LTC 527-2021 FLORIDA DEPARTMENT OF TRANSPORTATION {FOOT) 1-395 SIGNATURE BRIDGE PROJECT UPDATEDocuS ign Envelope ID : CEBC79C1-2758-4382-9AA6-FA5C9EFEBC53
MIAMI BEACH
OFFICE OF THE CITY MANAGER
NO . LTC# LETTER TO COMMISSION
TO:
FROM:
DATE :
Honorable Mayor Dan Gelbfjtvrer and Members of the City Commission
Alina T. Hudak, City Manag r
December 14, 2021
SUBJECT: FLORIDA DEPARTMENT OF TRANSPORTATION {FOOT) 1-395 SIGNATURE
BRIDGE PROJECT UPDATE
The purpose of this Letter to Commission is to transmit the attached presentation from the Florida
Department of Transportation on the status of the 1-395 Signature Bridge project. Page 22 of the
presentation contains a link to project website www .i395-miami.com where anyone may sign up
for project alerts/updates and Calendar of events.
Please feel free to contact me if you have any questions .
Attachment
0,; G_
ATH/LS/JRG/JFD
527-2021
City of Miami Beach Commission Update
December 8, 2021
2
ONGOING CONSTRUCTION
ACTIVITIES
•Mainline concrete pavement completed
from NW 17 Street to NW 29 Street
•Mainline concrete pavement
approximately 95% completed from NW
8 Street to NW 17 Street
•Ongoing concrete pavement replacement
work on 836/395 ramps to NB I-95
•Intelligent Transportation Systems
installation
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
3
ONGOING CONSTRUCTION
ACTIVITIES
•Beam shop drawings submitted.
Casting of beams to begin soon.
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
4
ANTICIPATED NIGHTTIME LANE CLOSURES ON THE I-95 CORRIDOR:
•Nighttime lane closure along I-95 between NW 8 Street and NW 29
Street
•Closure of I-95 entrance/exit ramps at NW 8 Street
•I-95 ramps to I-395 and SR 836
•Lane closure hours –9 p.m. to 5:30 a.m. weeknights, and 11 p.m. to 11
a.m. on Fridays and Saturdays
THREE MONTH LOOK
AHEAD
ONGOING LANE
CLOSURES
. . . .
••••• •••••
■ ■ ■ ■
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
5
•Ongoing widening work on the
eastbound SR 836 ramp to
northbound I-95 from one lane
to two lanes
•Ongoing rebar installation for
roadway deck construction
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
6
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
•Demolition work to tie in new
bridge to existing deck
•Ongoing installation bridge
overhang. Stay in place forms
(SIPs) starting soon.11-29-2021
7
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
Footer and pier construction in
the jury lot area of the Richard
Gerstein E. Justice Building
11-29-2021
8
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
Ongoing footer and pier construction in
the Grove Park area, east and west of
NW South River Drive
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
9
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
Ongoing pier cap erection west
of NW 17 Avenue
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
* This schedule does not reflect days added to the contract for
holidays, weather days or special events
10
ANTICIPATED NIGHTTIME LANE CLOSURES ON SR 836 CORRIDOR:
•Single and double lane closures along eastbound and westbound SR 836
•SR 836 ramps to northbound and southbound I-95
•Arterial roads under SR 836
•NW 17 Avenue and NW 12 Avenue ramps to SR 836
•Lane closure hours –9 p.m. to 5:30 a.m. weeknights, and 11 p.m. to 7 a.m. on
Fridays and Saturdays
•Full closure of all SR 836 travel lanes necessary during pier cap erection work.
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
■ ■
••••• ••••• • • • •
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
11
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
1
2
3
4
5
6
SIGNATURE BRIDGE FOUNDATIONS
CENTER PIER
Arch construction will begin with the construction of Arch 2
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
12
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
ARCH FOUNDATION
CONSTRUCTION
Arch 4 and 5 footers
West leg poured. East leg scheduled
for concrete pour mid-December
Ongoing rebar installation
Concrete pour for pedestal at Arch 2
scheduled for week of December 13
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
13
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES Arch 1
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
14
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES Arch 2
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
15
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
10-25-2021 11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
16
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
11-29-202110-25-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
17
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
18
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
Ongoing footer construction at the Overtown
Plaza alleyway
11-29-2021
•Three concrete footers at the
Overtown Plaza alleyway
completed
•Ongoing pier construction 11-29-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
19
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
WESTBOUND I-395 RAMP TO NORTHBOUND
I-95 REMOVED
11-29-202110-25-2021
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
20
ONGOING AND UPCOMING
CONSTRUCTION ACTIVITIES
WESTBOUND I-395 RAMP TO NORTHBOUND
I-95 REMOVED
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
21
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
•Lane closures along eastbound and westbound I-395
•Lane closures along Biscayne Boulevard and other arterial roadways
adjacent to I-395
•Closure hours –10 p.m. to 5:30 a.m. on weeknights, and 1 a.m. to 7
a.m. on Saturdays and Sundays
ONGOING LANE
CLOSURES
THREE MONTH LOOK
AHEAD
■ ■
••••• ••••• • • • •
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
22
COMMUNITY OUTREACH
PROJECT WEBSITE
•www.i-395miami.com
•Sign-up for project alerts/updates
Lane closure information
Upcoming construction activities
Presentations
•Calendar of events
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
•1035 NW 3 Avenue, Miami, Florida 33136 –Now open
Mondays, Wednesdays and Fridays
STAKEHOLDER MEETINGS
•Stakeholder meetings will be hybrid until further notice. Next meeting:
Wednesday, January 26, 2022; Location: CEI Project Office
/,,\ h CONNECTING
/ (I\~ 1MIAM1 ;:::::,::==
COMMUNITY MOBILITY SAFETY SUSTAINABILITY
• e •
786-280-0983
OGonzalez@mrgmiami.com
Contact:
Oscar Gonzalez
www.i-395miami.com
THANK YOU!
QUESTIONS?
23
A
COMMUNITY MOBILITY SAFETY SUSTAINABILITY