RESOLUTION 89-19803 RESOLUTION NO. 89-19803
A RESOLUTION OF THE CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA PROVIDING FOR
INCREASED APPROPRIATIONS TO WORK ORDER
NUMBER 2949 FOR THE LUMMUS PARK, PHASE II,
CONSTRUCTION FROM 5TH TO 9TH STREETS
WHEREAS, the City Administration has prepared cost estimates for the
Phase II completion of Lummus Park from 5th to 9th Streets in the amount of
$862,590.00; and
WHEREAS, as it is necessary to increase the appropriation of Work Order
No. 2949 to accomplish Phase II as planned; and
WHEREAS, as the funding of such increases is available through a DER
Grant and Bond Fund Number 360.
NOW, THEREFORE, BE I'!' DULY RESOLVED BY THE CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA, that the City Commission hereby
increase appropriation to Work Order No. 2949 by the amount of $862,590.00 for
the purpose of completing Lummus Park, Phase II, from 5th to 9th Streets.
PASSED and ADOPTED THIS 15th day of November , 1989.
VICE-MAYOR
Attest:
FORM APPROVED
")?--) LEGAL DEPT.
B y t 7
CITY CLERK
Date /��077
RAG/b
I I eti, 4 CWt ', e/c.v.%
p. :.` FLORIDA 3 3 1 3 9
,,,\Z',/....:_,),k\-S
V,4 C,4 TI UNL,4,ti D 1:. S A.
1p 4.e)* . — - - - —
)9
't,,,,P,F,.',-,:-izi,--\"
OFFICE OF THE CITY MANAGER CITY HALL
ROB W.PARKINS 1700 CONVENTION CENTER DRIVE
CITY MANAGER TELEPHONE: 673-7010
_ '6
COMMISSION MEMORANDUM NO 6.( "� ' r
N
DATE: November 15, 1989
TO: Mayor Alex Da• . • and
Members o e City Comm' io
.
W !'*
.
FROM: Rob W. Par . 1�•
City Manager 4r' l
SUBJECT: REQUEST FOR • PPROPRIATION INCREASE
WORK ORDER NUMBER 2949
LUMMUS PARK CONSTRUCTION, PHASE II
The City Administration has prepared cost estimates for the Phase II completion of Lummus
Park from 5th to 9th Streets in the amount of $862,590.00. The work will be completed in
several phases starting with grading, placement of irrigation, electrical facilities and sod,
west of the existing wall. The work is being sequenced so as to eliminate temporary
restoration costs on the Ocean Drive Project making these savings available for Park
construction.
A general breakdown of the proposed costs are as follows:
Demolition $122,880
Tree Relocation 8,250
New Wall 208,080
Walkways 163,218
Sod 84,393
Irrigation 55,976
Electrical 76,028
$718,825
Eng. Surveys
& Inspections 143,765
TOTAL COST $862,590
The sources of funding for this project are a DER grant of $140,000 to be used exclusively
for the walkways and $722,590 from Bond Fund No. 360 for the remainder of the work.
ADMINISTRATION RECOMMENDATION:
It is recommended that the City Commission adopt the Resolution authorizing the Request
for Appropriation in the amount of $862,590.00 for the Phase II Development of Lummus
Park from 5th to 9th Streets.
RWP/RAG/b
kiii- AGENDA0F •
ITEM
:: ..____.__.... ._.�,` V.L._.. . _..-.-_..-__ __..:..
DATE S
ORIGINAL
RESOLUTION NO. 89-19803
Providing for increased appropriations to
work order number 2949 for the Lummus Park
Phase II, construction from 5th to 9th
Streets.