Meeting Minutes 10.22.20
General Obligation Bond Oversight Committee
City of Miami Beach
MEETING MINUTES No. 21
October 22, 2020
Members in Attendance
Via Zoom:
Karen Rivo, Chair
Marie Peter, Vice Chair
Jeremy Waks
Francisco Diez-Rivas
Jack Glottman
Jason Greene
Wendy Squire
Ron Starkman
Sean Smith
Bryan Rosenfeld
Laura Veitia
Staff and Guests Attendance:
Maria Hernandez, Liaison
John Woodruff, GOB Working Group
Alex Denis, GOB Working Group
Eric Carpenter, GOB Working Group
Devin Ramirez
Thais Vieira
Allison Novack
David Martinez
Rudy de la Torre
Lily Alvarez
Jason Jacobson
Steven Feldman
Barbara Hernandez
Frank Garcia
Roland Aragunde
Kevin Pulido
Gedel Merzius
Vanessa Vazquez
Lauren Firtel
Rickelle Williams
Nelson Perez-Jacome
Robert Rabinowitz
Lauren Swan
Sarah Bassett
Paul Acosta
Elizabeth Wheaton
Lazaro Guerra
Jose Gonzalez
Josiel Ferrer
Nick Kallergis
Thomas Mooney
Meeting Start Time: 4:30 pm
General Note: These meeting minutes are condensed and seek to capture the overall intent of discussions
as interpreted by the meeting coordinator. Each paragraph indicates the time on the audio recording
where the discussion commenced during the meeting. For more detail on the discussion, please refer to
the audio recording in its entirety.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 2 of 9
I. Roll Call and Introductions
(Refer to the 10.22.20 Meeting Audio Recording on the G.O. Bond Website.)
0:02 Chair Karen Rivo called the meeting to order. Roll call was completed.
II. Committee Business
Adoption of Meeting Minutes
2:57 Chair Karen Rivo requested a motion to approve the September 24th minutes.
Motion:
3:10 Jason Greene made a motion to approve the minutes.
3:16 Jack Glottman seconded the motion. Motion passed.
No Meeting in November
3:28 Chair Karen Rivo reminded the Committee Members that there is no G.O. Bond Oversight
Committee meeting in November. The next meeting is on December 17th, 2020.
III. Community Outreach
4:00 Allison Novack informed the Committee Members that the G.O. Bond Road Show has started
up again, where Staff has been reaching out to residents and local professional groups informing
them on the G.O. Bond. On October 20th, both Maria Hernandez and she addressed the
Construction and Development Council at the Chamber of Commerce. Staff received good
feedback from the presentation and found that participants were interested in the City’s
procurement process in order to get involved with some future projects.
IV. Public Comment
8:10 Chair Karen Rivo asked if anyone from the public would like to ask a question or make a
comment.
No one spoke.
V. New Design Review Board Ordinance
(Refer to pages 2-10 on the Agenda & Handouts_10-22-20 and the recording on the G.O. Bond
Website.)
8:23 Nick Kallergis explained Ordinance No. 2020-4353, which was approved by City Commission
on September 16th, which requires the City to obtain an advisory recommendation of the Design
Review Board (DRB) for certain city projects, which do not currently require formal DRB review.
This is a non-binding recommendation and it specifies which projects it will apply to. Once a
project is first presented, the board has one month to make a recommendation, which is limited
to only the design of the proposed project.
11:50 Chair Karen Rivo asked Maria Hernandez how many G.O. Bond projects does this affect.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 3 of 9
12:06 Maria Hernandez explained that this ordinance is going to affect many of the projects such
as street lighting, new roadway and streetscape projects, medians, traffic circles, etc. Schedules
might need to be slightly adjusted to account for the Design Review Board approval process
14:12 Chair Karen Rivo asked what the initial reasoning for this ordinance was.
14:20 Thomas Mooney explained that this ordinance was referred by Commissioner Samuelian
to the Land Use Committee for discussion, regarding enhancing the aesthetics of the City’s public
infrastructure projects.
15:10 Ron Starkman noted that this ordinance will allow residents to weigh in on projects that
are in their area because the City will be required to send out meeting notices.
15:56 Nick Kallergis confirmed Ron Starkman’s comment.
16:53 Laura Veitia asked what the added timeline to the affected projects is, based on this new
process.
17:00 Thomas Mooney explained that there is a very strict time frame that the DRB must review,
which is 35 days. This new process may add about 60 days to the timelines, when you consider
noticing and outreach.
VI. 41st Street Corridor Update Presentation
(Refer to pages 11- the Agenda & Handouts_10-22-20 on the G.O. Bond Website.)
19:37 Maria Hernandez reminded the Committee Members of AECOM’s presentation at the last
Oversight Committee meeting for 41st Street Corridor. Sarah Bassett will be conducting the
presentation that was given at the Mayor’s 41st Street Blue-Ribbon Committee on October 15th.
After the presentation, Staff will be asking the Oversight Committee for 2 motions:
• A recommendation to fast track the project, meaning completing the project within
Tranche 2. Staff would have to advance funds from Tranches 3 and 4 to Tranche 2.
• The second motion is for the Committee to recommend that AECOM proceeds with a
hybrid design, which is based on the feedback from the community survey that was
conducted on October 1st and comments from the Mayor’s 41st Street Blue-Ribbon
Committee meeting.
23:30 Sarah Bassett from AECOM explained the presentation found on pages 11-65. They
received 159 responses from the public, mostly from residents who live in the area. In terms of
parking preference, Scheme 2 was more popular, which is to keep some parking on 41st Street
Elements that are being brought from Scheme 1 into the hybrid scheme are: enhance materials,
branded sidewalk pavement, colored textured crossings, some shade trees, multi-level plantings,
a gateway feature and bicycle parking. Elements that are being brought from Scheme 2 into the
hybrid scheme are: expanding the design boundary into side streets, some parking to remain on
41st Street, keeping palm trees, fixed seating at midblock, a gateway feature and bicycle parking.
While focusing on 41st Street.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 4 of 9
Explanation and presentation continued.
44:00 Ron Starkman noted that the presentation looks beautiful. He commented that it seems as
though some of the most expensive aspects from each scheme were combined into the hybrid
design. He asked how this is going to work with respect to the budget. His second question was
whether there will be a good use of permeable pavement for blue-green infrastructure which is
the direction he believes the City is trying to move in.
44:50 Sarah Bassett explained that AECOM will be making sure that all elements are feasible
within the budget. In terms of the pavement material, AECOM is exploring the kind of materials
that can fit the blue-green infrastructure condition.
45:54 Ron Starkman asked Sarah Bassett when will AECOM have the answer to both questions.
46:09 Maria Hernandez explained that part of AECOM’s scope of services is to give Staff a budget
for the final hybrid design, which is supposed to be about $10 million dollars in construction costs
and the remainder is for drawings, permits, etc. She stressed the importance of staying within
the budget.
48:38 Sarah Bassett added that AECOM will have an idea of material in cost per square foot, as
part of the schematic design that will be presented to the City.
49:10 Francisco Diez-Rivas explained that one of the biggest obstacles that was discussed at the
Mayor’s 41st Street Blue-Ribbon Committee meeting was the traffic around the peak times and
the traffic caused by people trying to parallel park. He explained how residents wanted
something to bring the hotel traffic to that area. He mentioned how a masterplan needs to be
done in order to answer what it is we are trying to create in that area.
52:30 Gedel Merzius explained that this project is a conceptual design to revitalize the corridor
space. The masterplan that Francisco Diez-Rivas mentioned is a zoning overlay, where Staff will
look at different parts of the corridor and research how business development can increase. This
is a completely different project that will need direction specifically from the Commission at a
later date.
54:02 Sarah Bassett explained that AECOM is focused on bicycle amenities and trying to reduce
the use of the car. In terms of traffic calming, materials can be used in order to signify that the
area is a pedestrian friendly environment. In terms of parking, some of the parking spaces will be
removed in order to widen sidewalks.
55:33 Maria Hernandez explained to Francisco Diez-Rivas that some of the attendees at the
Mayor’s 41st Street Blue-Ribbon Committee wanted all parking removed, which is what Scheme
1 shows. Then Staff received significant community input and residents emphasized they didn’t
want any of the spaces removed. With the hybrid plan staff is trying to appease both sides with
a solution that works.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 5 of 9
58:17 Chair Karen Rivo reminded the Committee Members that Maria Hernandez is looking for 2
motions.
58:41 Francisco Diez-Rivas mentioned how originally the City was trying to coordinate
construction where the two main Causeway entrances to the City would not be blocked. He asked
where the City stands with that now if a motion gets passed to fast track construction on 41st
Street.
59:16 Eric Carpenter explained that the MacArthur Causeway is way underway on the work and
completion is all dependent on the planning study being done on the Rail. He mentioned that it
would be reasonable for this motion to include any consideration of impacts from projects at the
entrances of Miami Beach.
Motion 1:
1:00:20 Jack Glottman made a motion to fast track the 41st Street project to be completed
by Tranche 2 or within a reasonable time, considering the other projects that are
occurring on the Causeways. Marie Peter seconded the motion. Motion passed
unanimously.
Motion 2:
1:02:37 Jack Glottman made a motion to recommend that AECOM proceeds with the
hybrid design, based on the feedback they received from the community survey, as well
as input from the Mayor’s 41st Street Blue-Ribbon Committee. Jason Greene seconded
the motion. Motion passed unanimously.
VII. Major Tranche 1 Projects Update
(Refer to pages 66-71 on the Agenda and Handouts Package found on the G.O. Bond Website.)
#45 Fire Station #1 – Current Completion Date: May 2023
1:03:24 David Martinez reminded the Committee that at the last Oversight Committee meeting
it was reported that the project was over budget and Staff was going to revisit the programming.
As a result, the Administration was unable to bring the budget down any further with the current
program, so it was therefore determined that it is not possible to design and construct the project
to include the 911 call center.
1:05:05 Maria Hernandez explained that the 911 call center was originally added to the project
scope without a change in the project budget. At the time of that decision it was assumed that
the funding could be found at a later date. Fast forward to today, post Covid-19, the 911 call
center portion of the project is unaffordable, therefore staff will move forward with the project
without the 911 call center. The renovation of the police station (GO #48 Police Headquarters) is
in Tranche 3 so Staff has several years to figure out where to relocate the 911 call center from
the Police station.
1:08:14 Jason Greene asked if this project is fully funded with the G.O. Bond or will supplemental
funding be needed.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 6 of 9
1:08:24 Maria Hernandez explained it is supposed to be fully funded only with G.O. Bond funds.
1:10:14 Chair Karen Rivo asked if the project is on schedule.
1:10:18 David Martinez explained the schedule has been impacted with this budgeting process
and will need to be adjusted by 4 to 5 months, to be completed by May 2023.
#1 72nd St. Community Complex – Current Completion Date: September 2023
1:10:59 David Martinez explained that Staff is expecting to receive the technical proposals for
the short-listed firms by November 16th. The selection committee will convene on December 7th
and make their recommendations, in order to bring this item to Commission in January to award
a contract to a design -build firm. Florida Power and Light has secured their permits to begin the
relocation of their transmission lines on the site.
1:12:24 Sean Smith asked if the plans will be brought to the Parks and Recreation Committee
before going to Commission in January.
1:12:42 David Martinez explained that Staff will not be engaged with a design-builder until it is
brought to Commission, so there will not be a design to provide, therefore it will not go to the
Parks and Recreation Committee before going to Commission in January.
Discussion continued.
#15 Par 3/Bayshore Park – Current Completion Date – December 2022
1:15:33 David Martinez reminded the Committee that Staff submitted several requested reports
to DERM 2 months ago. Until they approve these reports, Staff cannot proceed with the
permitting. DERM needed 60 days to review these reports. If Staff hears back within the next 2
weeks, the schedule is on time to begin procurement in early 2021.
1:17:11 Sean Smith asked David Martinez if until the project is out to bid, Staff does not know if
the full scope of the project can be completed and if it comes back overbudget, some items will
need to be removed.
1:17:21 David Martinez confirmed that is correct, and Staff is currently verifying and qualifying
the budget on this project.
#23 Pedestrian Bridge – Current Completion Date: June 2023
1:18:17 David Martinez explained that the tentative construction start is Summer 2022 with a
12-month duration. The plans are being updated for the condominium tower in order to begin
permitting of the tower project.
1:19:01 Marie Peter asked where the City is with the FDOT permit.
1:19:20 David Martinez explained that discussions with FDOT have already occurred, but
revisions to the plans will not be completed until the first quarter of 2021.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 7 of 9
1:20:25 Marie Peter asked if the train project is going to affect the bridge.
1:20:43 Eric Carpenter explained that the bridge was designed with the train project in
consideration. The County had to sign off with FDOT that they reviewed the drawings and agreed
they could work with what the City was proposing.
#24 Middle Beach Beachwalk PH3 – Current Completion Date: June 2021
1:21:33 David Martinez explained that the projected completion date is still June 2021. They
started the paver brick installation two weeks ago, but the weather has created a slow start.
#12 N. Beach Oceanside Beachwalk – Current Completion Date: February 2022
1:22:36 David Martinez explained that this is the last portion of the Beachwalk, from 79th to 87th
Streets This project is out to bid, and responses are expected by next month. Staff is working with
a different contractor in order to relocate some trees from the pathway. Compared to the other
sections of the Beachwalk that varies from 15-25 ft wide, this path will be 25 ft wide, with several
connections from the beach to the park.
VIII. Other Projects Update
(Refer to pages 72-76 on the Agenda and Handouts Package found on the G.O. Bond Website.)
#33 Part 1 Tree Planting – Current Completion Date April 2022
1:27:09 Elizabeth Wheaton reported that on October 14th, the City Commission approved the
Urban Forestry Masterplan, which provides guidance and goals in enhancing tree canopy from
17% today, up to 22%. She explained the map found on page 73. In year 1, 457 trees were planted
and so far, 576 trees have been planted in year 2. Staff has been able to leverage these projects
with Miami-Dade’s NEAT Streets Grants Program.
1:30:15 Laura Veitia explained that the plantings look great. She asked who maintains the trees,
the residents or the City.
1:30:42 Elizabeth Wheaton explained that private properties are required to maintain all trees
adjacent to their property. One of the elements in the Urban Forestry Masterplan is to create a
maintenance plan, which Staff is currently researching.
#40 41St St. Lighting Upgrades – Current Completion Date January 2021
1:32:35 Rudy de la Torre explained that Staff is ready to submit their application to the Design
and Review Board to be heard on January 5th. (Subsequent to this meeting, the City’s Legal and
Planning Departments have opined that this application is not required since this is a
maintenance project). Staff is in discussion with the FDOT to apply for their permitting process.
The FDOT has requested replacement, not only of the pedestrian lighting, but also for the
common roadway lighting. This addition of the 28 light fixtures has a cost of approximately
$15,000 which Staff considers minor when considering the benefits provided throughout the
entire corridor.
1:36:25 Jack Glottman asked if the additional costs fit within the G.O. Bond budget.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 8 of 9
1:36:38 Maria Hernandez explained that the original budget for this subproject was $85,000, by
doing it in-house. That amount and the additional $15,000 will be taken from the full budget of
$15 million dollars and the remaining amount will be used for the streetscape project.
#39 Part 1 Seawalls/Shorelines – Current Completion Date April 2022
1:38:24 Nelson Perez-Jacome explained that push button contracts were awarded at the October
14th Commission meeting. The remaining seawalls that Public Works is managing are in the design
phase and are on track to be started October 2021.
1:39:10 David Martinez explained that the seawall at 8100 Hawthorne Avenue, which is a City
owned parking lot, is approximately 216 ft. in length. This project was awarded as a renovation
of a parking lot about a month ago and Staff is currently finalizing contracts. Staff will hopefully
be mobilizing in December. The Maurice Gibb Park seawall is approximately 550 ft. in length and
includes a living shoreline component. The park is currently in the design phase. The third seawall
is located at Brittany Bay Park, which is approximately 465 ft. in length and also includes a living
shoreline component. This location is ready to go out for bid by December.
1:43:27 Jack Glottman asked if the same contractor was doing all the projects.
1:43:42 Nelson Perez-Jacome explained that currently there isn’t a specified contractor since the
locations are in the design phase, but the “Push Button” contracts provide a list of qualified
contractors.
1:44:05 David Martinez explained that in respect to the 3 projects CIP is working on, the seawalls
are a component to a larger project. Staff will be hiring a general contractor that may hire a sub-
contractor for the seawall.
IX. Program General Status & Sub-Projects Update, Closed Projects
(Refer to pages 77-85 on the Agenda & Handout Package on the G.O. Bond Website.)
1:45:08 Maria Hernandez explained the charts found on pages 77-85. Currently, the City has
spent $30 million dollars from the budget and $15 million dollars are encumbered. There are now
29 completed sub-projects, 8 under construction, 15 in design, and 16 in planning. There are 26
projects that are closed out and 3 that are completed and will be closed out very soon.
X. Quick Wins Remaining
(Refer to pages 86 & 87 on the Agenda & Handout Package on the G.O. Bond Website.)
#57 Cameras in Entertainment District - Current Completion for Lummus Park November 2020
1:49:15 Steve Feldman explained that the main fiber cables arrived in this week for Lummus Park
and the installation is pending scheduling due to weather. On Washington Avenue staff has been
working with Public Works and performed a walkthrough with one of the contractors to layout
the plan.
G.O. Bond Oversight Committee
Meeting Minutes No. 21
October 22, 2020
Page 9 of 9
#56 Cameras on Beachwalk – Current Completion December 2020
Steve Feldman explained that the directional boring of the Beachwalk from 14th Place towards
24th Street has been completed. The secondary boring for the other side of the Beachwalk will
begin shortly.
#44 Public Safety Radio System – Current Completion December 2020
1:51:20 Lazaro Guerra explained that today Staff met with the Legal Department to finalize the
amendment with the contractor. The amendment will be sent to the City Manager and then to
the contractor for execution as soon as the Legal Department is done reviewing the amendment.
Currently there are 8 sites and once this amendment gets executed, the 9th and final site will be
completed.
XI. Public Comment
No one from the public spoke.
XII. Adjournment
Meeting was adjourned.