2020-01-23 - Program General StatusPROGRAM GENERAL STATUS PROJECTS   12/19/19 1/23/20 VARIANCE  COMPLETE 3 3 0  ACTIVE 29 31 2  PENDING 6 4 -2  FUTURE 19 19 0  ALL 57 57 0   115** PROJECTS & SUB-PROJECTS*   12/19/19 1/23/20 VARIANCE    No. % No. % %  ACTIVE/COMPLETE 49 45% 56 50% 5%  CONSTRUCTION 17 16% 13 11% -4%  PLANNING / DESIGN 17 16% 26 23% 7%  COMPLETE 15 14% 17 15% 1%               FUTURE 60 55% 59 51% -4%   Legend: * A sub-project is an element of one of the main 57 approved G.O. Bond projects that is budgeted and therefore tracked as an individual line item with its own scope of work and implementation timeline. **Total number of sub-projects increased from 109 to 115.