C2A-Issue RFQ ROW Improvement Program Neighborhood No 13- Palm And Hibiscus IslCOMMISSION ITEM SUMMARY projects as "excellent" or On June 14, 2011, the City issued RFQ No. 35-10/11 for a Design Criteria Professional to prepare the Design Criteria Package for the Project, which is intended to be a design-build contract Subsequently, on September 14, 2011, the City Commission approved Resolution No. 2011-27710 authorizing the Administration to enter into negotfations; after various attempts to negotiate with first ranked consultant, the City was successful in negotiations with the second ranked consultant, C3TS. On February 8, 2012, the City Com mission approved Resolution No. 201 approving the execution of an agreement with C3TS to prepare the design criteria for the Palm and Hibiscus Neighborhood Right-of-Way Project C3TS shall provide the City with a Design Criteria Package for the Project that wm serve to define the design r"""''"'"t"'. for development of construction documents by the selected Design Build Firm and for submission of their proposal. The consists of landscaping, replacement of existing water main infrastructure, improved storm water drainage collection and disposal infrastructure including swale restoration, curb and and other facilities, roadway reconstruction I markings, sewer lining and repair, repair and/or extension of existing sidewalks to comply with ADA requirements, incorporation of traffic calming features. consistent with community preferences and the incorporation and the undergrounding of utilities, including Florida Power and Light (FPL), Atlantic Broadband (ABB) and AT&T. The City Commission's approval of this Resolution will allow staff to initiate the appropriate procurement process the RFQ for design build services for the Project The DBF selected pursuant to the RFQ will be responsible for the design, construction, and construction ""''n"'''" associated with the Project The contract with the successful DBF will be awarded in accordance with the established requirements for award of design build contracts under the Consultants' Competitive Negotiations Act by using either a proposal selection process, or a qualifications based selection process. OBPI Account ---------'-------------'''~~'''------------1 Impact Summary: 25 AGENDA ITEM__.:::;;:.__~-- 0 ATE --L,!:.____.::;;__.::;;;;;_ City of Miami Beach, 1700 Convention Cente: Drive, Miorni Beach, Florida 33139, COMMISSION MEMORANDUM TO: Mayor Matti Herrera Bower and Members the Cit~Commission FROM: Kathie G. Brooks, Interim City Manager DATE: October 2012 SUBJECT REQUEST FOR APPROVAL TO ISSUE A REQUEST FOR QUALIFICATIONS {RFQ) FOR DESIGN/BUILD SERVICES FOR RIGHT OF WAY INFRASTRUCTURE IMPROVEMENT PROGRAM NEIGHBORHOOD NO. 13: PALM & HIBISCUS ISLANDS Approve Issuance RFQ. BACKGROUND On May 3, the City Commission approved Resolution No. 2002-24853, approving and officially adopting the Basis of Design Report (BOOR) the Palm and Hibiscus Islands Neighborhood Right of Way (ROW) Improvement Project (the Project). The Palm-Hibiscus-Star Islands Association (HOA) elected to pursue the creation of a Special Taxing District with Miami-Dade County, in to the expense associated with its Utility Undergrounding project After petition drives and various required public hearings the registered voters elected on December 7, 201 to move forward with the Utility Undergrounding project for only Hibiscus Island. Palm Island West residents elected not to proceed with the Utility Undergrounding project (Palm Island already has the utilities underground). On June 14, 2011, the City issued RFQ No. 1 for a Design Professional to prepare the Criteria Package for the Project, which is intended to be a design-build contract Subsequently, on September 14, 2011, the City Commission approved Resolution No. 2011-27710 authorizing the Administration to enter negotiations; after various attempts negotiate with first ranked consultant, the was in negotiations with the second ranked consultant, On February 8, 201 the Commission approved Resolution No. 201 approving the execution an agreement with C3TS to prepare the design package for the Palm and Hibiscus Neighborhood Right-of-Way Improvement Project ANALYSIS C3TS provide the City with a Design Criteria Package for the Project that will serve to define the design requirements for development of construction documents by the selected Design Build 26 Commission Memomndum RFQ for DESIGN/BUILD SERVICES FOR RIGHT OF WAY iNFRASTRUCTURE IMPROVEMENT PROGRAM NEIGHBORHOOD NO 13. PALM & HIBISCUS ISLANDS October 24 .. 2012 2 of2 (RFQ) for wrr\nr:::.rn Neighborhood No. 1 27 of landscaping, and roadway AYl'An<::ll"on Of existing with including Florida Commission's approval of process advertising THIS PAGE INTENTIONALLY LEFT BLANK 28