C6A-Report- Capital Improvement Projects Oversight Committee Mtg On November 14(e MIAMI BEACH -
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov
To:
From:
Date:
COMMITTEE MEMORANDUM
Mayor Matti Herrera Bower and Members of the City Commission
Jorge M. Gonzalez, City Manager tV'~
January 11, 2012 \J U
Subject: REPORT OF THE CAPITAL IMPJ6VEMENT PROJECTS OVERSIGHT
COMMITTEE MEETING OF NOVEMBER 14,2011
The meeting was called to order at 5:45 p.m.
Please note: These minutes are not a full transcript of the meeting.
Full audio and visual record of this meeting available online on the City's website:
http:! I www.miamibeachfl.gov/video/video.asp
1. ATTENDANCE
See attendance sheet copy attached.
2. REVIEW AND ACCEPTANCE OF MINUTES 5:46pm
Report of the Capital Improvement Oversight Committee Meeting of October 17, 2011
MOTION: Acceptance of Minutes of the September 12, 2011 CIPOC Meeting.
MOVED: T. Trujillo 2nd: E. Carney
PASSED: Unanimous -WITH REVISIONS as per D. Kraai
3. PUBLIC COMMENTS 5:56 pm
Greg Carney, President of the Venetian Islands Homeowner Association, requested an update on
the rebidding for a contractor for the Venetian Islands project.
Aaron Sinnes, Senior Capital Projects Coordinator, presented the status of the project. The
Commission rejected all the bids that had been submitted through the ITB process. They did not
recommend a timeline on when the project should go into construction.
CIP staff met with the Engineer of Record (EOR-Schwebke Shiskin) and electrical engineers.
Savings have been identified for the electrical components, through this value engineering
process and staff plans to follow an aggressive timeline with the intention of awarding this project
to a contractor as early as February, followed by possible commencement of construction in
March or April. The first step is to amend the consultant's contract. Because the changes fall
under $25,000, there is no need to go back to Commission for these changes. The goal through
the value-engineering process here is to seek alternatives that result in cost savings, not redesign
of the project. Savings have already been identified in the concrete encasement and wiring of the
lighting, as well as some other areas.
The contract provides a range of up to 15% for the consultant to come in with an opinion of cost.
Saul Gross felt that this was too liberal and asked that staff look into this tolerance level for future
contracts.
STAFF ACTION: Look at the tolerance range provided for in the standard contract form for
consultants to provide opinions of estimate of costs. Compare with State guidelines and other
guidelines. • /1 /_A
• Agenda Item _<-=-<P.,...r-:~-73 . Date 1-1/-IL
CIPOC MEETING MINUTES, November 14, 2011
Page 2 of6
4.
Eleanor Carney clarified that Schwebke Shiskin was not contracted to do the electrical estimate.
Hillers Electric is the consultant who did the electrical. Probable cost estimate was not included in
the scope of work for Schwebke Shiskin. The cost estimate came from Hillers, hired under the
contract of the last EOR.
STAFF ACTION: Bring standard contract and the contract for consultant with information about
the probable cost estimate to CIPOC for review.
County work on Causeway-Greg Carney contacted Roberto Rodriguez just prior to the CIPOC
meeting, with concerns about safety practices in the County project. Sidewalks on the north side
of the causeway are presently unfinished, posing a safety hazard for walkers and bikers. Mr.
Carney had contacted the County project manager several weeks before, and was told that there
were conflicts with utilities which delayed the completion of the sidewalks. Mr. Carney requested
that some temporary fill material be placed in the holes until the sidewalks could be completed,
but was unsuccessful in getting his request filled. He asked the City to intervene. According to
staff at the meeting, the County was going to fill the holes with crushed rock that day.
OLD BUSINESS I REQUESTED REPORTS 6:30pm
Status of Water Reclamation Project in Golf Courses
Kevin Smith, Parks and Recreation Department Director, was prepared to present. Saul Gross
said that the request was actually made about the AMERESCO project, which he confused with
the lake reclamation project.
Mr. Smith did not give the presentation. Instead, ACM Duncan Ballantyne gave an update on the
AMERESCO project. He said that the most recent document analysis was provided to Mr. Kraai.
The administration has evaluated the material presented by AMERESCO and determined that
there is no cost benefit to the project. There would be what was determined an excessive period
of time before realizing a cost benefit.
Mr. Smith took the opportunity to invite the Committee members to the re-opening of the new
playground at South Pointe Park.
Status Report: Sunset Island I & II 6:16pm
Maria Hernandez, Senior Capital Project Coordinator, stated that some issues are being worked
out with the contractor. A Community Pre-construction meeting is planned to take place
Wednesday, November 16 and the first round of encroachment notices are planned to go out the
same day.
Staff reviewed the schedule submitted by the contractor and that has been the source of issues
between the City and DMSI. DMSI had submitted a new schedule just before the CIPOC meeting,
but staff had not yet had a chance to review this newest schedule. Issuance of the second Notice
to Proceed (NTP2) is contingent on acceptance of the schedule. The other item that needed
some resolution is the schedule of values.
The first NTP was issued in late August. Some instances in other projects that this contractor is in
involved in appear to have affected the contractor's performance in Sunset Islands. The
contractor promised certain items, such as concurrent crews, during the Technical Review Panel
(TRP), and now not providing that in the schedule. Some line items on the schedule of values
F:\CAPI\$aii\Comm. & CIPOC\Commission ltems\2012\CIPOC November 14 Meeting Minutes.docx
74
CIPOC MEETING MINUTES, November 14, 2011
Page3of6
have also changed in quantity since the TRP. This results in significant reduction in the cost of
the project. The contractor has invoked the 20% rule and has resubmitted a price that the City is
not willing to accept. Specifically, this has had an impact to cost in the area of water meter
relocations.
William Goldsmith, 1820 West 25th Street, member of the Sunset Island Homeowners
Association, gave his opinion on the situation. He first asked if the new schedule that was
submitted responded sufficiently to the requests made by the City on November 14 (in a letter
that is included in the Nov. 14 CIPOC agenda packet).
Fernando Vazquez stated that the contractor had just submitted the requested schedule before
the meeting, but staff had not yet had a chance to review it and that staff and the contractor also
needed to iron out the water meter pricing in the schedule of values.
Maria Hernandez handed Mr. Goldsmith a copy of the material that she had just received from
DMSI, Inc.
Mr. Goldsmith further pointed out his concerns with the construction schedule and the schedule of
values. He made the point, when Mr. Gross said that he had confidence in the work that Albert
Dominguez (Principal with DMSI) had done for the City before, that DMSI is not the same
company as Ric-Man International; and that DMSI had not done a lot of work with the City since
incorporating. Mr. Gross responded that the principals, superintendent and other key DMSI
personnel were the main people involved in City projects when they were with Ric-Man
International.
At the TRP, Mr. Goldsmith confirmed with Albert Dominguez that the number of meters listed on
the contract (200) was an over-estimate and requested a pro-rata reduction in the cost that would
reflect this and was told that, yes DMSI would do that. The last schedule of values submitted by
DMSI showed an increase in the cost of the meters. Also at the TRP, the panel asked if the
contractor will provide a construction trailer and, if not, a $25,000 credit (He did not finish his
statement, but was insinuating that the contractor reneged on this item. Mr. Gross asked if the
items mentioned at the TRP were included in the contract, offering direction to the City that
material representations made at the TRP should be passed on to the Legal Department for
inclusion in contracts. Maria Hernandez stated that she tried to do just that, particularly because
the material promise of parallel crews on site would ensure that the project stuck to a ten-month
schedule, as represented at the TRP. Recently, a contractor on another project under Ms.
Hernandez's direction, failed to provide concurrent crews as promised and it affected the
schedule adversely. She was unable to pursue action against this contractor because that item
was not included in the contract. Now, DMSI on this schedule has to stick to a new schedule of
12 months. Correspondence pertaining to the schedule is included in the agenda packet. The
final schedule, once agreed upon, will be certified.
Albert Dominguez, DMSI, said that the company presented many different ideas at the TRP.
Some ideas included different type of pipe, and installation at shallower depths, for example. Mr.
Dominguez stated that some parts of their proposal were rejected. He claimed that some of their
proposals actually reflect value-engineering towards getting better value in the project.
Saul Gross asked why the City rejected the idea of installing the pipe above the muck line.
Fernando Vazquez responded that the proposal was to install the pipe under the valley gutter,
which posed a problem for the Public Works Department and they rejected that proposal. Mr.
Dominguez said that item impacted other portions of the proposed schedule. If the City rejects
certain proposed means and methods, DMSI cannot guarantee the shorter schedule.
F:\CAPI\$aii\Comm. & CIPOC\Commission ltems\2012\CIPOC November 14 Meeting Minutes.docx
75
CIPOC MEETING MINUTES, November 14, 2011
Page4 of6
Mr. Dominguez said that some issues that are currently affecting DMSI crews at the Biscayne
Point project are now delaying the use of parallel crews for the Sunset Islands project. DMSI had
planned to roll some crews from Biscayne Point to Sunsets I & II, but now the work seems to be
delayed by almost 8 months.
Mr. Vazquez said that the City is working very hard to try and resolve the issue with the EOR on
Biscayne Point so that the schedule can be accommodated and approved for Sunset Islands.
Staff is confident that the issues will be ironed out before the next CIPOC meeting and then be
brought to Commission in December.
More deliberations continued. The conclusion of the discussion was that staff was working on
reaching a meeting of the minds among all parties, and if the City and the contractor cannot come
to an agreement, that staff proceed accordingly.
Status Reoort: Sunset Island Ill & IV 7:09 pm
Mattie Reyes, Senior Capital Project Coordinator said that the RFQ was advertised for a design
criteria professional and four companies responded. A selection committee was scheduled for
November 29.
Status Report: Lower North Bay Road 7:10pm
Maria Hernandez told the Committee that a 2nd Notice to Proceed will be issued the second week
in December. Encroachment surveys are being conducted and encroachment letters will go out
soon. Construction will begin by the end of the year (the contractor will take some time off for the
holidays). The EOR and the City are still reviewing the change order that was submitted, but that
will not delay the start of construction. The change order reflects $250,000 in the overall $5
million contract.
Saul Gross asked about water meter relocations and the process for those homeowners who
want to install a second meter. Residents who are interested in purchasing a second meter are
encouraged to call the Public Works Department to make arrangements for the meter. PWD will
coordinate with CIP for the properties that fall within a project.
Ms. Hernandez indicated that interested residents can call CIP and staff would
coordinate/facilitate the process, but the best course of action is to contact Public Works
Engineering directly at 305-673-7080 to request an additional meter. Once all the permitting is in
place and fees are collected, the CIP contractor would receive the work order from Public Works.
STAFF ACTION: Bring information about the process for obtaining sub-meters and irrigation
meters during a CIP ROW project to the next meeting. Clarify whether the process is slightly
streamlined when it takes place in conjunction with a CIP ROW project.
Status Report: Venetian Islands 7:14pm
*See above -topic was covered during Public Comments at 5:56.
Eleanor Carney had an additional question about the status of the encroachment notices for the
Venetian Islands. At the last meeting, CIPOC requested a schedule of notices to be provided.
This was not reflected on the staff action items. Robert Rodriguez responded that the surveys are
currently being done to determine encroachments at this stage. Ms. Carney expressed her
opinion that residents "are being held hostage" in the meantime. But there is a process and
typically, the encroachment notices do not go out until NTP 1 is issued after a contractor has
been hired, since coordination for removal involves the contractor. (There are other projects
where construction is imminent and encroachment notices are being sent out for those, since
they now take priority status). Stacy Kilroy stated that encroachments are such a bone of
contention for residents that sending notification as early as possible would give them time to deal
F:\CAPI\$aii\Comm. & CIPOC\Commission ltems\2012\CIPOC November 14 Meeting Minutes.docx
76
CIPOC MEETING MINUTES, November 14, 2011
Page5of6
with relocation of the encroachments should they choose that. Fernando Vazquez stated that
staff could go outside of regular procedure and send notices before a contractor is hired, but CIP
staff will first concentrate on those neighborhoods that are closer to construction. NTP for
Venetian Islands is expected in March or April. Ms. Carney reiterated that she wants notices sent
out as early as possible.
STAFF ACTION: Bring an outline of encroachment process to CIPOC that outlines the general
guidelines and timelines for encroachment removal.
Status Report: Palm and Hibiscus Islands 7:21 pm
Senior Capital Project Coordinator Grace Escalante told the Committee that the drawings and
binding estimate from FPL for undergrounding of utilities were received on October 27. The City
submitted the drawings to Atlantic Broadband and AT&T as well as a JOG contractor. At the time
of the CIPOC meeting, a meeting was planned for the following Thursday to coordinate all the
estimates for the work from all parties involved. Staff submitted the drawings to the Public Works
Department on November 3 for their review. Another meeting was scheduled with the top ranked
Design Criteria Professional (DCP). Since the proposal for the DCP have remained high, it is
likely that the second ranked firm will be recommended for negotiation, and the City may
terminate negotiations with the first-ranked firm. As soon as the City gets the total cost estimates
for the project, they will submit this to the County, and then the County will pursue a bond issue
and draft the inter-local agreement. The County promised that this would take four weeks. Once
the attorneys review the inter-local agreement, the package will be taken to City Commission for
approval.
Status Report: Flamingo Park 7:24 pm
Ms. Escalante stated that Pirtle Construction submitted an executed contract for pre-construction
services for the Tennis Center. The project is on schedule. An award, if we remain on schedule,
will be issued in February. The City has 100% permitted drawings for the Tennis Center. Once
Pirtle conducts a constructability review, and makes any necessary changes, they will submit a
guaranteed maximum price to go to Commission. If approved in February, construction can begin
in March of 2012 and is expected last one year.
Status Report: Stormwater Master Plan 7:27 pm
Rick Saltrick stated that the City is working with FOOT to finalize the connection with the Alton
Road project. He is confident in the progress. Saul Gross asked if the Sunset Harbor pump
station was tied in with the Flamingo stormwater project. Mr. Saltrick responded that the
consulting firm of APCTE recommended replacements with larger pumps rather than the original
plan to retro-fit the pump station. Once the DERM and DEP permits are acquired, the project can
start with a JOG contractor. Eleanor Carney clarified that the replacements are a better solution
than adding an additional station. Mr. Saltrick confirmed this. Mr. Gross asked if the engineers
who designed the currently inadequate stations are culpable for negligence or something similar.
The City has not pursued any action against the engineers.
Additional Discussion 7:30 pm
Dwight Kraai said he had still not received appropriate information on stormwater and sea-level
models that he had asked for. Mr. Ballantyne replied that the City will provide Mr. Kraai with
information prior to meeting with the consultant and the City Manager. Mr. Ballantyne has
performed a preliminary review of the proposal for the stormwater master plan from COM, and
asked Public Works to get some additional information from the consultant, especially the
information about sea-level rise that had been requested by Mr. Kraai. Once the proposal is
complete, the plan is to present it to the Finance and Citywide Projects Committee. There are
opportunities for Public input in this process. After the consultants have finalized design that
would satisfy criteria for FOOT, Mr, Saltrick will meet with FOOT and at that time the City can
F:\CAPI\$aii\Comm. & CIPOC\Commission ltems\2012\CIPOC November 14 Meeting Minutes.docx
77
CIPOC MEETING MINUTES, November 14, 2011
Page 6 of6
schedule a meeting with the City Manager and Mr. Kraai on this topic. The administration
recognizes that Mr. Kraai wants the opportunity to provide some input based on his professional
expertise in this matter before the process is closed.
STAFF ACTION: Bring back information to the next meeting on the timeline for this process and a
proposed date for meeting with Dwight Kraai. Mr. Ballantyne, in response to Mr. Kraai's inquiries,
has asked the consultant to re-evaluate the plans based on a more accurate range of sea-level
rise.
Meeting Adjourned: 7:35pm
Next CIPOC meeting is scheduled for Monday, December 12, 2011 at 5:30 p.m. in Commission
Chambers.
F:\CAPI\$aii\Comm. & CIPOC\Commission ltems\2012\CIPOC November 14 Meeting Minutes.docx
78