I-395 PHASE 1
Phase 1 work will include the construction of the eastbound and westbound outside
local lanes. Once constructed, traffic will be shifted to outside local lanes.
4
I-395 PHASE 2
Phase 2 work will include the construction of mainline I-395 in the center.
5
I-395 PHASE 3
Phase 3 work will see the final completion and opening of I-395 and the communal areas
under the bridges.
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
6
Lane and shoulder widths
reduced on the NB I-95 Ramp to
EB I-395 ramp
SB I-95 Ramp to EB I-395
two lane ramp has been
reduced to one lane
Traffic shift on the eastbound I-395
connector road has been completed
N
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
7
1
1
2
2
1.Remove median separator between the
eastbound I-395 mainline and local road
connector (Ongoing)
2.Remove median separator between the
eastbound I-395 mainline and the westbound
mainline (October)
3.Begin construction on westbound outside,
local road lanes (October)
4.Begin construction on eastbound outside,
local road lanes (October)
Work Zone Typical Section 3
4
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
8
•Utility relocations (Ongoing)
•Widening of NE 1 Avenue between NE 13 Street and I-395 for future traffic shift (Ongoing)
•Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue (August)
•Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;
Traffic to be routed to NE 13 Street and NE 11 Street. (August)
PHASE 1 –STEP 1
CONSTRUCTION ACTIVITIES THREE MONTH LOOK
AHEAD
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
9
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
10
Bridge foundation work for westbound Signature Bridge (December)
UPCOMING CONSTRUCTION
ACTIVITIES
THREE MONTH LOOK
AHEAD
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
11
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
•Southbound I-95 and northbound I-95 ramps to eastbound I-95
•Lane closures along I-395 mainline and connector road
•Lane closures along Biscayne Boulevard
•Permanent closure of NE 12 Street between Biscayne Boulevard and
NE 2 Avenue
UPCOMING CONSTRUCTION
ACTIVITIES
THREE MONTH LOOK
AHEAD
•Provide drivers with real-time
travel information;
•Encourage motorists to take
alternate routes;
•Clear incidents more quickly,
thereby reducing secondary
incidents; and
•Make work zones safer for
highway workers and motorists.
Smart Work Zone Management
System (SWZMS) -The project will
implement a SWZMS that will utilize
Intelligent Transportation System
(ITS) Devices such as traffic
cameras, data collection devices
and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
12
N
13
COMMUNITY OUTREACH
PROJECT WEBSITE
•www.i-395miami.com
•Sign-up for project alerts/updates
Lane Closure information
Upcoming construction activities
Presentations
•Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
•1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
•Ongoing individual stakeholder meetings and presentations
•Ongoing communications with CMB Communications and
Transportation Departments
•Next stakeholder meeting –August 19, 2019