LTC 166-2021 RUE VENDOME PUBLIC PLAZA - NOTICE OF LANE CLOSURES AT NIGHTO FFIC E O F THE C ITY M A N A G ER
LTC #
TO:
FROM:
DATE:
166-2021 LETTER TO COMMISSION
Mayor Dan Gelber and Members of the
Raul J. Aguila, Interim City Maga9@Lt
April 19, 2021
SUBJECT: RUE VENDOME PUBLIC PLAZA- NOTICE OF LANE CLOSURES AT NIGHT
The purpose of this Letter to Commission is to update the Mayor and City Commission on the status
of the project to construct a public plaza at Rue Vendome, adjacent to the Normandy Fountain, in
North Beach.
On March 3, 2020, the City broke ground on the construction project which permanently closed (to
vehicular traffic) that portion of Rue Vendome betw een 71 Street and Normandy Drive, to create a
public plaza which will extend to the area around the Normandy Fountain. The project is currently
eighty-five percent complete.
Closure of multiple lanes of traffic on 71 st Street is necessary to perform work associated with the
alteration of on-street parking/pedestrian crossings, and asphalt restoration. Traffic in the area is
heaviest during the day. To minimize the impact the closure will have on the east bound traffic, the
contractor will complete the pending work within the Florida Department of Transportation (FOOT)
Right of Way (ROW ) on 71 Street, working at night between 10:00pm - 5:30am, during the
period April 20, 2021 - April 23, 2021.
Traffic will be reduced to only one open lane on 71 st Street, and the Maintenance of Traffic (MOT)
procedures will be in place and modified as required to accomplish the work. Signage will be
provided directing traffic around the work area.
The neighborhood has been notified of the changes in traffic patterns and pedestrian routes via the
attached advisory (Attach ment "A"). Moderate levels of construction noise and light are expected
from the construction equipment and workers. The neighborhood business association has been
advised of the closures and night work.
Construction of the overall project is expected to be substantially complete in early May 2021.
Should you have any questions, please contact David Martinez at 305-673-7071.
A ttachm e nt A
MIAM/BEACH
RISING
.. ABOVE ~----~. '_,:.,·:-_: __ ....:__ ~ .. -~ '_
Rue Vendome Public Plaza
Project Update: April 2021
Project Overview and Benefits
Reconstruction of the Rue Vendome Plaza around the
Normandy Fountain is currently underway to create
an open, at grade, public plaza. This project involves
raising Rue Vendome between Normandy Drive and
71 Street to create a level, accessible public plaza.
Improvements include associated traffic signalization
adjustments, construction of the public plaza,
landscaping, lighting and other improvements
necessary to encourage public use as a venue for
various gatherings.
What's Happening
Starting the week of April 19, the contractor is
expected to initiate the demolition of the eastern
crosswalk on 71 Street. The work will take place
overnight. Two lanes may be closed during this time.
Timeline
The completion of this project has been delayed due to unforeseen conditions in the field. The
project is anticipated to be complete by June 2021.
The upcoming crosswalk work is approved to take place overnight to avoid further traffic
impacts on 71 Street.
Please note, this schedule may change due to weather or other unforeseen circumstances.
What to Expect
• Moderate levels of construction noise are expected during the day and during
approved night hours.
• Construction equipment, machinery and workers will be present in the work
zone.
• The construction fence will be relocated and adjusted.
• Some businesses will have limited access to the extent necessary for work to
proceed.
• Lane closure will be necessary at times on 71 Street.
• Pedestrian detour detours will be in effect at times.
• Other lane closures in the area may be necessary.
A tt ac h m e n t A
Please note, the project team is closely monitoring the situation surrounding COVID-19. The
contractor is enforcing strict social distancing measures and employees are using face covers
while on-site, including during break times.
Who to Contact
Kevin Pulido, Neighborhood Affairs Manager
786.568.6051
KevinPulido@miamibeachfl.gov