C2G-Award Contract Demolition Of The Normandy Shores Park BuildingCOMMISSION ITEM SUMMARY
Condensed Title:
Request for Approval to Award a Contract, Pursuant to Invitation to Bid (ITB) No. 014-2013TC,
for the Demolition of the Normand Shores Park Build in
Key Intended Outcome Supported:
Ensure quality and timely delivery of capital projects
Supporting Data (Surveys, Environmental Scan, etc.): The 2009 Customer Satisfaction
Survey indicated that 79% of businesses rated recently completed capital improvement
projects as "excellent" or "good."
Issue:
[ Shall the City Commission award the contract?
Item Summary/Recommendation:
As part of the FY 09/1 0 Capital Budget, the Parks and Recreation Department was approved
funding in the amount of $135,500 to replace the existing playground that was beyond repair
at the Normandy Shores Park. The funding request proposed the complete replacement of
the playground, safety surface, new fencing, furniture, fixture, and equipment.
In regards to the scope of work, the Contractor shall provide all labor, materials, equipment,
supplies, insurance, fuels, permits, retirement of utilities and any other items necessary to
complete the demolition work, the removal of demolition materials and disposal of materials
and related work as specified herein.
To achieve the desired scope, Invitation to Bid (ITB) 014-2013TC was issued on May 22,
2013, with an opening date of June 13, 2013. The solicitation was advertised and notices
were released to prospective bidders, of which 12 downloaded the solicitation. Bids were
received from three (3) bidders. After staff's review of the bids received, LCN Group, Inc. has
been deemed the lowest responsive, responsible bidder.
RECOMMENDATION
The Administration recommends the award of the contract to LCN Group, Inc., the lowest
responsive, responsible bidder pursuant to Invitation to Bid (ITB) 014-2013TC, for the
demolition of the Normandy Shores Park Building, in the amount of $34,875; plus approve a
project contingency of 10% for a not-to-exceed grand total of $38,363; further authorizing the
Administration to engage in value engineering to further reduce the cost and time for
completion of said project.
Advisory Board Recommendation:
IN/A
Financial Information:
Source of
Funds:
BPI
1
2
3
Total
Amount
$32,575
$3,488
$2,300
$38,363
: N/A
MIAMI BEACH
302-2019-069357
302-2019-069358
53
Account
Ci
M
JLM
AGENDA ITEM
DATE
C~G-
7-17-13
MIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov
TO: Mayor Matti Herrera Bower and Me
FROM: Jimmy L. Morales, City Manager
DATE: July 17, 2013
SUBJECT: REQUEST FOR APPROVAL 0 AWARD A CONTRACT, PURSUANT TO
INVITATION TO BID NO. 01 -2013TC, FOR THE DEMOLITION OF THE
NORMANDY SHORES PARK BUILDING.
ADMINISTRATION RECOMMENDATION
Approve the award of contract.
KEY INTENDED OUTCOME SUPPORTED
Ensure quality and timely delivery of capital projects.
FUNDING
$32,575 302-2019-069357 (Construction Fund)
$3,488 302-2019-069358 (Contingencies Fund)
----:-$-'-2-L,3_0_0_ 302-2019-000674 (Architect & Engineering Fund)
$38,363 Total
BACKGROUND
As part of the FY 09/1 0 Capital Budget, the Parks and Recreation Department was approved
funding in the amount of $135,500 to replace the existing playground that was beyond repair at
the Normandy Shores Park. The funding request proposed the complete replacement of the
playground, safety surface, new fencing, furniture, fixture, and equipment.
During project development, the Parks & Recreation Department worked internally to develop a
second phase of the park's revitalization, which included a new recreation building/activity
pavilion/restroom with storage space, similar to the one built in Fairway Park. A water
access/fishing dock and the new playground with shade and safety surfacing was also included.
In January 2012, the Parks and Recreation Department met with Commissioner Jorge Exposito
and Normandy Shores HOA Projects Committee Chair Mark Wojak to present the second
phase concept and gain initial feedback. Mr. Wojak agreed to take the concept to the
Normandy Shores HOA board for their comments. On February 14, 2012, Mr. Wojak
recommended that in lieu of the water access concept, the residents on Normandy Shores
would prefer a more open green space park which included the demolition of the existing
storage building/restroom that is in very poor condition. This restroom is currently utilized by
tennis players and a replacement is not included in this project, however, there is a public
restroom in the Normandy Shores Golf Club across the street. In addition, a vita course/ fitness
circuit similar to the one installed in Lummus Park, park furnishings such as benches, trash
54
Commission Memorandum-ITB 014-2013TC-Demolition of the Normandy Shores Park Building
July 17, 2013
Page2
receptacles etc., new fencing, and landscaping were part of the recommendations provided by
the residents.
SCOPE OF SERVICES
Demolition and removal of the structure shall include, as follows:
• The Contractor is responsible for contacting utility companies to retire the necessary
utilities (natural gas, water, and/or electricity) prior to demolition.
• Demolition and removal of structures shall include removal of the entire identified
structure(s) and contents to the construction limits.
• All concrete floor slabs, foundations, pilings, driveways, sidewalks, steps, parking
areas, and other above ground and underground improvements associated with the
structure shall be removed as noted.
• Fences shall remain, unless otherwise instructed to remove them.
• Cap all building sewer connections at existing wye locations.
• Develop an optional asbestos and lead paint abatement report.
• Removal of any identified underground storage tanks.
• Provide temporary erosion and sediment control on each respective property prior to
the start of demolition operations for the full duration of the project. Contractor shall
be responsible for the maintenance of controls and control structures and shall be
responsible for any clean-up due to failure or inefficiency of such controls.
Sedimentation run-off shall not be tolerated and if run-off occurs the Contractor shall
take corrective action immediately.
• Grading, backfill, sodding, and return to grade shall be performed as follows:
• All crawl spaces, lower levels, foundation areas, and any below ground area
shall be filled and compacted with earth. The backfill must not be frozen when
placed and shall be compacted to a density of 95% of maximum density of
the backfill material used as determined by ASTM designation D-698. The top
six (6) inches of backfill shall be made with soil suitable for growth of grass
and graded to natural grade of surrounding undisturbed earth.
• Final grading shall insure adequate drainage offsite and not permit pending of
water. All filled and disturbed ground shall be smoothed for mowing.
• The Contractor shall import clean fill as necessary to establish proper surface
grades but the Contractor may cut and fill on site to the extent possible. The
Contractor must supply samples of imported fill to be used and approved by
the City.
• In the event previously unknown hazardous materials are discovered by the
Contractor, the Contractor shall immediately suspend work in the specific location of
the hazardous material and immediately notify the City Project Manager;
• All demolition materials and debris shall be removed from the work concurrently with
progress of work. Contractor shall not allow mud and debris from vehicle transporting
demolition materials to litter any streets or highways. Contractor shall clean any such
mud or debris at its sole expense. The City will vigorously enforce all requirements
relating to clean-up of debris, dirt, mud, and demolition materials from the site and on
streets, highways, and adjacent properties. Cleanup shall follow immediately after
and at the same rate as construction and shall not be delayed until entire project is
finished. Contractor shall clean all right-of-way and easement areas that were
occupied by the Contractor in connection with the construction. All disturbed brush
and trees, all rubbish, excess materials, temporary structures, equipment, etc. shall
be removed and the area left in a neat and presentable condition. If at any time
55
Commission Memorandum-ITB 014-2013TC-Demolition of the Normandy Shores Park Building
July 17, 2013
Page3
during performance of work by Contractor the City's Project Manager determines that
cleanup is not being accomplished, the City's representative may direct, in writing, no
additional work can be accomplished without meeting certain requirements. If so
directed, no claim for additional time will be allowed. The Contractor is to provide
extra care during performance of work by Contractor to ensure that no rock, base
stone, string, stakes, or any other construction material is left in the water main or
irrigation lines. At the end of each construction day, the ends of all such lines shall
be sealed watertight and all points of entry are to be covered to prevent easy access.
No rain, storm water, or ground water shall be allowed to enter the water main or
irrigation systems.
• Contractor shall make every effort to locate and identify all underground pipe lines,
cables, and conduits by contacting the Florida One Call System and the owners of
underground utilities, by prospecting or otherwise, in advance of trench or excavation
operations. Contractor will be required to relocate the utility or work around it at no
cost to the City. It will be the responsibility of the Contractor to brace or otherwise
secure any utility poles or anchors close to the trenching operation. Contractor will
be solely responsible for any or all damages whether direct, indirect, or
consequential to the underground or above ground utilities, pipe lines, and
surroundings, and shall indemnify and hold harmless the City for any and all claims
or judgments whenever made as a result of the contractor's actions. If additional or
unexpected utility conflicts occur, the Contractor shall be responsible for coordinating
with the affected utility company to resolve the conflict and maintain progress on the
project. No time extensions will be granted for associated delays.
• Contractor shall maintain and enforce all necessary and adequate safety precautions
for the protection of life and property on all work performed. Contractor shall also
comply with all regulatory agencies requirements for safety and use extreme caution
to protect the project area to prevent accidents, damage, or injury involving
pedestrian or vehicular traffic in the project area. Barricades, safety screening, or
other acceptable methods shall be used as needed to keep the public out of danger
and to safely divert them around the project area.
• Contractor shall exercise proper precaution at all times for the protection of persons
and property and shall be responsible for all damages to persons or property, either
on or off the site, which occur as a result of the contractor's prosecution of the work.
The safety provisions of all applicable laws, building and construction codes, and
regulations shall be observed. Contractor shall take or cause to be taken such
safety and health measures, additional to those herein required, as the contractor
may deem necessary or desirable. Machinery, equipment and all hazards shall be
guarded in accordance with the safety provisions of the "Manual of Accident
Prevention of Construction" published by the Associated General Contractors of
America, Inc., to the extent that such provisions are not in conflict with applicable
local laws. Contractor shall maintain an accurate record of all cases of death,
occupational disease, and injury requiring medical attention or causing loss of time
from work, arising out of and in the course of employment on work under the
contract. The contractor shall promptly furnish the Local Public Agency with reports
concerning these matters. Contractor shall indemnify and save harmless the City and
the City's representative from any claims for damages resulting from personal injury
and/or death suffered or alleged to have been suffered by any person as a result of
any work conducted under this contract.
• Inspection by Department of Building Development Services for final permit shall be
requested by the Contractor within ten (1 0) days of completion of demolition of each
56
Commission Memorandum-ITB 014-2013TC-Demolition of the Normandy Shores Park Building
July 17, 2013
Page 4
separate site. Inspection to finalize demolition permit must be requested by
Contractor upon completion of demolition and site clean-up.
ITB PROCESS
Invitation to Bid (ITB) 014-2013TC was issued on May 22, 2013, with an opening date of June
13, 2013. The pre-bid conference was held on May 30, 2013. During the pre-bid conference,
prospective bidders were instructed on the procurement process and the information their
respective proposals should contain.
The Public Group and Bidnet issued bid notices to 31 and 276 prospective bidders respectively
of which 10 and 2 accessed the advertised solicitation respectively. In addition, 148 vendors
were notified via email, which resulted in the receipt of the following three (3) proposals:
• Cast Development, LLC
• Chin Diesel, Inc.
• LCN Group, Inc.
The following table provides the proposed total base bid prices of the three (3) responsive bids:
LCN Group, Inc.
Chin Diesel, Inc.
Cast Development, LLC
$34,875
$45,232
$46,047
After staff's review of the bids received, LCN Group, Inc. has been deemed the lowest
responsive, responsible bidder. Founded in 2004, LCN Group, Inc. is a licensed general
contractor specializing in demolition services that also possesses extensive knowledge and field
experience throughout South Florida. Notable clients include the City of Lauderhill and the
South Florida Water Management District.
CITY MANAGER'S DUE DILIGENCE
After considering the review and recommendation of City staff, the City Manager exercised his
due diligence and carefully considered the specifics of this ITB process. As a result, the City
Manager recommends to the Mayor and City Commission to award the construction contract to
LCN Group, Inc. as the lowest responsive, responsible bidder and authorize the Administration
to engage in value engineering to further reduce the cost and time for completion of said project.
CONCLUSION
The Administration recommends the award of the contract to LCN Group, Inc., the lowest
responsive, responsible bidder pursuant to Invitation to Bid (ITB) 014-2013TC, for the demolition
of the Normandy Shores Park Building, in the amount of $34,875; plus approve a project
contingency of 10% for a not-to-exceed grand total of $38,363; further authorizing the
Administration to engage in value engineering to further reduce the cost and time for completion
of said project.