ,• -•,... -. - .... rif / r i r if ./ , :. .. / . ., .,._ ., , ..„ I 1 r -, KN. ----',- -i . ,!.... ,,,•-_,, i . s r , # . c , — _ ..‘.._ A 4._.,,,,i*It ' I - l-- y 1 v f ner� —'� w.tl I• 1Et I 471 , 'I 1�n ,r i4ils whir i ier.111lP'°ka11111 ' 1 Y •I -III••I 1 ks:_41 fr r4iisd11i1'llitll�rl,iMRiiilr1a1114 o 11111x'. I1. I '.1 • t .,fi p t,k ail twi.ul,.t 71.„,„,„1U1Ur,7 SLjI W. ,:11j11e 11 r• I I -r-. _ - ° ;II i ( •'l - e1tY1 '.1�d11,a tkl :r1iup°�4111tr11111{lu',111111w;,1jrlUlrtt'•°- Ir ll 1 .I II 'I.t '',I; 11, r 4jk' '.. Mk uifrgk W+rr r1111w'i itithrr:j111'!r•'n'lllk$lillpil,.'�r1111u,,°:iP11»+,..rii II1 (- , it I rnhk•'fir kxll+r 1111af°11111rr1°i 111,..'rtRI rtlii :i u+ltatr:riull 117;.:•S:yr_111+::•ii`:tiiNillii 1 r. ' 1,. ' i! itll l ;:i11U{' alvialu; EXHIBIT C From: Rick Cawston<rcawston@cmilc.com> Sent: Tuesday, November 27, 2018 7:59 AM To: Yandy Fuentes Cc: Brian Thomason Subject: RE: DRB meeting on Ped-Bridge Yandy, My ap logies but it took some time to get updated pricing on the larger panels. Below is a summary of the proposed changes and associated costs. Upgrade Panel Dimension to a 5'tall continuous on length of bridge- $16,000 Increase Truss Height by 1'with increased profile and wind load - $19,500 Add framing to support panels (previous design utilized existing truss)- $14,000 Engineering Redesign of Truss, panels,frames with review and analysis- $5,000 Total cost of requested changes- $54,500 This does not affect the cost of powder coating at this time, however we have been notified by our powder coater of an increase effective January 1, 2019. Given that the current design meets the spirit and intent of the rendering provided,along with the cost of the design modifications, our recommendation would be to move forward with the current design and take advantage of 2018 powder coating prices. Please let us know how your client would like to proceed. Thanks, Rick From: I andy Fuentes<yfuentes@bergeroninc.com> Sent:Wednesday, November 7, 2018 8:11 PM To: Rick Cawston<rcawston@cmilc.com> Cc: Marta Banister<MBanister@cmilc.com>;Tom Hauer<THauer@gatordock.com>; Brian Thomason <bthorhason@bergeroninc.com> Subject: Re: DRB meeting on Ped-Bridge Thank you for the fast response. Sincerely, Yandy Fuentes Project Manager Bergeron Land Development Inc. 19612 SW 69th Place Fort Lauderdale, Florida 33332 Cell: (954) 658-6775 Page 1089 of 1648 Phone. (954) 680-6100 Fax: (954) 680-0666 Website:www.bergeronlanddev.com Email: fuentes@bergeroninc.com This message and any and all attachments are intended only for the recipients as named above and may contain confidential,proprietary, and/or privileged information. Unauthorized use, distribution, or reliance upon such information is not allowed. If you have received this message by mistake,please contact the sender and destroy all digital and hard copies. Sent fr m my iPhone On Nov 7, 2018, at 7:30 PM, Rick Cawston<rcawston@cmilc.com>wrote: We can do grey as a custom color for the $32,500 quoted. Standard colors are black, white, brown,green and blue are the standard colors that can be done for$26,000. Either option would include powder coating the entire bridge structure (excluding decking) but including the panels. • Page 1090 of 1648