LTC 312-2019 G.O. Bond Program Project Implementation Update No. 1G. 0. Bond Program -Project Implementation Update No. 1
May30, 2019
Page 2 of4
3-year tranches of funding. Since April, City staff and the Committee have been focusing efforts
on the implementation of the first tranche of 38 projects (67% of the number of projects in the
Program). Refer to Exhibit B attached for the Tranche 1 list of projects.
IMPLEMENTATION STATUS
Quick Wins
21 out of the 38 projects in Tranche 1, or 55%, are considered "Quick Wins", refer to Exhibit C
attached, and have been scheduled for completion within the first 12-14 months of the Program
ending on approximately June of 2020. The total budget for these projects is $39,423,000. The
status of each project falls into 5 general phases; Pre-Planning, Design & Permitting,
Procurement, Construction or Execution, and Closeout. As of May 16, the status of these projects
is summarized in Schedule 2 below:
Schedule 2
' UIC m ro1ec s a us 21 Q . k w· P . t St t
Item GOB Project No. I Name Pre-Planning Design I Procurement Construction Closeout No. Permitting or Execution
1 #24 Mid Beach Beachwalk x
2 #32 Palm & Hibiscus x
3 #33 StreetTree Plan x
4 #17 Polo Park x
5 #52 LED Lighting in Parks x
6 #2 Collins Park x
7 #4 Fairway Park x
8 #3 Crespi Park x
9 #21 Stillwater Park x
10 #47 License Plate Readers x x
11 #57 Cameras in Ent District x
12 #49 P. Safety Radio System x
13 #56 Cameras on Beachwalk x
14 #53 Security for Pub. Spaces x
15 #26 Roof Replacement x x
16 #18 Scott Rakow x
17 #13 North Shore Park x
18 #38 Street Pavement x
19 #37 Sidewalk Improvement x
20 #19 Soundscape Tech Core By Others -·-21 #42 Traffic Calming x
A narrative for the scope, status, and anticipated completion of each of the Quick Win projects
is attached as Exhibit C1 and an Implementation Timeline is attached as Exhibit D.
Other Tranche 1 Projects
In addition to the Quick Win projects, there are 17 other important Tranche 1 projects, with a
budget of $111,716,000, currently being implemented by the City. During the Committee
meeting of May 16, refer to Exhibit E agenda attached, staff provided the following updates:
#15 Community Park (Par 3)-$15,700,000
• Scope: Develop new park at 2795 Prairie avenue, with elements such as: lake, overlooks,
and amphitheater, tennis courts, playground, vita course & trail system, environmental
remediation, and resiliency components.
G. 0. Bond Program -Project Implementation Update No. 1
May 30, 2019
Page 3 of4
• Status: Design documents at 60-90 percent development. Pending Miami-Dade County
Regulatory and Economic Resources environmental remediation strategy approval.
Anticipated Invitation to Bid (ITB), November 2019.
• Anticipated Completion: Summer 2021.
#1 72nd Street Park, Library, and Aquatic Center -$10,800,000 for Tranche 1
• Scope: Design new facility at 72nd Street between Collins Avenue and Harding Avenue
that includes new recreational park space, roof-top competition pool, library/media
center, fitness gym with running track, and parking garage.
• Status: City currently completing due diligence, feasibility study, concept design, surveys,
cost estimates, geotechnical and environmental study.
• Anticipated Completion: 2023.
#4 Baywalk Pedestrian Bridge -$10,000,000
• Scope: Provide a continuous pedestrian path along Biscayne Bay from Government Cut
to Lincoln Road, by connecting the gaps in the existing public Baywalk, including
pedestrian bridge connection over 5th Street.
• Status: Project in design and permitting stage and will be presented to the Design Review
Board on June 6, 2019.
• Anticipated Completion: Summer 2020.
#8 Fire Station No. 1 -$7,000,000 for Tranche 1
• Scope: Replace Fire station #1, located at 1051 Jefferson Avenue in South Beach to
include the 911 Call Center. This station provides emergency assistance to the area
south of 15th Street, Star Island, Palm Island, Hibiscus Island, among other areas.
• Status: Project currently advertised for a design consultant with qualification opening
scheduled for June 24, 2019.
• Anticipated Completion: 2023.
PROGRAM REPORTING
As the remaining Tranche 1 projects begin implementation, City staff shall be reporting updates
to the Committee on a monthly basis, and also providing updates on the status of all projects
with supplemental reports and detailed timelines.
COMMUNITY INFORMATION AND OUTREACH
The GO Bond team is fully committed to maintaining transparent public information records,
proactive resident outreach efforts and quality customer service standards. The GO Bond brand
continues to showcase "Your Voice, In Action" - a reminder of all that's been made possible by
and forthe Miami Beach community.
The website [www.gomb2018.com] serves as a one-stop-shop for all GO Bond program
information. The new GO Blog was launched to feature stories on program milestones, public
impacts and community voices. Upcoming MB Magazine publications will feature a new column
that is dedicated to the GO Blog.
Neighborhood leaders have direct communication with GO Bond staff and will be kept updated
on upcoming projects which are important to them. Staff will attend community meetings as
requested and as needed.
This month's program updates, project advisories and multimedia postings were sent on the
City's social media outlets including Twitter, Facebook, Nextdoor, and Constant Contact and are
attached as Exhibit F.
G. 0. Bond Program -Project Implementation Update No. 1
May30, 2019
Page 4 of4
If there are any questions, please do not hesitate to contact myself or Maria Hernandez at
Extension 2584.
Attachments:
Exhibit A -Implementation Criteria Definitions
Exhibit B -Tranche 1 List of Projects by Amount
Exhibit C -Quick Wins List by Department
Exhibit C1 -Quick Wins Status Summary
Exhibit D -Quick Wins Implementation Schedule
Exhibit E -GOB Oversight Committee Meeting Agenda
Exhibit F -Community Outreach Report
JLM I MH
F:\cmgr\$ALL\GO Bond Program\Commission\L TCs\01 May 2019\LTC -May 2019 GO Bond Program Update.docx
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Exhibit B
Tranche 1 List of Projects by Amount
Item
No.
Project
No.Category Location Impl. Dept.Project Name GO Bond
Budget Notes Tranche 1
2019
1 15 Parks Mid CIP Bayshore Park (Par 3 /
Community Park)15,700,000
Regional impact project for Mid Beach; in Tranche
1 as project has been stalled for lack of funding for
years; Design being updated for blue/green
infrastructure; significant resiliency component
15,700,000
2 5 Parks South CIP PAL Facility, Flamingo Park &
Youth Center 30,550,000
Regional impact project for South Beach; PAL in
Tranche 1; Security Lighting in a separate GOB
project; Master Plan Elements and Resiliency
Strategies in Tranche 3
15,400,000
3 1 Parks North CIP 72nd Street Park, Library, and
Aquatic Center 53,800,000 Regional impact project for North Beach; Tranche
1: design, Tranche 2: construction 10,800,000
4 23 Parks South CIP Baywalk 15,000,000
Tranche 1: MacArthur Pedestrian Bridge ($10M),
assumes prioritized due to 500 Alton development
Tranche 2 to build consensus with property
owners and obtain permitting: South Bay Club
($2.8M); Bayview Terrace ($850K); Bay Garden
Manor ($1.35M)
10,000,000
5 49 Public Safety CW Police/Fire Public Safety Radio System 10,000,000
Tranche 1; City already under contract with Harris
Corporation, with projected December 2019
delivery
10,000,000
6 39 Infrastructure CW PW Resilient Seawalls and Living
Shorelines 10,000,000
Tranche 1 and 2; consultant to be engaged to
update existing matrix to prioritize City-owned
seawalls
8,000,000
7 38 Infrastructure CW PW Street Pavement Program 30,000,000
Use pavement assessment study and
neighborhood project schedule to prioritize the
projects at approximately $2.5M annually;
consider traffic impacts
7,500,000
8 45 Public Safety South CIP Replace Fire Station #1 10,000,000
Tranche 1; high priority for Fire and Police; need
to resolve location concerns; include 911 call
center (helps create space in Police HQ)
7,000,000
9 55 Public Safety CW PW Street Lighting Improvements 10,000,000
Tranche 1 & 2; Individual projects will come from
master plan which is currently being developed.
Design is still pending. Improves public safety and
results in O&M savings.
5,000,000
10 13 Parks North Prop Mgmt North Shore Park & Youth
Center 5,725,000
Tranche 1: painting center interior, interior
lighting, security cameras; roof; generator are
Quick Wins; jogging path; shade structure;
baseball field conversion; baseball LED lighting
takes longer
Tranche 2: useful life remaining for playground
and flooring; fence may be impacted by baseball
field conversion; reforestation
4,930,000
11 8 Parks South Special
Projects Lummus Park 4,737,000 Tranche 1; sequence before Ocean Drive project 4,737,000
12 24 Parks Mid CIP Middle Beach Beachwalk 4,500,000 Tranche 1; quick win; grants have been awarded 4,500,000
13 19 Parks South Tourism/CIP Soundscape Park 4,500,000 Tranche 1; cameras/projectors are quick wins;
restroom/storage facility will take longer 4,500,000
14 18 Parks Mid Prop Mgmt Scott Rakow Youth Center 5,088,000
Tranche 1: pool restroom and locker room;
security cameras; generator; impact windows;
HVAC; roof replacement; fire alarm;
Interior/exterior painting
Tranche 2: useful life remaining for: basketball
flooring; gymnastics flooring; mondo flooring at
ice rink; outdoor patio flooring
4,448,000
15 48 Public Safety CW Prop Mgmt Police Headquarters
Renovations 10,000,000
Tranche 2: feasibility study and new space design;
firing range renovation; HVAC controls and
window refurbishment
Tranche 2 for remaining improvements
4,000,000
16 37 Infrastructure CW PW Sidewalk Improvement
Program 13,000,000
Use sidewalk assessment study and neighborhood
project schedule to prioritize the projects at
approximately $1M annually
3,500,000
17 10 Parks Mid CIP Maurice Gibb Park 3,300,000
Tranche 1; design is substantially complete;
permitting process and remediation will drive
timeline; these funds are in addition to existing
project funds
3,300,000
18 54 Public Safety South CIP Marine Patrol Fire/Police
Facility 2,700,000
Moved from Tranche 4 to Tranche 1 at G.O. Bond
workshop on March 4th; include as part of
Maurice Gibb Park project
2,700,000
Implementation Tracking Sheet v17 1 of 2 5/27/2019
Exhibit B
Tranche 1 List of Projects by Amount
Item
No.
Project
No.Category Location Impl. Dept.Project Name GO Bond
Budget Notes Tranche 1
2019
19 26 Parks CW Prop Mgmt Roof Replacement for Cultural
Facilities 2,980,000 Tranche 1; quick win; reduces water intrusion and
operating costs 2,980,000
20 33 Infrastructure CW Env Street Tree Master Plan 5,000,000 Complete plan in year one and implement within
5 years; quick win for limited locations 2,500,000
21 43 Infrastructure CW Transp Protected Bicycle Lanes and
Shared Bike/Pedestrian Paths 5,000,000
Tranche 1: Chase Ave $830K; 23rd Street $1.5M;
Alton road design $170K
Tranche 2: Alton Rd construction $1.2M
Tranche 3: 63rd street (FDOT timing) need $2.3M
but have $1.3M
2,500,000
22 53 Public Safety South PW Security for Public Spaces 4,350,000
Prioritize portable bollards b/c can be used for
special events; all can be implemented in Tier 1
except for Lincoln Road bollards which are
dependent on that project schedule (approx. 5
years), assuming Tier 2
2,000,000
23 12 Parks North CIP North Beach Oceanside Park
Beachwalk 2,000,000 Tranche 1; Completely designed; Pending grant
from FDOT slows down timeline 2,000,000
24 47 Public Safety CW Police/Fire License Plate Readers 1,950,000
Tranche 1; improves public safety; use of state
road right of way still being negotiated; need
$480,000 for 8 quick win (non-state/county)
locations
1,950,000
25 40 Infrastructure Mid Special
Projects 41st Street Corridor 15,000,000
Tranche 1 & 2: shade structures, lighting, and bike
lanes
Tranche 2 & 3: widening of sidewalks (timing of
FDOT approval); replacement parking
1,500,000
26 42 Infrastructure CW Transp Neighborhood Traffic Calming
& Pedestrian-Friendly Streets 2,000,000
Tranche 1: Nautilus (quick win), Central Bayshore
North; Central Bayshore South is funded but tied
to Neighorhood Improvement Project
Tranche 2: Normandy and Palmview
1,500,000
27 57 Public Safety South Police/Fire Security Cameras in
Entertainment District 1,490,000
Tranche 1; quick win except for Collins Ave
locations because use of state road right of way
still being negotiated; improves public safety
1,490,000
28 52 Public Safety CW Parks LED Lighting in Parks 4,500,000
Tranche 1: Stillwater Park, Crespi Park, Tatum
Park, Normandy Isle Parkk
Tranche 2: Flamingo Park and North Shore Park
1,041,000
29 29 Parks North Special
Projects West Lots Redevelopment 5,000,000 Distribute funds over Tranches 1, 2, and 3 to
incentivize development 1,000,000
30 32 Infrastructure South CIP Palm & Hibiscus
Neighborhood Enhancements 1,000,000 Tranche 1; Neighborhood improvement project
currently in progress 1,000,000
31 50 Public Safety CW Police/Fire Security Cameras in Business
Districts 825,000
Tranche 1; improves public safety; timing depends
on using FDOT/County right of way or using our
own infrastructure
825,000
32 9 Parks South Parks Marjory Stoneman Douglas
Park 682,000
Tranche 1; playground and shade structure need
replacement; permitting with turtle-lighting will
take time
682,000
33 2 Parks South Parks Collins Park 640,000 Tranche 1; quick win; addresses safety concerns
with pavers 640,000
34 17 Parks Mid Parks Polo Park 500,000 Tranche 1; quick win; helps expand programming,
baseball fields & dugouts 500,000
35 56 Public Safety South Police/Fire Security Cameras on Beach
Walk 400,000 Tranche 1; quick win; improves public safety 400,000
36 4 Parks North Parks Fairway Park 260,000 Tranche 1; quick win; concurrent with CIP project 260,000
37 3 Parks North Parks Crespi Park 211,000 Tranche 1; quick win; improve security 211,000
38 21 Parks North Parks Stillwater Park 145,000 Tranche 1; quick win; improve security 145,000
38 out of 57 = 67% of the Projects in the Program 435,115,000 Total Less Issance Cost 151,139,000
Implementation Tracking Sheet v17 2 of 2 5/27/2019
Exhibit C
Quick Wins List by Department
#Proj.Category Location Impl. Dept.Project Name GO Bond
Budget Notes Quick Win
$ Amount
1 24 Parks Mid CIP Middle Beach Beachwalk 4,500,000 Tranche 1; quick win; grants have been awarded 4,500,000
2 32 Infrastructure South CIP Palm & Hibiscus
Neighborhood Enhancements 1,000,000 Tranche 1; Neighborhood improvement project
currently in progress 1,000,000
3 33 Infrastructure CW Env Street Tree Master Plan 5,000,000 Complete plan in year one and implement within
5 years; quick win for limited locations 500,000
4 17 Parks Mid Parks Polo Park 500,000 Tranche 1; quick win; helps expand programming,
baseball fields & dugouts 500,000
5 52 Public Safety CW Parks LED Lighting in Parks 4,500,000
Tranche 1: Stillwater Park, Crespi Park, Tatum
Park, Normandy Isle Parkk
Tranche 2: Flamingo Park and North Shore Park
1,041,000
6 2 Parks South Parks Collins Park 640,000 Tranche 1; quick win; addresses safety concerns
with pavers 640,000
7 4 Parks North Parks Fairway Park 260,000 Tranche 1; quick win; concurrent with CIP project 260,000
8 3 Parks North Parks Crespi Park 211,000 Tranche 1; quick win; improve security 211,000
9 21 Parks North Parks Stillwater Park 145,000 Tranche 1; quick win; improve security 145,000
10 47 Public Safety CW Police/Fire License Plate Readers 1,950,000
Tranche 1; improves public safety; use of state
road right of way still being negotiated; need
$480,000 for 8 quick win (non-state/county)
locations
480,000
11 57 Public Safety South Police/Fire Security Cameras in
Entertainment District 1,490,000
Tranche 1; quick win except for Collins Ave
locations because use of state road right of way
still being negotiated; improves public safety
700,000
12 49 Public Safety CW Police/Fire Public Safety Radio System 10,000,000
Tranche 1; City already under contract with Harris
Corporation, with projected December 2019
delivery
10,000,000
13 56 Public Safety South Police/Fire Security Cameras on Beach
Walk 400,000 Tranche 1; quick win; improves public safety 400,000
14 53 Public Safety South Police/Fire Security for Public Spaces 4,350,000
Prioritize portable bollards b/c can be used for
special events; all can be implemented in Tier 1
except for Lincoln Road bollards which are
dependent on that project schedule (approx. 5
years), assuming Tier 2
600,000
15 26 Parks CW Prop Mgmt Roof Replacement for Cultural
Facilities 2,980,000 Tranche 1; quick win; reduces water intrusion and
operating costs 2,980,000
16 18 Parks Mid Prop Mgmt Scott Rakow Youth Center 5,088,000
Tranche 1: pool restroom and locker room;
security cameras; generator; impact windows;
HVAC; roof replacement; fire alarm;
Interior/exterior painting
Tranche 2: useful life remaining for: basketball
flooring; gymnastics flooring; mondo flooring at
ice rink; outdoor patio flooring
3,910,000
17 13 Parks North Prop Mgmt North Shore Park & Youth
Center 5,725,000
Tranche 1: painting center interior, interior
lighting, security cameras; roof; generator;
jogging path; shade structure; baseball field
conversion; baseball LED lighting
Tranche 2: useful life remaining for playground
and flooring; fence may be impacted by baseball
field conversion; reforestation
1,256,000
18 38 Infrastructure CW PW Street Pavement Program 30,000,000
Use pavement assessment study and
neighborhood project schedule to prioritize the
projects at approximately $2.5M annually;
consider traffic impacts
4,000,000
19 37 Infrastructure CW PW Sidewalk Improvement
Program 13,000,000
Use sidewalk assessment study and
neighborhood project schedule to prioritize the
projects at approximately $1M annually
2,000,000
20 19 Parks South TCED Soundscape Park 4,500,000 Tranche 1; cameras/projectors are quick wins;
restroom/storage facility will take longer 3,800,000
21 42 Infrastructure CW Transp Neighborhood Traffic Calming
& Pedestrian-Friendly Streets 2,000,000
Tranche 1: Nautilus (quick win), Central Bayshore
North; Central Bayshore South is funded but tied
to Neighorhood Improvement Project
Tranche 2: Normandy and Palmview
500,000
21 Total Quick Wins 39,423,000$
Imlementation Tracking Sheet v 17 5/27/2019
Exhibit C1
Quick Wins Status Summary
#24 Mid Beach Beachwalk - $4,500,000
• Scope: Construct on-grade pedestrian walkway and demolish the existing wooden
boardwalk between 23rd Street to 45th Street.
• Status: Pending the Florida Department of Environmental Protection issuance of an
Environmental Permit. FDEP has 90 days to issue the permit.
• Anticipated Completion: October 2020. #32 Palm & Hibiscus - $1,000,000
• Scope: Improve landscaping along Palm Avenue, portions of Fountain Street, Palm Avenue median and other areas.
• Status: Pending the Palm & Hibiscus Design/Builder to complete the work in the neighborhood in order to get a separate contractor to do the work in this project.
• Anticipated Completion: May 2020.
#33 Street Tree Master Plan - $500,000
• Scope: Implement the Master Plan by planting trees to provide canopy coverage and shade, while also providing additional stormwater treatment and storage capacity.
• Status: Biscayne Pointe, Stillwater Neighborhood and 5th Street are slated for reforestation. Specifications are being developed and planting will begin in late Fall.
• Anticipated Completion: January 2020. #17 Polo Park - $500,000
• Scope: Implement various baseball facility improvements to park located at 4301 North Meridian Avenue, including new dugouts, irrigation, and fencing.
• Status: Projected to be completed by August 15th, as school is scheduled to commence on August 19th.
• Anticipated Completion: August 2019. #52 LED Lighting in Parks - $1,041,000
• Scope: Upgrade sports and pathway lighting to LED technology to improve illumination of areas and reduce energy costs at the following parks: Normandy Isle Park, Tatum Park, Stillwater Park, and Crespi Park.
• Status: Contract for standardized light fixtures was approved by Commission on April 10th.
• Anticipated Completion: November 2019. #2 Collins Park - $640,000
• Scope: New Pavers for walkways and plaza throughout the park located at 2100 Collins Avenue, to improve aesthetics, minimize safety concerns, and reduce ongoing repairs and maintenance.
• Status: Procurement timeline may be shortened once the new JOC program is in place; work commencement is dependent on the Art Basel Fair schedule.
• Anticipated Completion: February 2020.
Page 2 of 3
#4 Fairway Park - $260,000
• Scope: Implement various improvements to the park located at 200 Fairway Drive, including fence replacement and painting of the pavilion, office, and restrooms.
• Status: This project will be performed concurrently with the non-CIP project at this park.
• Anticipated Completion: March 2020.
#3 Crespi Park – $211,000
• Scope: Implement various improvements to the park at 7801 Crespi Boulevard, including a new walking/jogging path, fence replacement, and new paint and flooring to the building and restrooms.
• Status: Awaiting pricing from the contractor.
• Anticipated Completion: September 2019. #21 Stillwater Park - $145,000
• Scope: Implement various improvements to park located at 8440 Hawthorne Avenue, including fence replacement and new paint and flooring to building and restrooms.
• Status: Awaiting pricing from the contractor.
• Anticipated Completion: September 2019.
#47 License Plate Readers - $480,000
• Scope: Install license plate readers (LPR’s) at strategic locations to aid crime-fighting
and prevention efforts. Locations include: MacArthur Causeway, Julia Tuttle Causeway, and 71st Street.
• Status: Solicitation is currently with the Procurement Department for final review.
• Anticipated Completion: November 2019. #57 Cameras in Entertainment District - $700,000
• Scope: Improve public safety in the Entertainment District by adding security cameras. Two cameras would be installed at the intersections of Washington Avenue from 5th Street to 17th Street.
• Status: Standardization approved by Commission on May 8th. Procurement Department reaching out to vendors.
• Anticipated Completion: December 2019. #49 Public Safety Radio System - $10,000,000
• Scope: Replace the City’s end-of-life system with a new radio system, to be used by Police, Fire and public safety officers to communicate with each other, and with other agencies, when responding to emergency calls or in the field.
• Status: Currently in the implementation phase. Legal Department working on contract to include fixed pricing.
• Anticipated Completion: January 2020.
#56 Cameras on Beachwalk - $400,000
• Scope: Enhance security for residents and visitors along the beach walk from 14th Place to 23rd Street by adding 15 security cameras.
• Status: Will kick off after the Lummus Park Connectivity Project is completed.
• Anticipated Completion: March 2020. #53 Security for Public Spaces - $600,000
• Scope: Install portable bollard system to safeguard pedestrians and special event venues.
• Status: Piggyback analysis to GSA contract is being completed for direct purchase from manufacturer; 3-month lead time.
• Anticipated Completion: August 2019.
Page 3 of 3
#26 Roof Replacement - $2,980,000
• Scope: Replace roofs to avoid water intrusion and other negative impacts at cultural
facilities including the Colony Theater, Miami City Ballet, and Fillmore Theater.
• Status: Quotes received on May 9. Work is being procured through trade contracts.
• Anticipated Completion: March 2020.
#18 Scott Rakow – $3,910,000
• Scope: Improve Scott Rakow Youth Center located at 2700 Sheridan Avenue, including: roof replacement, renovations to pool facilities, window replacements, emergency generator, HVAC replacement, and security cameras.
• Status: Proposals from engineering firms for design received. Work being procured through trade contracts. Camera standardization approved by Commission on May 8th. Construction is phased around operation schedule.
• Anticipated Completion: June 2020. #13 North Shore Park - $1,256,000
• Scope: Improve North Shore Park and Youth Center located at 501 72nd street, including: addition of two baseball fields, emergency generator, baseball field conversion to artificial turf and lighting upgrades, roof replacement, new walking/jogging path, and security cameras.
• Status: Work being procured through trade contracts. Camera standardization approved by Commission on May 8th.
• Anticipated Completion: June 2020. #38 Street Pavement - $4,000,000
• Scope: Enhance the City’s pavement condition by resurfacing streets and implementing pavement preservation strategies.
• Status: Project groundbreaking was on May 10th and work is in progress.
• Anticipated Completion: August 2019. #37 Sidewalk Improvement - $2,000,000
• Scope: Improve walkability by replacing the City’s sidewalks that are rated at or below marginal per the City’s Sidewalk Condition Index.
• Status: Project groundbreaking was on May 10th and work is in progress.
• Anticipated Completion: April 2020. #19 Soundscape Tech Core - $3,800,000
• Scope: Improve public amenities for Soundscape Park located at 400 17th street for the upgrade of projectors, cameras, and servers to 4K ultra-high definition resolution to enhance the delivery of free cultural activities.
• Status: Procurement by New World Symphony has been completed. The grant agreement with NWS was approved at the May 8th Commission meeting.
• Anticipated Completion: August 2019. #42 Neighborhood Traffic Calming & Pedestrian-Friendly Streets - $500,000
• Scope: Promote pedestrian and bicycle safety by implementing various traffic calming
projects in the Nautilus neighborhood.
• Status: The bicycle lanes portion of the project is under County review for permit approval.
Traffic circles, speed tables, and signage do not require permits.
• Anticipated Completion: January 2020.
•
•
•
•
SOCIAL
1
Exhibit F
WEB
2
BLOG
3
NEWS
4
MEETINGS
5
Coming Up: