Change Order No. 3A Ric-Man Construction FL, Inc. IV\ I iA IVAA I AM IBEACH : - ROW'West Avenue-Phase II .
PROJECT NAME. Improvements South of 14th St . •
AlE CONSULTANT: CES Consultants, Inc.
CONTRACTOR: Ric-Man Construction FL,:Inc..
RPR/CEI: 1 I Chen Moore and Associates,.Inc. :
CHANGE ORDER NO. 3A DATE: 03/07/201:9 :
You are hereby directed to make the following changes to the Contract Documents:
DESCRIPTION OF This Change Order will reimburse the Design/Builder for the costs incurred in support of the Urban Land Institute
CHANGE: (ULI)Resiliency effort-Accelerator,with workshop;exhibits,designs,and meeting attendance,as well as the Re-
Start Impact,after a one year delay to the Project;which includes the loss of efficiency, loss of.employees;the :
costs during the pause and demobilizationof the project,re-start costs and costs of maintaining office and.
administrative support. • :- •
' This Change Order will also account for the expensesassociated with the 10 year.Storm Drainage Modeling
Study requested by the Public Works Engineering Department,to be prepared by the.Design/Builder:: ,
: These costs were:identified.and approved by.the City Commission during their December meeting, under :
Resolution number-2018-30653 and-this ie the first request from the$6,567;000:00:approved. .
REASON FOR Reimburse the Design/Builder for costs incurred during:the one year project delay and demobilization;ae well as :
CHANGE: : support of the ULI'Resiliency effort.' : :
CLASSIFICATION: Owner Directed IF,OTHER N/A: . . : :
ATTACHMENTS • . . . . . . . . . .
. .
CHANGE IN CONTRACT SUM . : . . . CHANGE IN CONTRACT TIME
Original Contract Sum: $12,809,754:10 Original Contract Time to Substantial 545: DAYS
Completion:.
Net change by'previouslyNet change from previous Change : :
$1;468,359.00 • 30 DAYS'.
authorized Change Orders: Orders:
Contract Sum prior'tothis Contract:Time to Substantial ' : • '
Change:Order:'. • $_14,278;113.00 Completion.prior to this Change 575 DAYS
Order is:
Contract Sum will be Contract Time will be
increased/decreased by this -2'9353
Change Orderin the amount _ ,094.85 increased/decreased by the: 0: DAYS.
of:. . . . . . •• . .
following days: .
New Contract:Sum'including this New Contract Time to Substantial. -`'='` ':
$14 631,207.85 575 DAYS
Change Order is: . . Completion is;. .• . . I
Approved by RPR/CEI: Approved by CIP Capital • •'ect Coordinator: . Approved by CIP.Division Director:..
Date 0g Rodriguez
`7 r e Date Date . :
Approv-• Engineer of Record Appro d :C i I Project Coordinator:: Appr••-. by IP'i irector:
3�?///9
�► 3 IDate. S na Bag i Date. . David 'a tinez,:P ;: IS5.
ate.
Approved by Contrac or: 0 her Other.
__ _ . til Bti 11
Date: . . Da Date.
/2s/ 9 Dan Gelber _ Rafael Granado
'A ROVED AS TO Mayor City Clerk
:FORM•&LANGUAGE - vii,
&FOR EXECUTION111
CDC �
City Attorney. Date :SIN 041 =_
ORP $ .
Page 1 of 1. . : I •i. .. l oRATF p• *t