Loading...
LTC 128-2022 COMMENCEMENT OF THE RELOCATION OF THE FPL TRANSMISSION LINES AT SURFACE PARKING LOT P92128-2022 MIAMI ACH OFFICE OF THE CITY MANAGER LTC # LETTER TO COMMISSION TO: FROM: DATE: Honorable Mayor Dan Gel tPe and embers of the City Commission Alina T. Hudak, City Mana e April 5, 2022 SUBJECT: COMMENCEMENT OF THE RELOCATION OF THE FPL TRANSMISSION LINES AT SURFACE PARKING LOT P92 The purpose of this Letter to Commission (L TC) is to inform the Mayor and Commission that Florida Power & Light (FPL) will soon be commencing with the relocation of the existing overhead transmission lines at the city owned parking lot P92, located between 72 nd and 73 rd Streets and between Collins and Harding Avenues. The existing overhead FPL transmission lines and distribution lines currently bisect the site of the future 72 nd Street Community Complex (Attachment A). These lines are supported by wooden utility poles located within the existing parking lot, and cross 72 nd and 73 rd Streets (Attachment B). On May 13, 2020, the City Commission approved Resolution 2020-31255 (Attachment C) for the relocation of the overhead transmission lines and associated power poles. FPL has completed their due diligence, engineering, design, and permitting for the relocation of the transmission lines. The installation of the new transmission poles and the relocation of the transmission lines is expected to commence in April 2022. The transmission lines will be rerouted, generally along the property line, in a westerly direction from its current location along 72 Street then north on Harding Avenue to 73 Street, then east along 73 Street and tying into the existing lines in the alleyway on the north side of 73 Street (Attachment A). In order to complete this task, certain trees will be impacted. Currently the tree permit has been issued and FPL will be identifying/tagging the trees that will be removed or re located, as required by the conditions of the tree permit. After the relocation of the transmission lines to the new poles , the existing wood poles, carrying the distribution lines, w ill remain and will be relocated at a later time. City staff, representatives from FPL, and the City's design criteria consultant, Desman Inc ., are coordinating potential routing and final location of the distribution lines in order to afford the greatest flexibility for the future 72 nd Street Community Center Complex, planned at this location. Should you have any questions, please contact David Martinez at 305-673-7071 . ATTACHMENTS: Attachment A -Existing Site Survey Overhead FPL Power Lines & New Transmission Pole & Line Route Attachment B -Photo of Existing Wood Utility Poles Attachment C -Resolution 2020-31255 ATH/LS/DM New transmission poles and the relocation of the transmission lines route (Yellow) Miami-Dade County, Florida • • 0 Deauville-Normandy Beach Miami Beach, Miami-Dade County, Florida 122308 Approximate Pole Installation Location -• -Existing Conductor Route (To Be Removed) Pole Removal Approximate Proposed Conductor Route Pole Replacement Attachment A lmagery:NAIP 2019 Existing Overhead Transmission & Distribution Lines (Red) Project Location Map 0 1 in= 118.3 feet Prepared By : Atkins N.A. Ecological Sciences ATKI NSoa1,,,b-,a,y26,2021 - ATTACHMENT B UTILITY POLES ATTACHMENT C RESOLUTION NO. 2020-31255 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, AUTHORIZING THE PURCHASE OF UTILITY RELOCATION SERVICES FROM FLORIDA POWER AND LIGHT (FPL), AS A SOLE SOURCE PURCHASE PURSUANT TO SECTION 2.367(d) OF THE MIAMI BEACH CITY CODE, FOR THE RELOCATION OF OVERHEAD TRANSMISSION LINES AND ASSOCIATED POWER POLES AT THE EXISTING CITY OWNED PARKING LOT (P92), ALLOWING FOR MORE DESIGN FLEXIBILITY AND EFFICIENCY AT THE FUTURE 72ND STREET COMMUNITY COMPLEX, LOCATED BETWEEN 72 STREET AND 73 STREET, AND BETWEEN COLLINS AVENUE AND HARDING AVENUE, IN THE AMOUNT OF $849,765.13, WITH PREVIOUSLY APPROPRIATED FUNDING, AND AUTHORIZING THE CITY MANAGER AND CITY ATTORNEY TO FINALIZE THE FACILITIES RELOCATION AGREEMENT, AND FURTHER AUTHORIZING THE CITY MANAGER AND CITY CLERK TO EXECUTE THE FACILITIES RELOCATION AGREEMENT WITH FPL. WHEREAS, on July 31, 2019, the Mayor and City Commission, via Resolution 2019- 30933, directed staff to proceed with a feasibility study and to begin the preparation of the Design Criteria Package for the 72nd Street Community Center Project (the "Project"), located at 263- 299 72 nd Street, the site that is currently used as City Parking Lot 92; and WHEREAS, the Administration and the design criteria professional for the Project,· Desman , Inc _ (the "Design Criteria Professional"}, have met with the Project's stakeholders to discuss and refine Project requirements; and WHEREAS, existing overhead FPL transmission lines currently bi-sect the site, supported by utility poles located within the parking lot; and WHEREAS, the feasibility study reviewed options for relocating the transmission lines, and determined that a relocation of the power lines would provide the eventual design-builder with more design flexibility in the location of the structures, and may lead to increased efficiency and creativity of design; and WHEREAS, City staff met with FPL to discuss the relocation of the FPL transmission lines, and FPL provided a non-binding preliminary estimate with two (2) options; and WHEREAS, the first option assumed a commitment by the City after November 1, 2019, at a cost of $1,583,600, with the FPL construction work taking place in 2021; and WHEREAS, the second option assumed a commitment prior to November 1, 2019, the estimated cost for this option at $1,028,600, saving the City $555,000 through reductions in FPL planned system hardening, with FPL construction commencing in September 2020; and WHEREAS, in addition, FPL had provided an alternative which proposed undergrounding the overhead lines, but FPL cannot, at this time, provide a budget or construction timeline, as it would require additional engineering; however, FPL estimated that the underground alternative has a cost range of ten to fifteen times greater than the non-binding cost options for above ground relocation; and WHEREAS, the Administration ultimately decided to proceed with the second option identified above, with an estimated cost of $1,028,600, resulting in savings in the estimated amount of $555,000 through reductions in FPL planned system hardening, with FPL's construction commencing in September 2020; and ATTACHMENT C WHEREAS, subsequent to the Administration's initial meetings with FPL, and FPL 's preparation of a non-binding cost estimate, the City Commission, on October 16 , 2019, approved Resolution 2019-31048, authorizing the sole source purchase for the preparation of a detailed Design and Binding Estimate, by FPL, for the relocation of the overhead transmission lines and associated power poles, in the amount of $154,180.00; and WHEREAS, City staff has met with FPL on several occasions, including during the exploratory (soft dig} site investigation work, and had multiple conversations regarding the proposed transmission power pole location and routing of the overhead power lines; and WHEREAS, the overhead transmission lines and associated power poles will be rerouted, generally along the property line, in a westerly direction from its current location along 72nd Street then north on Harding Avenue to 73rd Street, then east along 73rd Street and tying into the existing lines in the alleyway on the north side of 73rd Street; and WHEREAS, FPL has completed their due diligence, engineering and design , and has provided the Administration with a Facilities Relocation Agreement; and WHEREAS, the Facilities Relocation Agreement provides a detailed cost proposal for the relocation of the overhead transmission lines and associated power poles in the amount of $849,765 .13; and WHEREAS, FPL requires the execution of the Facilities Relocation Agreement and payment by July 1, 2020, prior to commencing the work, and the work is scheduled to be completed by the end of this year; WHEREAS , the Administration recommends authorizing the C ity Attorney and the City Manager to finalize the Facilities Relocation Agreement with FPL in the amount of $849,765.13, with previously appropriated funding, and further recommends authorizing the execution of the Fac ilities Relocation Agreement. NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORI DA, that the Mayor and City Commission hereby authorizes the purchase of utility relocation services from Florida Power and Light (FPL}, as a sole source purchase pursuant to Section 2.367(d} of the Miami Beach City Code, for the relocation of overhead transmission lines and associated power poles at the existing City owned Parking Lot (P92}, allowing for more design flexibility and efficiency at the future 72nd Street Community Complex, located between 72 Street and 73 Street, and between Collins Avenue and Harding Avenue, in the amount of $849,765.13, with previously appropriated funding , and authorizing the City Manager and City Attorney to finalize the Facilities Relocation Agreement with FPL, and further authorizing the City Manager and City Clerk to Execute the Facilities Relocation Agreement with FPL. PASSED and ADOPTED this ___!!_ctay of /n~ , 2020 . ranado, City Clerk APPROVED AS TO FORM & LANGUAGE & FOR EXECUTION - 72 t>w 1 0~-~ s 11 t t, rs City Attorney Date