Loading...
GOB - Flamingo Park PresentationFlamingo Park Status Update Office of Capital Improvement Projects July 2019 Budget Completed Projects $13.8M Ongoing Projects $4.2M Total Spent* (including grant money)$18m GOB Allocation $30.6M *This includes Grant/County funds totaling in $3.1m GO Bond Project Update •Baseball Field and Stadium Renovation –Original Design at 90% Completed, GO Bond items need to be incorporated •Softball Field Renovation –Ready for permitting –including resiliency items •New Open Greenspace –Butterfly Garden –Ready for permitting •New Entry Features –30% Design completed •Central Plaza Restoration –Water Feature –At conceptual design phase •New Multi-Use Path -Ready for permitting •Historic Lodge Renovation -Ready for permitting •Pedestrian Pathway Lighting and Landscape Improvements –Ready for permitting •Youth Center (PAL) -TBD