Contract Amendment Request for 28th Street Obelisk Restoration Project ably— ry3
Contract Amendment Request
Grant Number:SC729
Project Name:The 28th Street Obelisk Restoration Project
Grantee: City of Miami Beach
IDENTIFY THE PROPOSED CHANGES TO THE CONTRACT AS APPLICABLE
Existing Scope of Work
Grant funds will be used for the conservation,structural rehabilitation,and mechanical repair/replacement
of the 28th St. Obelisk and Pumping Station. Architectural; engineering and laboratory services are
provided for this project.All tasks associated with the Project,as outlined in the Project Description(see
Attachment A),will be completed by February 28,2019.
Amended Scope of Work
Grant funds will be used for the conservation,structural rehabilitation,and mechanical repair/replacement
of the 28th St. Obelisk and Pumping Station. Architectural, engineering and laboratory services are
provided for this project.All tasks.associated with the Project,as outlined in the Project Description(see
Attachment A),will be completed by June 30,2019..
Original Deliverables.
No changes
Other Changes
Existing language
2.Length of Agreement.This Agreement shall begin on July 1,2016,and shall end February 28,2019,
unless terminated in accordance with the provisions of Section 33 of this.Agreement. Contract extensions
will not be granted unless Grantee is able to provide substantial written justification and the Division
approves such extension.The Grantee's written request for such extension must be submitted to the Division
no later than thirty(30)days prior to the termination date of this Agreement.
12. Grant Reporting Requirements. k)Final Report.The Grantee must submit a Final Report to the
Division by February 28,2019,for the period ending February 28,2019.
Contract Amendment Request Form(Form DHR005),Effective 42015
Chapter 10+39.001.Florida Adrninisnal ve Code
14. Grant Completion Deadline. The grant completion deadline is February 28, 2019. The Grant
Completion Deadline is the datewhen all grant and matching funds have been paid out and expended in
accordance with the work described in the Scope of Work,detailed in the Estimated Project Budget.If the
Grantee finds it necessary to request an extension of the Grant Completion Deadline,the extension may
not exceed 120 days, unless the Grantee can demonstrate extenuating circumstances as described in
Section 15 of this Agreement.
Amended language
2.Length of Agreement.This Agreement shall begin on July 1,2016,and shall end June 30,2019 unless
terminated in accordance with the provisions of Section 33 of this Agreement. Contract extensions will not
be granted unless Grantee is able to provide substantial written justification and the Division approves such
extension.The Grantee's written request for such extension must be submitted to the Division no later than
thirty(30)days prior to the termination date of this Agreement.
12. Grant Reporting Requirements. k)Eleventh Project Progress Report is due by April 30,2019,
for the period ending March 31, 2019. 1)Final Report. The Grantee must submit a Final Report to the
Division by June 30,2019,for the period ending June 30,2019.
14.Grant Completion Deadline The grant completion deadline is June 30,2019.The Grant Completion
Deadline is the date when all grant and matching funds have been paid out and expended in accordance
with the work described in the Scope of Work, detailed in the Estimated Project Budget. If the Grantee
finds it necessary to request an extension of the Grant Completion Deadline,the extension may not exceed
120 days,unless the Grantee can demonstrate extenuating circumstances as described in Section 15 of this
Agreement.
Contract Amendment Request Fomi(Form DHR005),Effective 4-2015
Chapter LA-39.001.Florida Administrative Code
Reason for Changes
Additional time required to complete project.
Effect on Proposal Goals
Allows project to be fully completed.
Authorization
Authoriz, Official t+ the Grantee: J,, L ,n(Vbra_
Authorize► Officia S gnature Date
Authorized Official; + i• 's on of Historical Resources:
1
1 1 it
DHR p•v' eon birec or Date
Mail to the address below.
Florida Division of Historical Resources
RA.Gray Building
500 South.Bronough Street
Tallahassee,Florida 32399 APPROVED AS TO
FORM&LANGUAGE
&FOR EXECUTION
• 11E0
City Attorney Dote
10
Contract Amendment Request Form(Form DHR005),Effeetive 4-2015
Chapter 1A-39.001.Florida Administrative Code