LTC 213-2023 G.O. Bond Program - Project Implementation Update No. 27M IAM I BEACH
OFFICE OF THE CITY MANAGER
LTC# LETTER TO COMMISSION
TO:
FROM:
DATE:
Honorable Mayor Dan Gel~ber and Members of the City Commission
Alina T. Hudak, City Mana
May 9, 2023
SUBJECT: G.O. Bond Program - Project Implementation Update No. 27
The purpose of this Letter to the Commission ("LTC") is to advise you on the status of the
implementation of the 44 General Obligation Bond (G.O. Bond) Projects approved by the City
Commission for the first tranche of funding (Tranche 1) in the amount of $152,466,449 including
issuance costs.
Refer to attached Exhibit A and A1 for the meeting agendas which took place with the G.O. Bond
Oversight Committee ("the Committee") on March 30, 2023 and April 20, 2023. The following
information includes excerpts from both meetings. For complete meeting agendas, handouts,
minutes, presentations, and audio recordings, visit the website www.GOMBinfo.com and click on
the Oversight Committee tab to see Meeting Records.
IMPLEMENTATION STATUS
Project Dashboard and Program Progress Report
As of April 17, 2023, a total of 32 out of 44 Tranche 1 projects are in some form of "Active" status
and 11 projects are completed. Chart 1 below shows the full breakdown by Category.
Chart 1
PROJECT ACTIVITY
Tranche 1
44 Complete
11
Active
32
Pending
1
- Future
13
75% of all GOB Projects are
Complete or Active = 43
PROJECT CATEGORY
Parks Infrastructure Public Safety All
PROJECT Complete 8 2 11
STATUS Active 12 10 10 32
Pending 0 0
Future 9 3 13
All 30 14 13 57
213 - 2023
G.O. Bond Program - Project Implementation Update No. 27
May 9, 2023
Page 2 of 5
Approximately $59 million have been expended and another $22.6 million are encumbered for a
total of $81.6 million out of the $151.1 million of available Tranche 1 funds. Chart 2 below shows
the full breakdown of the expenditures broken down by Category.
Chart 2
Tranche 1 Progress
Most of the 44 projects in Tranche 1 have different components which are considered distinct
projects, or “subprojects”, that are tracked separately and have separate budgets, procurement,
and implementation schedules.
The Tranche 1 Subproject Activity Summary depicted in Charts 3 and 4 summarize the subproject
activity into Status, Category and Funding amount.
Subproject Tracking Summary by Phase
The tracking summary indicates that 43 (49%) of the 88 total Tranche 1 subprojects have been
completed, 7 (8%) are under construction, 28 (32%) are in a design phase, 6 (7%) are in a planning
phase, and 4 (5%) are pending to become active. Chart 3 on the following page shows the status
of all subprojects broken down by Phase and Category.
• 19% of all GOB Funds are Spent or
Encumbered = $81M out of $435M
G.O. Bond Program - Project Implementation Update No. 27
May 9, 2023
Page 3 of 5
Chart 3
The total expenditures funding summary for each of the subproject categories on Chart 4 below
indicates that as of April 17, 2023, the 43 completed subprojects equate to $36 million of the budget
(24%), $24 million (16%) equate to subprojects under construction, $67.5 million (45%) equate to
subprojects that are in the design phase, $19 million (13%) equate to subprojects that are in the
planning phase, and a total equating to $4.5 million (3%) are for subprojects which are pending to
become active. For a full breakdown, by project, refer to attached Exhibit B.
Chart 4
G.O. Bond Program - Project Implementation Update No. 27
May 9, 2023
Page 4 of 5
Subproject Progress
Chart 5 below compares the status of subprojects from previous months to the current month, dating
back to October 2019.
Chart 5
PROJECT FUND TRANSFERS & SWAPS
At the April 20th meeting, the Administration requested approval from the committee to allow the
temporary realignment (or swap) of $150,000 from sub-project GO #37 Sidewalk Improvements to
GO #33 Tree Planting to allow the Urban Forestry Division to continue moving forward with the
program. A memorandum explaining the swap is attached as Exhibit C, and the Committee made
a motion to accept the recommendation of staff to allow the funding swap. LTC#181-2023 was sent
to the City Commission to notify them of the motion made.
CONSTRUCTION COMMENCEMENTS IN 2023
A summary graph of all projects proposed to commence construction during the 2023 calendar year
was provided. Refer to Exhibit D.
TRANCHE 1 PROJECTS UPDATE
The following Tranche 1 project updates were discussed at the March 30th and April 20th meetings.
Refer to Exhibit E for further details and information for each of the following:
#01 72nd St. Community Complex
#10 Maurice Gibb Park
#15 PAR 3 / Bayshore Park
#23 Pedestrian Bridge
#31 Ocean Drive Corridor/Lummus Park
#37 Sidewalks – Tranche 1
#38 Streets – Tranche 1
#43 23 St. Streetscape Improvements & Chase Ave/34 St Shared Use Path
#45 Fire Station #1
#48 Police HQ Facility – Tranche 1
#54 Marine Patrol Facility
G.O. BOND FOR ARTS & CULTURE
At the March 30th Oversight Committee Meeting the Administration reported that on March 27th, the
City Commission approved the form of grant agreement to be executed by organizations receiving
grant awards. The Administration also reported that at the March 31st Finance & Economic
G.O. Bond Program - Project Implementation Update No. 27
May 9, 2023
Page 5 of5
Resiliency Committee (FERC) meeting, the Administration provided recommendations for Tranche
1 funding and presented the Tranche 1 Summar y.
At the Ap ril 20" Oversight Com mittee meeting, the Administration reported the updated Tranche 1
Summary, which incorporates recommendations made at the March 31° FERC meeting, showed a
revised amount of $101,700,000 for Tranche 1 to be recommended to The City Commission for
approval at the April 28" Com mission meeting. Th e Administration requested support from the
Committee to endorse staff's recommendation. L TC#181-2023, dated April 21, 2023, was sent to
the City Commission to notify them of the motion made. Refer to Exhibit F Updated Summary Chart
draft.
Miami Beach Classical Music Festival
Per the direction provided by Commission pursuant to Resolution 2023-32509, the Oversight
Committee was tasked with selecting a level of funding up to $1.5 million from the Miscellaneous
Arts & Culture category to award to the Miami Beach Classical Music Festival (MBCMF) to invest
in projection mapping and production equipment to utilize during live concerts. At the March 30th
Oversight Committee meeting, Michael Rossi, Founder and Artistic Director of the MBCMF,
presented the proposed project. The Committee was provided 10 minutes of a presentation from
the MBCM F, 10 minutes for Q & A and 15 minutes for deliberations and discussion among the
Committee members. After deliberations the Committee recommended the maximum available of
amount of $1.5 million to be recommended for award to the MBCMF. L TC#151-2023, dated March
31, 2023, was sent notifying the City Commission of the Committee's recommendation.
COMMUNITY INFORMATION AND OUTREACH
The Administration continues to perform public information and outreach activities through various
community meetings, Constant Contact emails, direct mailings, publications, social media
platforms. Please see attached Exhibit G to view recent materials.
The Administration held a groundbreaking for Maurice Gibb Park on April 4", An advisory was sent
through NextDoor and Constant Contact to notify residents of the groundbreaking. An invite was
also sent to residents via email and posted on Facebook and Twitter.
The website, www .GOMBlnfo.com, continues to be updated with the latest construction advisories,
press releases, project photos, implementation updates, public presentations, and more. For more
information, please contact Maria Hernandez at mariahernandez@miamibeachfl.gov or via
cellphone at (786) 371-3168.
Attachments:
Exhibit A- GOB Oversight Committee Agenda for March 30, 2023
Exhibit A1 - GOB Oversight Committee Agenda for April 20, 2023
Exhibit B - Subproject and Project List by Phase
Exhibit C- Project Funds Swap Memorandum
Exhibit D - Construction Commencement Graph
Exhibit E- 2018 Tranche 1 Project Updates
Exhibit F - Updated Arts & Culture Tranche 1 Sum mary Chart
Exhibit G- Commun ity Information and Outreach
€w uet
F:\cmgr\$ALL\GO Bond Program\LTC Program Updates\2023\2 April\G.O. Bond Program - Project Implementation Update No. 27.docx
__________________________________________________________________________________________________
Legend: (P) Planning Phase, (D) Design Phase, (C) Construction Phase, (PN) Pending, (F) Future Tranche
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo, Chair
Maria Hernandez, Liaison
AGENDA – VIRTUAL MEETING
March 30, 2023
I.Roll Call and Introductions All 4:30pm
•Announcements
•New Members Formal Introductions
II.Committee Business Karen Rivo 4:50pm
•Adoption of Meeting Minutes from 2-16-23
III.Community Outreach Kevin Pulido 4:55pm
•Upcoming / Recent Past Public Meetings & Events
G.O. Bonds for Arts & Culture
IV.G.O. Bond for Arts & Culture Update 5:00pm
a.3/27/23 Commission Meeting
•Grant Agreements & Next Steps MH / RD
b.3/31/23 Finance Committee Meeting
•Memo & Updated Workplan MH / JG
V.Public Comment Public 5:45pm
VI.MB Classical Music Festival 5:55pm
•Introduction of the Item (5 Minutes)Maria Hernandez
•Presentation (10 Minutes)Michael Rossi 6:00pm
•Q & A (10 Minutes)GOB Committee 6:10pm
•Deliberations and Recommendation (15 Minutes) GOB Committee 6:20pm
2018 G.O. Bonds
VII.2018 Projects – Critical Updates CIP / Staff 6:35pm
VIII.Public Comment Public 6:50pm
IX.Adjournment 7:00pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the
City Manager and City Commission from a macro perspective regarding the timely progress, overall goals, costs,
including financial efficiencies, and the timely completion of General Obligation Bond Program projects
approved by the voters in the City of Miami Beach. The Committee shall have the following powers & duties:
1.Receive input from the public, the City Administration, City consultants, and the City’s Inspector General, as
needed, to make recommendations relative to the overall timing, cost efficiencies, and prioritizatio n of the
G.O. Bond Program projects.
2.Provide general oversight to ensure that G.O. Bond Program project timelines, budgets (including cost
efficiencies) are prioritized and achieved, and that the projects are completed in accordance with the
scope of work approved by the voters.
3.Review City staff and G.O. Bond Program project manager’s progress reports and provide monthly reports
to the City Commission.
Exhibit A
__________________________________________________________________________________________________
Legend: (P) Planning Phase, (D) Design Phase, (C) Construction Phase, (PN) Pending, (F) Future Tranche
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo, Chair
Maria Hernandez, Liaison
AGENDA – VIRTUAL MEETING
April 20, 2023
I.Roll Call and Introductions All 4:30pm
II.Committee Business Karen Rivo 4:50pm
•Adoption of Meeting Minutes from 3-30-23
III.Community Outreach Kevin Pulido 4:55pm
•Upcoming / Recent Past Public Meetings & Events
2018 Bonds
IV.Funding Swap for Tree Planting Thais Vieira 5:00pm
V.Program General Status Update Maria Hernandez 5:10pm
VI.2018 Bonds Projects Update CIP / PWD / FM 5:20pm
•72nd St. Complex (P), Bayshore Park (D),
Ocean Dr/Lummus Park (P), Pedestrian Bridge (D),
Marine Patrol Facility (D), 23 St Streetscape (D),
Chase/34 St Shared Use Path (D), FS#1 (D),
Streets & Sidewalks (C), Police HQ (D)
VII.Public Comment Public 6:10pm
G.O. Bonds for Arts & Culture
VIII.G.O. Bond for Arts & Culture Update Staff / Legal 6:20pm
4/28/23 Commission Meeting
•Tranche 1 Recommendation
•Public Benefits Chart Update
•Revised Grant Agreement
IX.Public Comment Public 6:50pm
X.Adjournment 7:00pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City
Manager and City Commission from a macro perspective regarding the timely progress, overall goals, costs, including
financial efficiencies, and the timely completion of General Obligation Bond Program projects approved by the voters
in the City of Miami Beach. The Committee shall have the following powers & duties:
1.Receive input from the public, the City Administration, City consultants, and the City’s Inspector General, as
needed, to make recommendations relative to the overall timing, cost efficiencies, and prioriti zation of the G.O.
Bond Program projects.
2.Provide general oversight to ensure that G.O. Bond Program project timelines, budgets (including cost efficiencies)
are prioritized and achieved, and that the projects are completed in accordance with the scope of work
approved by the voters.
3.Review City staff and G.O. Bond Program project manager’s progress reports and provide monthly reports to the
City Commission.
Exhibit A1
G.O. BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Count % Count $ Budget $ Encumbered $ Spent % Spent $ Available
Closed #53 PORTABLE BOLLARDS Public Safety Police 1 07-31-2019 1 1%599,916 - 599,915 1.02%-
Closed #17 POLO PARK Parks Parks & Recreation 1 08-11-2019 1 1%493,673 - 493,673 0.84%-
Closed #19 SOUNDSCAPE 4K TECHNOLOGY Parks Tourism & Culture 1 09-30-2019 1 1%3,748,495 - 3,748,495 6.37%-
Closed #13 NORTH SHORE LIGHTS & PAINT Parks Property Management 1 10-14-2019 1 1%130,300 - 130,210 0.22%89
Closed #52 TATUM PARK LED LIGHTING Public Safety Parks & Recreation 1 10-14-2019 1 1%52,758 - 52,758 0.09%-
Closed #52 CRESPI PARK LED LIGHTING Public Safety Parks & Recreation 1 10-21-2019 1 1%41,780 - 41,780 0.07%-
Closed #52 STILLWATER PARK LED LIGHTING Public Safety Parks & Recreation 1 10-21-2019 1 1%41,780 - 41,780 0.07%-
Closed #26 COLONY THEATRE ROOF Parks Property Management 1 10-24-2019 1 1%299,650 - 299,650 0.51%-
Closed #21 STILLWATER PARK Parks Parks & Recreation 1 11-08-2019 1 1%142,440 - 142,440 0.24%-
Closed #3 CRESPI PARK Parks Parks & Recreation 1 11-09-2019 1 1%184,920 - 184,919 0.31%1
Closed #18 SCOTT RAKOW PAINT Parks Property Management 1 11-12-2019 1 1%116,776 - 116,776 0.20%-
Closed #47 MACARTHUR CSWY READERS Public Safety Police 1 11-28-2019 1 1%64,904 - 64,904 0.11%-
Closed #52 NORMANDY ISLE PARK LED LIGHTING Public Safety Parks & Recreation 1 12-02-2019 1 1%212,599 - 212,593 0.36%5
Closed #18 SCOTT RAKOW HVAC Parks Property Management 1 12-06-2019 1 1%137,303 - 137,302 0.23%-
Closed #13 NORTH SHORE ROOF Parks Property Management 1 12-16-2019 1 1%375,000 - 374,722 0.64%276
Closed #18 SCOTT RAKOW ROOF Parks Property Management 1 01-05-2020 1 1%127,218 - 127,217 0.22%-
Closed #26 MIAMI CITY BALLET ROOF Parks Property Management 1 01-15-2020 1 1%758,824 - 758,824 1.29%-
Closed #13 NORTH SHORE CAMERAS Parks Property Management 1 02-04-2020 1 1%205,699 - 60,858 0.10%144,841
Closed #18 SCOTT RAKOW CAMERAS Parks Property Management 1 02-05-2020 1 1%250,000 - 110,659 0.19%139,340
Closed #32 PALM & HIBISCUS LANDSCAPING Infrastructure Capital Improvement Projects 1 03-25-2020 1 1%1,000,000 - 1,000,000 1.70%-
Closed #18 SCOTT RAKOW WINDOWS Parks Property Management 1 04-16-2020 1 1%699,999 - 198,887 0.34%501,110
Closed #26 FILLMORE ROOF Parks Property Management 1 05-15-2020 1 1%1,874,156 - 1,874,154 3.19%-
Closed #4 FAIRWAY PARK PAVILION Parks Parks & Recreation 1 05-15-2020 1 1%50,000 - 35,044 0.06%14,955
Closed #2 COLLINS PARK Parks Parks & Recreation 1 05-28-2020 1 1%557,287 - 557,287 0.95%-
Closed #13 NORTH SHORE GENERATOR Parks Property Management 1 06-30-2020 1 1%524,999 - 503,861 0.86%21,138
Closed #18 SCOTT RAKOW GENERATOR Parks Property Management 1 06-30-2020 1 1%803,748 - 729,717 1.24%74,029
Closed #18 SCOTT RAKOW POOL Parks Parks & Recreation 1 07-06-2020 1 1%977,998 - 977,104 1.66%893
Closed #47 71 ST. ENTRANCE READERS Public Safety Police 1 07-12-2020 1 1%31,582 - 31,582 0.05%-
Closed #47 JULIA TUTTLE CSWY READERS Public Safety Police 1 09-21-2020 1 1%89,186 - 89,185 0.15%1
Closed #57 LUMMUS PARK/OCEAN DRIVE CAMERAS Public Safety Police 1 02-28-2021 1 1%824,845 - 824,845 1.40%-
Closed #4 FAIRWAY PARK FENCE Parks Parks & Recreation 1 03-10-2021 1 1%209,999 - 205,917 0.35%4,082
Closed #40 41 STREET LIGHTING UPGRADES Infrastructure Public Works Department 1 03-13-2021 1 1%102,999 - 99,173 0.17%3,825
Closed #56 CAMERAS- BEACHWALK Public Safety Police 1 04-02-2021 1 1%693,219 - 693,218 1.18%-
Closed #24 MIDDLE BEACH BEACHWALK PH3 Parks Capital Improvement Projects 1 12-27-2021 1 1%4,500,000 - 4,214,178 7.16%285,821
Closed #18 SCOTT RAKOW GYM FLOORS Parks Parks & Recreation 1 01-21-2022 1 1%322,561 - 322,451 0.55%110
Closed #9 MSD PLAYGROUND AND SIDEWALKS Parks Parks & Recreation 1 08-05-2022 1 1%553,999 - 524,410 0.89%29,588
Closed #52 FLAMINGO PARK LED LIGHTING Public Safety Parks & Recreation 1 11-14-2022 1 1%1,044,143 - 1,044,143 1.78%-
Closed #18 SCOTT RAKOW OTHER FLOORS Parks Parks & Recreation 1 08-30-2023 1 1%203,798 - 203,798 0.35%-
Closed Sum 38 43%23,048,553 - 21,828,429 37%1,220,104
Closed Count 38 43%38 38 38 0.00%38
CITY OF MIAMI BEACH Page 1 of 3 4/17/2023
Exhibit B
G.O. BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Count % Count $ Budget $ Encumbered $ Spent % Spent $ Available
Complete #42 NAUTILUS TRAFFIC CALMING Infrastructure Transportation 1 01-14-2022 1 1%739,499 22,500 712,627 1.21%4,371
Complete #49 PUBLIC SAFETY RADIO SYSTEM Public Safety Fire 1 04-30-2022 1 1%9,700,000 1,190,426 8,502,920 14.46%6,653
Complete #12 N. BEACH OCEANSIDE BEACHWALK Parks Capital Improvement Projects 1 06-06-2022 1 1%1,999,999 64,831 1,935,167 3.29%-
Complete #50 DADE BLVD. CORRIDOR CAMERAS Public Safety Police 1 08-03-2022 1 1%165,674 - 127,436 0.22%38,238
Complete #50 71 STREET CORRIDOR CAMERAS Public Safety Police 1 12-22-2022 1 1%211,999 1,634 83,673 0.14%126,692
Complete Sum 10 11%12,817,171 1,279,391 11,361,823 19%175,954
Complete Count 5 6%5 5 5 0.00%5
Construction #57 COLLINS AVE/WASH AVE CAMERAS Public Safety Police 1 09-29-2023 1 1%665,154 39,197 249,802 0.42%376,155
Construction #47 OTHER READERS CITYWIDE Public Safety Police 1 12-30-2023 1 1%1,390,000 50,866 429,209 0.73%909,924
Construction #39 SEAWALLS/SHORELINES - TRANCHE 1 Infrastructure Public Works Department 1 02-29-2024 1 1%4,999,998 2,660,589 1,845,229 3.14%494,178
Construction #37 SIDEWALKS - TRANCHE 1 Infrastructure Public Works Department 1 03-29-2024 1 1%4,110,066 119,652 3,539,231 6.02%451,181
Construction #33 TREE PLANTING - TRANCHE 1 Infrastructure Environmental 1 03-30-2024 1 1%2,620,000 366,945 2,190,945 3.72%62,109
Construction #38 STREETS - TRANCHE 1 Infrastructure Public Works Department 1 03-30-2024 1 1%5,800,000 318,724 5,352,408 9.10%128,866
Construction #10 MAURICE GIBB PARK Parks Capital Improvement Projects 1 12-08-2024 1 1%4,500,000 4,263,959 211,392 0.36%24,647
Construction Sum 28 32%$24,085,218 $7,819,932 $13,818,216 23%$2,447,060
Construction Count 7 8%7 7 7 0.00%7
Design #55 STREET LIGHTING - TRANCHE 1 Public Safety Public Works Department 1 07-17-2023 b 1 1%3,500,000 206,377 201,671 0.34%3,091,951
Design #53 CONVENTION CENTER BOLLARDS Public Safety Public Works Department 1 08-28-2023 1 1%783,128 726,480 55,804 0.09%843
Design #53 SOUNDSCAPE PARK BOLLARDS Public Safety Public Works Department 1 08-28-2023 1 1%225,198 174,295 50,729 0.09%174
Design #53 SOUTH POINTE PARK BOLLARDS Public Safety Public Works Department 1 08-28-2023 1 1%391,668 342,332 49,206 0.08%130
Design #34 A.G.IMPROVEMENTS - INDIAN CREEK Infrastructure Public Works Department 1 08-31-2023 1 1%1,112,000 1,111,636 - 0.00%364
Design #48 POLICE HQ FACILITY - TRANCHE 1 Public Safety Property Management 1,2 10-31-2023 b 1 1%6,573,271 37,315 1,496,070 2.54%5,039,886
Design #50 ALTON RD. CORRIDOR CAMERAS Public Safety Police 1 12-02-2023 1 1%211,999 19,598 92,621 0.16%99,779
Design #13 N.S. PLAYGROUND & REFORESTATION Parks Parks & Recreation 1 01-30-2024 1 1%794,999 - 4,546 0.01%790,453
Design #42 PALM VIEW TRAFFIC CALMING Infrastructure Transportation 1 03-18-2024 1 1%86,349 4,040 42,387 0.07%39,922
Design #19 SOUNDSCAPE RESTROOMS/STORAGE Parks Parks & Recreation 1 03-31-2024 1 1%699,999 31,501 15,907 0.03%652,590
Design #43 CHASE AVE/34 ST SHARED USE PATH Infrastructure Capital Improvement Projects 1 06-18-2024 1 1%830,000 42,439 253,946 0.43%533,614
Design #5 FLAMINGO PARK MASTER PLAN Parks Capital Improvement Projects 1 08-28-2024 1 1%15,150,000 453,415 534,770 0.91%14,161,813
Design #23 PEDESTRIAN BRIDGE Parks Capital Improvement Projects 1 08-30-2024 1 1%8,999,999 7,259,137 1,690,254 2.87%50,606
Design #43 23 ST. STREETSCAPE IMPROVEMENTS Infrastructure Capital Improvement Projects 1 09-27-2024 1 1%1,499,998 57,977 586,819 1.00%855,202
Design #9 MSD PARK LIGHTING Parks Parks & Recreation 1 10-01-2024 1 1%127,999 31,235 7,194 0.01%89,570
Design #25 WATERWAY RESTORATION Parks Capital Improvement Projects 1 10-17-2024 1 1%100,000 - 27,111 0.05%72,888
Design #43 ALTON ROAD SHARED USE PATH Infrastructure Transportation 1 10-30-2024 b 1 1%50,000 - - 0.00%50,000
Design #42 NORMANDY ISLE TRAFFIC CALMING Infrastructure Transportation 1 10-31-2024 1 1%293,999 82,390 144,240 0.25%67,368
Design #42 BAYSHORE SOUTH TRAFFIC CALMING Infrastructure Transportation 1 12-18-2024 1 1%380,148 109,600 182,939 0.31%87,608
Design #15 PAR 3 / BAYSHORE PARK Parks Capital Improvement Projects 1 05-12-2025 1 1%15,699,999 8,718 863,549 1.47%14,827,731
Design #45 FIRE STATION #1 Public Safety Capital Improvement Projects 1,2 08-26-2025 1 1%4,000,000 997,255 1,253,784 2.13%1,748,958
Design #30 SKATE PARK Parks Parks & Recreation 1 10-30-2025 1 1%749,999 49,708 39,726 0.07%660,565
Design #54 MARINE PATROL FACILITY Public Safety Capital Improvement Projects 1,2 11-07-2025 1 1%1,999,999 351,898 221,320 0.38%1,426,779
Design #23 BAYVIEW TERRACE LINK Parks Capital Improvement Projects 1,2 01-22-2026 1 1%169,999 - 75,131 0.13%94,868
Design #23 SOUTH BAY CLUB LINK Parks Capital Improvement Projects 1,2 01-22-2026 1 1%559,999 - 176,551 0.30%383,448
Design #23 BAY GARDEN MANOR LINK Parks Capital Improvement Projects 1,2 02-03-2026 1 1%269,999 - 79,101 0.13%190,898
Design #50 41 ST. CORRIDOR CAMERAS Public Safety Capital Improvement Projects 1 07-21-2026 1 1%235,324 - 17,999 0.03%217,324
Design #40 41 ST CORRIDOR IMPROVEMENTS Infrastructure Capital Improvement Projects 1,2 07-21-2026 1 1%1,977,318 1,210,713 688,913 1.17%77,691
Design Sum 140 159%$67,473,390 $13,308,059 $8,852,288 15%$45,313,023
Design Count 28 32%28 28 28 0.00%28
CITY OF MIAMI BEACH Page 2 of 3 4/17/2023
G.O. BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Count % Count $ Budget $ Encumbered $ Spent % Spent $ Available
Planning #5 FLAMINGO YOUTH CENTER FACILITY Parks Capital Improvement Projects 1,2 09-28-2023 b 1 1%250,000 168,561 29,220 0.05%52,218
Planning #36 WASHINGTON AVE. CORRIDOR Infrastructure Economic Development 1,2 07-01-2024 b 1 1%397,616 - 213,740 0.36%183,876
Planning #1 72 ST. COMMUNITY COMPLEX Parks Capital Improvement Projects 1,2 06-25-2026 1 1%10,800,000 - 2,266,841 3.85%8,533,158
Planning #46 OCEAN RESCUE NOBE FACILITY Public Safety Capital Improvement Projects 1,2 01-27-2028 1 1%1,000,000 - 15,658 0.03%984,342
Planning #31 OCEAN DRIVE CORRIDOR Infrastructure Capital Improvement Projects 1,2 09-20-2028 1 1%2,000,000 - 406,500 0.69%1,593,500
Planning #8 LUMMUS PARK Parks Capital Improvement Projects 1 09-19-2029 1 1%4,736,999 - 25,761 0.04%4,711,237
Planning Sum 36 41%$19,184,615 $168,561 $2,957,720 5%$16,058,331
Planning Count 6 7%6 6 6 0.00%6
Pending #13 NORTH SHORE PATH & FIELDS Parks Capital Improvement Projects 1,2 (blank)1 1%1,409,000 - - 0.00%1,408,999
Pending #29 WEST LOTS - TRANCHE 1 Parks Economic Development 1 (blank)1 1%1,000,000 - - 0.00%1,000,000
Pending #18 SCOTT RAKOW ICE RINK FLOORS Parks Parks & Recreation 1 (blank)1 1%413,640 - - 0.00%413,640
Pending #52 FLA. PARK LED LIGHTING - FIELDS Public Safety Capital Improvement Projects 1 (blank)1 1%1,655,856 - - 0.00%1,655,856
Pending Sum 28 32%$4,478,496 $0 $0 0%$4,478,495
Pending Count 4 5%4 4 4 0.00%4
88 100%$151,087,443 $22,575,943 $58,818,476 100%$69,692,967
CITY OF MIAMI BEACH Page 3 of 3 4/17/2023
Note: b indicates end of Phase, not end of project.
Page 1 of 1
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, FL 33139 Tel. 305-673-7010 Fax: 305-673-7782
Office of the City Manager
MEMORANDUM
TO: Karen Rivo, Chair, and G.O. Bond Oversight Committee, (the “Committee”)
FROM: Maria Hernandez, G.O. Bond Program Director
DATE: April 20, 2023
SUBJECT: GO #33 – Tree Planting / GO #37 – Sidewalk Improvements
GOB PROJECT FUNDS TRANSFER & SCOPE CHANGE PROTOCOL
•Protocol #11: Funding Swap Between 2 or more Tranche 1 projects within the same Category.
BACKGROUND
GO #33 - Tree Planting – Tranche 1
The Urban Forestry Division of the Environment & Sustainability Department has made great progress
during Tranche 1, planting over 1,900 trees in various neighborhoods and parks throughout the City.
Biscayne Point is the next neighborhood targeted for reforestation. An Invitation to Quote (ITQ) will be
issued within the next couple of weeks. The estimated project cost exceeds the funding amount currently
available in Tranche 1.
GO #37 – Sidewalk Improvements
The Public Works Department has also made great progress during Tranche 1, replacing over 600,000
SF of sidewalk to date throughout various neighborhoods. However, based on the current workplan and
schedule, it is anticipated that that this project will not require all the funding currently allocated in
Tranche 1.
RECOMMENDATION
The administration recommends the re-alignment of the $150,000 available from sub-project GO #37
Sidewalk Improvements to GO #33 Tree Planting to allow the Urban Forestry Division to continue
moving forward with the program.
Once approved, the revised distribution of funding between Tranches will be as follows:
Tranche 1
Current
Budget
Funding
Swap
Tranche 1
Amended
Budget
Tranche 2
Current
Budget
Tranche 2
Amended
Budget
Tranche 3
Budget Total Budget
#37 Sidewalk Improvements 4,110,066 ($150,000) 4,010,066 4,989,934 5,089,934 3,900,000 $ 13,000,000
#33 Tree Planting 2,620,000 $150,000 2,720,000 2,380,000 2,280,000 - $ 5,000,000
Exhibit C
www.GOMBInfo.com
Bold
2023 CONSTRUCTION COMMENCEMENTS
$40.9 Million Total GOB Budget
First Quarter
-Collins /Wash Ave
Cameras
Second Quarter
-Maurice Gibb Park
-Bollards
-Bayshore Park
-Above Ground Improv.
(Indian Creek)
Third Quarter
-Pedestrian Bridge
-23 St. Streetscape
-Soundscape Storage
Fourth Quarter
-Police HQ. (RTCC)
-N.S. Park Playground
-Chase Ave/34 St.
Bold Text Indicates Projects have Commenced
Exhibit D
Exhibit E
neighborhood.
CITY OF MIAMI BEACH
G.O. BOND for ARTS and CULTURE
ALL FACILITIES Total Amounts
(approved July 2022)Ownership Structure Grant Project
Budgets
Project
Execution By:*Quick Wins Shovel
Ready **Tranches Tranche 1
1 Bass Museum of Art 20,100,000$ City Owned -$ FM / CIP Yes (CRR)No 1,2 10,589,000$
2 Miami City Ballet 12,000,000 City Owned - FM / CIP Yes (CRR)No 1 12,000,000
3 Miami City Ballet - Workforce Housing 4,000,000 Dev & Ground Lease 4,000,000 Servitas No Possibly 1 4,000,000
4 Fillmore Miami Beach 29,100,000 City Owned - CIP No No 1,2 12,406,000
5 Colony Theater 7,480,000 City Owned - FM Yes (CRR)No 1,2 4,100,000
6 Miami Beach Botanical Garden 6,270,000 City Owned - FM / CIP Yes (CRR)No 1 6,270,000
7 Art Deco Welcome Center 1,420,000 City Owned - FM / CIP Yes (CRR)No 1 1,420,000
8 New World Symphony 5,700,000 Ground Lease 5,700,000 NWS Yes Yes 1 5,700,000
9 Holocaust Memorial Miami Beach 7,150,000 Lease 7,150,000 Skyline No No 1 7,150,000
10 Byron Carlyle Theater 30,570,000 City Owned - CIP No No 1,2 10,590,000
11 North Beach Oceanfront Center (UNIDAD)1,183,000 City Owned - FM Yes (CRR)No 1 1,183,000
12 MB Hispanic Community Cntr (Coral Rock House)767,000 Not City Owned 767,000 UNIDAD Yes Yes 1 767,000
13 Collins Park Cultural Center (Miami New Drama)7,670,000 City Owned - CIP No No 1 7,670,000
14 Miami Beach Bandshell 3,770,000 City Owned - CIP No No 1 3,770,000
15 The Wolfsonian - FIU 5,000,000 Not City Owned 1,500,000 FIU No No 1,2 1,500,000
16 The Jewish Museum of Florida - FIU 750,000 Not City Owned 750,000 FIU Yes Yes 1 750,000
All Facilities Total 142,930,000$ 19,867,000$ 89,865,000$
OTHER PROJECTS
17 Artistic Playgrounds 3,835,000$ City Owned -$ Parks Yes (Portion)Yes 1 3,835,000$
18 Aquatic Sculpture Park 5,000,000 State Land - TBD Yes (Phase 1)Yes 1 5,000,000
19 Misc. A & C: Collins Park Rotunda 1,500,000 City Owned - CIP No Yes 1 1,500,000
20 Misc. A & C: MB Classical Music Festival ***1,500,000 City Owned - TBD Yes N/A 1 1,500,000
21 Workforce Housing for Cultural Institutions 4,000,000 TBD - TBD TBD TBD 2 -
Other Projects Total 15,835,000$ -$ $11,835,000
Tranche 1 Total 63.96%$ 101,700,000
Tranche 2 Total 36.04%57,300,000$
TOTAL 158,765,000$ 19,867,000$ 159,000,000$
GRAND TOTAL (Rounded Up)159,000,000$
*CRR refers to Capital Renewal & Replacement Projects
** Tranche 2 Notes:
#1 Bass Museum of Art: Expansion construction approximately 45% complete in T1. Remaining in T2.
#4 Fillmore Miami Beach: Construction approximately 40% complete in T1. Remaining in T2.
#5 Colony Theater: T2 scope requires completion of Collins Park Cultural Center space.
#10 Byron Carlyle: Construction approximately 25% complete in T1. Remaining in T2.
#21 Workforce Housing for Cultural Institutions: Undetermined Projects go to T2.
*** Misc. A&C: MB Classical Festival: amount recommended by the GOB Oversight Committee on March 30.