LETTER TO COMMISSION
December 17, 1998
TO: Mayor Neisen O. Kasdin and
Members of the City Commission
FROM: Sergio Rodriguez
City Manager
SUBJECT: SOUTH POINTE STREETSCAPE
On September 23, 1998, the City Commission and RDA Board appropriated $3.8 million to
implement the South Pointe Streetscape, as prioritized.
An RFQ was issued on November 25, 1998, seeking proposals to prepare a master plan including
design, construction and bid documents and to assist in the construction bidding and administration
ofthe South Pointe Streetscape project. The scope of work will address the priority list including
undergrounding utility components. The priority streetscape projects include First Street from
Ocean Drive to W ashington Avenue, Third Street from Ocean Drive to Michigan Avenue including
the Mosaic Plaza, Washington Avenue from South Pointe Drive to Fifth Street, Jefferson Avenue
from Second Street to Fifth Street and Euclid Avenue from Third Street to Fifth Street. A total of
383 notices were sent out which generated 35 requests for RFQs. Responses from qualified
proposers are due on December 30, 1998.
Please note that W ashington Avenue improvements from Fifth Street to Sixth Street are included
in the streetscape plan prepared by Savino and Miller, and included in the Washington Avenue
Streetscape Plan appropriation approved by the City Commission on December 16, 1998.
The Duany Plater-Zyberk plan will serve as a basis for the South Pointe Master Plan and the project
will be phased based upon available funding. The master plan will serve as the coordinating
document to ensure consistent integration and coordinated undergrounding of intersecting streets.
The proposed time line for the South Pointe Streetscape project is as follows:
RFQ issued: November 25, 1998
Responses due: December 30, 1998
Evaluation Committee appointed: Prior to December 30, 1998
Evaluation Committee meets: week of January 4, 1999
Authorization to negotiate contract: January 20, 1999
Award contract: February 3, 1999
Master Plan due: April 30, 1999
Working/construction drawings: By the end of May, 1999
Request for bids for construction: By the end of June, 1999
Award: Last meeting in July, 1999
Begin construction: August, 1999
Construction Build-out: By Summer, 2000 (9 months - 1 year)
The following are the proposed members of the Evaluation Committee:
Dean Grandin (or designee)
Julio Grave de Peralta (or designee)
Michael Rath
Marla Dumas
Bob Christoph, SP AB Chair
Edward Resnik
David Sine, SP AB Member
Please provide any suggestions or comments.