1. Agenda & Handouts_5-09-24__________________________________________________________________________________________________
Legend: (P) Planning Phase, (D) Design Phase, (C) Construction Phase, (PN) Pending, (V) Various Phases, (F) Future Tranche
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo, Chair
Maria Hernandez, Liaison
AGENDA
May 9, 2024
I.Roll Call and Introductions All 4:00pm
II.Committee Business Karen Rivo 4:05pm
•Adoption of Meeting Minutes from 4-11-24
III.Inspector General Quarterly Report Discussion Chair / Committee 4:15pm
2022 G.O. Bonds for Arts & Culture
IV.Arts & Culture Program General Status Update Maria Hernandez 4:30pm
V.2022 Bonds Projects Update PM / CIP / MH 4:35pm
•J. Gleason Theater (P), Byron Carlyle Theater (P),
Bass Museum (C), NOBE Oceanside Center (C), Reefline (P)
VI.Grant Projects Scope Variation Maria Hernandez 5:00pm
VII.Public Comment Public 5:15pm
2018 G.O. Bonds
VIII.Program General Status Update Maria Hernandez 5:25pm
IX.2018 Bonds Projects Update CIP 5:30pm
•FS#1 (D), Ped Bridge (D), Baywalks (D)
X.Public Comment Public 5:40pm
XI.Community Outreach N. Affairs Division 5:50pm
•Recent Past Public Meetings / Upcoming Events MH / KPulido
XII.Public Comment Public 5:55pm
XIII.Adjournment 6:00pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City
Manager and City Commission from a macro perspective regarding the timely progress, overall goals, costs, including
financial efficiencies, and the timely completion of General Obligation Bond Program projects approved by the voters
in the City of Miami Beach. The Committee shall have the following powers & duties:
1.Receive input from the public, the City Administration, City consultants, and the City’s Inspector General, as
needed, to make recommendations relative to the overall timing, cost efficiencies, and prioritization of the G.O.
Bond Program projects.
2.Provide general oversight to ensure that G.O. Bond Program project timelines, budgets (including cost efficiencies)
are prioritized and achieved, and that the projects are completed in accordance with the scope of work
approved by the voters.
3.Review City staff and G.O. Bond Program project manager’s progress reports and provide monthly reports to the
City Commission.
www.GOMBInfo.com
G.O. BOND for ARTS & CULTURE
PROGRAM UPDATE
May 9, 2024
SECTION IV
www.GOMBInfo.com
MAIN PROJECTS STATUS
•100% of all Tranche 1 Projects are Complete or Active = 20 •6.1% of all Tranche 1 Funds are Spent
or Encumbered= $6.2M out of $101.7M
www.GOMBInfo.com
SUBPROJECTS STATUS
•91% of all T1 Subprojects are
Complete or Active = 42
•18% of the value of all T1 Projects are
Complete or Under Construction
www.GOMBInfo.com
3/7/24 4/11/24 5/9/24 VARIANCE
COMPLETE 0 1 1 0
ACTIVE 18 19 19 0
PENDING 2 0 0 0
FUTURE 1 1 1 0
ALL 21 21 21 0
SUMMARY - ALL MAIN PROJECTS
www.GOMBInfo.com
No.%No.%No.%
ACTIVE/COMPLETE 40 87%42 91%42 91%0
CONSTRUCTION 6 6%8 17%10 22%2
PLANNING / DESIGN 33 30%31 67%28 61%-3
CLOSED / COMPLETE 1 1%3 7%4 9%1
REMAINING 6 13%4 9%4 9%0
TOTAL SUB-PROJECTS 46 46 46
4/11/24
SUMMARY SUB-PROJECTS - TRANCHE 1
3/7/24 VARIANCE5/9/24
www.GOMBInfo.com
2024 CONSTRUCTION COMMENCEMENTS
$21.8 Million Total GOBAC Budget
First Quarter
Colony Electrical Improv. (Complete)
Second Quarter
Art Deco Welcome Ctr Roof Access Ladder (Complete)
Bass Misc. Improvements
Bass Fire Alarm
Bass Mechanical
Collins Park Rotunda
Colony Technology
Colony FF&E
Hispanic Comm. Center
Holocaust Memorial
NBOC Furniture
NBOC Kitchen
Third Quarter
NBOC Doors/Windows Seal
NBOC Painting
NBOC Sound /Acoustics
N.Shore Artistic Playground
Fourth Quarter
Aquatic Sculpture Park PH1
Bass Technology
Colony Bldg. Improv.
Colony Security & Comm.
Bold Text Indicates Projects have Commenced in Calendar Year
G.O. BOND ARTS AND CULTURE PROJECT LIST BY PHASEActive PhaseNo.Project Name Category Department Tranche Anticipated End Date ↑Count %Count $ Budget $ Encumbered $ Spent% Spent$ AvailableClosed14 MB BANDSHELL CANOPY PROJECTION MAPPING City OwnedGrant ‐ Facilities Management101‐30‐20241 2%153,000 ‐ 153,000 1 ‐ Closed Sum‐ 0%153,000 ‐ 153,000 ‐ Closed Count1 2%1 1 1 1 Complete05 COLONY ELECTRICAL IMPROVEMENTSCity OwnedFacilities Management101‐05‐20241 2%134,200 117,538 286 0 16,376 Complete20 MB CLASSICAL MUSIC FESTIVALOther Projects Loan102‐29‐20241 2%1,500,000 ‐ 1,484,757 1 15,243 Complete07 ART DECO LADDER/ROOF ACCESSCity OwnedFacilities Management105‐10‐20241 2%15,600 ‐ 416 0 15,184 Complete Sum‐ 0%1,649,800 117,538 1,485,460 46,802 Complete Count3 7%3 3 3 3 Construction 11 NBOC COMMUNITY ROOM FURNITURECity OwnedFacilities Management107‐30‐20241 2%78,600 ‐ 168 0 78,432 Construction 01 BASS AUTOMATIC SHADE SYSTEMCity OwnedFacilities Management107‐31‐20241 2%230,600 63,737 33,323 0 133,541 Construction 01 BASS LIGHTING IMPROVEMENTSCity OwnedFacilities Management111‐14‐20241 2%463,000 345,077 987 0 116,936 Construction 19 COLLINS PARK ROTUNDACity OwnedCapital Improvement Projects102‐27‐20251 2%1,500,000 1,320,440 3,150 0 176,410 Construction 01 BASS MISCELLANEOUS IMPROVEMENTSCity OwnedFacilities Management106‐16‐20251 2%833,000 62,807 1,776 0 768,418 Construction 03 WF HOUSING (COLLINS PARK)Non‐City Owned Grant ‐ CIP110‐18‐20251 2%4,000,000 ‐ ‐ ‐ 4,000,000 Construction 05 COLONY TECHNOLOGY IMPROV.City OwnedGrant ‐ Facilities Management111‐11‐20251 2%2,594,000 ‐ 550,000 0 2,044,000 Construction 05 COLONY FF&ECity OwnedFacilities Management112‐09‐20251 2%445,400 18,770 949 0 425,681 Construction 08 NEW WORLD SYMPHONYNon‐City Owned Grant ‐ Facilities Management110‐09‐20261 2%5,700,000 ‐ 415,535 0 5,284,465 Construction 12 HISPANIC COMMUNITY CNTR.Non‐City Owned Grant ‐ Facilities Management1(blank)1 2%767,000 ‐ 62,334 0 704,666 Construction Sum‐ 0%16,611,600 1,810,831 1,068,221 13,732,548 Construction Count10 22%10 10 10 10 Design01 BASS FIRE ALARM SYSTEMCity OwnedFacilities Management109‐30‐20241 2%2,305,900 416,581 4,915 0 1,884,404 Design11 NBOC DOORS & WINDOWS SEALCity OwnedFacilities Management110‐01‐20241 2%161,800 3,662 345 0 157,793 Design11 NBOC SOUND SYSTEM & ACOUSTICSCity OwnedFacilities Management110‐01‐20241 2%408,300 39,914 19,785 0 348,601 Design17 NORTH SHORE ARTISTIC PLAYGROUNDOther Projects Parks & Recreation111‐29‐20241 2%238,000 ‐ ‐ ‐ 238,000 Design05 COLONY BLDG. IMPROVEMENTSCity OwnedFacilities Management1,212‐31‐20241 2%639,500 74,167 1,363 0 563,970 Design01 BASS MECHANICAL IMPROVEMENTSCity OwnedFacilities Management109‐18‐20251 2%290,500 120,023 6,137 0 164,340 Design17 S. POINTE ARTISTIC PLAYGROUNDOther Projects Parks & Recreation110‐30‐20251 2%1,126,000 9,554 ‐ ‐ 1,116,446 Design11 NBOC PAINTINGCity OwnedFacilities Management111‐24‐20251 2%141,400 ‐ 301 0 141,099 Design05 COLONY SECURITY & COMM. SYSTEMSCity OwnedFacilities Management112‐10‐20251 2%286,900 ‐ 612 0 286,288 Design02 MCB ELECTRICAL IMPROVEMENTSCity OwnedFacilities Management107‐30‐20261 2%393,500 ‐ 839 0 392,661 Design02 MCB ELEVATOR MODERNIZATIONCity OwnedFacilities Management107‐30‐20261 2%524,800 ‐ 1,119 0 523,681 Design02 MCB FF&ECity OwnedFacilities Management107‐30‐20261 2%719,100 ‐ 1,533 0 717,567 Design02 MCB MECHANICAL IMPROVEMENTSCity OwnedFacilities Management107‐30‐20261 2%900,000 ‐ 1,918 0 898,082 Design02 MCB MISCELLANEOUS IMPROVEMENTSCity OwnedFacilities Management107‐30‐20261 2%1,944,600 ‐ 4,145 0 1,940,455 Design02 MCB TECH. IMPROVEMENTSCity OwnedGrant ‐ Facilities Management107‐30‐20261 2%7,518,000 ‐ 248,609 0 7,269,391 Design01 BASS TECHNOLOGY IMPROVEMENTSCity OwnedFacilities Management1(blank)1 2%604,000 ‐ 1,288 0 602,712 Design09 HOLOCAUST MEMORIAL MBNon‐City Owned Grant ‐ Facilities Management1(blank)1 2%7,150,000 ‐ 128,000 0 7,022,000 Design Sum‐ 0%25,352,300 663,902 420,909 24,267,490 Design Count17 37%17 17 17 17 CITY OF MIAMI BEACH5/5/2024 ‐ 9:43 PMSECTION IV
G.O. BOND ARTS AND CULTURE PROJECT LIST BY PHASEActive PhaseNo.Project Name Category Department Tranche Anticipated End Date ↑Count %Count $ Budget $ Encumbered $ Spent% Spent$ AvailablePlanning10 BYRON CARLYLE THEATERCity OwnedFacilities Management1,207‐31‐2024 b1 2%10,590,000 ‐ 22,240 0 10,567,760 Planning18 AQUATIC SCULPTURE PARK ‐ PH. 1Other Projects Grant109‐30‐2024 b1 2%2,779,500 ‐ ‐ ‐ 2,779,500 Planning11 NBOC CATERING KITCHEN EXPANSIONCity OwnedFacilities Management110‐31‐20241 2%392,900 67,116 838 0 324,946 Planning16 JEWISH MUSEUM OF FLORIDANon‐City Owned Grant ‐ Facilities Management108‐29‐20251 2%750,000 ‐ ‐ ‐ 750,000 Planning17 LA GORCE ARTISTIC PLAYGROUNDOther Projects Parks & Recreation109‐30‐20251 2%674,000 ‐ ‐ ‐ 674,000 Planning13 COLLINS PARK CULTURAL CNTR.City OwnedCapital Improvement Projects110‐13‐20261 2%7,670,000 ‐ 16,108 0 7,653,892 Planning14 MB BANDSHELL BUILDING IMPROVEMENTSCity OwnedCapital Improvement Projects110‐23‐20261 2%3,617,000 345,632 7,596 0 3,263,772 Planning06 MIAMI BEACH BOTANICAL GARDENCity OwnedCapital Improvement Projects109‐26‐20271 2%6,270,000 ‐ 13,168 0 6,256,832 Planning01 BASS MUSEUM MULTIPURPOSE ADDITIONCity OwnedCapital Improvement Projects1,208‐17‐20291 2%5,862,000 ‐ 12,311 0 5,849,689 Planning04 FILLMORE (JACKIE GLEASON)City OwnedFacilities Management1,2(blank)1 2%12,406,000 ‐ 26,053 0 12,379,947 Planning15 THE WOLFSONIANNon‐City Owned Grant ‐ Facilities Management1,2(blank)1 2%1,500,000 ‐ ‐ ‐ 1,500,000 Planning Sum‐ 0%52,511,400 412,748 98,314 52,000,339 Planning Count11 24%11 11 11 11 Pending07 ART DECO LIGHTINGCity OwnedCapital Improvement Projects1(blank)1 2%156,000 ‐ 333 0 155,667 Pending07 ART DECO MUSEUM EXPANSIONCity OwnedCapital Improvement Projects1(blank)1 2%1,248,400 ‐ 2,622 0 1,245,778 Pending17 OTHER ARTISTIC PLAYGROUNDSOther Projects Parks & Recreation1(blank)1 2%1,797,000 ‐ ‐ ‐ 1,797,000 Pending18 AQUATIC SCULPTURE PARK ‐ PH. 2Other Projects Grant1(blank)1 2%2,220,500 ‐ ‐ ‐ 2,220,500 Pending Sum‐ 0%5,421,900 ‐ 2,954 5,418,946 Pending Count4 9%4 4 4 4 46 100%$101,700,000 $3,005,018$3,228,8573% $95,466,124CITY OF MIAMI BEACH5/5/2024 ‐ 9:43 PM
SECTION V
www.GOMBInfo.com
GRANT AGREEMENT
SCOPE VARIATION DISCUSSION
SECTION VI
www.GOMBInfo.com
GRANT AGREEMENT
SCOPE VARIATION
www.GOMBInfo.com
www.GOMBInfo.com
www.GOMBInfo.com
QUESTIONS / COMMENTS
G.O. BOND
PROGRAM UPDATE
May 9, 2024
www.GOMBInfo.com
SECTION VIII
www.GOMBInfo.com
CURRENT
MAIN PROJECTS STATUS
•98% of all Tranche 1 Projects are
Complete or Active = 43
•75% of all Tranche 1 Funds are Spent or
Encumbered = $118.3M out of $157.4M
www.GOMBInfo.com
SUBPROJECTS STATUS
•97% of all T1 Subprojects are
Complete or Active = 86 •54% of the value of All T1 Projects
are Complete or Under Construction
www.GOMBInfo.com
*
**
***
Total number of subprojects was updated to reflect the revised G.O. Bond Implementation Plan approved by the City Commission on April 21, 2021
GO#25 - Waterway Restoration Project moved from Tranche 2 to Tranche 1
GO#18 - Scott Rakow Youth Center - One sub-project sub-divided into 2
GO#34 - Above Ground Improvements - Indian Creek Sub-Project moved from Tranche 2 to Tranche 1
GO#52 - LED Lighting in Parks - One sub-project sub-divided into 2
GO#5 - Flamingo Park Historic Lodge - One sub-project sub-divided into 2
GO# 43 - Alton Rd Shared Use Path sub-project removed
GO# 48 - Real Time Intelligence Center sub-project added
No.%No.%No.%No.%No.%No.%No.%
ACTIVE/COMPLETE 44 68%69 95%80 95%83 98%85 96%85 96%86 97%1
CONSTRUCTION 16 15%9 12%11 13%8 9%11 12%11 12%11 12%0
PLANNING / DESIGN 23 21%31 42%36 43%35 41%29 33%27 30%28 31%1
CLOSED / COMPLETE 5 5%29 40%33 39%40 47%45 51%47 53%47 53%0
REMAINING 21 32%4 5%4 5%2 2%4 4%4 4%3 3%-1
TOTAL SUB-PROJECTS 65 73 84 *85 **89 89 ***89
SUMMARY SUB-PROJECTS - TRANCHE 1
10/17/19 VARIANCE12/01/22 05/09/2404/11/2411/18/2112/17/20 12/14/23
www.GOMBInfo.com
Bold
2024 CONSTRUCTION COMMENCEMENTS$46.3 Million Total GOB Budget
First Quarter
Second Quarter
-Bayshore Traffic Calming
-Soundscape Storage
-Pedestrian Bridge
-Flamingo Park Lodge
Third Quarter
-Bayshore Traffic Calming
-Street Lighting
-N. Shore Playground
-Police HQ
-Flamingo Pk Butterfly Garden *
Fourth Quarter
-Flamingo Park Softball Field
-MSD Park Lighting
-23rd Streetscape
-Fire Station 1 (if it remains
at current site)
Bold Text Indicates Projects have Commenced in Calendar Year
Red Text Indicates Projects that have changed from last month
*Contingent upon Fire Station 1 Project
G.O. BOND PROJECT LIST ‐ SAVINGS
Active Phase Category Project Name Count Budget Encumbered Spent Savings Transferred
Revised
Budget Available
Proposed
Transfer
Closed Infrastructure #32 PALM & HIBISCUS LANDSCAPING 1 1,000,000 ‐ 1,000,000 ‐ ‐ 1,000,000 ‐
Closed Infrastructure #40 41 STREET LIGHTING UPGRADES 103,000 ‐ 99,173 3,825 ‐ 103,000 3,825
Closed Infrastructure #42 NAUTILUS TRAFFIC CALMING 739,499 ‐ 712,627 26,871 ‐ 739,499 26,871
Closed Infrastructure #34 A.G. IMPROVEMENTS ‐ INDIAN CREEK 1,112,000 1,111,636 363 ‐ 1,112,000 363
Infrastructure Sum 4 2,954,499 ‐ 2,923,436 31,059 ‐ 2,954,499 31,059
Closed Parks #17 POLO PARK 1 499,998 ‐ 493,673 6,325 (6,325) *493,673 ‐
Closed Parks #19 SOUNDSCAPE 4K TECHNOLOGY 1 3,799,999 ‐ 3,748,495 51,503 (51,503) ***3,748,496 ‐
Closed Parks #13 NORTH SHORE LIGHTS & PAINT 1 130,300 ‐ 130,210 89 ‐ 130,300 89
Closed Parks #26 COLONY THEATRE ROOF 1 300,000 ‐ 299,650 350 (350) *299,650 ‐
Closed Parks #21 STILLWATER PARK 1 144,999 ‐ 142,440 2,559 (2,559) *142,440 ‐
Closed Parks #3 CRESPI PARK 1 210,998 ‐ 184,919 26,079 (26,079) *184,919 ‐
Closed Parks #18 SCOTT RAKOW PAINT 1 130,000 ‐ 116,776 13,224 (13,224) *116,776 ‐
Closed Parks #18 SCOTT RAKOW HVAC 1 150,000 ‐ 137,302 12,697 (12,697) *137,303 ‐
Closed Parks #13 NORTH SHORE ROOF 1 375,000 ‐ 374,722 276 ‐ 375,000 276
Closed Parks #18 SCOTT RAKOW ROOF 1 1,124,000 ‐ 127,217 996,782 (996,782) *127,218 ‐
Closed Parks #13 NORTH SHORE CAMERAS 1 205,699 ‐ 60,858 144,841 ‐ 205,699 144,841
Closed Parks #18 SCOTT RAKOW CAMERAS 250,000 ‐ 110,659 139,340 ‐ 250,000 139,340 139,340
Closed Parks #26 MIAMI CITY BALLET ROOF 760,000 758,825 1,175 (1,175) *758,825 ‐
Closed Parks #18 SCOTT RAKOW WINDOWS 700,000 198,887 501,110 ‐ 700,000 501,110 326,579
Closed Parks #26 FILLMORE ROOF 1,920,000 1,874,154 45,844 (45,844) *1,874,156 ‐
Closed Parks #4 FAIRWAY PARK PAVILION 50,000 ‐ 35,044 14,955 ‐ 50,000 14,955
Closed Parks #2 COLLINS PARK 640,000 ‐ 557,287 82,713 (82,713) *557,287 ‐
Closed Parks #13 NORTH SHORE GENERATOR 524,999 ‐ 503,861 21,138 ‐ 524,999 21,138
Closed Parks #18 SCOTT RAKOW GENERATOR 816,000 ‐ 729,717 86,281 (12,252) *803,748 74,029 74,029
Closed Parks #18 SCOTT RAKOW POOL 977,998 ‐ 977,104 893 ‐ 977,998 893 893
Closed Parks #4 FAIRWAY PARK FENCE 209,999 ‐ 205,917 4,082 ‐ 209,999 4,082
Closed Parks #18 SCOTT RAKOW GYM FLOORS 322,561 ‐ 322,451 110 ‐ 322,561 110 110
Closed Parks #24 MIDDLE BEACH BEACHWALK 4,500,000 ‐ 4,214,178 285,821 (75,497) ***4,424,503 210,324 210,324
Closed Parks #9 MSD PLAYGROUND AND SIDEWALKS 553,999 ‐ 524,410 29,588 553,999 29,588
Closed Parks #18 SCOTT RAKOW OTHER FLOORS 203,798 203,798 ‐ 203,798 ‐
Closed Parks #12 N. BEACH OCEANSIDE BEACHWALK 1,999,999 ‐ 1,999,999 ‐ ‐ 1,999,999 ‐
Parks Sum 26 21,500,346 ‐ 19,032,553 2,467,775 (1,327,000) 20,173,346 1,140,775 751,275
Closed Public Safety #53 PORTABLE BOLLARDS 1 600,000 ‐ 599,915 84 (84) 599,915 ‐
Closed Public Safety #52 TATUM PARK LED LIGHTING 1 151,999 ‐ 52,758 99,240 (99,240) 52,758 ‐
Closed Public Safety #52 CRESPI PARK LED LIGHTING 1 86,999 ‐ 41,780 45,218 (45,218) 41,780 ‐
Closed Public Safety #52 STILLWATER PARK LED LIGHTING 1 86,999 ‐ 41,780 45,218 (45,218) 41,780 ‐
Closed Public Safety #47 MACARTHUR CSWY READERS 1 120,000 ‐ 64,904 55,095 (55,095) 64,904 ‐
Closed Public Safety #52 NORMANDY ISLE PARK LED LIGHTING 1 715,000 ‐ 212,599 502,405 (502,405) 212,599 ‐
Closed Public Safety #47 71 ST. ENTRANCE READERS 240,000 ‐ 31,582 208,417 (208,417) 31,582 ‐
Closed Public Safety #47 JULIA TUTTLE CSWY READERS 200,000 ‐ 89,185 110,814 (110,814) 89,186 ‐
Closed Public Safety #56 BEACHWALK CAMERAS 700,000 ‐ 693,218 6,781 (6,781) 693,219 ‐
Closed Public Safety #57 LUMMUS PARK/OCEAN DRIVE CAMERAS 824,845 ‐ 824,845 ‐ ‐ 824,845 ‐
Closed Public Safety #52 FLAMINGO PARK LED LIGHTING 1,044,143 1,044,143 ‐ ‐ 1,044,143 ‐
Closed Public Safety #50 DADE BLVD. CORRIDOR CAMERAS 165,674 ‐ 131,420 34,254 ‐ 165,674 34,254
Closed Public Safety #50 71 STREET CORRIDOR CAMERAS 211,999 ‐ 85,307 126,692 ‐ 211,999 126,692
Closed Public Safety #53 CONVENTION CENTER BOLLARDS 783,128 ‐ 782,013 1,115 ‐ 783,128 1,115
Closed Public Safety #53 SOUTH POINTE PARK BOLLARDS 391,668 ‐ 335,362 56,306 ‐ 391,668 56,306
Closed Public Safety #53 SOUNDSCAPE PARK BOLLARDS 225,198 ‐ 223,665 1,533 ‐ 225,198 1,533
Complete Public Safety #49 PUBLIC SAFETY RADIO SYSTEM 9,700,000 1,187,771 8,505,575 6,653 ‐ 9,700,000 6,653
Public Safety Sum 17 16,247,652 1,187,771 13,760,051 1,299,825 (1,073,272) ** 15,174,378 226,553
Total Sum 47 40,702,497 1,187,771 35,716,040 3,798,659 (2,400,272) 38,302,223 1,398,387 751,275
Note: Red figures are projected project savings from Completed projects.
* $1.2M Transfer to GOB #10 ‐ Maurice Gibb Park
**$1M Transfer to GOB #48 ‐ Police HQ
***$126,970 Transfer to GOB #19 ‐ Soundscape Storage
www.GOMBInfo.com
REPLACE
PROJECT COMPLETION –TRANCHE 1
SUMMARY
Category
Sub
Projects Budget Savings % Available
Infrastructure 4 2,954,499 31,059 1%- 31,059
Parks 26 21,500,346 2,467,775 11%(1,327,000) 1 (751,275) 3 389,500
Public Safety 17 16,247,652 1,299,825 8%(1,073,272) 2 - 226,553
TOTAL 47 40,702,497 3,798,659 9%(2,400,272) (751,275) 647,112
1 Transfer to #10 - Maurice Gibb Park and #19 - Soundscape Storage
2 Transfer to #48 - Police Headquarters Facility
3 Proposed Transfer to #10 - Maurice Gibb Park (May 15, 2024 Commission Meeting - Budget Amendment)
Proposed
Transfer
Prior
Transfers
G.O. BOND PROJECT LIST BY PHASEActive Phase Project NameCategory DepartmentTranche Anticipated End Date ↑Count % Count $ Budget $ Encumbered $ Spent % Spent $ AvailableClosed#53 PORTABLE BOLLARDS Public Safety Police107‐31‐20191 1%599,916 ‐ 599,915 100%‐ Closed#17 POLO PARKParksParks & Recreation108‐11‐20191 1%493,673 ‐ 493,673 100%‐ Closed#19 SOUNDSCAPE 4K TECHNOLOGY ParksTourism & Culture109‐30‐20191 1%3,748,495 ‐ 3,748,495 100%‐ Closed#13 NORTH SHORE LIGHTS & PAINT ParksProperty Management110‐14‐20191 1%130,300 ‐ 130,210 100%89 Closed#52 TATUM PARK LED LIGHTING Public Safety Parks & Recreation110‐14‐20191 1%52,758 ‐ 52,758 100%‐ Closed#52 CRESPI PARK LED LIGHTING Public Safety Parks & Recreation110‐21‐20191 1%41,780 ‐ 41,780 100%‐ Closed#52 STILLWATER PARK LED LIGHTING Public Safety Parks & Recreation110‐21‐20191 1%41,780 ‐ 41,780 100%‐ Closed#26 COLONY THEATRE ROOF ParksProperty Management110‐24‐20191 1%299,650 ‐ 299,650 100%‐ Closed#21 STILLWATER PARK ParksParks & Recreation111‐08‐20191 1%142,440 ‐ 142,440 100%‐ Closed#3 CRESPI PARKParksParks & Recreation111‐09‐20191 1%184,920 ‐ 184,919 100%1 Closed#18 SCOTT RAKOW PAINT ParksProperty Management111‐12‐20191 1%116,776 ‐ 116,776 100%‐ Closed#47 MACARTHUR CSWY READERS Public Safety Police111‐28‐20191 1%64,904 ‐ 64,904 100%‐ Closed#52 NORMANDY ISLE PARK LED LIGHTINGPublic Safety Parks & Recreation112‐02‐20191 1%212,599 ‐ 212,593 100%5 Closed#18 SCOTT RAKOW HVAC ParksProperty Management112‐06‐20191 1%137,303 ‐ 137,302 100%‐ Closed#13 NORTH SHORE ROOF ParksProperty Management112‐16‐20191 1%375,000 ‐ 374,722 100%276 Closed#18 SCOTT RAKOW ROOF ParksProperty Management101‐05‐20201 1%127,218 ‐ 127,217 100%‐ Closed#26 MIAMI CITY BALLET ROOF ParksProperty Management101‐15‐20201 1%758,824 ‐ 758,824 100%‐ Closed#13 NORTH SHORE CAMERAS ParksProperty Management102‐04‐20201 1%205,699 ‐ 60,858 30%144,841 Closed#18 SCOTT RAKOW CAMERAS ParksProperty Management102‐05‐20201 1%250,000 ‐ 110,659 44%139,340 Closed#32 PALM & HIBISCUS LANDSCAPING Infrastructure Capital Improvement Projects103‐25‐20201 1%1,000,000 ‐ 1,000,000 100%‐ Closed#18 SCOTT RAKOW WINDOWS ParksProperty Management104‐16‐20201 1%699,999 ‐ 198,887 28%501,110 Closed#26 FILLMORE ROOFParksProperty Management105‐15‐20201 1%1,874,156 ‐ 1,874,155 100%‐ Closed#4 FAIRWAY PARK PAVILION ParksParks & Recreation105‐15‐20201 1%50,000 ‐ 35,044 70%14,955 Closed#2 COLLINS PARKParksParks & Recreation105‐28‐20201 1%557,287 ‐ 557,287 100%‐ Closed#13 NORTH SHORE GENERATOR ParksProperty Management106‐30‐20201 1%524,999 ‐ 503,861 96%21,138 Closed#18 SCOTT RAKOW GENERATOR ParksProperty Management106‐30‐20201 1%803,748 ‐ 729,717 91%74,029 Closed#18 SCOTT RAKOW POOL ParksParks & Recreation107‐06‐20201 1%977,998 ‐ 977,104 100%893 Closed#47 71 ST. ENTRANCE READERS Public Safety Police107‐12‐20201 1%31,582 ‐ 31,582 100%‐ Closed#47 JULIA TUTTLE CSWY READERS Public Safety Police109‐21‐20201 1%89,186 ‐ 89,185 100%1 Closed#57 LUMMUS PARK/OCEAN DRIVE CAMERASPublic Safety Police102‐28‐20211 1%824,845 ‐ 824,845 100%‐ Closed#4 FAIRWAY PARK FENCE ParksParks & Recreation103‐10‐20211 1%209,999 ‐ 205,917 98%4,082 Closed#40 41 STREET LIGHTING UPGRADES Infrastructure Public Works Department103‐13‐20211 1%102,999 ‐ 99,173 96%3,825 Closed#56 CAMERAS‐ BEACHWALK Public Safety Police104‐02‐20211 1%693,219 ‐ 693,218 100%‐ Closed#24 MIDDLE BEACH BEACHWALK PH3 Parks Capital Improvement Projects 1 12‐27‐20211 1%4,424,503 ‐ 4,214,178 95%210,324 Closed#42 NAUTILUS TRAFFIC CALMING Infrastructure Transportation101‐14‐20221 1%739,499 ‐ 712,631 96%26,867 Closed#18 SCOTT RAKOW GYM FLOORS ParksParks & Recreation101‐21‐20221 1%322,561 ‐ 322,451 100%110 Closed#12 N. BEACH OCEANSIDE BEACHWALK ParksCapital Improvement Projects106‐06‐20221 1%1,999,999 ‐ 1,999,999 100%‐ Closed#50 DADE BLVD. CORRIDOR CAMERAS Public Safety Police108‐03‐20221 1%165,674 ‐ 131,420 79%34,254 Closed#9 MSD PLAYGROUND AND SIDEWALKSParksParks & Recreation108‐05‐20221 1%553,999 ‐ 524,410 95%29,588 Closed#18 SCOTT RAKOW OTHER FLOORSParksParks & Recreation110‐28‐20221 1%203,798 ‐ 203,798 100%‐ Closed#52 FLAMINGO PARK LED LIGHTINGPublic Safety Parks & Recreation111‐14‐20221 1%1,044,143 ‐ 1,044,143 100%‐ Closed#50 71 STREET CORRIDOR CAMERAS Public Safety Police112‐22‐20221 1%211,999 ‐ 85,307 40%126,692 Closed#53 CONVENTION CENTER BOLLARDS Public Safety Public Works Department109‐07‐20231 1%783,128 ‐ 782,013 100%1,115 Closed#53 SOUNDSCAPE PARK BOLLARDS Public Safety Public Works Department112‐01‐20231 1%225,198 ‐ 223,665 99%1,533 Closed#53 SOUTH POINTE PARK BOLLARDS Public Safety Public Works Department112‐11‐20231 1%391,668 ‐ 335,362 86%56,306 Closed#34 ABOVE GROUND IMPROV‐INDIAN CRKInfrastructure Public Works Department103‐30‐20241 1%1,112,000 ‐ 1,111,636 100%363 Closed Sum46 52%28,602,221 ‐ 27,210,463 1,391,737 Closed Count46 52%46 46 46 46 CITY OF MIAMI BEACH5/3/2024 ‐ 3:37 PMSECTION VIII
G.O. BOND PROJECT LIST BY PHASEActive Phase Project Name Category Department Tranche Anticipated End Date ↑Count % Count $ Budget $ Encumbered $ Spent % Spent $ AvailableComplete #49 PUBLIC SAFETY RADIO SYSTEM Public Safety Fire 1 04‐30‐20221 1%9,700,000 1,187,771 8,505,575 1 6,653 Complete Sum2 2%9,700,000 1,187,771 8,505,575 6,653 Complete Count1 1%1 1 1 1 Construction #37 SIDEWALKS ‐ TRANCHE 1 Infrastructure Public Works Department 1 06‐30‐20241 1%3,960,066 24,995 3,827,276 1 107,793 Construction #38 STREETS ‐ TRANCHE 1 Infrastructure Public Works Department 1 06‐30‐20241 1%5,800,000 198,807 5,511,021 1 90,170 Construction #33 TREE PLANTING ‐ TRANCHE 1 Infrastructure Environmental 1 09‐30‐20241 1%2,770,000 12,774 2,520,573 1 236,652 Construction #48 REAL TIME INTELLIGENCE CENTER Public Safety Property Management 1 09‐30‐20241 1%701,460 531,301 19,650 0 150,508 Construction #50 ALTON RD. CORRIDOR CAMERAS Public Safety Police 1 11‐30‐20241 1%211,999 ‐ 113,025 1 98,973 Construction #57 COLLINS AVE/WASH AVE CAMERAS Public Safety Police 1 11‐30‐20241 1%665,154 ‐ 291,565 0 373,589 Construction #39 SEAWALLS/SHORELINES ‐ TRANCHE 1 Infrastructure Public Works Department 1 12‐04‐20241 1%4,999,999 1,166,677 3,705,703 1 127,617 Construction #5 FLAMINGO PARK HISTORIC LODGE Parks Capital Improvement Projects 1 12‐08‐20241 1%1,051,675 1,019,639 ‐ ‐ 32,036 Construction #10 MAURICE GIBB PARK Parks Capital Improvement Projects 1 12‐09‐20241 1%4,500,000 2,071,042 2,428,956 1 ‐ Construction #47 OTHER READERS CITYWIDE Public Safety Police 1 12‐30‐20241 1%1,390,000 142,004 544,770 0 703,225 Construction #15 PAR 3 / BAYSHORE PARK Parks Capital Improvement Projects 1 09‐17‐20251 1%20,166,104 10,712,663 9,452,480 0 959 Construction Sum44 49%$46,216,457 $15,879,902 $28,415,019 $1,921,522Construction Count11 12%11 11 11 11 Design #48 POLICE HQ FACILITY ‐ TRANCHE 1 Public Safety Property Management 1,2 10‐01‐2024 b1 1%5,871,811 258,548 1,709,219 0 3,904,042 Design #9 MSD PARK LIGHTING Parks Parks & Recreation 1 11‐16‐20241 1%127,999 27,638 12,737 0 87,624 Design #13 N.S. PLAYGROUND & REFORESTATION Parks Parks & Recreation 1 11‐29‐20241 1%794,999 341,912 358,512 0 94,575 Design #42 PALM VIEW TRAFFIC CALMING Infrastructure Transportation 1 12‐30‐20241 1%86,349 ‐ 46,427 1 39,922 Design #19 SOUNDSCAPE RESTROOMS/STORAGE Parks Parks & Recreation 1 01‐01‐20251 1%827,001 657,240 53,885 0 115,875 Design #5 FLAMINGO PARK MASTER PLAN Parks Capital Improvement Projects 1 05‐27‐20251 1%14,098,325 642,443 1,137,897 0 12,317,983 Design #42 BAYSHORE SOUTH TRAFFIC CALMING Infrastructure Transportation 1 07‐11‐20251 1%380,148 16,788 335,207 1 28,153 Design #55 STREET LIGHTING ‐ TRANCHE 1 Public Safety Public Works Department 1 07‐23‐20251 1%3,500,000 88,179 573,174 0 2,838,646 Design #43 CHASE AVE/34 ST SHARED USE PATH Infrastructure Capital Improvement Projects 1 09‐17‐20251 1%830,000 25,596 386,140 0 418,263 Design #43 23 ST. STREETSCAPE IMPROVEMENTS Infrastructure Capital Improvement Projects 1 12‐16‐20251 1%1,549,998 22,515 769,074 0 758,409 Design #23 PEDESTRIAN BRIDGE Parks Capital Improvement Projects 1 01‐25‐20261 1%8,999,999 7,161,982 1,837,409 0 606 Design #42 NORMANDY ISLE TRAFFIC CALMING Infrastructure Transportation 1 02‐01‐20261 1%293,999 18,212 254,524 1 21,263 Design #8 LUMMUS PARK Parks Capital Improvement Projects 1 04‐28‐20261 1%4,736,999 1,034,172 58,107 0 3,644,719 Design #54 MARINE PATROL FACILITY Public Safety Capital Improvement Projects 1,2 05‐08‐20261 1%1,999,999 335,015 363,737 0 1,301,245 Design #25 WATERWAY RESTORATION Parks Capital Improvement Projects 1,2 09‐18‐20261 1%499,999 ‐ 28,631 0 471,368 Design #45 FIRE STATION #1 Public Safety Capital Improvement Projects 1,2 10‐25‐20261 1%5,746,058 2,287,182 2,156,167 0 1,302,706 Design #40 41 ST CORRIDOR IMPROVEMENTS Infrastructure Capital Improvement Projects 1,2 06‐15‐20271 1%2,428,318 879,563 1,437,647 1 111,107 Design #50 41 ST. CORRIDOR CAMERAS Public Safety Capital Improvement Projects 1 09‐07‐20271 1%235,324 ‐ 17,999 0 217,324 Design #1 72 ST. COMMUNITY COMPLEX Parks Capital Improvement Projects 1,2 03‐14‐20281 1%10,800,000 6,081,337 2,983,434 0 1,735,228 Design #23 BAY GARDEN MANOR LINK Parks Capital Improvement Projects 1,2 05‐19‐20281 1%269,999 72,127 129,296 0 68,575 Design #23 BAYVIEW TERRACE LINK Parks Capital Improvement Projects 1,2 05‐19‐20281 1%169,999 48,258 121,510 1 230 Design #23 SOUTH BAY CLUB LINK Parks Capital Improvement Projects 1,2 05‐19‐20281 1%559,999 60,839 262,123 0 237,037 Design #31 OCEAN DRIVE CORRIDOR Infrastructure Capital Improvement Projects 1,2 04‐22‐20291 1%1,549,000 734,064 466,413 0 348,523 Design #52 FLA. PARK LED LIGHTING ‐ FIELDS Public Safety Capital Improvement Projects 1 (blank)1 1%1,655,856 ‐ ‐ ‐ 1,655,856 Design Sum120 135%$68,012,178 $20,793,610 $15,499,269 $31,719,279Design Count24 27%24 24 24 24 CITY OF MIAMI BEACH5/3/2024 ‐ 3:37 PM
G.O. BOND PROJECT LIST BY PHASEActive Phase Project NameCategory DepartmentTranche Anticipated End Date ↑Count % Count $ Budget $ Encumbered $ Spent % Spent $ AvailablePlanning#36 WASHINGTON AVE. CORRIDOR Infrastructure Economic Development1,210‐01‐2024 b1 1%397,616 ‐ 213,740 1 183,876 Planning#5 FLAMINGO YOUTH CENTER FACILITY ParksCapital Improvement Projects1,209‐24‐20271 1%250,000 167,701 33,880 0 48,418 Planning#46 OCEAN RESCUE NOBE FACILITY Public Safety Capital Improvement Projects1,208‐20‐20291 1%1,000,000 237,945 75,050 0 687,004 Planning#29 WEST LOTS ‐ TRANCHE 1ParksEconomic Development1(blank)1 1%1,000,000 ‐ ‐ ‐ 1,000,000 Planning Sum24 27%$2,647,616$405,646$322,670$1,919,298Planning Count4 4%4 4 4 4 Pending#30 SKATE PARKParksParks & Recreation1(blank)1 1%750,000 49,708 39,726 0 660,565 Pending#13 NORTH SHORE PATH & FIELDS ParksCapital Improvement Projects1,2(blank)1 1%1,009,000 ‐ ‐ ‐ 1,008,999 Pending#18 SCOTT RAKOW ICE RINK FLOORSParksParks & Recreation1(blank)1 1%413,640 ‐ ‐ ‐ 413,640 Pending Sum21 24%$2,172,640$49,708$39,726$2,083,204Pending Count3 3%3 3 3 3 89 100%$157,351,112 $38,316,637 $79,992,722 51%$39,041,693CITY OF MIAMI BEACH5/3/2024 ‐ 3:37 PM
SECTION IX
#23 SOUTH BAY CLUB LINK
Scope Contact
Project Details
Phase
Department:
G.O. Bond Funding
Budget:
Encumbered:
Spent:
Spent%:
Project Timeline
100%
Name:
Email:
Phone:
Update
null
-For additional project details refer to the PROGRESS REPORT on this website M1crosoff8tng i-rsnetorporation
Note: Click on blue hyperlink number to go directly to the agenda item. When accessing from the G.O. Bond website,
download the document first.
ITEMS RELATED TO G.O. BOND PROGRAM PROJECTS
AT VARIOUS CITY COMMISSION & COMMITTEE/BOARD MEETINGS & VIRTUAL PUBLIC
COMMUNITY MEETINGS
UPCOMING MEETINGS:
Yellow Highlight – G.O. Bond for Arts & Culture Items
5/15/2024 (8:30 am) City Commission Meeting
•C4 AK – 41st Street Corridor Project Status & Future Direction - Referral to LUSC
•C4 AN – Ocean Drive Corridor Project Status & Future Direction – Referral to LUSC
•C7 B – Maurice Gibb Park - Lunacon Engineering Change Order No. 1
•C7 C – Maurice Gibb Park – Coastal Systems Engineering Amendment No. 3
•C7 K – Office Space Lease for MBPD Personnel During Headquarters Renovation
•C7 T – Accept FERC’s Recommendation to Proceed with Phases 1 and 2 of the First Street
Project
•C7 AE – Discussions with Live Nation Regarding New Theater at Jackie Gleason Site
•R7 B – Capital Budget Amendment – Savings Transfer for Maurice Gibb Park, Funding Swap
for Log Cabin and Funding for MBPD Personnel Temporary Relocation
•R7 F – Temporarily Suspend Expenditures Towards Fire Station 1 Project at SSCC
•R9 AG – Discuss and Take Action on Analysis of Potential Alternative Sites for Fire Station 1
5/19/2024 (10:30 am) Finance & Economic Resiliency Committee – Pending Agenda
•Infrastructure Tranche 2 (Declaration of Intent to Issue)
5/22/2024 (10:00 am) Public Safety & Neighborhood Quality of Life Committee – Pending Agenda
Date TBD West Lots Community Charette
•Potential Recreational and Park Uses (at North Shore Park and Youth Center)
*Note: All upcoming items are subject to change. For the most accurate items for each meeting, please
review the agendas on the City’s website.
Agendas: https://www.miamibeachfl.gov/city-hall/city-clerk/agenda-archive-main-page-2
Meeting Notices: https://www.miamibeachfl.gov/city-hall/city-clerk/meeting-notices/
Commission Committee Acronyms: FERC – Finance & Economic Resiliency Committee, LUSC – Land Use
& Sustainability Committee, PSNQLC – Public Safety and Neighborhood Quality of Life Committee
_____________________________________________________________________________________
SECTION XI
Page 2 of 2
Note: Click on blue hyperlink number to go directly to the agenda item. When accessing from the G.O. Bond website,
download the document first.
PAST MEETINGS:
5/2/2024 (5:30 pm) Flamingo Park Lodge Groundbreaking Ceremony
5/1/2024 (5:00 pm) Land Use and Sustainability Committee
• Item 1 – Discuss Programming for the New Byron Carlyle G.O. Bond Project – Moves to City
Commision with an unfavorable recommendation due to split vote
• Item 6 – Expedite the Opening of the Baywalk and Move Developmewnt of the Baywalk up
on the G.O. Bond Prioritization List. Discussed. Return with update at the next meeting
4/19/2024 (10:30 am) Finance & Economic Resiliency Committee
• Item 7 – Discussion regarding adding Shade Trees and Re-paving Parking Lot P-63 – Not
Heard
• Item 35 – Discuss Funding and Path Forward of the First Street Project (GOB Above Ground
Funding from a Future Tranche) – Approved to send to the next Commisson Meeting
• Item 39 – Discuss the Programming for the New Byron Carlyle Project – Deferred
4/16/2024 (6:00 pm) Groundbreaking Ceremony for Collins Park Rotunda
4/3/2024 (8:30 am) City Commission Meeting
• C2 A – Award ITN for Management / Operations of Collins Park Rotunda - Adopted
• C4 H – Referral to FERC / LUSC – Review Two Models for Byron Carlyle Cultural Center -
Approved
• C4 P – Referral to PSNQL – Expand Tree Canopy in North Beach - Approved
• C7 L – Temporarily Suspend Expenditures Towards Fire Station 1 Project at SSCC – Not Heard
• C7 T – Prioritize Log Cabin Reconstruction - Adopted
• C7 Y – Direct Administration to Explore Construction of a New Theater @ Jackie Gleason
Theater Site – Return to the May Meeting with Administration’s recommendation
• R7 E – County Referendum Regarding Construction of Fire Station 1 at Flamingo Park -
Adopted
• R9 N – Discuss/Take Action to make Log Cabin a G.O. Bond Priority - Withdrawn
• R9 AN – Discuss Alternate Sites for New Fire Station No. 1 Project – Not Heard