Loading...
LTC 247-2003 CITY OF MIAMI BEACH Office of the City Manager Letter to Commission No. To: From: Subject: Mayor David Dermer and Date: October 8, 2003 Members of the City Commission Jorge U. Gonzalez ['~ J~'~ City Manager ~.~ FPL INSTALLATION OF NEW UNDERGROUND DUCT BANK ON ALTON ROAD This LTC is to inform you that Florida Power & Light Company (FPL) has been installing a new electrical underground duct bank on Alton Road, from 29t~ Street to 41st Street. This project is part of the FPL capital improvements program to modernize and upsize their electrical power distribution system in Miami Beach. The contractor suffered construction delays in their planned schedule due to unexpected weather conditions and unforeseen soil conditions. City staff has met with FPL representatives and received a commitment that the project will be completed no later than October 31, 2003. We are monitoring the contractor's daily progress and will keep you appraised if there are any other significant delays that will prevent them from achieving the promised completion date. For your information, the current asphalt patch in the completed sections is only of temporary nature. FPL is required to complete full lane restoration of the pavement which includes milling and resurfacing the full width of the travel lane in the areas that were e ×~a~'~ '~FHB\II c: Robert C. Middaugh, Assistant City Manager F{red H. Beckmann, Director of Public Works Mike Alvarez, Assistant Public Works Director F:\WORK~ALL~0LUCY LLOPIS~LTC\FPL Duct Bank Installation.doc