R7G-Execute Change Order 3 Roadway Improvements Along West AvenueCURRENT STATUS ln preparation for the October gth King Tides (an especially high tide event that occurs twice a year, when there is alignment of the gravitational pull between sun and moon), Public Works staff conducted a field inspection throughout the areas that are known to be affected during this event. lnitial flooding was observed on West Avenue between 6th and 8th Streets. To alleviate the flooding, staff utilizel water pumps and installed temporary plugs; however, a more permanent solution is required. Currently, there is a pump station under construction on 6th Street. Public Works staff is recommending the installation of a new 48-inch drain pipe from 6th to 8th Streets, where an existing 48-inch gravit! outfall is located. Staff is also requesting additional capacity in the drainage system on 10'n and 14tn Streets, which would be installed by the City and FDOT. Considering that the streets mentioned above will already be undergoing construction, the Public Works Department would like to incorporate work that was projected to be addressed in a future neighborhood improvement in order to minimize public disruption. This would consist of street reconstruction along 1oth, 14th, and lTthStreets, and WestAvenue between 6th and 8th Streets. Work includes undergrounl improvements such as: storm, sewer and water; and above-ground improvements such as: sidewalks, curbs, streets and lighting. Staff is also recommending an additional pump station on 17th Street and Alton Road, where an old gravity drainage system is located, to properly manage stormwater on 17th Street and Lincoln Road. THE ADMINISTRATION RECOMMENDS ADOPTING THE RESOLUTION. COMMISSION ITEM SUMMARY AGENNA ITEM Dh"{E R1 G rc-tq *tq Condensed Title: A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Approving And Authorizing The Mayor And City Clerk To Execute Change Order No. 3 To The Agreement With Bergeron Land Development, lnc., Dated April 30, 2014 (The Agreement), Related To The Completion Of Roadway lmprovements Along West Avenue Between 6tn And 8th Streets And 10th, 14th, And 17th Streets West Of Alton Road With A Stormwater Pump To Be Constructed At 17th Street, Further lncreasino The Cost Of The $15,670.000 Ensure value and of Data (Survevs. EnvironmentalScan. etc.): N/A N/A Eric T., ext.6012 T:\AGENDA\201 4\OctobeAOctober 29\PUBLIC # AAIAAAISIACH 170 g MIAMIBEACH City of Miomi Beoch, 1700 Convention Cenier Drive, Miomi Beoch, Florido 33139, www.miomibeochfl.gov COMMIS lON MEMORANDUM TO: Mayor Philip Levine and Members FROM: Jimmy L. Morales, City Manager DATE: October 29,2014 SUBTECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAM! BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 3 TO THE AGREEMENT WITH BERGERON LAND DEVELOPMENT, tNC., DATED ApRtL 30, 2014 (THE AGREEMENT), RELATED TO THE COMPLETION OF ROADWAY TMPROVEMENTS ALONG WEST AVENUE BETWEEN 6TH AND 8TH STREETS AND IOTH, 14th, AND 17TH STREETS WEST oF ALToN RoAD WITH A SToRMwATER PUMP TO BE GONSTRUCTED AT 17TH STREET, FURTHER INCREASING THE COST OF THE AGREEMENT BY $15,670,000. ADMINISTRATION REGOMM EN DATION The Administration recommends adopting the Resolution FUNDING BACKGROUND At its February 12, 2014 meeting, Resolution number 2014-28498 was adopted by the City Commission, accepting the findings and recommendation of the City Manager in declaring an emergency, pursuant to Subsection 287.055(9XcXO)(a)(1) of the Florida statute, and as permitted, pursuant to Section 2-367(e) of the City Code, waiving, by 5/7ths vote, the competitive bidding requirement, and authorizing the City Manager to take the following actions: To procure the necessary emergency design and construction services, pursuant to a negotiated design-build contract for the remaining stormwater pump stations for 6th, 1Oth and 14th Streets, with Bergeron Land Development, lnc. (Bergeron), an Florida Department of Transportation (FDOT) contractor for the Alton Road lmprovements Project, in an amount not to exceed $1 1,250,000 At its June 11,2014 meeting, the City Commission approved Resolution No. 2014-28636, authorizing the Mayor and City Clerk to execute Change Order No. 1 to the Bergeron agreement, in the amount of $1 ,000,000, plus a project contingency in the amount of $100,000, for a total cost of $1 ,100,000. The change order also allowed for a seawall construction at 1Oth Street, construction of an outfall, converting a Bay Road pump station to direct discharge to the bay at 14th Street, and the installation of additional check valves at various locations that required protection from tidal flooding. the City mission 171 Commission Memorandum -Bergeron pump stafions lmprovements - Change Order No. 3 Page 2 of 2 At its September 30, 2014 meeting, the City Commission approved Resolution 2014-28768, authorizing the Mayor and City Clerk to execute Change Order No. 2 to the Bergeron agreement, for the completion of roadway improvements along 6th Street and West Avenue between Sth and 6th Streets and a new seawall at 14th Street, further increasing the cost of the agreement by $3,006,544. CURRENT STATUS ln preparation for the October gth King Tides (an especially high tide event that occurs twice a year, when there is alignment of the gravitational pull between sun and moon), Public Works staff conducted a field inspection throughout the areas that are known to be affected during this event. lnitial flooding was observed on West Avenue between 6th and 8th Streets. To alleviate the flooding, staff utilized water pumps and installed temporary plugs; however, a more permanent solution is required. Currently, there is a pump station under construction on 6th Street. Public Works staff is recommending the installation of a new 48-inch drain pipe from 6th to 8th Streets, where an existing 48-inch gravity outfall is located. Staff is also requesting additional capacity in the drainage system on 10'n and 14'n Streets, which would be installed by the City and FDOT. Considering that the streets mentioned above will already be undergoing construction, the Public Works Department would like to incorporate work that was projected to be addressed in a future neighborhood improvement in order to minimize public disruption. This would consist of street reconstruction along 1Oth, 14th, and 17th Streets, and West Avenue between 6th and 8th Streets. Work includes underground improvements such as: storm, sewer and water; and above-ground improvements such as: sidewalks, curbs, streets and lighting. Staff is also recommending an additional pump station on 17th Street and Alton Road, where an old gravity drainage system is located, to properly manage stormwater on 17th Street and Lincoln Road. GOST ANALYSIS Bergeron has submitted a cost proposal in theappriximate amount of $14,920,000 (Attachment) for services stated above. The City's Public Works Department has reviewed the proposal and the cost breakdowns and deems the cost to be fair and reasonable. We are proposing a not to exceed cost of $15,670,000 which includes a 5% contingency. CONCLUSION The Administration recommends adopting the Resolution. Attachment: Bergeron's cost proposal dated 10121114th rl,u JLM/MT/g(C/BAM/FRS T:\AGENDA\2014\October\October 29\PUBLIC WORKS\Bergeron stormwater pump stations Change Order No 3 MEMO.docx 172 / ---) ----s l.':t-)I Bergeron Bid Considerations Bergeron here by submits the price of 514,921,493.2lfor the scope tisted herein and within the DCp. This price is based on: 19612 S.W. 69 Place Fort Lauderdale, F[ 33332 Office Phone (954) 680-51m 10th Street 14th Street 17th Street West Ave(6tn to 8s1 West Ave(17th to Lincoln) Signa I ization Contingency Lighting Contingency L.ano DevelopmENT, Inlc. Construction Cost s1-,7g7,ggo.27 s2,051,204.34 s4,456,949.00 52,476,O49.94 S1,390,919.73 s 765,864.90 S 692,397.46 Fax Numbers Engineerlng (954) 252-8064 Estimatlng (9541 680-0666 LOl2uL4 Savings on 10th from FDOT work S 1:06,123.70 Savings on 14th from FDOT work S 61,309.09 Alternatives Storm only on west Ave.(6th to 8th; 5 390,04g.s3 100% Design on remaining West Ave Neighborhood Design Cost $197,778.@ S225,632.0o s457,969.00 s272,366.00 514G,047.00 S 78,24s.00 s 66,701.00 S2,540,881.00 And these bid considerations are as follows for the CIty of Miaml Beach Roadway lmprovements atong portions West Aue, t0s, tetr, and 17s as shown above. MOT consideratlon is based on temporary roadway closures with detourc. Special Notes and Standard Terms and Conditions are shown in Exhibit A with construction price breakdown Exhibit B shows work areas. Regards,-"fu;r-5 Chad Widup Operations Manager (9s4) 680 - 6100 CWid up@ berseroninc.com 173 Benefit to running the additional 48" down to 8th Street and connecting to 5th Street Pump Station o An area prone to rainfall flooding is the area between 8th and 7t^. By connecting the system to the pump station you can mitigate this flooding. The main goal being to have everything installed and operational before the April Spring Tides. Benefit to ROW to ROW construction while installing the 48" down to 8th & connecting to 5th Pumps . By awarding Bergeron the ROW to ROW roadwork, the public will only be interrupted once. By having Bergeron perform the work you can ensure the most efficient coordination between the Alton Road Project and proposed work. You can also expect a more improved drainage system that can not only help with the tidal flooding but also start addressing the flooding associated with rainfall events. Bergeron will also be able to continue to promote the safety of the pedestrian and local traffic. Benefit to the reconstruction of 10th Street FDOT limits to Biscayne Bay o Minimize impact to residents o Ensure the best possible MOT coordination between the proposed work and Alton Rd by having Bergeron perform. Bergeron will also be able to continue to promote the safety of the pedestrian and local traffic. o Raising the road and upgrading drainage to help further reduce tidal flooding and also fight against rainfall events. Placing new piping greatly improves drainage which resolves the issue of stormwater flooding. Benefit to the reconstruction of 14th Street FDOT limits to Biscayne Bay o Minimize impact to residents o Ensure the best possible MOT coordination between the proposed work and Alton Rd by having Bergeron perform. Bergeron will also be able to continue to promote the safety of the pedestrian and local traffic. o Raising the road and upgrading drainage to help further reduce tidal flooding and also fight against rainfa ll events . By upgrading to a single run of 48" RCP you can ensure a much cleaner efficient flow into your pumps. Currently the Pumps are pulling from cracked, damaged, aged clay pipe. The southern 35" was already granted to FDOT for their use. lf the CMB does not upgrade the northern 36" they also face a reduction in capacity. 174 Benefit to the reconstruction of 17th Street FDOT timits to lntersection of West Ave and Bay Rd along with a new Pump Station. o Minimize impact to residents o Ensure the best possible MOT coordination between the proposed work and Alton Rd by having Bergeron perform. Bergeron will also be able to continue to promote the safety of the pedestrian and local traffic. o Raising the road and upgrading drainage to help further reduce tidal flooding and also fight against rainfall events o The largest driver is perhaps the fact that the 17th area was the only area captured on the news to experience flooding. Currently we have a temporary pump on-site to keep the area dry. To mitigate these temporary measures, reconstruction of the roadway along with a new pump station will be most beneficial to the City. Bergeron will also utilize and coordinate closely with Gannett Fleming who is designing the Bridge for Bay Rd crossing Collins Canal. o Bergeron understands the critical nature of having 17th street pump station up and running before the April Spring Tides, and if awarded by November t,2Ot4 our team is fully confident we can deliver as we did previously on 14th & lOth Street. 175 city of Miami Beach Roadway l0/2llz0l4 BERGERON LAND DEVELOPMENT INC. 19612 S.W.69th ptece FL Lauderdale, FL 33332 Contact Mlke Mflter Phone: 954{tMt00 ext 2lg Fer 954{8(H)666 City ofMiaai Beacb (30s) 673-7080 BnreMovrry r' Jji"..*'-f.,;-t...,j ]tilDEITI{.O,IIII Ouote To: Phoae: Eeri Attn: JobNamc: Date ofPlans: RerrisiolrDate: 21000 22000 230t0 23020 23030 230/i0 23050 26000 270o0 31000 32000 33010 33020 33030 33040 AI\{OUNT 1.50 331 .54 ,. 193.60 377 0.00 -22,304.74 I8.96 723.70 46t.72t.70 3.76 DESCRIPTION llr g66yj66 Iin6 371.16 10!h Sheet - IDOT Deduct 10th Strect Subtotel - FDOT Deduct Pags 1 of4 33050 176 42000 36000 37000 41000 43010 43020 43030 43050 u025 54308 543 15 s5150 55400 55560 55580 55590 s5600 55605 55885 55890 55895 55900 8s000 90000 55750 55800 NOTES: NOTES: 14th Street - FDOT Deduct 14th Street - FDOT Deduct Subtotal West Ave 48" Onlv from 6th to Eth Street 313,483.73 West Ave,48" OnIy 6th to Eth street Subtotal West Ave (6th to E th Street West Ave (6th to 8th West ave (Lincoln to 17th West Ave (Lincoln to lTth Street) Subtotal AMOUNT 7.56 r 57.83 301,t20.57 n 260,435.00 14.60 313.483.73 ,.' $390,048.53 743.63 551,098.18 e. 351.870.80 372,167.64 357,195.96 5. l0 375,288.47 30'7,525.48 226,606.38 14.60 198,128.70 1.53 207 .00 .80 .60 .46 Page2ol4 177 RESOLUTION TO BE SUBMITTED 178 THIS PAGE INTENTIONALLY LEFT BLANK 179