294A-98 RDA
RESOLUTION NO. 294A-98
A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE
BOARD OF THE MIAMI BEACH REDEVELOPMENT AGENCY
AUTHORIZING THE EXECUTION OF THE AMENDED
REIMBURSEMENT AGREEMENT WITH THE FLORIDA
DEPARTMENT OF TRANSPORTATION AND APPROPRIATING
$359,808 FOR THE COLLINS AVENUE RECONSTRUCTION
PROJECT FROM THE MIAMI BEACH REDEVELOPMENT
AGENCY SERIES 1996 B BONDS
WHEREAS, the Florida Department of Transportation (FDOT) and the City entered into a
Reimbursement Agreement for the full reconstruction of Collins Avenue on September 24, 1998; and
WHEREAS, the schedule to complete the work contemplated under the Agreement was
determined to be incompatible with the opening of the Convention Center Hotel in October 1998; and
WHEREAS, the City desires to implement an interim plan for the reconstruction of Collins
Avenue from 15th Street to Lincoln Road that will meet the scheduled opening of the Convention Center
Hotel; and
WHEREAS, the interim plan consists of replacing the sidewalks, curb and gutter and the milling
and reasphalting of the roadway in lieu of fully reconstructing the roadway in phases; and
WHEREAS, FDOT has agreed to fund the interim plan, in the amount of $359,808 and have
prepared an Amended Reimbursement Agreement for the Project; and
WHEREAS, funds are available for appropriation from the Miami Beach Redevelopment Agency
Series 1996 B Bonds in the amount of $359,808 for the Project; and
WHEREAS, the City and FDOT wish to enter into the attached Amended Reimbursement
Agreement which provides for reimbursement of the incremental expenses to be incurred by the City for
the construction and construction-inspection of this Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CHAIRMAN AND MEMBERS OF
THE BOARD OF THE MIAMI BEACH REDEVELOPMENT AGENCY, to authorize the execution
of the attached Amended Reimbursement Agreement between the Florida Department of Transportation
and the City of Miami Beach, in the amount of $359,808 in State Funds, for the Collins Avenue
Reconstruction Project, from 15th Street to Lincoln Road, which Project is to be constructed by a City
contractor in 1998, on an expedited schedule.
PASSED AND APPROVED this
3rd
day of June
~/!
CHAIRMAN
,1998.
ATTEST:
~~t favhM
SECRETARY
APPROVED AS TO
fORM & LANGUAGE
& FOR EXECUTION
~ 'l/~/<;J
City Att ne Date
F\WORK\$ALLICA TESDlCOMMMEMlFDOTCOLL. RES
Miami Beach
Redevelopment Agency
1700 Convention Center Drive
Miami Beach, Florida 33139
Telephone: (305) 673- 7295
Fax: (305)673-7772
REDEVELOPMENT AGENCY MEMORANDUM No.q8-~o
TO:
Chairman and Members of the Board
of the Miami Beach Redevelopment Agency
DATE: June 3, 1998
FROM:
Sergio Rodriguez
Executive Director
..
SUBJECT:
A RESOLU ON F THE CHAIRMAN AND MEMBERS OF THE BOARD
OF THE MIAMI BEACH REDEVELOPMENT AGENCY AUTHORIZING
THE EXECUTION OF AN AMENDED REIMBURSEMENT AGREEMENT
WITH THE FLORIDA DEPARTMENT OF TRANSPORTATION AND
APPROPRIATING $359,808 FOR THE COLLINS A VENUE
RECONSTRUCTION PROJECT FROM THE MIAMI BEACH
REDEVELOPMENT AGENCY SERIES 1996 B BONDS
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
BACKGROUND:
On September 24, 1997 the City Commission approved Resolution 97-22536 authorizing the Mayor
and the City Clerk to execute a reimbursement agreement between the Florida Department of
Transportation (FDOT) and the City of Miami Beach in the amount of$1.43 million for the purpose
of reconstructing Collins Avenue from Espanola Way to Lincoln Road. Under the terms of this
agreement the City is to bid and construct the project on behalf of the FDOT. The City is also
required to advance the necessary funds to construct the project and seek reimbursement from the
FDOT when the work is completed.
The final reconstruction plans designed by the FDOT engineers were estimated to cost
approximately $2 million and take nine (9) to twelve (12) months to build. The plans required the
contractor to completely remove the entire roadway to the sub-grade and replace it in phases. The
schedule to complete this work was determined to be incompatible with the opening of the
Convention Center Hotel in October 1998.
SClUTtl VClI~t:
l?edevel()pment Uistrict
Agenda Item
l?~e
Date
3A
t:,- 3-CfS
On March 17. 1998 City staff met with FOOT officials and discussed the City's desire to implement
an interim plan for the reconstruction of Collins Avenue from 15th Street to Lincoln Road, which
will meet the scheduled opening of the Convention Center Hotel. The interim plan consists of
replacing the sidewalks, curb and gutter and the milling and resurfacing of the roadway. The cost
to accomplish the interim plan is estimated at $359,808. The FOOT officials have agreed to fund
the interim plan and have prepared an amended reimbursement agreement for the project that reflects
the proposed work.
ANAL YSIS:
The amended reimbursement agreement with FOOT provides $329,808 for construction and $30,000
for construction engineering inspection (CEI). The funds have been budgeted by FOOT in fiscal
year 1997-1998. The total of$359,808 in State funds will be available for disbursement to the City,
on an incremental basis, after the FOOT receives and approves the contractor invoices as the work
progresses.
The City utilizes a bidding procedure that complies with State rules and regulations, which will be
required for the construction of this project. Construction, utilizing existing bids, is scheduled to
begin July 1, 1998 and be completed by October 1, 1998.
Funds in the amount of$359,808 are available for appropriation into a work order from the Miami
Beach Redevelopment Agency series 1996 B bonds.
CONCLUSION:
The City Commission and the RDA should adopt the resolution authorizing the amended
reimbursement agreement with the FDOT which is essential for the City to meet the scheduled
completion date that has been established.
\