Loading...
149-1998 LTC CIT'V OF MIAMI BEACH CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139 http:\\cLmiami-beach,fl.us L T C N 149-1998 . . . o. LETTER TO COMMISSION October 21, 1998 TO: Mayor Neisen O. Kasdin and Members of the City Co ission FROM: Sergio Rodriguez City Manager SUBJECT: STATUS OF 16TH STREET GARAGE Attached, please find a status report prepared by Tishman on the 16th Street garage as requested at the October 7, 1998 City CommissionlRDA meeting. The contractor, developer, project architect, owner's representative and City staff have been meeting daily to address all pending issues affecting the opening date ofthe garage. These meetings have enabled us to closely monitor any impediments and prioritize action necessary to effectuate the opening ofthe garage prior to the hotel's completion date. As we reported at the Commission Meeting today, Beauchamp, the contractor, is targeting a substantial completion (TCO) date of October 30, 1998; however, Loews (developer), Zyscovich (project architect), Tishman ( owner's representative) and City staff do not believe that Beauchamp will be able to obtain the TCa within the projected time frame and feel a more realistic date of November 15, 1998 is likely. Please advise if you would like a more detailed briefing and/or if you have any questions. SR:CMC/jph r>>Y Attachment c: Murray Dubbin, City Attorney Lawrence Levy, First Assistant City Attorney -rBHMAN FROM: Michael Meyer TO: Christina CUelVO Assistant City Manager City of Miami Beach Miami Beach. Fl. FAX#: (305) 673-7782 DATE: October 20, 1998 PAGES: S Following is fax re Garage construction.... cc: Kent Bonde David Cates Pat D' Addio Bernard Zyscovich Larry Levy TOO~ NVJmS I.L LCOO 696 6161 XVd 00:L1 aaL 86/06/01 Tishm<1n Hold Corporation October 20, 1998 Ms. Christina Cuervo Assistant City Manager City of Miami Beach Miami Beach, FL Dear Christina, At your request, I am writing to clarifY some of the issues and questions raised about the Garage construction during the most recent Commission hearing Project BackgroUnd Construction on the 16th StreetGarage broke ground on June 2 1997, following a competitive bidding process which resulted in the award ofa lump sum contract to Beauchamp Construction Company. Pursuant to the terms oCthe garage development agreement, St. Moritz Hotel Corp. (Loews) was designated as the developer charged with direct management of the project on behalf of the owner, the Redevelopment Agency. This arrangement was negotiated as a result of the heightened sensitivity Loews had about the risk they would incur if the Garage were not to be completed in time for the hotel opening. As developer, Loews could coordinate the construction and maintain a greater degree of control. Tishman was later retained by the Redevelopment Agency to serve as an Owner's Representative to provide, as Murray nubbin's memo of October 7 to the Mayor and Commission summarizes, "review and advice on monetary items, construction methods, and project scheduling". Loews was further charged with the role of leasing agent for the retail space in the garage out of a mutual concern ~etween the Redevelopment Agency and Loews for the caliber of tenants that would locate across from the hotel. Project Status I called a meeting on September 9. Harry Mavrogenes' last day on the job and your first, to review issues and coordinate the transition with Loews and the Redevelopment Agency. During that meeting Harry signed change order number 57 which had been heavily negotiated by Loews, Tishman. and Beauchamp representatives to close-out all open change orders to that date in time. We anticipated a small number of change orders after that point to complete some remaining work but it was seen as mostly mop-up and not a threat to the remaining $228,000 contingency. Part ofthe settlement of the change order involved an extension of the contractual completion date of October 2, 1998 by two weeks to October 16. The contract provides that the contractor has 30 days after obtaining of the temporary certificate (TeO) of completion date to complete punch list items and obtain a Certificate of Occupancy (CO) after which time $1,000 a day in liquidated damages must be paid by the Tishm:m Hotel COlpOtation 666 Fifth Avt:nue. New York, NY 10103.0256 (212) 399-3600 Fax (212) 262-0037 ~OO III NVHHS 1.1 L&OO ~9~'~1~1 XVd 10:Ll aa1 86/0~/Ol contractor until the CO is granted. As part of the settlement, Beauchamp agreed to certain milestones to complete the work - substantial completion of the Garage and Collins retail by October 16, 16th street retail by October 24 and Washington retail by November 1. During the meeting I expressed the concern that we would lose out leverage to get Beauchamp to perform on a timely basis since this has been a problem throughout the course of the project. It was agreed that Harry would sign the change order and you would hold it and release it upon demonstration of performance and the correction of the dollar value of Beauchamp's total contract. Our report to the Commission was prepared two weeks later and incorporated the milestone dates we believed we had locked-in. Since that time, the Redevelopment Agency's project team has been frustrated by delays in the performance of work which was the basis of Pat D' Addio's exasperated comments to the Commission the other week. An added factor in the recent delay has been the emergence of several unforseen conditions at the time of the settlement change order. Among the major items are ~ 1. Sewer Line/Grease Traps In late September, Redevelopment Agency staff and Tishman became aware that the plumbing contractor had improperly installed the sanitary sewers in the building. Remediation work is now underway and expected to be complete by October 23. 2. WJl1dow Permit Beauchamp has failed to obtain a window permit. 3. Stonn Shutters! Wmdow Dispute Beauchamp proposes to substitute storm shutters for impact glass. Beauchamp has failed to obtain a storm shutter permit. The architect is reviewing the contract issue, 4. Second Floor Retail Waterproofing A dispute has arisen on the interpretation of the system type to be used and the permit required. 5. Signage Loews was to order and install signage for the building which will not be installed until October 29. 6. Elevator Start-Up During the installation of the east elevator a missing item was identified that could hold up future certification, and therefore a steel beam needed to be ordered and installed, Schedule and Plan of Action Daily project meetings with all project representatives have been instituted to coordinate and troubleshoot problems on an expedited basis- Beauchamp believes they will be able to obtain a TeO for the parking or non - retail portion of the Garage by October 30. The retail space has separate issues associated with it and will take coo If] NVHHS IJ. LCOO 696 6161 XVd' 10:L1 3fil 96/06/01 longer to complete. but will not delay use of the garage for parking. However, Loews Tislunan) and Redevelopment Agency staff as well as the architect do not believe that Beauchamp will be able to complete in the time frame Beauchamp is projecting. We have broken the project down into three principal components and have highlighted the principal tasks remaining by area along with our best estimate oCthe likelihood of obtaining a TeO by certain dates. PARKING AREA COWNS & 16th WASHINGTON RETAIL & STREET RETAIL ANCHOR HOTEL WatelprOOfingl SCCoDdmy pour wiJldoWs/Shutters Flood plain Varimce Fire Alarm & Test Flood Barriers Restaurant tenant infulstIUCture CableBmriers Railings west & East Elevators Railings Security Booth DrywallICeiling Fire Alann Panel Permanent P~ ScwcrlUtilitiesrrurnaround Rd./Sitework wiudows/Shutterslflood Barriers Ligbl Badllcs Exterior Lighting with poles L8Ddscaping Telephone Ben South Signage In the best estimate oCthe Redevelopment Agency, Loews) Tishman and the architect's project s~ the likelihood of certain completion milestones is as follows: Probability olTCO PARKING AREA COLLINS &: 16th Sr. WASHINGTON SI. by: RETAIL RETAIL &: ANCHOR . HOTEL ... November 1 25% 25% 0% NovemberS 50% 50% 0% November 1 S 75% 75% Oo/D . Thi, COJllpOMnt oj ,he work is on hold becQwe of the jntensity ol,he undergrollnd work requi1V!d for a poten,ial re,taurall' ~tmtnlt and IlTUclUraI ;!IUel involving the lllllonC buildi1lgJ. LoeW8 will adviJi! ICMdule. tOO III NVlmS I.L LCOO 696 6161 XVd 10: L 1 3f1L 86/06101 Conclusion While we continue to apply pressure on the contractor on a daily basis we believe we will ocperience several more weeks of delay. At this point, the removal of Beauchamp is not a realistic solution to the problem. This was an option we had discussed internally earlier in the project but not recently since we felt the Garage was close to the originally projected completion date and on budget and that a termination of the general contractor would involve increased delay and cost However, we have a high degree of confidence that the remaining issues can be resolved and work completed in time for the hotel opening. For that reason, the project staff and architect do not think it prudent for the City to fast track the approval of a TeD from the Building Department as it would reduce the limited leverage we have remaining and may result in compromises to quality and design that would not be in the City's long term interest. This position should be re-considered if incompleteness of the Garage were to jeopardize the hotel opening- Mi 1 Meyer Vice President SOO~ NVImSIJ. LCOO Z9Z Z1Z1 IVd ZO:L1 Hal 86/0Z/01