UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Ongoing concrete pavement saw
cutting in preparation for concrete
replacement
TRAFFIC SHIFT:
All I-95 travel lanes shifted to the
right on southbound I-95 from SR
836 to NW 8 Street to allow the
contractor to construct new bridge
foundations.
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
3
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
ANTICIPATED NIGHTTIME LANE CLOSURES ON THE I-95 CORRIDOR:
•Full closure of northbound and southbound I-95 to relocate a crane
to the east side of I-95
•Nighttime lane closure along I-95 between NW 8 Street and NW 29
Street
•Continuous weekend lane closures for pavement work
•Closure of I-95 entrance ramp at NW 8 Street
•I-95 ramps to I-395 and SR 836
4
Ongoing work on
eastbound SR 836 from
NW 17 Avenue to the
Miami River and from
NW 12 Avenue to I-95
for bridge widening
CONSTRUCTION ACTIVITIES
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
5
ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR:
•Single and double lane closures along eastbound and westbound SR 836
•NW 17 Avenue under SR 836
•SR 836 ramps to northbound and southbound I-95
•Arterial roads under SR 836
•NW 17 Avenue and NW 12 Avenue ramps to SR 836
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
6
1.Removal of median separator
between the eastbound I-395
mainline and the westbound
mainline (Ongoing)
2.Construction of westbound outside,
local road lanes. Foundation work
started at NE 2 Avenue and is
moving towards the west
(Ongoing)
3.Begin demolition of portions of
existing eastbound I-395 to allow
for the construction of new bridge
foundations (February)
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
1
2
3
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
7
CONSTRUCTION ACTIVITIES
I-395 steel sheet pile driving for Signature
Bridge center pier
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
8
•Auger Cast Pile (ACP) Operations
for Segmental Bridges started in late
December 2019
•ACP Completed: 160/1948
o I-395 Segmental ACP –857
o I-395 Signature ACP –520
o SR 836 Viaduct ACP -571
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
9
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Shift traffic to the left on the westbound
MacArthur Causeway approach to Biscayne
Boulevard exit (February 17, 2020)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
10
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Lane shift (to south side) on the
westbound MacArthur Causeway ramp
to Biscayne Boulevard to allow for
clearing and grubbing activities. This
will allow for construction of new
retaining wall (February,17 2020)
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
11
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will
be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street)
and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur
Causeway)
Close Bayshore loop ramp to EB MacArthur Causeway (March 2020)
1
1
2
2
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
12
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
•Lane closures along eastbound and westbound I-395
•Lane closures along Biscayne Boulevard and other arterial roadways
adjacent to I-395
•I-395 to I-95 ramp closures
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
13
COMMUNITY OUTREACH
PROJECT WEBSITE
•www.i-395miami.com
•Sign-up for project alerts/updates
Lane closure information
Upcoming construction activities
Presentations
•Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
•1035 NW 3 Avenue, Miami, Florida 33136
STAKEHOLDER MEETINGS
•Ongoing individual stakeholder meetings and presentations
•Next stakeholder meeting –March 16, 2020
786-280-0983
OGonzalez@mrgmiami.com
Contact:
Oscar Gonzalez
www.i-395miami.com
THANK YOU!
14