R7G-Execute GMP Amendment South Pointe Park Pier ProjectCOMMISSION ITEM SUMMARY ~ondensed Title· A Resolution Approving And Authorizing The Mayor And The City Clerk To Execute Guaranteed Maximum Price (GMP) Amendment No. 1 To The Pre-Construction Services Agreement With The Weitz Company, Dated April 5, 2012, For Construction Management At Risk Services For The South Pointe Park Pier Project, In The Amount Of $4,809,017 With Funding For This Amendment Previously Appropriated As Follows: $1 ,442,417 From The South Pointe Capital Fund 389; And $3,366,600 From The South Pointe COT Agreement Rev/Municipal Resort Tax Fund 388. Key Intended Outcome Ensure well-designed quality capital projects Supporting Data (Surveys, Environmental Scan, etc.): The 2012 Customer Satisfaction Survey indicated that 81% of businesses rated completed capital improvement projects as "excellent" or "good." Issue: J Shall the Commission Adopt the Resolution? Item Summary/Recommendation: On June 1, 2012, the Weitz Company held a bid opening which representatives of the City and Atkins attended. Subcontractors submitted sealed bids which were opened by Weitz in the presence of the City and Atkins. The GMP submitted, prior to negotiation, was for the amount of $5,527,465. Following a number of discussions, evaluation of value-engineering (VE) options, and analysis of constructability recommendations, Weitz submitted the current negotiated GMP in the amount of $4,809,017 (Attachment A). The GMP reflects current market conditions and additional scope never anticipated in the original BOOR and required by the Environmental permitting agencies: associated with the relocation of the existing protected corals. This work involves a 30 day notice prior to the relocation and the proper monitoring to the satisfaction of the environmental permitting agencies prior to the demolition phase. It also includes the entrance plaza, the waterside construction of the pier and the offsite storage/staging area due to limited access from the park. The final estimate of probable construction cost conducted by Atkins, the Engineer of Record, on August 26, 2011 is $4,454,433. Since the CMR construction contract does not contemplate any change orders and assumes the owner's risk in the construction process, the final estimated construction cost of $4,836,637 includes the 10% CMR premium (Attachment C). In order to obtain further assurance that the best value for this project had been negotiated, the City contracted CMS Estimating Services (CMS), to perform an independent construction cost estimate. CMS' estimated construction cost is $4,778,559 which includes a 10% CMR premium (Attachment B). The administration is of the opinion that the final GMP is a competitive, fair and a reasonable price as the difference between the comparative estimates and the GMP is less than 1% and within industry standards. Currently, the City has a Florida Inland Navigation District (FIND) Assistance Program Phase I grant approval for design consulting fees in the amount of $323,077. This grant amount will be reimbursed upon compliance with the grant requirement to award a construction contract by September 30, 2012. In addition, the City has applied for the Fl NO Assistance Program Phase II, in the amount of $986,000, for reimbursement of construction costs for the South Pointe Park Pier project. The construction duration of this project has been negotiated at 448 calendar days. This includes 90 day pre- construction activities, commencing with the relocation of the corals prior to demolition of the pier. It is recommended that the Mayor and City Commission adopt the resolution. Advisory Board Recommendation: IN/A Financial Information: Source of Funds: MIAMI BEACH 77-067357 2577-067357 2577-069358 515 Account AGENDA ITEM ~.;...;R;.....7 __ DATE Cf-/2-/2.. MIAMI BEACH City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov COMMISSION MEMORANDUM TO: Mayor Matti Herrera Bower and Members of the Cit FROM: Kathie G. Brooks, Interim City Manager DATE: September 12, 2012 SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND THE CITY CLERK TO EXECUTE GUARANTEED MAXIMUM PRICE (GMP) AMENDMENT NO. 1 TO THE PRE-CONSTRUCTION SERVICES AGREEMENT WITH THE WEITZ COMPANY, DATED APRIL 5, 2012, FOR CONSTRUCTION MANAGEMENT AT RISK SERVICES FOR THE SOUTH POINTE PARK PIER PROJECT, IN THE AMOUNT OF $4,809,017 WITH FUNDING FOR THIS AMENDMENT PREVIOUSLY APPROPRIATED AS FOLLOWS: $1,442,417 FROM THE SOUTH POINTE CAPITAL FUND 389; AND $3,366,600 FROM THE SOUTH POINTE COT AGREEMENT REV/MUNICIPAL RESORT TAX FUND 388. ADMINISTRATION RECOMMENDATION Adopt the resolution. KEY INTENDED OUTCOME SUPPORTED Ensure well-designed quality capital projects FUNDING Funding for this amendment in the amount of $4,809,017 has been previously appropriated as follows: $1 ,442,417 from the South Pointe Capital Fund 389; and $3,366,600 from the South Pointe COT Agreement Rev/Municipal Resort Tax Fund 388. ANALYSIS The Mayor and City Commission at its December 14, 2011 meeting authorized the Administration to issue an RFQ for a Construction Manager at Risk (CMR) firm to provide pre- construction services and construction phase services via a Guaranteed Maximum Price (GMP) amendment for the South Pointe Park Pier Project. RFQ No.18-11/12 was issued on December 19, 2011 and the Weitz Company (Weitz) submitted their proposal and were interviewed along with four (4) other CMR firms. On January 12, 2012, the selection committee unanimously ranked the Weitz Company as the top-ranked firm. Pursuant to the City Manager's recommendation, on February 8th, 2012, the Mayor and City Commission approved Resolution No. 2012-27831, authorizing the Mayor and City Clerk to execute a Pre-Construction Services Agreement with the Weitz Company. These services included: review of project requirements, existing on-site conditions, review of preliminary budget, project scheduling and phasing, value engineering, and submission of constructability recommendations to Atkins of North America (Atkins), the AlE of Record. 516 Commission Memorandum-Weitz Company GMP for the South Pointe Park Pier Project September 12, 2012 Page 2 of 3 On June 1, 2012, Weitz held a bid opening which was attended by representatives of the City and Atkins. Subcontractors submitted sealed bids which were opened by Weitz in the presence of the City and Atkins. The GMP submitted, prior to negotiation, was in the amount of $5,527,465. Following a number of discussions, evaluation of value-engineering (VE) options, and analysis of constructability recommendations, Weitz submitted the current negotiated GMP in the amount of $4,809,017 (Attachment A). The GMP reflects the current market conditions as well as additional scope not anticipated and additional requirements by the Environmental permitting agencies: associated with the relocation of the existing protected corals. This work involves a 30 day notice prior to the relocation and the proper monitoring to the satisfaction of the environmental permitting agencies prior to the demolition phase. It also includes the entrance plaza, the waterside construction of the pier and the offsite storage/staging area due to limited access from the park. The final estimate of probable construction cost conducted by Atkins, the Engineer of Record, on August 26, 2011 is $4,454,433. Since the CMR construction contract does not contemplate any change orders and assumes the owner's risk in the construction process, the final estimated construction cost of $4,836,637 includes the 10% CMR premium (Attachment C). In order to obtain further assurance that the best value for this project had been negotiated, the City contracted CMS Estimating Services (CMS), to perform an independent construction cost estimate. The estimated construction cost as submitted by CMS is $4,344,145. Since the CMR construction contract does not contemplate any change orders and assumes the owner's risk in the construction process, the estimator has recommended an additional 10% premium on their estimated construction cost, for a total of $4,778,559 (Attachment B). The administration is of the opinion that the final GMP is a competitive, fair and a reasonable price as the difference between the comparative estimates and the GMP is less than 1% and within industry standards. Currently, the City has a Florida Inland Navigation District (FIND) Assistance Program Phase I grant approval for design consulting fees in the amount of $323,077. This grant amount will be reimbursed upon compliance with the grant requirement to award a construction contract by September 30, 2012. In addition, the City has applied for the FIND Assistance Program Phase II, in the amount of $986,000, for future reimbursement of construction costs for the South Pointe Park Pier project. The construction duration of this project has been negotiated at 448 calendar days (includes 90 days for pre-construction environmental compliance) and it is anticipated that this work will commence in October 2012 (pending the approval of the USACE permit). The first activity will be the relocation of the corals prior to the demolition of the existing pier. The City is taking measures to offset any impact to the project schedule and FIND grant deadlines. The anticipated Project Schedule for the construction of the South Pointe Park Pier is as follows: Commission GMP Awarded: Anticipated Notice to Proceed Number One: Anticipated Notice to Proceed Number Two: Anticipated Construction Start: Anticipated Substantial Completion: 517 September 12, 2012 October 1, 2012 -(30 day notice & coral relocation) December 1, 2012 -(demolition of existing pier) January 2013 January 2014 Commission Memorandum-Weitz Company GMP for the South Pointe Park Pier Project September 12, 2012 Page 3 of3 CONCLUSION The Administration recommends the approval of the attached resolution authorizing the Mayor and the City Clerk to execute Guaranteed Maximum Price (GMP) Amendment No. 1 to the Pre- Construction Services Agreement with the Weitz Company, dated April 5, 2012, for Construction Management at Risk Services for the South Pointe Park Pier project, in the amount of $4,809,017. Attachments: Attachment A: The Weitz Company-Construction Management at Risk GMP Document Attachment B: CMS -Third Party Estimate of Construction Costs Attachment C: Atkins -Estimate of Probable Construction Cost T:\AGENDA\2012\9-12-12\South Point Park Pier-GMP Amendment Weitz. MEMO.doc 518 519 ATTACHMENT A ''.41Hif1 BUILD IN GOOD COMPANY~ Project: South Pointe Park Pier Job#: Trade Descr:pUon dd for MMFX reinforcing steel in primary $ 520 CONSTRUCTION MANAGEMENT SERVICES, INC. 10 Falrway Drive • Suite 301 • Deerfield Beach, Florida 33441 '95,H81-1611 'FAX 954-427-3142 SOUTH POINTE PARK PIER PROJECT , CITY OF MIAMI BEACH 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33109 GMP CONSTRUCTION DOCUMENTS COST ESTIMATE August 31, 2012 PREPARED FOR: CITY OF MIAMI BEACH PREPARED BY: CMS-CONSTRUCTION MANAGEMENT SERVICES, INC. CMS FILE # 21 01 Quantity Surveyors • Construction Managers 521 MAIN SUMMARY CMS-CONSTRUCTION MANAGEMENT SERVICES, INC. Conlident!al Page 1 CMS-Construclion Management Services, Inc. 1 0 Fairway Drive, Suite 301 Deerfield Beach, Fl33441 954-481·1611 CMS FILE# 2101 SOUTH POINTE PARK PfER PROJECT CJTY OF MIAMI BEACH 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33109 GMP CONSTRUCTION DOCUMENTS COST ESTIMATE August 31, 2012 PR_EPARED FOR: CITY OF MIAMI BEACH MAIN SUMMARY DIVISJON DESCRIPTION AMOUNT ~21000 ..... 02000 .lf3000 GENERAl CONDITIONS "" '"""'"""" '"""'="""~""' S!Tf:: WO~I${ DEMO C0t!9RE7E f_!JIOIST. PROTECTIOt:L )DOORS & WINDOWS 1 """"~~~~""~~"'"'' 1FIN1SHES ·~~~~..t~~-••.. ·····~~·-~~--~~-~~··· ········~ !sPEC!~_LTIES I Sl(3_t,IAGE ..... . EO!l!f'~J!HI . '·""·"·'~·-~~-~~~-.F!J.EN!§!ilt-l~~-~~~ SPECIAL CONSTR~UCTION ..... . }1000 ..... . 32000 1.0% 2.5% 5.0% Prepared by Gary Weinstein 8!3112012 522 ' 596,611.46[ 1 3?§J21~:.Q.~J-.~·-·· 11 o, 202. nl ......................................... 0.001 ·-············ ··········~······' ·····==<·-''············· ........... !U!Q: 29,l{O?cilfL~ _ ·····················~--~ 95,Q~?,If!l: .2.0Q~ .Q.OO% 0.48~·-· . 0.71% ~-0.00% ~~~ O.QQ.~• ······················~······~·· --t!.15% 9:Q.Q~ 5~3,833.89 1 12.98% ................................ 111, .. ·''~"--1~~-~--~··· 2.57% ~-0.68%_~~~-. 0.79% ~~~~~~,~~~'t?O"& 2.03% -~--~-~~ Page 1 QUALIFICATIONS CMS-CONSTRUCTION MANAGEMENT SERVICES, INC. Confidential Page 1 CMS-Construction Management Services, Inc. 10 Fairway Drive, Suite 301 Deerfield Beach, Fl 33441 954-481-1611 CMS FILE# 2101 SOUTH POINTE PARK PIER PROJECT CITY OF MIAMI BEACH MIAMI BEACH, FLORIDA 33109 GMP CONSTRUCTION DOCUMENTS COST ESTIMATE August 31, 2012 QUALIFICATIONS ITEM 1 THIS COST ESTIMATE IS BASED ON A STANDARD OPEN-BID PROCESS. 2 IF TYPE OF CONTRACT: 11CM -AT· RISK." ADD AJiPROXIMATEL Y 10 T0-15% TO THE COST 3 GENERALCONDlTIONSAREBASEDON A 12:MONTH CONTRACT. --· '""-·-· 'v'"'~- ··--·ITHls ESTiMATEISBASED ON DRAWINGS BY ATK-INS DATED JUNE 20, 2012:AND ADDITIONAL INFORMATION 4 IAT MEETiNG ON 8/2812012. 5 !Due to the present volatile natureol the construction market, construction materlaTcostcou!dcfiange . !substantially prior to construction. jAn Allo~§!Il9ifor ALL!:§EMITSgf $152,00Q:22Js Inc]yged ......... ·•········ ~ .Te~t!ng is lncludgf!:~~-... .. . .... 8 ~lmpactJE?~.2L21h~ruUI1ty company chargt;~s are .. f:.!OT.Jn~ludt!d. ... Prepared by Gary Weinstein 8/3112012 Page 1 523 ATTACHMENT C South Pointe Park Pier Project City of Miami Beach 100% Submittal Package South Pointe Park Pier Project Estimate of Probable Construction Cost DESCRIPTION Site work Mis./Constr, Disruption Adjustments ate (Allowance Removal of existing pier (Allowance} Survey and Construction layout (A!!owance} atee Watch Personnel [Allowance) New Pier Decking-1 x 6 Premium IPE Wood Decking IPE Wood Decldn Cit s (Allowance) New Stainless Steel Grating Decking-2" Deep (Allowance New Guard Railing-SS (A1!owam:;e} 524 QTY 118 8,500 Rev: B/26/2011 TOTALPRlGE EA $1,00\LCO $1 i 8,000 $20,000 $1,000 $2,500.00 $120.00 $162,900 $37,713 $110,250 $370,000 $161,600 $20,000 $464,600 $360,0 SPPF Project South Pointe Park Pier Project City of Miami Beach 100% Submittal Package South Pointe Park Pier Project Estimate of Probable Construction Cost igh grade (A 3161 Wood-Fishing Area (Allowance) New Concrete Pavers (Allowance) New Coral Stone Edging (Allowance\ New 12" x 12" Shell Pavers (Allowance) SS Bike Racks (Allowance) New Bike Racks Concrete Pad (Allowance) Low Level Retaining Walls (Allowance) wance) s -on Pier, includes shipping and handling n (Allowance) aste Containers -on Pier, incL shipping & .a & installation (Allowance) Service to Pier-4" DIP 525 Rev: 8126/2011 $5,000 $9,900 $1,760 SPPP Project South Pointe Park Pier Project City of Miami Beach 100% Submittal Package DIV South Pointe Park Pier Project Estimate of Probable Construction Cost Fittings, etc. South Pointe Park Pier Project Subtotal Direct Costs General Conditions @ 12% Subtotal Bonds & Insurance (includes Builders Risk)@ 4.5% Building Permit (Allowance) Subtotal Overhead & Profit @ 8% Subtotal Unforeseen Conditions Allowance @ 5% Subtotal Total Probable Construction Cost 526 Rev: 812612011 $22,500 $5,000 $121 028 $10,000 $60,000 $70 000 $3,601,429 $432,171 $4,033,600 $181,512 $50,000 $4,265,112 _j_341 ,209 ~ $230,316 $4,836,637 $4,836,637 SPPP Project RESOLUTION TO BE SUBMITTED 527 THIS PAGE INTENTIONALLY LEFT BLANK 528