Amendment No. 3 to the Design/Build Agreement with RIC-MAN Construction, Inc.
00tg- 3at/14 AMENDMENT NO. 3 TO THE DESIGN/BUILD AGREEMENT BETWEEN THE CITY OF MIAMI BEACH AND RIC-MAN CONSTRUCTION, INC. FOR THE DESIGN AND CONSTRUCTION OF A PORTION OF THE SEA WALL ALONG THE COLLINS CANAL IN THE VICINITY OF THE CARL FISHER CLUBHOUSE, TO REPLACE THE EXISTING DILAPIDATED SEA WALL, AS PART OF THE 19th STREET STORMWATER PUMP STATION IMPROVEMENTS PROJECT FOR THE CONVENTION CENTER IN AN AMOUNT NOT TO EXCEED $593,000.00, PLUS OWNER'S CONTINGENCY IN THE AMOUNT OF $59,300.00, FOR A TOTAL OF $652,300.00; WITH ' PREVIOUSLY APPROVED FUNDING. This Amendment No. 3 to the Design/Build Agreement dated on or about June 17, 2017, between the CITY OF MIAMI BEACH, a municipal corporation existing under the laws of the Stat6 of Florida (the "CITY"), and Ric-Man Cons ction Florida, Inc., ("Ric-Man" or "Design- Builder"), is made and entered this tel day of oevyt � , 2018. RECITALS WHEREAS, on January 17, 2017, the City entered into a Design/Build Agreement with Ric-Man Construction, Inc. (Ric-Man) to develop, design, and construct the Stormwater Pump Station on 19th Street between Convention Center Drive and Meridian Avenue, in the amount of $6,332,389.80; and WHEREAS, on February 9, 2018, the Mayor and City Commission adopted Resolution No. 2017-30020, to incorporate a permanent emergency generator as part of the Project Amendment No. 1 to the Design/Build Agreement was executed in the negotiated amount of $630,013.00, revising the total contract amount to $6,962,402.80; and WHEREAS, on March 23, 2018, Amendment No. 2 to the Design/Build Agreement was executed in the amount of $387,124.00 plus owner's contingency of $38,712.00, as approved by the Mayor and City Commission pursuant to Resolution No. 2018-30220, to design and construct an extension of the Botanical Garden along the Collins Canal as part of the 19th Street Stormwater Pump Station Improvements Project, revising the total contract amount to a total of$7,388,238.80; and WHEREAS, on July 25, 2018, the Mayor and City Commission adopted Resolution. No.2018-30414 authorizing the City Manager to negotiate and execute Amendment No. 3 to the Design/Build Agreement between the City of Miami Beach and Ric- Man Construction, Inc., for the design and construction of approximately 170 linear feet of sea wall, in the vicinity of the Carl Fisher Club House, in the amount of $593,000.00, plus $59,300.00 owner's contingency, revising the total contract amount to a not-to-exceed total of$8,040,538.80; and WHEREAS, this work is to be coordinated with the Carl Fisher Clubhouse Renovation Project and the design and construction of this project shall be as depicted on the City ' Engineer's Design Criteria included in the original Design/Build Agreement between the City of Miami Beach and Ric-Man Construction, Inc., for the 19th Street Stormwater Pump Station Improvements Project, as per enclosed Exhibit-2, Sea Wall sketches, Miami Beach Public Works Engineering Standard Drawings and documents herein and as approved by the City's Public Works Department— Engineering Division; and NOW, THEREFORE, the parties hereto, and in consideration of the mutual promises, covenants, agreements, terms, and conditions herein contained, and other good and valuable consideration, the respect and adequacy are hereby acknowledged, do agree as follows: 1. -ABOVE RECITALS The above recitals are true and correct and are incorporated as a part of this Amendment No. 3. 2. MODIFICATIONS a. The Agreement is amended to incorporate Exhibit-1 (proposal)attached hereto. b. In consideration for the additional work set forth in Exhibit-1, the City shall pay Ric- Man the total not-to-exceed amount of $593,000.00 plus owner's contingency of $59,300.00, in accordance with the terms and conditions of the Agreement. c. The work associated with this Amendment No. 3, shall include an extension in the Contract Time of 101 days, as stipulated in the attached Design/Builder's schedule in Exhibit-3 for the sole purpose of completing the Carl Fisher Sea Wall as part of the 19th Street Stormwater Pump Station Improvements Project, resulting in a Final Completion date of March 8, 2019, as set forth in the Design/Builder's schedule. d. The amount and time set forth herein are the maximum agreed to by both the City and Design/Builder for all work associated with this Amendment No. 3. Design/Builderr attests that the Contract adjustment provided herein is reasonable, and constitutes compensation in full for all costs, claims, markup, and expenses, direct or indirect, attributable to this Amendment, including but not limited to compensation in full for any delays, acceleration, or loss of efficiency encountered by Design/Builder in the performance of the Work through the date of this Change Order. In consideration of the compensation and time, if any, in this Amendment No. 3, the Design/Builder hereby releases the City from all Claims, demands, or causes of action arising out of the transactions, events and occurrences giving rise to this Amendment No. 3. This written Amendment No. 3 is the entire agreement between the City and Design/Builder with respect to this Amendment. No other agreements or modifications shall apply to this contract amendment unless expressly provided herein. 3. OTHER PROVISIONS All other provisions of the Agreement, as amended, are unchanged. 4. RATIFICATION The City and Design/Builder ratify the terms of the Agreement, as amended by this Amendment No. 3. IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 3 to be executed in their names by their duly authorized officials as of the date first.-et forth above. ATTEST: CITY O' MIAMI BEA! Oce 3100 SW 15th Street CONST. FL,INC. Deerfield Beach, Florida 33442 DEERFIELDBEACH.FtORIDA Office:(954)426-1221 EXHIBIT-1 ~` �f Fax:(954)426-1226 City of Miami Beach 08/16/2018 Capital Improvement Projects Office Sent via e-mail 1700 Convention Center Drive Miami Beach, FL 33139 Attn:Jorge Rodriguez RE: Carl Fisher Sea Wall—CO to 19th St P.S. Contract Dear Jorge, Per your request please find the detailed pricing spread sheet and pertinent back-up information in support of the Design, Permitting and Construction of the Carl Fisher Sea Wall. As you are aware 30%drawings were submitted for your review today,August 13,2018. The detailed scope of the proposal is contained within the drawings and under the attached pricing sheet for review and approval. Ric-Man Construction FL, Inc(RMCF)will be utilizing American Empire Builders (AEB) as the Sea Wall Sub-Contractor for this project. AEB's familiarity with the conditions, having performed the sea wall work directly adjacent to this work recently for the Convention Center Pump Station, was key in selecting them for this work. Attached please find a preliminary schedule detailing the design permitting and construction effort required to bring this project to a successful conclusion as a change order to the existing 19th street Pump Station Project.As such a time extension to the existing Contract completion date of November 27,2018 will be necessary. The primary impact to the current completion date is the permitting process for the DERM, Class I and USA COE permits.The permitting effort will commence upon approval of 60% drawings which we expect to submit by September 14,2018.The City's direct involvement in expediting the modification of the existing COE/DERM permits is vital to achieving the attached proposed dates as well as controlling the approval and release of the CMB Building Department Permits. It should be understood that in the event new permits for the COE/DERM are required, delays to construction start could be many months off. As such, RMCF will require language in the Change Order relieving it from any Liquidated Damages or penalties associated with delays in acquiring the necessary permits associated with this project. RMCF strongly recommends a two (2)tier NTP approach to this work.Tier 1 for Design/Permitting and IFC drawings followed by separate NTP for construction with an agreed to duration (Tier2). R I C - M AN CONSTRUCTION FLORIDA , I N C . \ ,, I y u a l t i . n + r It n i r I fit n I , + • IttiCA44, 3100 SW 15th Street CONGA FL,INC. Deerfield Beach, Florida 33442 DEERFIELDBEACHFLs°DA Office:(954)426-1221 Fax:(954)426-1226 RMCF proposes a Change Order in the amount of$593,000 with a completion date of March 8, 2019 based on the permitting durations provided within the attached CPM Fragnet under the conditions described above. • We look forward to proceeding with this important work and please contact me if you have any questions or comments. Sincerely Michael R Fischer COO Ric-Man Construction FL, Inc. CC: John Klion Sabina Baglieri Attachments: • Carl Fisher Sea Wall Pricing and Scope Sheet dated 8/13/18 • WSP Design and Permitting proposal • AEB Sea Wall Proposal • Gardening Angel Nursery proposal • Trench drain Material proposal • 30% Drawing submittal • CPM Fragnet to existing 19th St Pump station Schedule R I C - M AN CONSTRUCTION FLORIDA , I N C . Ric-Man Construction FL,Inc Carl Fisher Sea Wall CO 08/13/2018 Assumptions: Contract Completion date to be extended to March 8,2019(see attached fragnet submission) This proposal is based on existing to be modified COE Derm permits as expedited with the CMB support.Building Permits will be expedited by the CMB within the durations proposed. Sea Wall design follows criteria established for the 19th St PS project-no test pile program is included Vibration Monitoring is included during pile driving operations only Tree Mitigation is included per the attached 30%dwgs No landscaping,seeding,sodding,irrigation is included RMCF to provide finished subgrade only-final grading,sloping or drainage-not included. The operation is land based-barrier fencing will be removed and/or relocated by RMCF to allow free access for equipment and staging Access will be permitted by the City from the Washington Ave.RMCF to provide and restore access Security Guard or shack from access point is not included Contingency$are not included in the attached estimate Existing utility relocations are not included Item Quantity Subcontractor Material Labor Rate Labor Total Equipment Total Cost MH Design/Permits/supervision Design Fee/Permits/Mitigation Plan $ 79,810.00 $ 79,810.00 Survey-line and grade/Layout 20 hours $ 1,900.00 $ 1,900.00 Supervision PM 32 97.00 $ 3,104.00 $ 320.00 Supt $ 3,424.00 120 75.00 $ 9,000.00 $ 1,200.00 $ 10,200.00 Vibration Monitoring 30 days $ 4,000.00 Pile Logs/Monitoring 30 days 120 28.75 $ 3,450.00 $ 4•x•00 Mobilization $ 3,450.00 MOT Access-install and restore 20 46.00 $ 920.00 MOB/Demob Equipment/supplies $ 5,000.00 40 51.00 $ 2,040.00 $ 920.00 Site Work $ 12,000.00 103480200000° 00 51.00 $ 1,200.00 $ 8,240.00 $ 5,100.00 $ 21;020000..0000 ,000.00 Fencing-remove exist-re-install 200'+ $ 19,100.00 trucking Site clearing/debris removal $ 2,000.00 80 46.00 $ 3,680.00 Clear and grub 80 51.00 $ 4,080.00 $$$$$$ 5,680.00 Tree Mitigation 40 $ 8,320.00 13 ea 51.00 $ 23:806948300...000000 ,040.00 $ 7,160.00 $ 12,400.00 Cat loader Turbidity Curtain and Maintain $ 6,525.00 50 $ 1,000.00 51.00 $ 2,550.00 $ 7,050.00 $ 9,200.00 trucking an Existing wall removal/debris control and removal/excav for panels 100'+ 30 28.75 $ 893.00 $ 16,125.00 Finish sub-grade to established elevations 200 $ trucking an 51.00 $ 10,200.00 $ 20,975.00 $ 1.893.00 100 525454181816....0..70000050000 1.00 $ 5,100.00 Sea Wall $$$ 1282:,$03052000...000000 2,500.00 $ 31,175.00 trucking ar Pile,Panel and Cap Installation incl Wing walls $ 17,600.00 loader,D07 Closure at corner locations $260,000.00 Stair Landing slab 5 ea $ 2,000.00 70cy 25 51.00 $ 1,275.00 _ $ 260, Trench drain w/end caps $10,000.00 280 $ 000.00 Rip Rap 80 IF $13,722.00 46.00 $ 12,880.00 $ $ Handrail 200 T 40 46.00 $ 1,840.00 700.00 3.275.00 140 $ 8,400.00 $ 8,000.00 20 51.00 $ 1,020.00 $ 1,800.00 $ 23,580.00 p $ 17,362.00 Pumping $ 1,520.00 E Ldr w/bh 1377 $ 10,540.00 Subtotal $ 8,400.00 $374,635.00 $39,722.00 Tax 7% $ 69,172.00 $ 64,745.00 H&P-10/4 $ 3,026.00 $ 14,985.00 $ 548,274.00 AL $ 3,972.20 $389,620.00 $ 6,917.20 $ $ 3.026.00 •nd and Insurance $46,720.20 6.474.50 $ 76,089.20 $ $ 32,348.90 roject 71,219.50 $ 583,648.90 ed to Price $ 11,672.98 $ 595$ ,321.88 $ S(2,321.88) 93 Ric-Man Construction FL,Inc Carl Fisher Sea Wall CO 08/13/2018 Assumptions: Contract Completion date to be extended to March 8,2019(see attached fragnet submission) This proposal is based on existing to be modified COE Derm permits as expedited with the CMB support.Building Permits will be expedited by the CMB within the durations proposed. Sea Wall design follows criteria established for the 19th St PS project-no test pile program is included Vibration Monitoring is included during pile driving operations only Tree Mitigation is included per the attached 30%dwgs No landscaping,seeding,sodding,irrigation is included RMCF to provide finished subgrade only-final grading,sloping or drainage-not included. The operation is land based-barrier fencing will be removed and/or relocated by RMCF to allow free access for equipment and staging Access will be permitted by the City from the Washington Ave.RMCF to provide and restore access Security Guard or shack from access point is not included Contingency$are not included in the attached estimate Existing utility relocations are not included Item Quantity Subcontractor Material Labor Rate Labor Total Equipment Total Cost MH Design/Permits/Supervision Design Fee/Permits/Mitigation Plan $ 79,810.00 $ 79,810.00 Survey-line and grade/Layout 20 hours $ 1,900.00 $ 1,900.00 Supervision PM 32 97.00 $ 3,104.00 $ 320.00 $ 3,424.00 Supt 120 75.00 $ 9,000.00 $ 1,200.00 $ 10,200.00 Vibration Monitoring 30 days $ 4,000.00 $ 4,000.00 Pile Logs/Monitoring 30 days 120 28.75 $ 3,450.00 $ 3,450.00 Mobilization MOT 20 46.00 $ 920.00 $ 920.00 Access-install and restore $ 5,000.00 40 51.00 $ 2,040.00 $ 1,200.00 $ 8,240.00 MOB/Demob Equipment/supplies $ 12,000.00 100 51.00 $ 5,100.00 $ 2,000.00 $ 19,100.00 trucking Site Work Fencing-remove exist-re-install 200'+ $ 2,000.00 80 46.00 $ 3,680.00 $ 5,680.00 Site clearing/debris removal 80 51.00 $ 4,080.00 $ 8,320.00 $ 12,400.00 Cat loader and Dozer Clear and grub 40 51.00 $ 2,040.00 $ 7,160.00 $ 9,200.00 trucking and disposal($ 3,000) Tree Mitigation 13 ea $ 6,525.00 50 51.00 $ 2,550.00 $ 7,050.00 $ 16,125.00 trucking and disposal($ 3,000) Turbidity Curtain and Maintain $ 1,000.00 30 28.75 $ 893.00 $ - $ 1,893.00 Existing wall removal/debris control and removal/excav for panels 100'+ 200 51.00 $ 10,200.00 $ 20,975.00 $ 31,175.00 trucking and disposal($3,000)incl Finish sub-grade to established elevations 100 51.00 $ 5,100.00 $ 12,500.00 $ 17,600.00 loader,Dozer and Roller Sea Wall Pile,Panel and Cap Installation incl Wing walls $ 260,000.00 $ 260,000.00 Closure at corner locations 5 ea $ 2,000.00 25 51.00 $ 1,275.00 $ - $ 3,275.00 Stair Landing slab 70cy $10,000.00 280 46.00 $ 12,880.00 $ 700.00 $ 23,580.00 Pumping Trench drain w/end caps 80 LF $13,722.00 40 46.00 $ 1,840.00 $ 1,800.00 $ 17,362.00 FE Ldr w/bhoe Rip Rap 200 T $ 8,000.00 20 51.00 $ 1,020.00 $ 1,520.00 $ 10,540.00 Handrail 140 $ 8,400.00 $ 8,400.00 1377 • Subtotal $ 374,635.00 $39,722.00 $ 69,172.00 $ 64,745.00 $ 548,274.00 Tax 7% $ 3,026.00 $ 3,026.00 OH&P-10/4 $ 14,985.00 $ 3,972.20 $ 6,91772,0 $ 6,474.50 $ 32,348.90 TOTAL $389,620.00 $46,720.20 $ 76,089.20 $ 71,219.50 $ 583,648.90 2%Bond and Insurance $ 11,672.98 Total Proiect $ 595,321.88 EXHIBIT-2 6 r li II''I �,., m = .;� ...... ®, III;, ` O EXIST.SEAWALL _,,..,._ '` `„•` _ ~i rO BUILT AS PART OF o� 44 u, cc cc PUMP STATION , 00.\ , - — PROJECT. �O ....rpt �, ":.M.. 0 til w �* e� • IX[�onLM.K q,.Aawrdrt O '''''._...e o i `� SWIMIllt.M[tU4,B.un f.COMPLID Z / b[NMNIOfUWNWm�xtWlMlf�lM -7,7,...:,""::.. �•Y1 PROPOSED "\ 4 / ,IXtt.t..TO“M. t ,o„ Q• �=® a CONTINUATIONUM.TODD Cm PM • fes .DriDel OF SEAWALL .. `w .,.�,a.a. �_'IT= CARL FISHER STAIRS �"• "usuutt 9./3 ... 1 a3 SEAWALL/STEMWALLS —»--�}i - - 0, ""'"� m AS PART OF SCOPE OF WORK. 0 t Cat-- EXIS1 UNDERMINED, \----\ ,, SEAWALL SECTION TO :' , BE STABILIZED �� A � "'” can[nnarcOMP �m..> (( EXISTING \ \ SEAWALL TO REMAIN - ..).,.....1.1t„e: su u \ t e - Ir, .� f oNi I 5s E kr 1 IL • •. - . • ' ! . . Wilk •} EXIST.SEAWALL..— 11) ,\ ""ftwm. BUILT AS PART OF r �,p0! , ...•••"" PUMP STATION v v �'�"' 84Gi.J WAIL il �' �\ ..� .... Cg d r l ,._ PROPOSED �. ♦\ C_0 1 ;I CONTINUATION N- m / OF SEAWALL A ",."� ` _ CARL FISHER STAIRS \ y \ �,.. "'"/acma� —._.,„_.„.•••••••t.,„ SEAWALL/STEMWALLS gl '�"°.°° \ AS PART OF SCOPE OF &p W _ WORK. 1\, Q1P %\ �COJ.. !� WALL LExlGiw. Ilo � 1..-....,...• x'51 I ':uE1=11,.IrEu W%.J6 L6i,J67N.3o' (F.)EA =1 ;✓/L'_I SEC7.C'.70 ' r �- i \ r( mmtmw OA. ..i EXISTING n SEAWALL TO > i REMAIN j \ i ��A,rN> fO_O fJ-I o.� TuF \ WO GAL firs wet 64 e \of er+-f rcPof cse Tod of da l /rte.. rr70 6.t3.7b �i r,,mf IIIIIIIII 4- "T-- �z` novae's, Te,� II .L.?4412' , ..r, a 6t kIPE 44 — semen ' *ova.-- i...,Z.N. .J 7.:,cif - - - 1 ,_ I - - - _—.___1-:.-;_.7-7_,._______ _.- ____ _ ---- -- T j i I I l , I I_ I i I I I i # I r• r.shoe I I I . I �� 1 II _a------ ______________________f- I1,_ -�- - 1 ! i I 1'. i I —e„.G RLe&. to-d' (,) I:7.1,i -1 C C 13n rrry (r ) � g�*ta x� P�E 6�,,40 � i.b6 toe 114.14,40 Imo. CM4)44- /JA“.. _ EGiVif•p b nl ió4rl A-7TEAe0 kt.1 6 Poe >— ` (ND rJart> a 1 --- Gur tErF 40.41• .1- rA, \s"._ J 7 __________ . Ir .______. r 1 IT fr r‘t,..), I o 3:L' ti I I g>�y,J I1 ) I I I i I /zi'I`4 1 1 I I I ,‘ rlo, ) I n 1 vJ ., To W'Ny L41,441I I _ pia,. 4"414C",;____-\5TM45 ,EC.S.?i GVtRETI;If. ,�•St�• 1 1 1 I I 1 I 1 4 I eL.z.70 / / I �--�-1 PAF(NO 1 1 1 �- `a`""` _ I r Z . To,.iOW a. #S.70 Pt' •F ow ''�i/%' 7 tz. .t,70 O��" ♦ 1 I �. ► I 1 3 e/I 1 �i�� i l I �i 6017..f /,04..l / II �ez'-S.$o i%'r �I I r g44"frP ti 3 SPA Gr 9'v' 0-) = ZXX040) Sear,a✓ ,e-7 NOTES: THE FOLLOWING STRUCTURAL NOTES ARE FOR USE AS A GUIDE STANDARD. A STRUCTURAL ENGINEER OR ARCHITECT LICENSED IN FLORIDA SHALL PREPARE CALCULATIONS AND STRUCTURAL DRAWINGS AS PER FLORIDA BUILDING CODE (FBC) WITH SUBMITTAL. THE DESIGN SHALL PROVIDE A CONCRETE SEAWALL ASSEMBLY WITH A 30-YEAR USEFUL SERVICE LIFE. THESE GUIDE STANDARDS ARE FOR THE REPAIR OF EXISTING SEAWALLS AND FOR THE CONSTRUCTION OF NEW SEAWALLS. THE STANDARD SEAWALL DETAILS SHOW THE REPAIR. GENERAL 1. ELEVATIONS SHOWN REFER TO THE NORTH AMERICAN VERTICAL DATUM OF 1988. 2. THE SITE SPECIFIC MEAN HIGH WATER (MHW) AND MEAN LOW WATER (MLW) LEVEL MUST BE INCLUDED IN THE PLANS. 3. IT IS THE INTENT OF THESE GUIDE STANDARDS TO BE IN ACCORDANCE WITH APPLICABLE CODES AND REQUIREMENTS OF AUTHORITIES HAVING JURISDICTION. 4. IT IS THE INTENT OF THESE PLANS TO COMPLY WITH LOCAL, STATE, AND FEDERAL ENVIRONMENTAL PERMITS ISSUED FOR THIS PROJECT. IT SHALL BE THE OWNER'S RESPONSIBILITY TO FAMILIARIZE AND GOVERN HIMSELF BY ALL PROVISIONS OF THESE PERMITS. 5. APPLICABLE BUILDING CODE: FLORIDA BUILDING CODE (FBC) 2010 OR CURRENT EDITION. 6. STANDARD SEAWALL DESIGN IS FOR NON-OCEANFRONT PROPERTIES ONLY. FOR LOCATIONS SUBJECT TO STORM SURGES WITH POUNDING SURF, ERODING SHORELINES AND WAVES OVERTOPPING FROM COASTAL STORM EVENTS, THE STANDARD SEAWALL DESIGN SHALL NOT BE USED. 7. AS-BUILT/RECORD SURVEY WILL BE REQUIRED UPON COMPLETION OF SEAWALL. SURVEY SHALL BE PERFORMED BY A PROFESSIONAL SURVEYOR AND MAPPER LICENSED IN THE STATE OF FLORIDA. REFER TO CITY OF MIAMI BEACH PUBLIC WORKS MANUAL PART 1 SECTION 1 A.2. PRECAST CONCRETE PILING 0 1. PRECAST CONCRETE PILES SHALL BE 12"x12" OR 14"x14" PILES WITH 5000 P.S.I MIN. CONCRETE AND 4-1/2" DIA. 270 K.S.I. ASTM A416 LOW-LAX STRANDS WITH 2 lc MIN. CONCRETE COVER TO TIES. THEY SHALL BE DRIVEN TO A MINIMUM BEARING CAPACITY OF 25 TONS WITH 12' MINIMUM PENETRATION INTO FIRM MATERIAL BELOW SILT LAYER. A SUB-SOIL INVESTIGATION AND REPORT SHALL BE PROVIDED BY A CERTIFIED GEOTECHNICAL ENGINEER LICENSED IN FLORIDA. BATTER PILES AT 4:12 SLOPE WHERE SHOWN ON PLANS. 0 00 a CONCRETE AND REINFORCING STEEL co 1. ALL CONCRETE (EXCEPT PRECAST PILES) SHALL HAVE A 0.40 WATER/CEMENT RATIO AND SHALL ATTAIN A MINIMUM COMPRESSIVE STRENGTH OF(f'c) 5000 P.S.I AT THE END OF 28 DAYS. FOUR (4) CONCRETE CYLINDERS SHALL BE TAKEN FOR EACH 50 CUBIC YARDS OR FRACTION THEREOF AND SHALL BE TESTED AT 3, 7 AND 28 DAYS. SLUMP SHALL NOT EXCEED 5" (+/- 1"). '=• 2. ALL REINFORCEMENT SHALL BE 60000 PSI MINIMUM YIELD (Fy) NEW BILLET STEEL IN ACCORDANCE WITH ASTM A615 IW GRADE 60. ALL BAR LAPS SHALL BE A MINIMUM OF 48 BAR DIAMETERS. PLACING OF REINFORCEMENT SHALL S CONFORM TO THE LATEST ACI MANUAL OF STANDARD PRACTICE CODES. - 3. ALL CONCRETE SHALL BE PLACED WITHIN 90 MINUTES FROM BATCH TIME, AND VIBRATED AS REQUIRED BY THE ACI L4- MANUAL OF CONCRETE PRACTICE. TEMPERATURE OF CONCRETE AT THE TIME OF PLACEMENT SHALL BE BETWEEN 75' AND 100' F. i iSOIL 1. NEW FILL MATERIAL SHALL BE CLEAN FILL WITH NO ORGANIC OR OTHER DELETERIOUS COMPONENTS, AND SHALL BE COMPACTED IN 12" (MAX.) LIFTS TO AT LEAST 95% OF THE MODIFIED PROCTOR MAXIMUM DRY DENSITY (ASTM z D-1557). E 9 I a 1 1 C 0 g MIAMI BEACH �PE11LVD,D IIID PUBLIC WORKS DEPARTMENT o„Zo,S2015 SEAWALL NOTES BS 1 c 1700 CONVENTION CENTER DRIVE.MIAMI BEACH.FL 33139 NEW 36" WIDE x 16' DEEP CONCRETE SEAWALL CAP ALUMINUM PIPE GUIDE RAIL WITH (5) #5 CONTINUOUS BARS T&B & #3 CLOSED PER FDOT INDEX 870 TIES 0 12' O.C. AND (3) /3 CLOSED TIES 0 EACH SIDE OF EACH PILE 0 3' O.C. VERIFY CAP REMOVE EXISTING SEAWALL CAP AS REINFORCING BY STRUCTURAL CALCULATIONS REQUIRED TO CONSTRUCT NEW WALL • PROVIDE /8 HOOKED DOWEL DRILL & EPDXY 12- MIN. INTO KING PILE 38' MIN. ALL EXPOSED EDGES TO BE EXTEND PILE STRANDS r CHAMFER e' MIN. @�D 15' MIN. INTO CAP 3• 3. 1 6 A'SOD SOD SIDEWALK r T.O. PROPOSED CAP 101 r " 71I°MIN.EL=+7.25'NGVD 1929 7.-1• I ~Z. WIN.EL-+570 NAVD 1988 4 • 18' 4 • SEE STANDARD CONCRETE SIDEWALK DETAIL N 12 dii-F,MHW EXISTING SEAWALL TO BE REPAIRED OR EI-=—NAVD 88 • MODIFIED. ACTUAL CONDITIONS WILL VARY liAtir L.MLW NEW SEAWALL PANEL PLACED IN J TEL=�IAVD 88 '0 FRONT OF EXISTING WALL SEE o REINFORCING DETAIL ON SW4 NEW 9' THICK PRECAST cm 2 , CONCRETE BULKHEAD PANEL I '^ • .I 1 WHERE WAVE ACTION OR SWIFT CURRENTS < ARE ANTICIPATED PLACE FDOT RUBBLE X L RIP-RAP (BANK AND SHORE) ON 2:1 SLOPE • APPROX. TO CONTROL EROSION 3 = = F NEW 12"x12• PRECAST KING PILE AT 3 0 � �/ 10'-0' 0.C. WITH 12' MIN. EMBEDMENT o r PINTO FIRM MATERIAL PILES TO HAVE A cc zo _y\— • I I� 25 TON CAPACITY 1\._ 1. I IW 1.0 BERM (MIJTUNE) 0 1 o 1: APPROX. FACE OF loj NEW 12'x12" PRECAST BATTER PILE DOMING WALL PARTIALLY ADJ. TO KING PILE AT 10'-0" O.0 sx FAILING AND ROTATING WITH 12' MIN. EMBEDMENT INTO ARM J MATERIAL PILES TO HAVE A 25 TON 3 CAPACITY i O NI0 0 2 i Y 3 .. N W 9 1 ID In SEAWALL SECTION 1 a FOR RETAINED FILL NOT TO EXCEED 10'-0" DEPTH o NOT TO SCALE al cs i MIAMI BEACH APPROVED REVISED TITLE • SEAWALL - 10' MAX. DEPTH BS2 PUBLIC WORKS DEPARTMENT 07/2015 SECTION VIEW Iv 1700 CONVENTION CENTER TREE.MIAMI BEACH.FL.33139 F:\WORK\=ALL)CAD—DWG\STANDARDS\CMB STANDARD DETAILS\Public Macke Manual (2D1S1\CMB Seawall Details MAO STANDARD SEAWALL DETNLS.dwa 9 8 a m 0 N 10' 0.C. MAX. -A0CO m-0 171n � m a 10' O.C. MAX. =a m I 12"x12" BATTER PILE AS PER Z SECTION 12"x12" KING PILE AS 24„ PER SECTION MAX. NEW 9" THICK PRECAST CONCRETE BULKHEAD PANEL 1 z g oo mili a_ A � f Q \ / O v Z_J \ Q 1 1 / o w _ _ _ , I v1 ilIL O D I I— r o EXISTING SEAWALL D I PROPOSED SIDEWALK Z 0 10 m * D X 0 M 1 BS2 I PLAN VIEW OF WALL FOR 10'-0" MAX. W RETAINED FILL BEHIND WALL (1) NOT TO SCALE CO 5.. 5., N• 11 • • • • • • • • Z O • X U Q LY) • cl_W LL • #5 HORIZ BARS ®6" • O.C. • G • #5 VERT A) BARS 012" • O.C. • O • VI • • Co' \ bo 5„ (TYP.) FOR 10'-0" 0/C KING PILES, VERIFY FIELD CONDITION AND FABRICATE PANELS 2" SHORTER THAN ACTUAL KING PILE a TO j SPACING vii J NOTES: 1. VERIFY PANEL THICKNESS AND REINFORCING BY STRUCTURAL CALCULATIONS. 2. #5 VERTICAL BARS EXTEND 12" MIN. BEND PER SECTION DETAIL AFTER PANELS ARE IN PLACE. i m STANDARD SEAWALL PANEL ELEVATION FOR RETAINED FILL NOT TO EXCEED 10'-0" NOT TO SCALE 0 0 APPROVED REVISED FIT.! PUBLIWC SEAWALL BEACH SEAWALL - 10' MAX. DEPTH BS4 1. T 07'2015 STANDARD PANEL ELEVATION 1700 CONVENTION CENTER DRIVE.MIAMI BEACH.FL.33139 ♦ • NEW 38" WIDE x 16" DEEP CONCRETE SEAWALL. CAP ALUMINUM PIPE GUIDE RAIL WITH (5) 05 CONTINUOUS BARS T&B & #3 CLOSED PER FOOT INDEX 870 TIES 0 12" O.C. AND (4) #3 CLOSED TIES 0 4" O.C. 0 EACH SIDE OF EACH PILE. VERIFY CAP REMOVE EXISTING SEAWALL CAP AS REINFORCING BY STRUCTURAL CALCULATIONS REQUIRED TO CONSTRUCT NEW WALL • PROVIDE #6 HOOKED DOWEL DRILL & EPDXY 12" MIN. INTO KING PILE 38' MIN. ALL EXPOSED EDGES TO BE D PILE STRANDS rCHAMFER r MIN. i y 15"MIN. INTO CAP 3•^ 1' cr . AI SOD SOD SIDEWALK 1 T.O. PROPOSED CAP :�[ T �, MIN.El...-+7.25'NGVD 1929 ' AAT/, I 1 ~ . cZ MIN.EL-+5.70'NAVD 1988 Al j Y 4 • f 16" 4 SEE STANDARD CONCRETE SIDEWALK DETAIL 12 • L MHW IP EXISTING SEAWALL TO BE REPAIRED OR EL _ NAVD 88 MODIFIED. ACTUAL CONDITIONS WILL VARY 1 • I < 1MLW lo NEW SEAWALL PANEL PLACED IN " EL AVD 88 b1 FRONT OF EXISTING WALL SEE REINFORCING DETAIL ON SW4 NEW 9" THICK PRECAST a 2 CONCRETE BULKHEAD PANEL Q 1 WHERE WAVE ACTION OR SWIFT CURRENTS Z ARE ANTICIPATED PLACE FOOT RUBBLE • RIP-RAP (BANK AND SHORE) ON 2:1 SLOPE APPROX. TO CONTROL EROSION ---A tlS • _ , NEW 14"x14" PRECAST KING PILE AT 2 S �/'� 10'-0" O.C. HATH 121 MIN. EMBEDMENT 0 N ��INTO FIRM MATERIAL PILES TO HAVE A o i \ 25 TON CAPACITY mz • _.. 1-.3 BERM (MUULINE) o • o APPROX. FACE OF NEW 14"x14" PRECAST BATTER PILE x EXISTING WALL PARTIALLY ADJ. TO KING PILE AT 10'-0" 0.0 It FAILING AND ROTATING WITH 12' MIN. EMBEDMENT INTO FIRM N MATERIAL PILES TO HAVE A 25 TON 0 CAPACITY U n E. raO i Z I 111 VF I- F W 9 a to • SEAWALL SECTION 2 FOR RETAINED FILL NOT TO EXCEED 14'-0" DEPTH F. NOT TO SCALE 0 APPROVED REVISED TITLE MIAMIBEACH SEAWALL - 14' MAX. DEPTH BS5 PUBLIC WORKS DEPARTMENT 07/2015 SECTION VIEW 1: 1700 CONVENTION CENTER DRIVE.MAW BEACH.FL 33139 .F:\WORK\tALL'CAD—DWG\STANDARDi\CN@ STANDARD_DETAll S\Public Works Manual (2915)\CMB Seawall Details\CMB STANDARD SEAWALL DETAILS.dwa • . 8 W 4 r — UL PJ 10' O.0 MAX. TX CP -OW m rn I 10' 0.C. MAX. I 3 t 7 I 14"x14" BATTER PILE AS PER m = SECTION 14"x14" KING PILE AS 24" PER SECTION MAX. NEW 9" THICK PRECAST CONCRETE > [BULKHEAD PANEL o I -r A _ 1, a 0 \ / O 3 / 7 \ / \ N W IN i7 - D r r EXISTING SEAWALL 1- ' I PROPOSED SIDEWALK D Z - m XI ----- I 0 m 1 71 BS5 2 PLAN VIEW OF WALL FOR 14'-0" MAX. co RETAINED FILL BEHIND WALL U) NOT TO SCALE 0) iv • } • • • • • • • • z 0 p • X U Q W O W � � I d In #5 HORIZ 14 BARS ©6" • O.C. Z • • #5 VERT BARS 012" • O.C. •0 sy • Sm • o_nJ • v � � 5- (TYP.) "(TYP.) FOR 10'-0" 0/C KING PILES, VERIFY FIELD CONDITION AND 9" FABRICATE PANELS 2" SHORTER THAN ACTUAL KING PILE TO SPACING La W NOTES: 1. VERIFY PANEL THICKNESS AND REINFORCING BY STRUCTURAL CALCULATIONS. 2. #5 VERTICAL BARS EXTEND 12" MIN. BEND PER SECTION DETAIL AFTER PANELS ARE IN PLACE. STANDARD SEAWALL PANEL ELEVATION FOR RETAINED FILL NOT TO EXCEED 14'-0" NOT TO SCALE MIAMI BEACH APPROVED REVISED SEAWALL - 14' MAX. DEPTH BS7 PUBLIC WORKS DEPARTMENT 07/2015izN STANDARD PANEL ELEVATION 1700 CONVENTION CENTER DRIVE,MIAMI REACH.FL.JJI J9 MILESTONES MS-04 FINAL COMPLETION(SC+60 DAYS= 11/27/2018) 0 0 0% 08-Mar-19* -74 KB52-5 DAY CARL FISCHER SEAWALL CHANGE ORDER F CARL FISCHER SEAWALL DESIGN PRELIMINARY ENGINEERING (30%) r� , CFSW-1000 RMCF NTP FOR 30% 0 0 100% 10-Jul-18 A KB52-5 DAY • CFSW-1010 TOPO SURVEYAND TREE SURVEY 16 0 100% 10-Jul-18 A 31-Jul-18 A KB52-5 DAY MillIMIIIIMI CFSW-1020 30% DESIGN DEVELOPMENT 4 4 0% 01-Aug-18 06-Aug-18 -72 KB52-5 DAY CFSW-1030 30%REVIEW BY RMCF 4 4 0% 07-Aug-18 10-Aug-18 -72 KB52-5 DAY III CFSW-1040 ADDRESS RMCF COMMENTS&SUBMIT 30%DESIGN 1 1 0% 13-Aug-18 13-Aug-18 -72 K1352-5 DAY I CFSW-1050 CMB REVIEW&APPROVE 30% DESIGN 10 10 0% 14-Aug-18 23-Aug-18 -102 KB52-7 DAY „x,„60% DESIGN s CFSW-2000 RMCF/CMB NTP FOR 60% 0 0 0% 24-Aug-18 -74 KB52-5 DAY • CFSW-2020 TREE DISPOSITION PLAN 10 10 0% 24-Aug-18 06-Sep-18 -38 KB52-5 DAY ` ii CFSW-2030 60% DESIGN DEVELOPMENT 10 10 0% 24-Aug-18 06-Sep-18 -74 KB52-5 DAY MIMI CFSW-2010 BENTHIC SURVEY(BY OTHERS) 15 15 0% 24-Aug-18 13-Sep-18 -03 Y,652-5 DAY MINIM CFSW-2040 60% DESIGN QA/QC 2 2 0% 07-Sep-18 10-Sep-18 -74' KB52-5 DAY MI CFSW-2050 60% REVIEW BY RMCF 2 2 0% 11-Sep-18 12-Sep-18 -74 KB52-5 DAY II CFSW-2060 ADDRESS RMCF COMMENTS&SUBMIT 60% DESIGN 2 2 0% 13-Sep-18 14-Sep-18 -74 KE52-5 DAY I I CFSW-2070 CMB REVIEW&APPROVE 60% DESIGN 10 10 0% 15-Sep-18 24-Sep-18 -68 KB52-7 DAY mil 100% DESIGN r ::— qv,.�- --- CFSW-3000 100% DESIGN DEVELOPMENT 5 5 0% 25-Sep-18 01-Oct-18 -48 KB52-5 DAY MN CFSW-3010 100% DESIGN QA/QC 2 2 0% 02-Oct-18 03-Oct-18 -48 KE52-5 DAY f. CFSW-3020 100% REVIEW BY RMCF 2 2 0% 04-Oct-18 05-Oct-18 -48 K852-5 DAY • CFSW-3030 ADDRESS RMCF COMMENTS&SUBMIT 100%DESIGN 2 2 0% 08-Oct-18 09-Oct-18 -48 KP52-5 DAY •CFSW-3040 CMB REVIEW&APPROVE 100% DESIGN 10 10 0% 10-Oct-18 19-Oct-18 -57 KB52-7 DAY 3, i CFSW-3050 ADDRESS CMB COMMENTS 2 2 0% 22-Oct-1823-0ct-18 -41 KB52-5 DAY0 ■� PERMITTING M _..I s■t CFSW-4000 USACOE DEPT.OF ARMY PERMIT MODIFICATION 60 60 0% 24-Aug-18 15-Nov-18 -58 KB52-5 DAY i CFSW-4010 FDEP/SFWMD ERP MODIFICATION 60 60 0% 24-Aug-18 15-Nov-18 -58 KB52-5 DAY CFSW-4030 CMB TREE PERMIT 60 60 0% 24-Aug-18 15-Nov-18 -58 KB52-5 DAY i CFSW-4020 RER-DERM TREE PERMIT 30 30 0% 07-Sep-18 18-Oct-18 -38 KB52-5 DAY r i CFSW-4040 RER-DERM CLASS 1 PERMIT 50 50 0% 14-Sep-18 22-Nov-18 -63 KB52-5 DAY i CFSW-4050 CMB BUILDING DEPT. PERMIT 60 60 0% 17-Sep-18 07-Dec-18 -74 KB52-5 DAY I CFSW-4060 ISSUE CONSTRUCTION DOCUMENTS 0 0 0% 07-Dec-18 -102 KB52-7 DAY CARL FISCHER SEAWALL PROCUREMENT CFSW-5000 PREPARE&SUBMIT PILE-WEAP ANALYSIS 5 5 0% 10-Oct-18 16-Oct-18 -33 KB52-5 DAY t 1 CFSW-5020 PREPARE&SUBMIT PILE MATERIAL 5 5 0% 10-Oct-18 16-Oct-18 -43 KB52-5 DAY 0 CFSW-5050 PREPARE&SUBMIT VIBRATION MONITORING LOCATIONS 5 5 0% 10-Oct-18 16-Oct-18 -33 KB52-5 DAY 0 ' CFSW-5130 PREPARE&SUBMIT REDI-MIX CONCRETE MIX DESIGN 5 5 0% 10-Oct-18 16-Oct-18 -33 KB52-5 DAY 0 • CFSW-5150 PREPARE&SUBMIT HANDRAIL 5 5 0% 10-Oct-18 16-Oct-18 9 KB52-5 DAY II CFSW-5180 PREPARE&SUBMIT TRENCH DRAIN 5 5 0% 10-Oct-18 16-Oct-18 19 KB52-5 DAY I1 1 CFSW-5070 PREPARE&SUBMIT PRE-CAST PANEL SHOP DRAWINGS 10 10 0% 10-Oct-18 23-Oct-18 -41 K352-5 DAY t CFSW-5100 PREPARE&SUBMIT REBAR 10 10 0% 10-Oct-18 23-Oct-18 -48 K352-5 DAY I CFSW-5200 PREPARE&SUBMIT LANDSCAPING/PLANT SCHEDULE 10 10 0% 10-Oct-18 23-Oct-18 9 KB52-5 DAY , i CFSW-5010 REVIEW&APPROVE PILE-WEAP ANALYSIS 5 5 0% 17-Oct-18 23-Oct-18 -33 KB52-5 DAY 0 CFSW-5030 REVIEW&APPROVE PILE MATERIAL 5 5 0% 17-Oct-18 23-Oct-18 -43 KB52-5 DAY F- CFSW-5060 REVIEW&APPROVE VIBRATION MONITORING LOCATIONS 5 5 0% 17-Oct-18 23-Oct-18 -33 K352-5 DAY ! _1 CFSW-5140 REVIEW&APPROVE REDI-MIX CONCRETE MIX DESIGN 5 5 0% 17-Oct-18 23-Oct-18 -33 K352-5 DAY 0 limil•N Remaining Level of Effort ® Critical Remaining Work Page 1 of 2 ® Actual Work • •Milestone inning Remaining Work CFSW-5190 REVIEW&APPROVE TRENCH DRAIN 5 5 0% 17-Oct-18 23-Oct-18 19 KB52-5 DAY SEM CFSW-5080 REVIEW&APPROVE PRE-CAST PANEL SHOP DRAWINGS 5 5 0% 24-Oct-18 30-Oct-18 -41 KB52-5 DAY 1 CFSW-5110 REVIEW&APPROVE REBAR 5 5 0% 24-Oct-18 30-Oct-18 -48 KB52-5 DAY 1 CFSW-5040 FABRICATE& DELIVER PILE MATERIAL 10 10 0% 24-Oct-18 06-Nov-18 -43 KB52-5 DAY il CFSW-5170 FABRICATE& DELIVER HADRAIL 10 10 0% 24-Oct-18 06-Nov-18 9 KB52-5 DAY f CFSW-5210 REVIEW&APPROVE LANDSCAPING/PLANT SCHEDULE 10 10 0% 24-Oct-18 06-Nov-18 9 KB52-5 DAY I CFSW-5120 FABRICATE& DELIVER REBAR 10 10 0% 31-Oct-18 13-Nov-18 -48 KB52-5 DAY CFSW-5090 FABRICATE& DELIVER PRE-CAST PANELS 42 42 0% 31-Oct-18 11-Dec-18 -57 KB52-7 DAY CARL FISCHER SEAWALL CONSTRUCTION CFSW-6000 CARL FISCHER SEAWALL CONSTRUCTION MTP 0 0 0% 10-Dec-18 -74 KB52-5 DAY CFSW-6010 MOBILIZE 2 2 0% 10-Dec-18 11-Dec-18 -74 KB52-5 DAY CFSW-6020 CLEAR&GRUB I PREPARE SITE 5 5 0% 12-Dec-18 18-Dec-18 -74 KB52-5 DAY CFSW-6030 TREE REMOVAL I MITIGATION 1 1 0% 19-Dec-18 19-Dec-18 -74 KB52-5 DAY CFSW-6040 CONCRETE PILE INSTALLATION 23 23 0% 20-Dec-18 21-Jan-19 -74 KB52-5 DAY CFSW-6050 EXCAVATION FOR PANELS 10 10 0% 22-Jan-19 04-Feb-19 74 KB52-5 DAY CFSW-6060 CONCRETE PANEL INSTALLATION 10 10 0% 28-Jan-19 08-Feb-19 -74 KB52-5 DAY CFSW-6070 FRP CONCRETE PILE CAP 10 10 0% 11-Feb-19 22-Feb-19 -74 KB52-5 DAY CFSW-6110 PLACE RIP RAP 2 2 0% 25-Feb-19 26-Feb-19 -68 KB52-5 DAY CFSW-6080 BACKFILL SITE TO SUBGRADE 3 3 0% 25-Feb-19 27-Feb-19 -74 KB52-5 DAY CFSW-6100 INSTALL HANDRAIL 3 3 0% 25-Feb-19 27-Feb-19 -69 KB52-5 DAY CFSW-6120 PLANTING AND FINAL GRADING 3 3 0% 28-Feb-19 04-Mar-19 -72 KB52-5 DAY CFSW-6090 FRP SLAB AT STAIRS 5 5 0% 28-Feb-19 06-Mar-19 -74 KB52-5 DAY CFSW 6130 DEMOBILIZE 2 2 0% 07-Mar-19 08-Mar-19 -74 KB52-5 DAY ammo' Remaining Level of Effort ® Critical Remaining Work ® Actual Work • •Milestone Page 2 of 2 EMI Remaining Work