Resolution 2024-32960 I I `
RESOLUTION NO.' 2024-32960
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, URGING THE FLORIDA
DEPARTMENT OF TRANSPORTATION TO PHASE AND/OR
RESCHEDULE THE START DATE FOR THE FUTURE ALTON
ROAD RECONSTRUCTION PROJECT FROM THE NORTH
MICHIGAN AVENUE TO EAST OF ALLISON ROAD, UNTIL THE
COMPLETION OF THE I-395/STATE ROAD 836/1-95 SIGNATURE
BRIDGE PROJECT AND THE VENETIAN CAUSEWAY BRIDGE
REPLACEMENT PROJECT TO AVOID FURTHER IMPACTS TO
TRAFFIC ENTERING AND EXITING MIAMI BEACH.
WHEREAS, State Road ("SR") 907/Alton Road is an arterial roadway under the
jurisdiction of the Florida Department of Transportation ("FDOT"); and
WHEREAS, the FDOT is currently planning to reconstruct Alton Road from North
Michigan Avenue to East of Allison Road (the"Alton Road Reconstruction Project"), which
will provide roadway, drainage, street lighting and traffic signalization improvements,
enhance the City's water and sewer infrastructure, and provide safer facilities for bicyclists
and pedestrians; and
WHEREAS, at present, the segment of Alton Road from North Michigan Avenue
to South Ed Sullivan Drive/43rd Street is currently funded by the FDOT and anticipated to
begin construction in 2026; and the construction of the project is reasonably expected to
cause traffic congestion in the area; and
WHEREAS, additionally, there are other projects on major thoroughfares being
undertaken by the FDOT and Miami-Dade County, including the I-395/SR 836/1-95 Miami
Signature Bridge ("Signature Bridge Project") which is in construction and anticipated to
be completed in late 2027, and the Venetian Causeway Bridge Replacement Project,
which is in design and anticipated to begin construction in 2025, both of which will affect
vehicular traffic exiting and entering the City of Miami Beach; and
WHEREAS, the initiation of the Alton Road Reconstruction project in 2026 is likely
to further exacerbate traffic congestion in the City, causing inconvenience and frustration
for residents, visitors, and commuters; and
WHEREAS, considering the delays on the completion of the Signature Bridge and
the construction project impacts on traffic entering and exiting Miami Beach, the Mayor
and City Commission respectfully urge FDOT to consider phasing and/or rescheduling
the start date for the Alton Road Reconstruction project until after the completion of the
I-395/SR 836/1-95 Signature Bridge project and the Venetian Causeway Bridge
Replacement project would help minimize disruptions to traffic flow and alleviate the
burden on residents and businesses.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission hereby urge the Florida Department of Transportation to phase and/or
reschedule the start date for the future Alton Road Reconstruction project from the North
Michigan Avenue to East of Allison Road, until the completion of the I-395/SR 836/1-95
Signature Bridge project and the Venetian Causeway Bridge Replacement project to
avoid further impacts to traffic entering and exiting Miami Beach.
PASSED and ADOPTED this /3 day of a , 2024.
ATTEST:
MAR, 1 5 2024 Steven Meiner, Mayor
Rafa E. Granado, City Clerk
(sponsored ;by Commissioner Alex J. Fernandez _ : '' y-�,
Co-sponsored by Commissioner Laura Dominguez)
:INCORPORATED;
Co-Sponsored by Commissioner Tanya K.Bhatt617/�, ;9►
•;�R ,._
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
City Attorney Date
Resolutions -C7 V
MIAMI BEACH
COMMISSION MEMORANDUM
TO: Honorable Mayor and Members of the City Commission
FROM: Rafael A. Paz, City Attorney
DATE: March 13, 2024
SUBJECT:A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, URGING THE FLORIDA DEPARTMENT OF
TRANSPORTATION TO RESCHEDULE THE START DATE FOR THE
PROPOSED ALTON ROAD RECONSTRUCTION PROJECT UNTIL THE
COMPLETION OF THE I-395/STATE ROAD 836/1-95 SIGNATURE BRIDGE
PROJECT AND THE VENETIAN CAUSEWAY BRIDGE REPLACEMENT
PROJECT TO AVOID FURTHER IMPACTS TO TRAFFIC ENTERING AND
EXITING MIAMI BEACH. •
BACKGROUND/HISTORY
Was this Agenda Item initially requested by a lobbyist which, as defined in Code Sec. 2-481,
includes a principal engaged in lobbying? No
If so, specify name of lobbyist(s)and principal(s): N/A
ANALYSIS
The proposed Resolution is submitted at the request of the sponsors, Commissioners Alex
Fernandez and Laura Dominguez, for consideration at the March 13, 2024 Commission
meeting.
The Resolution will be submitted via Supplemental Agenda.
SUPPORTING SURVEY DATA
N/A
FINANCIAL INFORMATION
N/A
Is this a"Residents Right Does this item utilize G.O.
to Know" item,pursuant to Bond Funds?
City Code Section 2-14?
No No
Page 344 of 1070
Legislative Tracking
Office of the City Attorney
Sponsor
Commissioners Alex Fernandez and Laura Dominguez
Page 345 of 1070
MIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov
Office of the City Clerk
Tel: 305-673-741 1
March 19, 2024
District Six Secretary Stacy Miller
Florida Department of Transportation
1000 N.W. 111 Avenue
Miami, FL 33172
Dear District Six Secretary Miller,
Attached please find a copy of City of Miami Beach Resolution No. 2024-32960:
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, URGING THE FLORIDA DEPARTMENT OF
TRANSPORTATION TO PHASE AND/OR RESCHEDULE THE START DATE
FOR THE FUTURE ALTON ROAD RECONSTRUCTION PROJECT FROM THE
NORTH MICHIGAN AVENUE TO EAST OF ALLISON ROAD, UNTIL THE
COMPLETION OF THE I-395/STATE ROAD 836/1-95 SIGNATURE BRIDGE
PROJECT AND THE VENETIAN CAUSEWAY BRIDGE REPLACEMENT
PROJECT TO AVOID FURTHER IMPACTS TO TRAFFIC ENTERING AND
EXITING MIAMI BEACH.
(Sponsored by Commissioners Alex J. Fernandez and Laura Dominguez and
Co-sponsored by Commissioner Tanya K. Bhatt)
This Resolution was passed and adopted by the Mayor and City Commission of the City of Miami
Beach on March 13, 2024.
Respectfully,
Rafael E. Granado
City Clerk
c: Commissioner Alex J. Fernandez
Commissioner Laura Dominguez
Commissioner Tanya K. Bhatt
MIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov
Office of the City Clerk
Tel:305-673-7411
March 19, 2024
Secretary Jared W. Perdue
Florida Department of Transportation
605 Suwannee Street
Tallahassee, FL 32399
Dear Secretary Perdue,
Attached please find a copy of City of Miami Beach Resolution No. 2024-32960:
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, URGING THE FLORIDA DEPARTMENT OF
TRANSPORTATION TO PHASE AND/OR RESCHEDULE THE START DATE
FOR THE FUTURE ALTON ROAD RECONSTRUCTION PROJECT FROM THE
NORTH MICHIGAN AVENUE TO EAST OF ALLISON ROAD, UNTIL THE
COMPLETION OF THE I-395/STATE ROAD 836/1-95 SIGNATURE BRIDGE
PROJECT AND THE VENETIAN CAUSEWAY BRIDGE REPLACEMENT
PROJECT TO AVOID FURTHER IMPACTS TO TRAFFIC ENTERING AND
EXITING MIAMI BEACH.
(Sponsored by Commissioners Alex J. Fernandez and Laura Dominguez and
Co-sponsored by Commissioner Tanya K. Bhatt)
This Resolution was passed and adopted by the Mayor and City Commission of the City of Miami
Beach on March 13, 2024.