Resolution 77-15510 RESOLUTION NO. 77-15510
A RESOLUTION OF THE CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, APPROVING AND AGREEING,
IN PRINCIPLE, A PROGRAM FOR THE DESIGN AND CON-
STRUCTION OF WATER SUPPLY FACILITIES TO MEET
REQUIREMENTS OF THE MUNICIPALITIES OF THE VILLAGE
OF BAL HARBOUR AND TOWN OF BAY HARBOR ISLANDS AND
AUTHORIZING THE CITY MANAGER TO EMPLOY POST,
BUCKLEY, SCHUH & JERNIGAN, INC. AS CONSULTING
ENGINEERS AND PLANNERS FOR SAID PROPOSED PROJECT
AND THE PREPARATION OF AN APPROPRIATE AGREEMENT
BETWEEN THE CITY OF MIAMI BEACH AND SAID MUNIC-
IPALITIES, INCLUDING A RATE ARBITRATION CLAUSE
THEREIN AND ADVISING MIAMI-DADE WATER AND SEWER
AUTHORITY OF THE PURPOSE AND INTENT OF THE CITY
COMMISSION OF THE CITY OF MIAMI BEACH TO ACCOM-
PLISH THE FOREGOING.
WHEREAS, the municipalities of the Village of Bal Harbour
and the Town of Bay Harbor Islands desire and require further and
additional water pressures and supplies within their corporate
limits to meet the present and future needs of their citizens and
residents, and
WHEREAS, representatives of said municipalities and of
the City of Miami Beach have appeared before the Miami-Dade Water
and Sewer Authority on a number of occasions for the purpose of
addressing and determining the most feasible solution, from a
practical and legal standpoint, of the problems involved, and
WHEREAS, the said Authority has recommended that the
City of Miami Beach and the Village of Bal Harbour and the Town of
Bay Harbor Islands evolve and thereafter implement an appropriate
plan for meeting the water requirements of the Village of Bal
Harbour and the Town of Bay Harbor Islands, and
WHEREAS, said Authority has requested that the City Com-
mission of the City of Miami Beach formally express good faith
assurances that the City of Miami Beach will design and construct
such additional facilities and additions to the existing City of
Miami Beach water system to meet the needs of said municipalities
and to prepare an appropriate agreement, including a rate structure
to be set forth therein with suitable provisions for arbitration
in the event of differences of interpretation thereof, between
said municipalities, with all reasonable speed and dispatch, and
WHEREAS, the City Manager has presented to the City Com-
mission his Memorandum No. 6642 dated December 21, 1977, the
contents whereof being familiar to the City Commission of the City
of Miami Beach;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, that said Commission Memorandum
No. 6642 be and the same is hereby expressly incorporated herein
by reference; that the City Commission of the City of Miami Beach
does hereby approve, ratify and confirm the contents thereof;
BE IT FURTHER RESOLVED BY THE CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, that the City Manager of the City of
Miami Beach be and he is hereby authorized and directed to execute
and implement the purposes and content of said Commission Memoran-
dum No. 6642;
OFFICE OF THE CITY ATTORNEY-1700 CONVENTION CENTER DRIVE-MIAMI BEACH,FLORIDA 33139
BE IT FURTHER RESOLVED BY THE CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, that certified copies of this
Resolution be transmitted forthwith to the Miami-Dade Water and
Sewer Authority, the Village of Bal Harbour and the Town of Bay
Harbor Islands;
BE IT FURTHER RESOLVED BY THE CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, that the City Manager be and he is
hereby authorized and directed to submit, with all convenient
speed, to the City Commission of the City of Miami Beach appro-
priate summaries of progress in the implementation hereof; it
being the desire, purpose and intention of the City Commission of
the City of Miami Beach that interim and final approval of plans,
specifications and contract documents be procured from said City
Commission in compliance with all requirements of law.
PASSED and ADOPTED this 21st day of December, 1977 .
•
K(I�
Mayor
Attest:
City Clerk
- 2
OFFICE OF THE CITY ATTORNEY- 1700 CONVENTION CENTER DRIVE-MIAMI BEACH,FLORIDA 33139
FLORIDA 3 3139
"VACAT/ONLAND U. S. A.-
OFFICE
."OFFICE OF THE CITY MANAGER
D.A.SOUTHERN CITY HALL
CITY MANAGER 1700 CONVENTION CENTER DRIVE
COMMISSION MEMORANDUM NO. 6642 TELEPHONE: 673.7010
DATE: December 21, 1977
TO: Mayor Leonard Haber, Ph.D. , and
Members of the City Commission
FROM: D. A. Southern
City Manager
SUBJECT:' INCREASED WATER SUPPLY FOR BAL HARBOUR
AND BAY HARBOR ISLANDS
The City of Miami Beach has for many years supplied water to
the Village of Bal Harbour through a master water meter
located at 87th Street, and through their jointly owned water
transmission system, Bal Harbour has supplied water to the
Town of Bay Harbor Islands. In addition, these municipalities
have been purchasing water from the City of North Miami Beach.
This arrangement has not been satisfactory to Bay Harbor
Islands and Bal Harbour for various reasons which, in recent
years, have resulted in low water pressures within their water
distribution systems, and for the Town of Bay Harbor Islands,
an inability to meet the recently adopted Metropolitan Dade
County fire flow requirements. Also, within the last year the
City of North Miami Beach has notified the two municipalities
of intent to discontinue selling water to them.
Based upon several meetings with engineers and representatives
from Bal Harbour and Bay Harbor Islands, together with internal
engineering reviews, it has been determined that: 1) Miami
Beach has ample water supply to meet the need; 2) a water
distribution system can be designed and constructed to provide
the water volumes and pressures required and/or desired; and
3) with minimum modifications and construction within the City
of Miami Beach, a new 20-inch water main can be installed in
86th Street from Collins Avenue to Byron Avenue interconnecting
all existing water mains in the North end of the City.
The new 20-inch main within the City limits, together with
engineering costs and the installation of two master meters at
86th and Byron Avenue, can be accomplished in a relatively short
time period at an estimated cost of $74,000. Funding for this
work can be immediately arranged in the City Capital Improvements
Budget, and surveying and engineering design can commence
immediately with completion in approximately 30 days.
AGENDA
ITEM R "7 - 3
—1—
DATE l-e -
COMMISSION MEMORANDUM NO. 6642
The City of Miami Beach has always provided water service
through master meters at 87th Street, and can provide proper
water supply and pressure at that point of service within
45 days, or less, from commencement of construction. The work
can be accomplished with City personnel; therefore, there will
not be any delay due to the preparation of bid specifications,
bidding, bid award, execution of contract documents, etc.
Further, so that there is no question concerning Miami Beach' s
ability and willingness to fully supply the total water require-
ments, such an affirmative, positive position should be set
forth by City Commission resolution.
In addition to improvement of the Miami Beach water distribution
along the northern city limits, it will be necessary: 1) to
jointly consider with Bal Harbour and Bay Harbor Islands the
best method of financing and construction the required addi-
tional_ water system improvements within those communities;
2) to provide mutual assistance, including joint legal actions
if necessary, to expedite obtaining any easements required and
to expedite construction; 3) to offer and negotiate mutual
emergency repair assistance, or to provide full maintenance
service by agreement should it be determined that Bal Harbour
and Bay Harbor Islands will continue to own and operate the
major water distribution systems, including storage and pumping
facilities, within their communities as in the past; and 4) to
negotiate an extended term major water user agreement that would
contain provisions regarding utility cost accounting, a standard
water rate costing formula and other standard and accepted pro-
visions currently being used between the Dade Water and Sewer
Authority and that Authority' s more recent water customers.
To proceed further, the City Commission must be willing to
accept and endorse the basic concepts embodied here, doing
so by adoption of the positions by resolutions for forwarding
to Bal Harbour, Bay Harbor Islands and the Metropolitan Dade
County Water and Sewer Authority. Further, it is recommended
that the City Commission authorize retention of the firm of
Post, Buckley, Schuh & Jernigan, Inc. , Consulting Engineers
and Planners, as proposed in their letter dated December 19,
1977, to prepare bulk water sales agreements and to participate
in negotiations with Bal Harbour and Bay Harbor Islands.
lit4
DAS:mb
-2-
ORIGINAL
RESOLUTION NO. 77-15510
(Agreement in principle of program for
design/construction of water supply
facilities to meet requirements of:
Bal Harbour/Bay Harbor Islands and
authorizing City Mgr.to employ Post,
Buckley, Schuh & Jernigan, Inc. ,etc.)