R9D CMB Commission UpdateCity of Miami Beach Commission Update
September 11, 2019
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
2
•Construction of new drainage, median concrete barrier wall and pavement replacement on I-95 between
NW 17 Street and NW 29 Street (Ongoing)
•Construction of foundations for overhead sign structures (Ongoing)
•Erection of new sign structures along I-95. This work will require nighttime full closures of I-95
between NW 17 Street and NW 29 Street (late-September)
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
3
Concrete pavement replacement along the median on I-95 between NW 17 Street and NW 29
Street.
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
4
Ongoing work on eastbound SR 836 from NW 17 Avenue to the Miami River and from NW 12
Avenue to I-95 for bridge widening.
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
5
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Demolition of SR 836 traffic railing and removal of bridge beams between the Lawrence Canal and
NW 17 Avenue
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
6
12
1.Demolition of median separator
between the eastbound I-395 mainline
and local road connector (Ongoing)
2.Removal of median separator between
the eastbound I-395 mainline and the
westbound mainline (October)
3.Begin construction on westbound
outside, local road lanes (October)
4.Begin construction on eastbound, local
road lanes (October)
Work Zone Typical Section
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
3 4
3
2
1
4
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
7
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
8
•Implement traffic shift on
westbound I-395 from NE
1 Avenue to I-95. Traffic
will be shifted to the left
(mid-September)
•Begin demolition of
outside I-395 on-ramp that
was closed as part of the
NE 12 Street Closure (late
-September)
1
2
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
1
2
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
9
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Auger Cast Pile Load Testing begins mid/late September
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
10
Bridge foundation work for westbound Signature Bridge (January 2020)
UPCOMING CONSTRUCTION
ACTIVITIES
THREE MONTH LOOK
AHEAD
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
11
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
•Southbound I-95 and northbound I-95 ramps to eastbound I-395
•Lane closures along I-395 mainline and connector road
•Lane closures along Biscayne Boulevard
UPCOMING CONSTRUCTION
ACTIVITIES
THREE MONTH LOOK
AHEAD
•Provide drivers with real-time
travel information;
•Encourage motorists to take
alternate routes;
•Clear incidents more quickly,
thereby reducing secondary
incidents; and
•Make work zones safer for
highway workers and motorists.
Smart Work Zone Management
System (SWZMS) -The project is
implementing a SWZMS that will
utilize Intelligent Transportation
System (ITS) devices such as traffic
cameras, data collection devices
and portable message signs to:
TRAFFIC MANAGEMENT SYSTEM
12
N
13
COMMUNITY OUTREACH
PROJECT WEBSITE
•www.i-395miami.com
•Sign-up for project alerts/updates
Lane closure information
Upcoming construction activities
Presentations
•Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
•1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
•Ongoing individual stakeholder meetings and presentations
•Ongoing communications with CMB Communications and
Transportation Departments
•Next stakeholder meeting –September 16, 2019
786-280-0983
OGonzalez@mrgmiami.com
Contact:
Oscar Gonzalez
www.i-395miami.com
THANK YOU!