GOB Sidewalks Progress Report09/17/2019
Sidewalks Sidewalk SF Curb & Gutter LF Cost
North Beach 5,368 384 35,978.80$
Middle Beach 11,895 715 68,531.10$
South Beach 19,573 755 113,564.50$
Total 36,836 1,854 218,074.40$
General Obligation Bond Progress Report
Notes:
Quick wins completed in North Beach and Middle Beach
South Beach work is on track to meet our quick win deadline in May