LTC 022-2004 Phase II of the South Pointe Neighborhood Presentation CITY OF MIAMI BEACH
Office of the City Manager
Letter to Commission No. 022-2004
To:
From:
Subject:
Mayor David Dermer and Date: January 23, 2004
Members of the City Commission
Jorge M. Gonzalez (~
City Manager
PRESENTATION AND DISCUSSION OF THE PROPOSED BASIS OF DESIGN
REPORT FOR PHASE II OF THE SOUTH POINTE NEIGHBORHOOD RIGHT-
OF-WAY IMPROVEMENT PROJECT AT THE JOINT FINANCE AND
CITYWIDE PROJECTS AND NEIGHBORHOODS COMMITTEE MEETING OF
JANUARY 28, 2004.
This Letter to Commission is an update of the Referral to a joint meeting of the Finance
and Citywide Projects Committee and the Neighborhoods Committee regarding the Basis
of Design Report (BODR) for Phase II of the South Pointe Neighborhood Right-of-Way
(ROW) Improvement Project. This item was referred by the City Commission at the
September 10, 2003 Commission meeting. The item included a requirement for the
meeting to be scheduled for an evening time, and to be held in a location in the South
Pointe area.
This meeting has been scheduled for Wednesday, January 28, 2004 at $:30PM at South
Pointe Elementary, located at 1050 4th Street, Miami Beach, FL. A copy of the Draft
BODR will be delivered to you along with the agenda for this meeting.
Below is an update to the project since the September 10, 2003 Commission Meeting.
Through the City's ongoing Planned Progress Capital Improvement Program, staff and
consultants are moving forward with the planning and design of Phase II of the South
Pointe Neighborhood ROW Improvement Project. The project area is bounded by
Washington Avenue on the east, 2nd Street on the south, 5th Street on the north, and Alton
Road on the west. The project includes comprehensive stormwater, water, and
streetscape improvements. The City has followed its standard planning procedure for the
project which includes the identification of needed improvements and the consideration of
various alternatives which meet those needs. As part of the process, two Community
Design Workshop (CDW) meetings were held on March 4, 2003 and May 1, 2003 and
general consensus among the participating residents was obtained. A draft BODR was
then developed and circulated for review. A component of the BODR review was the
presentation of the proposed improvements to the Historic Preservation Board (HPB) and
the Design Review Board (DRB) for the areas that fall within their jurisdictions.
For most of the City's Neighborhood ROW Improvement Projects, the next step in the
process is a review of the BODR by the GO Bond Oversight Committee prior to review and
approval by the Commission. Doing so meets the GO Bond Fund spending oversight
Letter to Commission
Joint Finance &Citywide Projects and Neighborhoods Committees Meeting - 1/28/04
January 23, 2004
Page 2 of 2
requirements and provides another advertised public forum for discussion of the planned
improvements. In the case of the South Pointe neighborhood, funding is provided by the
South Pointe RDA rather than GO Bond funds, so it is not appropriate to bring the item to
the GO Bond Oversight Committee. In order to provide a level of review and public
participation for this project that is equivalent to that of the GO Bond funded projects, the
BODR has been referred to a joint meeting of the Neighborhood and Finance and Citywide
Projects Committees for presentation and discussion. As with the G.O. Bond Projects, the
BODR, if approved by the joint committee, will be presented to the full Commission for
approval at the next Commission meeting.
The Joint Committee Meeting will provide an opportunity for a discussion of all proposed
project elements, and particularly the proposed streetscape and parking treatments for
Jefferson Avenue from 5th Street to 2n°Street. The HPB has provided initial direction in
response to the presentation of the BODR as a discussion item. The HPB direction is
substantially different from that preferred by the Community as determined through the
Community consensus process. The HPB direction raises concerns with regard to propsed
parking orientations on Jeffereson Avenue, i.e., angled parking vs. parallel vs. median
parking; and also raises the policy issue of whether the City should reclaim existing
encroachments. HPB had recommended reclamation of encroachments during Phase I of
the South Pointe project. At that time, when the City attempted to follow the same course
of action, a storm of controversy and criticism was generated and the design was revised
during the construction phase to make the encroachment reclamation unnecessary. A
portion of this discussion is addressed in the attached letter from me to Mr. Mitch Novick,
Historic Preservation Board Chair. I have also attached a memo from me to
Commissioner Steinberg which specifically discussed the Jefferson Avenue parking
alternatives.
Also noteworthy is the fact that Wolfberg Alvarez, the City's consultant for Phase II of the
South Pointe Neighborhood ROW Improvement Project, has advised the City that their
sub-consultant, Duany Plater Zyberk (DPZ) has voluntarily removed themselves from this
project. Many of the concepts proposed by DPZ were chosen by the community and are
present in the BODR. As you may know, DPZ was also the consultant that prepared a
Master Plan for the South Pointe Redevelopment Area many years ago. Please be
assured that the DPZ Master Plan remains the guiding planning document for the area.
Should you wish to review the BODR in greater detail, or if you have any questions, staff
and I would be pleased to meet with you individually prior to the joint Committee Meeting
on Wednesday, January 28, 2004.
Attachments
C: Robed C. Middaugh, Assistant City Manager
_ z,~/~reet, CIP Office Director
/ ~-.,/1:~/"J;;~~:\cM~M~S~CMO Assignments~LTC-S. Pt. Joint Mtg 012804..doc
CITY OF MIAMI BEACH
Office of the City Manager
Interoffice Memorandum
To:
From:
Subject:
Commissioner Richard Steinberg
Jorge M. Gonzalez
City Manager
Jefferson Avenue Parking and Design Issues
Date: September 8, 2003
The following information is provided in response to the issues raised in the e-mail from
Randall Robinson, forwarded to my office on July 16, 2003.
Please note that during the planning effort for Phase II of the South Pointe Right of Way
(ROW) Improvement Project, ClP staff and consultants developed a number of different
parking schemes for each block within the project. These schemes took into account the
various existing ROW widths and were presented and discussed with residents at two
Community Design Workshop (CDW) meetings held on March 4th, 2003 and May 1st, 2003.
As illustrated in the attached pages from the presentation made at the second CDW, three
alternative parking schemes were developed for Jefferson Avenue: (D1) parallel parking on
both sides of the street; (D2) angle parking on one side of the street and parallel on the
other; and (D3) angle parking in a median with parallel parking on one side of the street.
During the CDW meetings, all three alternatives were presented; attendees were advised
that Option D3 would require approval from the City's Fire Department, since medians
affect the Fire Department's ability to properly stage life safety equipment, and that such
approval might be difficult to obtain. The consensus of the residents in attendance was to
implement Option D2, which did not present inherent concerns about emergency vehicle
staging, yet addressed the need for additional parking in the area.
Having achieved consensus with residents, CIP staff presented the three options along
with the balance of the project concept plan as a discussion item to the Historic
Preservation Board (HPB) on July 8, 2003. Board members expressed varying reactions to
the concept plan with general support being evident except on two issues: parking along
Jefferson Avenue and utilization of the outermost two feet of right of way on each side of all
of the streets within the project area. Board member Randall Robinson requested that the
median angle parking option be explored further with the Fire Department, and that the City
reconsider reclamation of the 2-ft strip of right of way for incorporation in the project.
CIP staff had previously met with the Fire Department to discuss median proposals for the
Lake Pancoast and North Shore neighborhoods. During those discussions, the Fire
Department had clearly indicated their position that they would only approve of new
medians where mid-block "breaks" of approximately 40-ft in length are included. These
"breaks" were deemed necessary because Fire Department ladder trucks require 18-ft
clear pavement widths to deploy their stabilizer arms. This need is usually met by utilizing
the combined travel lanes of a two-lane street, a space that is typically 20 to 26-feet wide.
However, the construction of a new median on a two-lane street narrows available travel
lane space to approximately 11 feet, which is insufficient for Fire Department vehicle
deployment.
M~dian Parking in South Pointe
August 21, 2003
Page 2
Subsequently, in response to Mr. Robinson's request, CIP staff again met with Fire
Department representatives to discuss the Jefferson Avenue median parking concept, as
well as the pedestrian median proposed for Drexel Avenue in the Flamingo/Lummus
Neighborhood Project. The Fire Department stated that they would only support the
Jefferson Avenue median parking if it included breaks like the ones specified for the Lake
Pancoast and North Shore designs. However, the project design consultant estimates that
the inclusion of these breaks in the Jefferson Avenue design would drastically reduce the
number of spaces to below the number created by implementing the recommended
curbside angled parking. Hence, the Administration continues to recommend curbside
angle parking (Option D2) for the Jefferson Avenue corridor.
For the pedestrian median proposed on Drexel Avenue, the Fire Department agreed to
accept the proposed continuous median contingent upon the tree planting scheme being
altered to create a number of breaks with adjacent dedicated bump outs to allow for the
staging of ladder truck outriggers. The application of this approach to the Jefferson Avenue
corridor would have the same effect of creating a mid-block break since it would be the
median parking spaces that would be removed rather than the trees.
For pedestrians, the median parking treatment creates a safety issue by having them exit
their parked vehicle and cross the street in the middle of the block. This can be partially
resolved by including a walkway in the median that would lead them to the crosswalk at the
nearest intersection. However, the inclusion of a sidewalk of adequate width to meet this
need would limit or prevent the installation of trees and landscaping in the median. The
City would not support Mr. Randall's suggestion that the affected streets be reclassified as
parking lots to address this issue as such action would have other negative consequences.
In response to Mr. Robinson's concerns regarding reclamation of the full width of the
existing right of way, the City has been able to achieve the design goals of the project
without utilizing the additional 4 feet of right of way that is currently encroached on by a
number of private fences, walls, landscaping, etc. In regard to the proposed median angle
parking, the utilization of these 4 feet would add only 2 feet to each travel lane which still
does not meet the Fire Department's ladder truck width requirements. In general, the CIP
Office has been attempting in the right of way improvement program to use only that
portion of the right of way that is required to meet the project's design goals. If the design
goals can be met without using the full right of way, then the City can avoid the contentious
and lengthy process of removing encroachments from the right of way. This general
approach does not preclude the City from using the full right of way at a future time if so
required.
ClP and consultant staff presented the above information in summary form to the HPB,
again as a discussion item, at their meeting on August 12, 2003. The presentation
included, at the request of Mr. Robinson, a median parallel parking option (Alternate D4,
also attached) that had not been previously considered and is not recommended by the
Project designers or the CIP Office for the same reasons identified above.
Despite the staff recommendation, the Board requested that this option be implemented on
Jefferson Avenue, with the understanding that there would still be a forty 40 feet long break
in the middle of each block and that the implementation of the scheme would likely require
Median Parking in South Pointe
August 21, 2003
Page 3
the use of all 70 feet of right of way, necessitating the removal of a number of documented
encroachments. All of the safety concerns discussed above remain to be addressed if this
option is implemented. This option also yields significantly fewer spaces than the curbside
angle parking option supported at the community meetings.
At this point in the process, since the item has only been presented to the HPB as a
discussion item, the Board's request is a recommendation which the CIP Office will discuss
further with the project team and with regulatory agencies such as Miami-Dade County and
the City's Public Works Department to ensure that the HPB scenario does not create an
unsafe condition for pedestrians or traffic. If it is determined that an unsafe condition
exists, then staff will be unable to endorse the HPB recommendation.
As this is not a G.O. Bond project, the initial review of the Basis of Design Report (BODR)
will not be presented to the G.O. Bond Oversight Committee. Staff will bring the BODR,
however, to the Finance and Citywide Projects Committee for discussion prior to it's bein~
taken up by the City Commission. There will be an item on the September 10"'
Commission Agenda requesting that a review of the South Pointe BODR and in particular
the parking issues and proposals for Jefferson Avenue be referred to the next Finance and
Citywide Projects Committee.
Please contact me if you require any further information on this issue.
JMG,~H\dps
C: Mayor and City Commission
Robed C. Middaugh, Assistant City Manager
Tim Hemstreet, ClP Director
F:\CAPI~;alI\Donald\CIP\ROW Projects~South Pointe'~3~edianparkingresponse. DOC
Streetscapes
Jefferson Avenue
70' ~K) w,
-Streetscapes
Jefferson Avenue
Alternate 2
· Angled Parking
Orientation to be
Determined
I
Streetscapes
Jefferson Avenue
Alternate 3
· Angled Parking
Orientation to be
Determined
I t't.L~L J,~Jj,tl~
GITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
www.miamibeachfl.gov
Office of the City Manager
Telephone 305-673-7010
Facsimile 305-673-7782
October 21, 2003
Mitch Novick, Chair
City of Miami Beach Historic Preservation Board
1700 Convention Center Drive
Miami Beach, FL 33139
Dear Mr. Novick:
Thank you for your recent letter expressing concerns about the status of right-of-way
encroachments in the Ocean Beach Historic District. This matter was discussed in detail
during two Community Design Workshops (CDW) regarding proposed plans for Phase II of
the South Pointe Neighborhood Right of Way Improvement Project. These plans, which
have only been developed to the concept level, have been presented to the Historic
Preservation Board (HPB) as discussion items. Input from the HPB and numerous other
review entities will be analyzed and then incorporated as appropriate into actual
construction plans which will be brought back to the HPB as an official item for approval at
the appropriate stage in design.
It is my understanding that none of the encroachments referred to in your letter have been
individually designated as being historic. Such designation would be an action taken by
the Historic Preservation Board rather than the City Attorney's Office. There are a number
of encroachments that are elements, such as walls and entrance features, of historically
contributing buildings. However, these encroachments have not been individually
designated as historic. A comprehensive list and description of the encroachments is
being prepared by the Project design team.
In general, the direction taken for streetscape improvement projects throughout the City
has been to remove encroachments, if necessary, to implement recommended and desired
improvements. As was explained at the two presentations that have been made to the
HPB, the general design concept for Phase II of the Project has been to focus planned
improvements within the right of way currently used while implementing all desired
improvements. This design approach developed as a result of the bitterly critical and
extremely vocal public outcry opposing the Phase I design concept, which completely
redesigned the streets utilizing the full right-of-way width, and thus, called for the removal
of many existing encroachments.
As you may remember, at that time, there was extensive discussion by the community and
the City Commission advising staff that this was an extremely inappropriate and insensitive
approach that was damaging to the historic character and fabric of the neighborhood. The
project design was subsequently modified during construction, which created a great deal
October 21,2003
Page 2 of 2
of disruption, to limit the improvements to the existing area of the right of way in use. This
modified design was well received by the community and therefore was adopted as a
starting point for planning Phase II of the project.
Staff has advised me that it appears the HPB's concern about full utilization of the right of
way stems, in part, from a desire to implement a median parking design. This design has
been analyzed and considered but has not been supported for a variety of reasons by a
number of other entities whose input into the project design is very important. Various
versions of the design have been considered, including those that would require use of the
full right of way and others that could be implemented in the existing area of use. While
the City would like to avoid the problems experienced in Phase I of the project with
utilization of the full right of way, this is not the primary reason that the median design is not
supported at this time. The main objections to the design stem instead from concerns
about public safety, traffic flow, and emergency access. However, a final decision has not
been made on this proposed concept. It will be discussed further at a joint meeting of the
Neighborhood Committee and Finance and Citywide Projects Committee which will be held
in November, and then subsequently by the City Commission. All of the Historic
Preservation Board's concerns will be reported at these meetings and you and members of
the Board are welcome to attend as well.
I can assure you that the City is making every effort to balance the complex needs
addressed by the Project which include parking, safety, drainage, lighting, preservation and
enhancement of neighborhood character, pedestrian and vehicular flow, street trees, and
many others.
Should you have further concerns, or if I can provide additional information, please let me
know.
Sincerely,
e Gonz~lez
City Ma~
J MG/~-IYds
C: /~R(~bert C. Middaugh, Assistant City Manager
Tim Hemstreet, Capital Improvement Projects Office Director : :~.~
F:~CAPI~$alI\Donald\CIP~:~OW Projects\South Pointe\cmhpencroachementresponse.doc