R9D CMB Commission UpdateCity of Miami Beach Commission Update September 11, 2019 * This schedule does not reflect days added to the contract for holidays, weather days or special events 2 •Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between NW 17 Street and NW 29 Street (Ongoing) •Construction of foundations for overhead sign structures (Ongoing) •Erection of new sign structures along I-95. This work will require nighttime full closures of I-95 between NW 17 Street and NW 29 Street (late-September) UPCOMING & ONGOING CONSTRUCTION ACTIVITIES * This schedule does not reflect days added to the contract for holidays, weather days or special events 3 Concrete pavement replacement along the median on I-95 between NW 17 Street and NW 29 Street. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 4 Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12 Avenue to I-95 for bridge widening. UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 5 UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Demolition of SR 836 traffic railing and removal of bridge beams between the Lawrence Canal and NW 17 Avenue SR 836 UPCOMING CONSTRUCTION ACTIVITIES 6 12 1.Demolition of median separator between the eastbound I-395 mainline and local road connector (Ongoing) 2.Removal of median separator between the eastbound I-395 mainline and the westbound mainline (October) 3.Begin construction on westbound outside, local road lanes (October) 4.Begin construction on eastbound, local road lanes (October) Work Zone Typical Section UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 3 4 3 2 1 4 * This schedule does not reflect days added to the contract for holidays, weather days or special events 7 UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 8 •Implement traffic shift on westbound I-395 from NE 1 Avenue to I-95. Traffic will be shifted to the left (mid-September) •Begin demolition of outside I-395 on-ramp that was closed as part of the NE 12 Street Closure (late -September) 1 2 UPCOMING & ONGOING CONSTRUCTION ACTIVITIES 1 2 * This schedule does not reflect days added to the contract for holidays, weather days or special events 9 UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Auger Cast Pile Load Testing begins mid/late September SR 836 UPCOMING CONSTRUCTION ACTIVITIES 10 Bridge foundation work for westbound Signature Bridge (January 2020) UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD SR 836 UPCOMING CONSTRUCTION ACTIVITIES 11 ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR: •Southbound I-95 and northbound I-95 ramps to eastbound I-395 •Lane closures along I-395 mainline and connector road •Lane closures along Biscayne Boulevard UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD •Provide drivers with real-time travel information; •Encourage motorists to take alternate routes; •Clear incidents more quickly, thereby reducing secondary incidents; and •Make work zones safer for highway workers and motorists. Smart Work Zone Management System (SWZMS) -The project is implementing a SWZMS that will utilize Intelligent Transportation System (ITS) devices such as traffic cameras, data collection devices and portable message signs to: TRAFFIC MANAGEMENT SYSTEM 12 N 13 COMMUNITY OUTREACH PROJECT WEBSITE •www.i-395miami.com •Sign-up for project alerts/updates Lane closure information Upcoming construction activities Presentations •Calendar of events OUTREACH OFFICE IN THE OVERTOWN COMMUNITY •1035 NW 3 Avenue, Miami, Florida 33136 STAKEHOLDER MEETINGS •Ongoing individual stakeholder meetings and presentations •Ongoing communications with CMB Communications and Transportation Departments •Next stakeholder meeting –September 16, 2019 786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez www.i-395miami.com THANK YOU! 14