WABRP Recommendations 2015.04.29WASHINGTON AVENUE VISION AND MASTER PLAN
WASHINGTON AVENUE BLUE RIBBON PANEL Recommendations
2015.04.29
SUMMARY
GOALS & OBJECTIVES
Study and envision Washington in a transformational light
Preserve the historical, architectural and cultural character of Washington Avenue as City’s “Main Street”
Provide for redevelopment, adaptive reuse and infill resulting in economic vitality for the betterment of the community and the City as a whole
1.4.
2.
5.
3.
6.
Create commercial development opportunities that provides quality goods and services to neighborhood residents and tourists alike
Allow for a high level of mobility for pedestrians, cyclists, automobiles and public transit; and
Plan for quality public spaces and beach access to capitalize on the corridor’s location and surrounding environs.
• Historic Grid - walkable pedestrian environment
• One-mile Corridor from Lincoln Road to 5th Street*
• Twenty-five City Blocks
• Typical Block Size is 280’ by 400’
• 100’-0” Public Right-of-Way (Same as Lincoln Road)
• Most Landmark Buildings front Washington Avenue
• +/- 100 Historic Properties along Flamingo Park Historic
District (+/- 87 contributing historic properties)
• Handful of Major Landowners
• Walk along Lincoln Road from Alton to Washington is 3/4
mile distance
• North / South - Ocean / Collins / Washington
STUDY AREA
WASHINGTON AVENUE
PLANNING TIMELINE
OCT 2014 NOV 2014 DEC 2014 JAN2015 FEB2015 MAR 2015 APRIL 2015
Project Coordination
Task 1.0: Visioning Workshops (3)
Task 2.0: Concept Design and Master Planning
WASHINGTON AVENUE VISION AND MASTER PLAN
Presentation to Land Use Committee
Presentation to Commission
Workshop 1: Neighborhood, Local Issues & Mobility (11.14.2014)
Workshop 2: Tourism-Oriented Issues (11.21.2014)
Workshop 3: Retail and Branding Issues (12.12.2014)
WABRP Meeting 1: Preliminary Master Plan Ideas JAN. 26
WABRP Meeting 2: Updated Draft Master Plan FEB. 12
WABRP Meeting 3: Draft Master Plan Considerations FEB. 27
WABRP Meeting 4: Draft Review Meeting #1 MAR. 6
WABRP Meeting 5: Draft Review Meeting #2 MAR. 13
WABRP Meeting 6: FINAL Concept Master Plan MAR. 27 Additional WABRP MEETINGSAPRIL 01
APRIL 15
PLANNING PROCESS
VISION:
Washington Avenue as the MAIN STREET of Miami Beach where
residents and tourists can enjoy unique boutiques, ethnic restaurants,
convenient services, edgy nightlife and cultural experiences, all within
our walkable low scale historic architecture.
1935 Washington Avenue View1950 Washington Avenue View
c. 1939
Washington Avenue c. 1939 Today
LINCOLN ROADWASHINGTON AVE11TH STREET14 TH STREET12 4 53
PUBLIC INFRASTRUCTURE INVESTMENTS
• INTERIM ‘PILOT PROJECT’ VS LONG TERM IMPROVEMENTS - (IE. PAINT FIRST, FOLLOW WITH IMPLEMENTING ALL INFRASTRUCTURE IMPROVEMENTS UNDER CIP OR CRA AS FUNDING BECOMES AVAILABLE)
• SIDEWALKS ‘PAVEMENT TO PARKS’ PROGRAM - INTRODUCING “PARKLETS”
• OPPORTUNITY FOR PARKING P3’S WITHIN CENTER DISTRICT ZONE
• ENHANCE EAST / WEST CONNECTION ALONG 11TH STREET
CATALYST PROJECT: PRIVATE INVESTMENT
• USES - HOTEL, OFFICE AND RETAIL
• RESIDENTIAL USES (?)
• PRESERVATION OF EXISTING HISTORIC BUILDINGS
• ADDRESS PARKING NEEDS VS. CODE REQUIREMENTS - CONSIDER OPTIONS
NEW CULTURAL DISTRICT
• RELOCATION OF POLICE DEPARTMENT
• REUSE POLICE DEPT. PARKING GARAGE FOR PUBLIC USE
• NEW ‘ARTS / FILM / VIDEO’/TECHNOLOGY INCUBATOR
• THE WOLFSONIAN - EXPANDED ARTS & CULTURE PROGRAMMING
• NEW CIVIC PARK / BIKE STATION AT MUNICIPAL PARKING LOT (AT CORNER OF 10TH & WASHINGTON, ACROSS FROM THE WOLFSONIAN)
DREXEL AS LOCAL PEDESTRIAN CONNECTOR • PEDESTRIAN CONNECTION ALONG DREXEL BETWEEN ESPAÑOLA WAY AND 14TH STREET
• 1/2 MILE WALK BETWEEN FIU MBUS URBAN STUDIOS, NEW WORLD CENTER SOUNDSCAPE PARK AND CINEMATHEQUE
CATALYST PROJECT: PRIVATE INVESTMENT
• CONNECT WASHINGTON TO LINCOLN ROAD VIA “WOONERF” PUBLIC STREETSCAPE IMPROVEMENTS (IE. T-SHAPED AREA AT WA / LINCOLN INTERSECTION, TOWARDS COLLINS - UP TO JAMES)
• CREATE NEW BUS HUB ON LINCOLN, EAST OF WASHINGTON
• PROVIDE PUBLIC ACCESS VIA DIAGONAL CONNECTOR BETWEEN LINCOLN ROAD AND WASHINGTON AVENUE THRU 420 LINCOLN BLOCK
WASHINGTON
AVENUE
SOUTH END
GATEWAY
CENTER
DISTRICT
DREXEL &
ESPAÑOLA
NORTH END
GATEWAY12345
LINCOLN ROADWASHINGTON AVE11TH STREET14 TH STREET12 4 53
CATALYST
PUBLIC INFRASTRUCTURE INVESTMENTS
• INTERIM ‘PILOT PROJECT’ VS LONG TERM IMPROVEMENTS - (IE. PAINT FIRST, FOLLOW WITH IMPLEMENTING ALL INFRASTRUCTURE IMPROVEMENTS UNDER CIP OR CRA AS FUNDING BECOMES AVAILABLE)
• SIDEWALKS ‘PAVEMENT TO PARKS’ PROGRAM - INTRODUCING “PARKLETS”
• OPPORTUNITY FOR PARKING P3’S WITHIN CENTER DISTRICT ZONE
• ENHANCE EAST / WEST CONNECTION ALONG 11TH STREET
CATALYST PROJECT: PRIVATE INVESTMENT
• USES - HOTEL, OFFICE AND RETAIL
• RESIDENTIAL USES (?)
• PRESERVATION OF EXISTING HISTORIC BUILDINGS
• ADDRESS PARKING NEEDS VS. CODE REQUIREMENTS - CONSIDER OPTIONS
NEW CULTURAL DISTRICT
• RELOCATION OF POLICE DEPARTMENT
• REUSE POLICE DEPT. PARKING GARAGE FOR PUBLIC USE
• NEW ‘ARTS / FILM / VIDEO’/TECHNOLOGY INCUBATOR
• THE WOLFSONIAN - EXPANDED ARTS & CULTURE PROGRAMMING
• NEW CIVIC PARK / BIKE STATION AT MUNICIPAL PARKING LOT (AT CORNER OF 10TH & WASHINGTON, ACROSS FROM THE WOLFSONIAN)
DREXEL AS LOCAL PEDESTRIAN CONNECTOR • PEDESTRIAN CONNECTION ALONG DREXEL BETWEEN ESPAÑOLA WAY AND 14TH STREET
• 1/2 MILE WALK BETWEEN FIU MBUS URBAN STUDIOS, NEW WORLD CENTER SOUNDSCAPE PARK AND CINEMATHEQUE
CATALYST PROJECT: PRIVATE INVESTMENT
• CONNECT WASHINGTON TO LINCOLN ROAD VIA “WOONERF” PUBLIC STREETSCAPE IMPROVEMENTS (IE. T-SHAPED AREA AT WA / LINCOLN INTERSECTION, TOWARDS COLLINS - UP TO JAMES)
• CREATE NEW BUS HUB ON LINCOLN, EAST OF WASHINGTON
• PROVIDE PUBLIC ACCESS VIA DIAGONAL CONNECTOR BETWEEN LINCOLN ROAD AND WASHINGTON AVENUE THRU 420 LINCOLN BLOCK
WASHINGTON
AVENUE
SOUTH END
GATEWAY
CENTER
DISTRICT
DREXEL &
ESPAÑ OLA
NORTH END
GATEWAY12345PLACEMAKING OPPORTUNITIES
VISION AND MASTER PLAN
1. SERVICES
2. TRANSPORTATION, INFRASTRUCTURE &
GREENSPACE
3. PLACEMAKING OPPORTUNITIES
4. REGULATORY CHANGES
5. IMPLEMENTATION
COMPREHENSIVE PACKAGE OF RECOMMENDATIONS
BY THE MAYOR’S WA BLUE RIBBON PANEL FOCUSED
ON FIVE SPECIFIC CATEGORIES:
VISION AND MASTER PLAN
1. Washington Avenue PILOT PROJECT FOR ONE YEAR
2. City to issue and RFP TO PROPERTY OWNERS
between 9th and 13th Streets to buy their air rights and build
a municipal garage of 275+ spaces above existing ground floor
retail
3. Redesign the CONNECTION from LINCOLN
ROAD to WASHINGTON AVENUE as a new gateway
destination and create a NEW BUS HUB on Lincoln Road
8 MAIN IDEAS FOR WASHINGTON AVENUE REVITALIZATION:
VISION AND MASTER PLAN
4. RELOCATE THE POLICE STATION TO THE CITY
CENTER (near a re-built City Hall on the west side of the P
Lot) and re-purpose the police station as a 100,000 sf office
building with the 419 parking space garage available to the
general public.
5. INCENTIVES FOR DEVELOPMENT that don’t include
increasing FAR: Raise the maximum allowable height to 75
feet for larger projects and eliminate for five years the parking
impact fee for new hotels and new small office buildings.
VISION AND MASTER PLAN
6. IMPROVE DELIVERY OF CITY SERVICES to make
Washington Avenue safe and clean: dedicated police foot
patrols; enhanced homeless outreach; afternoon litter pick up.
7. CREATE A FUNDING MECHANISM FOR STREETSCAPE
IMPROVEMENTS by expanding down Washington Avenue
the CRA that currently covers City Center.
8. ESTABLISH A WASHINGTON AVENUE TASK FORCE to
monitor City progress in implementing the Master Plan ideas
and provide guidance to the City throughout the process.
VISION AND MASTER PLAN11. WASHINGTON AVENUE PILOT PROJECT FOR 1-YEAR
a) Expand the sidewalks into the existing parking lane to make room for outdoor cafes, establish guidelines for parklets and waive sidewalk café fees.
b) Bring a protected bike lane to both sides of the street.
c) Move the on street parking over one lane. Bus stops and freight loading zones are located in this parking lane just as they are now. One lane remains for cars traveling in each direction, same as Collins Avenue.
d) Embrace Washington Avenue as a main transit street for a bi directional trolley or bus rapid transit connecting downtown and the Convention Center.
e) Establish a trolley dedicated to Washington Avenue running from the Convention
Center to 5th Street or South Pointe Park.
EXISTING 1
PROPOSED INTERIM / PILOT PROJECT
• (1) ONE LANE ONLY FOR VEHICULAR TRAVEL NORTH/SOUTHBOUND
• PROTECTED BIKE LANE + PARALLEL PARKING ON BOTH SIDES
• EXTENDED SIDEWALKS ON EAST + WEST SIDE
PHOTO: SAN FRANCISCO (SIMILAR - FOR ILLUSTRATIVE PURPOSES ONLY)
WIDENED SIDEWALK PROTECTED
BIKE LANE
PARKING
1
PILOT PROJECT (INTERIM): WASHINGTON AVENUE WITH MEDIAN
• (1) ONE LANE ONLY FOR VEHICULAR TRAVEL NORTH & SOUTHBOUND
• PROTECTED BIKE LANE + PARALLEL PARKING ON BOTH SIDES
• EXTENDED SIDEWALKS ON EAST + WEST SIDE OF WASHINGTON1
PILOT PROJECT (INTERIM): WASHINGTON AVENUE WITH MEDIAN
• (1) ONE LANE ONLY FOR VEHICULAR TRAVEL NORTH & SOUTHBOUND
• PROTECTED BIKE LANE + PARALLEL PARKING ON BOTH SIDES
• EXTENDED SIDEWALKS ON EAST + WEST SIDE OF WASHINGTON1
VISION AND MASTER PLAN
2. RFP FOR PURCHASE OF AIR RIGHTS TO BUILD
MUNICIPAL PARKING GARAGE BETWEEN 9TH & 13TH 2
VISION AND MASTER PLAN
3. REDESIGN THE CONNECTION BETWEEN LINCOLN ROAD
AND WASHINGTON AVE 3
VISION AND MASTER PLAN
3. REDESIGN THE CONNECTION BETWEEN LINCOLN ROAD
AND WASHINGTON AVE 3
NORTH GATEWAY DISTRICT PROJECT:
“WOONERF” Project + NEW BUS HUB AT WASHINGTON AND LINCOLN ROAD3
VISION AND MASTER PLAN
4. RELOCATE THE POLICE STATION TO CITY CENTER
REPURPOSE EXISTING BUILDING FOR OFFICE & PUBLIC PARKING 4CENTER DISTRICT
VISION AND MASTER PLAN
5. INCENTIVES FOR DEVELOPMENT that don’t include
increasing FAR: Raise the maximum allowable height to 75 feet for larger
projects and eliminate for five years the parking impact fee for new hotels
and new small office buildings.5
VISION AND MASTER PLAN
6. IMPROVE DELIVERY OF CITY SERVICES to make
Washington Avenue SAFE AND CLEAN: 6• Dedicated police foot patrols;
• Enhanced homeless outreach;
• Afternoon litter pick up.
VISION AND MASTER PLAN
7. CREATE A FUNDING MECHANISM FOR STREETSCAPE IMPROVEMENTS
by expanding down
Washington Avenue the CRA that
currently covers City Center.COLLINS AVE17TH ST
MERIDIAN AVE16TH ST
11T H ST
15TH ST
D A D E B L V D
ALTON CTLIN COLN RD
WEST AVEWASHINGTON AVEN BAY RDLENOX AVEALTON RDEUCLID AVEMICHIGAN AVEPRAIRIE AVEOCEAN DROCEAN CT14TH ST
W 2 8 T H S T
PENNSYLVANIA AVE21ST ST
COLLINS CTN MERIDIAN AVEJEFFERSON AVELIN COLN M ALL R D
22ND STPINE TREE DRPARK AVE13TH ST
LIN COLN L N
ESPA NO LA WAY
12TH ST JAMES AVEDREXEL AVEFLAMINGO DR23RD ST
BAY RDN LINC OLN L N
S
U
N
S
E
T D
R
19TH ST
20TH S T
14TH PL
10TH ST
27TH ST
15TH T ER W PROMENADE ST18TH ST
CONVENTION CENTER DR26TH ST
FLAMINGO PLBAY DRINDIAN CREEK DRN MI
CHI
GAN AVELIBERTY AVE28TH ST
W 25TH ST
W 24 TH ST
LAKE AVEW 26TH ST
14TH T ER
W 23RD ST COLLINS AVE EW 21 ST ST
W 27TH ST
MERIDIAN CTMIAMI BEACH DR24TH TER
W A S H IN G T O N C T
20TH ST
W 27 TH ST
DREXEL AVE13TH S T
W 24TH ST
W 23 RD ST
18TH ST
BAY RD19TH ST 19TH ST
18TH ST
14TH ST
W 28 TH ST
WEST AVEW PROMENADE ST12TH STBAY RD18TH ST
690 0 690345 Fee t
This map was prepared by the Miami Dade County
Enterprise Technology Services Department
Geographic Information Systems (GIS) Division
December, 2007
For the Office of Strategic Business Management
Legend
Miami Beach City Center CRA
Highway
Major Road
Street
Miami-Dade County
Miami Beach City Center CRA 7
VISION AND MASTER PLAN
8. ESTABLISH A WASHINGTON AVENUE TASK FORCE to monitor City progress in implementing the Master Plan
ideas and provide guidance to the City throughout the process.8
ZYSCOVICH