395_836_95 CMB 5-13-2020City of Miami Beach Commission Update
May 13, 2020
2
This PowerPoint presentation was prepared by the Florida Department of
Transportation (FDOT) staff and has been made available to the public as part of
public records access. Any dissemination of this presentation by anyone or entity
other than FDOT staff is not official. Any questions can be sent to FDOT-
D6PIO@dot.state.fl.us.
This presentation may not be altered.
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
3
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
•Contractor completed concrete
pavement replacement of the three
inside southbound I-95 lanes from
NW 29 Street to south of NW 20
Street on Sunday, May 3.
•Contractor implemented continuous
lane closures on northbound I-95 to
complete the concrete pavement
replacement of the lanes adjacent to
the median from NW 20 Street to NW
29 Street.
•The continuous lane closures will
expedite the concrete replacement
phase of the project by at least four
weeks.
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
4
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:
•Nighttime lane/ramp closure along I-95 between NW 8 Street and NW
29 Street
•Closure hours have been adjusted based on current traffic
conditions to 8 p.m. until 8 a.m.
•Continuous lane closures (24/7) for extended periods of up to three
to four weeks are planned for northbound I-95
5
•Traffic shifted on westbound SR
836 from the Miami River to east
of NW 17 Avenue to the left side
of the roadway
•Traffic shifted on eastbound SR
836 from NW 17 Avenue to the
Miami River to the right side of the
roadway
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
6
•Contractor implemented a
continuous closure of the outside
eastbound SR 836 lane to expedite
the replacement of the concrete
pavement with asphalt pavement
•Demolition of median area on SR
836 has started at NW 12 Avenue
and will be moving to the west over
the Miami River
•Contractor has started Auger Cast
Pile (ACP) testing program on SR
836 for the foundations of the new
double decked section
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
7
ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:
•Single and double lane/ramp closures along eastbound and westbound
SR 836
•Arterial roads under SR 836
•Closure hours have been adjusted based on current traffic
conditions to 8 p.m. until 8 a.m.
•Continuous lane closures (24/7) are being implemented along SR
836
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
8
•Construction of the center
signature bridge foundations
(Ongoing)
•Construction of westbound outside,
local road bridge foundations
(Ongoing)
•Demolition of portions of existing
eastbound I-395 to allow for the
construction of new bridge
foundations (Ongoing)
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
9
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
The westbound I-395 ramp to
northbound I-95 has been reduced
from two lanes to one lane
The reduction in lanes is necessary
to reconstruct the section of I-95
where the eastbound SR 836 ramp
and westbound I-395 ramp join I-95
The lane reduction is expected to be
in place for approximately 18 months
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
10
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
•Westbound MacArthur Causeway
Ramp lane to Biscayne Boulevard
has been shifted to the left to allow
for the construction of a new
retaining wall on the right side
Only one travel lane is available
on the ramp from the MacArthur
Causeway to North Bayshore
Drive
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
11
UPCOMING & ONGOING
CONSTRUCTION ACTIVITIES
Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will
be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street)
and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur
Causeway).
Close Bayshore loop ramp to EB MacArthur Causeway (June 2020)
1
1
2
2
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
12
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
•Lane closures along eastbound and westbound I-395
•Lane closures along Biscayne Boulevard and other arterial roadways
adjacent to I-395
•I-395 to I-95 ramp closures
•Closure hours have been adjusted based on current traffic
conditions to 8 p.m. until 8 a.m.
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
13
COMMUNITY OUTREACH
PROJECT WEBSITE
•www.i-395miami.com
•Sign-up for project alerts/updates
Lane closure information
Upcoming construction activities
Presentations
•Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
•1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT
THIS TIME)
STAKEHOLDER MEETINGS
•Stakeholder meetings will be held virtually until further
notice, Date TBD.
786-280-0983
OGonzalez@mrgmiami.com
Contact:
Oscar Gonzalez
www.i-395miami.com
THANK YOU!
14