HomeMy WebLinkAboutLTC 514-2025 G.O Bond Program - Project Implementation Update No. 39MIAMI BEACH
OFFICE OF THE CITY MANAGER
LTC #514-2025 LETTER TO COMMISSION
TO:
FROM:
DATE:
Honorable Mayor Steven Meinerl a�d �m�e City Commission
Eric Carpenter, City Manager Bue ��
December 5, 2025
SUBJECT: G.O. Bond Program -Project Implementation Update No. 39
The purpose of this Letter to the Commission ("L TC") is to advise you on the status of theimplementation of the 46 General Obligation Bond (G.O. Bond) Projects approved by the City
Commission for the first tranche of funding (Tranche 1 ), totaling $160.69 million (including accruedinterest transfers), and $19.83 million approved under the Declaration of Intent to Issue Tranche 2
(referred to herein after as Tranche 2). It also covers the progress of the 20 G.O. Bond Arts &Culture projects approved for Tranche 1, in the amount of $107 .2 million (including accrued interest
transfers).
Refer to Exhibits A and A 1 for the agendas of the G.O. Bond Oversight Committee ("the Committee")
meetings held on September 18, 2025 and November 20, 2025. The following information includesexcerpts from both meetings. For complete meeting agendas, handouts, minutes, presentations,
and audio recordings, visit the website www.GOMBinfo.com and click on the Oversight Committee
tab to see Meeting Records.
IMPLEMENTATION STATUS -2018 BONDS
Project Dashboard and Program Progress Report
As of November 20, 2025, a total of 30 out of the 46 current tranche projects are in some form of
"Active" status, 15 projects have been completed, and 1 is pending. Chart 1 below shows the fullbreakdown by Category.
PROJECT ACTIVITY
PROJECT STATUS
Complett
Active
Pending
Future
All
Chart 1
Current <46
PROJECT CATEGORY
Palits
0
JO
cor;i�te�
Actrve 30
Pending 1
10
0
14
Future
/ 11
•9896 of all active TrancheProjects are Complete or
Active = 45 out of 46
Public Safety
10
0
13
All
IS
JO
11
57
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 2 of9
A total of $113.6 million has been expended,with an additional $28.9 million encumbered,bringing
the total to $142.5 million out of the available $180.5 million in funds.Chart 2 below provides a
detailed breakdown of the expenditures by Category.
Chart 2
PROJECT EXPENDITURES
Tranche 1
$160.69M Spent$113.64M
Encumbered$28.87M
Available$30.02M
Future
'$264.22M
•79%of all active Tranche Funds
are Spent or Encumbered=
$142.5M out of $180.5M
tranche 2
$19.83M
PROJECT CATEGORY
Parks Infrastructure Public Safety Total
PROGRAM Spent $59.573.912 $30,146,497 $23,915.708 $113,636,117
FUNDS Enumbered $17.866.278 $4,997.509 $6002.388 $28.866,175
Available $15,429.005 $14,359,397 $8,233.928 $38,022,330
Future $81,167.054 $148,246,777 $34,809,034 $264,222.865
Total $174,036,249 $197,750,180 $72,961,058 $444,747,487
Tranche 1 Progress
Most of the 46 projects have different components which are considered distinct projects,or
"subprojects",that are tracked separately and have separate budgets,procurement,and
implementation schedules.
The Tranche 1 Subproject Activity Summary depicted in Charts 3 and 4 on the next page summarize
the subproject activity into Status,Category and Funding amount.
Subproject Tracking Summary by Phase
As indicated on Chart 3 on the following page,of the 92 total subprojects in Tranche 1,58 (63%)
have been completed,11 (12%)are under construction,14 (15%)are in a design phase,7 (8%)
are in a planning phase,and 2 (2%)are pending.
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 3 of9
Chart 3
TRANCHE1
SUBPROJECT ACTIVITY
Tranche 1
100%
•98%of all Tl Subprojects
are Complete or Active =
90 out of 92
SUBPROJECT CATEGORY
Parks infrastru cture Public Safety All
Su8PR0ECT Complete 32 7 19 58
STATUS Construction 4 3 4 11
Design $4 14
Panning $7
Pending 0 0 2
Total 48 16 28 92
The total expenditures for each of the subproject categories are outlined in Chart 4 below.As of
November 20,2025,the 52 completed subprojects equate to $78.6 million of the budget (49%),
$32.5 million (20%)equate to subprojects under construction,$45 million (28%)equate to
subprojects that are in the design phase,$3.6 million (2%)equate to subprojects that are in the
planning phase,and $946.6 thousand (1%)has been earmarked for pending subprojects.For a
more detailed breakdown by project,refer to the attached Exhibit B.
TRANCHE1
SUBPROJECT EXPENDITURES
Tranche 1
100%
Chart 4
Complete
49%
Construction20%
Design28
Planning
Pending
1%•69%of the value of All Tl Projects are
Complete or Under Construction
SU8PROJECT CATEGORY
Parks Infrastructure Public Safety Total
SUBPROJECT Complete $43.259.595 $12.800.93 $17.531,695 $78,592.203
FUNDS Construction $15,139.565 $10.,602,150 $5,767.152 $32.508,867
Design $2.273.420 $.072,79 $10,0,3,190 $44,999,357
Planning $2.249.996 $397.66 $999.999 $3,647,611
Pending $946.639 IO $0 $946.639
Total $92,869,223 $29,673,418 $38,152,036 $160,694,677
G.0.Bond Program -Project Implementation Update No.39
December 3,2025
Page 4 of9
Subproject Progress
Chart 5 below compares the status of subprojects from previous months to the current month,dating
back to October 2019.
Chart 5
SUMMARY SUB-PROJECTS-TRANCHE 1
10/17/19 12/17/20 11/18/21 12/01/22 12/14/23 12/19/24 09/18/25 11/20/25 VARIANCENo.%No.%No.%No.%No.%No.%No.%No.%
ACTIVE/COMPLETE 44 68%69 95%80 95%83 98%85 96%87 97%90 98%90 98%0
CONSTRUCTION 16 15%9 12%11 13%8 9%11 12%11 12%16 17%11 12%-5
PLANNING /DESIGN 23 21%31 42%36 43%35 41%29 33%27 30%22 24%21 23%-1
CLOSED/COMPLETE 5 5%29 40%33 39%40 47%45 51%49 54%52 57%58 63%6
REMAINING 21 32%4 5%4 5%2 2%4 4%3 3%2 2%2 2%0
/TOTAL SUB-PROJECTS \ss 1 73 84 1 85 2 89?90 4,5 92%7 92
"Total number of subprojectswas updatedto reflectthe revisedG.O.Bond Implementation Plan
approved by theCity Commission on Aprl 21,2021
go25 -WaterwayRestoration Project moved fromTranche 2 to Tranche 1
"go18-Scott RakowYouth Center-Onesub-project sub-divided into2
GO34-AboveGroundImprovements -Indian Creek Sub-Project moved fromTranche 2to Tranche l
GO52-LED Lightingin Paris-Onesubprojectsub-divided into 2
GO5-Flamingo Park Historic Lodge -Onesubproject sub-diided into2
GO43-Alton Rd SharedUse Path subproject removed
GO48-Real TimeIntelligence Centersub-project added
4GO#13-North Shore Path &Fields movedfromTranche l to Tranche 2
&GO27Log Cabin moved from Tranche 2toTranche 1
"gos7-La Gore Park moved fromTranche 2toTranche l
"sos5-Newsubproject -Flamingo ParkSoftball Field
'so19-New subproject -SoundscapeParkSound System
Tranche 1 Expenditure Status
As of November 20,2025,a total of $104.7 million has been expended,and $30.2 million is
currently encumbered,totaling $134.9 million of the $160.7 million allocated for Tranche 1.The
breakdown of expenditures by Category is shown in Chart 6 below.
Chart 6
PROJECT EXPENDITURES TRANCHE 1
Tranche 1
$160.69M
Encumbered
$30.20M
Ava/able$25.83M
•84%of all T1 Funds are
Spent or Encumbered =
$134.9M out of $160.7M
PROGRAM Spent
FUNDS numbered
Available
Total
PROJECT CATEGORY
Parks Infrastructure Public Safety Total
$55.972.481 $25,111662 $23.581.930 $104,666,073
$20,542956 $3.361.972 $6.295.365 $30,200,293
$16,353.758 $1,199.778 $8274.727 $25.828.263
$92.869,195 $29,673.,412 $38,152.022 $160,694,629
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 5 of9
Tranche 2 Progress
Tranche 2 consists of 5 Infrastructure Category subprojects,all of which are continuations of
projects launched in Tranche 1.Currently,all 5 subprojects are in progress,with 4 in the
construction phase and 1 in the design phase.For a detailed breakdown by project,refer to the
bottom section of the attached Exhibit B.
Tranche 2 Expenditure Status
As indicated in Chart 7 below,as of November 20,2025,$5 million has been expended,and $1.7
million has been encumbered for a total of $6.7 million out of the $19.8 million of Tranche 2 funds.
Chart 7
PROJECT EXPENDITURES TRANCHE 2
Tranche 2
$19.83M
Encumbered$1.69M
Ava/able$13.16M
PROJECT CATEGORY
Infrastructure Total
•34%of all T2 Funds are
Spent or Encumbered=
$6.7M out of $19.8M
PROGRAM Spent
FUNDS ncumbered
Available
Total
$4982.552
$1.687.821
$13,159.620
$19,829,993
$4,982.552
$1,687.821
$13,159.620
$19,829,993
Construction Commencements (2025 -2026)
A chart outlining all projects that commenced construction in 2025 and those anticipated to begin
during the 2026 calendar year was presented.Refer to Exhibit C.
Projects Update
The following Tranche 1 projects were discussed during the September 18 and November 20,2025
meetings.Refer to www.GOMBinfo.com for further details and information for each of the following:
#01 72°St.Community Complex
#15 Bayshore Park
#23 Pedestrian Bridge
#27 Log Cabin
#29 West Lots
#30 Skate Park
#40 41 st St Corridor
#42 Bayshore Traffic Calming
#42 Normandy Isle Traffic Calming
#45 Fire Station #1
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 6 of9
IMPLEMENTATION STATUS --2022 ARTS &CULTURE BONDS
Project Dashboard and Program Progress Report
The G.O.Bond for Arts &Culture was fully funded on July 27,2023.As of November 20,2025,18
out of the 20 Tranche 1 projects are in some form of "Active"status and 2 have been completed.
Chart 8 below shows the full breakdown by Category and Project Status.
Chart 8
TRANCHE 1
PROJECT ACTIVITY
Tranche I
20
•100%of all Tranche 1 Projects are
Complete or Active=20
PROJECT CATEGORY
City-Owned Non-City Owned Other Projects AI
OJ£CT Complete 0 2
STATUS Active 11 18
Pending 0 0 0 0
Future 0 0
Al 11 6 4 21
Approximately $22.2 million has been expended and another $3.9 million has been encumbered
for a total of $26.1 million out of the $107.2 million available Tranche 1 funds.Chart 9 below
shows the full breakdown of the expenditures broken down by Category.
Chart 9
PROJECT EXPENDITURES
Tranche 1
$107.24
future
$57.3M'
Spent$22.2M
Encumbered$3.9M
•24%of all Tranche I Funds are Spent
or Encumbered=$26.1 out of $107.2M
PRGRAM Spent
FUNDS numbered
Available
Future
Total
PROJECT CATEGORY
City-Owned Non-CityOwned Other Projects Total
$0262607 $446434¢$400291 $22.231.532
$3,2&4,177 $$58615 $3,870,191
$04,442.00 $1920,56¢$5,/46,94 $81,109,066
$49.565.000 $3500.00 $4,235.000 $57,300,000
$126,573,789 $23367.,000 $14,570,000 $164,510,789
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 7 of9
Tranche 1 Progress
Most of the 20 projects in Tranche 1 have different components which are considered distinct
projects,or "subprojects",that are tracked separately and have separate budgets,procurement,
and implementation schedules.The Tranche 1 Subproject Activity Summary depicted in Chart 10
below and 11 on the next page,summarize the subproject activity into Status,Category and Funding
amount.
Subproject Tracking Summary by Phase
Of the 48 total subprojects in Tranche 1,12 (25%)have been completed,11 (23%)are under
construction,17 (35%)are in a design phase,4 (8%)are in a planning phase,and 4 (8%)are
pending.Chart 10 below shows the status of all subprojects broken down by Phase and Category.
Chart 10
TRANCHE1
SUBPROJECT ACTIVITY
Tranche 1
100%
Construction23%
Design
35%
Planning
•91%of all Tl Subprojects are
Complete or Active =44 out of 48
SUBPROJECT CATEGORY
City Owned Non-City Owned Other Projects All
SUBPROJECT Complete 8 3 12
STATUS Construction 7 3 11
Design 13 2 2 17
Planning 4 0 0 4
Pending 2 0 2 4
All 34 6 8 48
The total expenditures for each of the subproject categories are outlined in Chart 11 on the following
page.As of November 20,2025,the 12 completed subprojects equate to approximately $8.8 million
(8%)of the tranche 1 budget,$25.7 million (24%)equate to subprojects that are under construction,
$32.2 million (30%)equate to subprojects that are in the design phase,$37.3 million (35%)equate
to subprojects that are in the planning phase,and $3.2 million (3%)has been earmarked for
pending subprojects.For a full breakdown,by project,refer to attached Exhibit D.
G.O.Bond Program -Project Implementation Update No.39
December 3,2025
Page 8 of9
Chart 11
SUBPROJECT EXPENDITURES
Tranche l
100%Complete8%
Construction
24%
Design30%
Planning
Pending3%
•32%of the value of all Tl Projects are
Complete or Under Construction
SUBPROJECT Complete
FUNDS Construction
Design
Planning
Pending
Total
SUBPROJECT CATEGORY
CityOwned Non-City Owned Other Projects Total
$1.509.312 $4,000,000 $3,295,416 $8,804,728
$11.368598 $13.617,000 $705.821 $25,691,419
$26.485.989 $2.250.000 $3,454,316 $32,190.305
$37.341.690 $0 $0 $37.,341.690
$303.200 $0 $2.879.447 $3,182.647
$77,008,789 $19.8617.000 $10,33.000 $107,210,789
Subproject Progress
Chart 12 below compares the status of subprojects from previous months to the current month,
dating back to March 2024.
Chart 12
SUMMARY SUB-PROJECTS-TRANCHE 1
3/7/24 7/18/24 9/19/24 12/19/24 3/12/25 5/15/25 9/18/25 11/20/25 VARIANCENo.%No.%No.%No.%No.%No.%No.%No.%
ACTIVE/COMPLETE 40 87%42 89%44 94%45 96%43 91%43 91%43 91%44 92%1
CONSTRUCTION 6 6%8 17%10 21%10 21%10 21%9 19%11 23%11 23%0
PLANNING I DESIGN 33 30%28 60%28 60%29 62%24 51%24 51%21 45%21 44%0
CLOSED/COMPLETE 1 1%6 13%6 13%6 13%9 19%10 21%11 23%12 25%1
REMAINING 6 13%5 11%3 6%2 4%4 9%4 9%4 9%4 8%0
I TOTAL SUB-PROJECTS 46 47 47 47 47 47 47 48
•1118 Aquatic Sculpture Park-PH3 added
••1111 NBOC Structural Repairs added
Construction Commencements (2025 -2026)
A chart outlining all projects that commenced construction in 2025 and those anticipated to begin
during the 2026 calendar year was presented.Refer to Exhibit E.
Tranche 1 Projects Update
The following Tranche 1 project updates were discussed during the September 18 and November
20,2025 meetings.Refer to www.GOMBinfo.com for further details and information for each of
the following:
#04 Fillmore
#10 Byron Carlyle Theater
#11 North Beach Oceanfront Center
#13 Collins Park Cultural Center
#14 MB Bandshell Building Improvements
G.0.Bond Program -Project Implementation Update No.39
December 3,2025
Page 9 of 9
Community Information and Outreach
The Administration continues to perform public information and outreach activities through various
community meetings,Constant Contact emails,direct mailings,publications,and the City's social
media platforms.
Several project advisories have also been circulated via Constant Contact to keep residents
informed about ongoing construction activities in their neighborhoods.These updates have covered
a range of projects including Street Paving,Sidewalk Repairs,Seawalls,Street Lighting,Bayshore
Park,23°Street Improvements,La Gorce Park Playground,Flamingo Park Softball Field,and
Pedestrian Bridge.In addition,a Virtual Public Meeting for the Log Cabin Project was held on
September 4,followed by the Grand Opening of Bayshore Park on September 28,and the
inauguration of The Reefline (Aquatic Sculpture Park)on October 21.
The website,www.GOMBlnfo.com,continues to be updated with press releases,project photos,
implementation updates,and more.For additional information,please contact Thais Vieira at
thaisvieira@miamibeachfl.gov or via cellphone at (305)216-1000.
Attachments:
Exhibit A -GOB Oversight Committee Agenda for September 18,2025
Exhibit A1-GOB Oversight Committee Agenda for November 20,2025
Exhibit B -2018 GOB Subproject and Project List by Phase
Exhibit C -2018 GOB Construction Commencement Graph
Exhibit D -Arts &Culture Bond Subproject and Project List by Phase
~¥Arts &Culture Bond Construction Commencement Graph
F:\CMGR\$ALL\GO Bond Program\LTC Program Updates\202514 -Nov\G.O.Bond Program -Project Implementation Update No.39.docx
EXHIBIT A
GO
MIAMIBEACH
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo,Chair
Thais Vieira,Liaison
AGENDA
September 18,2025
I.
II.
Ill.
IV.
Roll Call and Introductions
Committee Business
•New Member
•Adoption of Meeting Minutes from 05-15-25 and 07-8-25
Tranche 2 -New Declaration of Intent to Issue
Funding Charts
All
Karen Rivo
TV/JG
TV/JG
4:00pm
4:05pm
4:10pm
4:20pm
2018 G.O.Bonds
V.
VI.
VII.
Program General Status Update
2018 Bonds Projects Update
•72a St (D),FSI (D),41St Corridor (D)Log Cabin (D),
West Lots (P),Skate Park (PN)
Public Comment
Thais Vieira
CIP/Parks
Public
4:40pm
4:45pm
5:10pm
2022 G.O.Bonds for Arts &Culture
VIII.
IX.
X.
XI.
XII.
Arts &Culture Program General Status Update
2022 Bonds Projects Update
•Fillmore (P),Byron (P),Collins Park Cultural Ctr.(P)
Community Outreach
•Recent Past Public Meetings /Upcoming Events
Public Comment
Adjournment
FAC/CIP/ED
Thais Vieira
KP/TV
Public
5:20pm
5:25pm
5:45pm
5:50pm
6:00pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City
Manager and City Commission from a macro perspective regarding the timely progress,overall goals,costs,including
financial efficiencies,and the timely completion of General Obligation Bond Program projects approved by the voters
in the City of Miami Beach.The Committee shall have the following powers &duties:
l.Receive input from the public,the City Administration,City consultants,and the City's Inspector General,as
needed,to make recommendations relative to the overall timing,cost efficiencies,and prioritization of the G.O.
Bond Program projects.
2.Provide general oversight to ensure that G.O.Bond Program project timelines,budgets (including cost efficiencies)
are prioritized and achieved,and that the projects are completed in accordance with the scope of work
approved by the voters.
3.Review City staff and G.O.Bond Program project manager's progress reports and provide monthly reports to the
City Commission.
Legend:(P)Planning Phase,(D)Design Phase,(C)Construction Phase,(PN)Pending,(V)Various Phases,(F)Future Tranche
EXHIBIT AIGO
MIAMIBEACH
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo,Chair
Thais Vieira,Liaison
AGENDA
November 20,2025
I.
II.
Ill.
Roll Call and Introductions
Committee Business
•Committee Members re-appointments
•Adoption of Meeting Minutes from 09-18-25
Tranche 2 -New Declaration of Intent to Issue (Update)
All
Karen Rivo
Thais Vieira
4:00pm
4:05pm
4:10pm
2022 G.O.Bonds for Arts &Culture
IV.Arts &Culture Program General Status Update Thais Vieira 4:15pm
V.2022 Bonds Projects Update FACCIP 4:20pm
•Fillmore (P),Byron (P),NBOC (V),Bandshell (D),
Bass Museum Addition (P)
VI.Public Comment Public 4:55pm
2018 G.O.Bonds
VII.Program General Status Update Thais Vieira 5:05pm
VIII.2018 Bonds Projects Update CIP/Transp.5:10pm
•Bayshore Park,FSl (D),Log Cabin (D),Ped Bridge (C),
Traffic Calming (D)
IX.Community Outreach KP/TV 5:45pm
•Recent Past Public Meetings/Upcoming Events
X.Public Comment Public 5:50pm
XI.Adjournment 6:00pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City
Manager and City Commission from a macro perspective regarding the timely progress,overall goals,costs,including
financial efficiencies,and the timely completion of General Obligation Bond Program projects approved by the voters
in the City of Miami Beach.The Committee shall have the following powers &duties:
1.Receive input from the public,the City Administration,City consultants,and the City's Inspector General,as
needed,to make recommendations relative to the overall timing,cost efficiencies,and prioritization of the G.O.
Bond Program projects.
2.Provide general oversight to ensure that G.O.Bond Program project timelines,budgets (including cost efficiencies)
are prioritized and achieved,and that the projects are completed in accordance with the scope of work
approved by the voters.
3.Review City staff and G.O.Bond Program project manager's progress reports and provide monthly reports to the
City Commission.
Legend:(P)Planning Phase,(D)Design Phase,(C)Construction Phase,(PN)Pending,(V)Various Phases,(F)Future Tranche
EXHIBIT B
G.O.BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Date 1'Count %Count $Budget $Encumbered $Spent %Spent $Available
Closed #53 PORTABLE BOLLARDS Public Safety Police 1 07-31-2019 599,916 599,915
Closed #17 POLO PARK Parks Parks &Recreation 1 08-11-2019 493,673 493,673
Closed #19 SOUNDSCAPE 4K TECHNOLOGY Parks Tourism &Culture 1 09-30-2019 3,748,495 3,748,495
Closed #13 NORTH SHORE LIGHTS &PAINT Parks Property Management 1 10-14-2019 130,300 130,210 89
Closed #52 TATUM PARK LED LIGHTING Public Safety Parks &Recreation 1 10-14-2019 52,758 52,758
Closed #52 CRESPI PARK LED LIGHTING Public Safety Parks &Recreation 1 10-21-2019 41,780 41,780
Closed #52 STILLWATER PARK LED LIGHTING Public Safety Parks &Recreation 1 10-21-2019 41,780 41,780
Closed #26 COLONY THEATRE ROOF Parks Property Management 1 10-24-2019 299,650 299,650
Closed #21 STILLWATER PARK Parks Parks &Recreation 1 11-08-2019 142,440 142,440
Closed #3 CRESPI PARK Parks Parks &Recreation 1 11-09-2019 184,919 184,919
Closed #18 SCOTT RAKOW PAINT Parks Property Management 1 11-12-2019 116,776 116,776
Closed #47 MACARTHUR CSWY READERS Public Safety Police 1 11-28-2019 64,904 64,904
Closed #52 NORMANDY ISLE PARK LED LIGHTING Public Safety Parks &Recreation 1 12-02-2019 212,599 212,593 5
Closed #18 SCOTT RAKOW HVAC Parks Property Management 1 12-06-2019 137,303 137,302
Closed #13 NORTH SHORE ROOF Parks Property Management 1 12-16-2019 375,000 374,722 276
Closed #18 SCOTT RAKOW ROOF Parks Property Management 1 01-05-2020 127,218 127,217
Closed #26 MIAMI CITY BALLET ROOF Parks Property Management 1 01-15-2020 758,824 758,824
Closed #13 NORTH SHORE CAMERAS Parks Property Management 1 02-04-2020 205,699 60,858 144,841
Closed #18 SCOTT RAKOW CAMERAS Parks Property Management 1 02-05-2020 110,660 110,659
Closed #32 PALM &HIBISCUS LANDSCAPING Infrastructure Capital Improvement Projects 1 03-25-2020 1,000,000 1,000,000
Closed #18 SCOTT RAKOW WINDOWS Parks Property Management 1 04-16-2020 373,420 198,887 174,531
Closed #26 FILLMORE ROOF Parks Property Management 1 05-15-2020 1,874,156 1,874,155
Closed #4 FAIRWAY PARK PAVILION Parks Parks &Recreation 1 05-15-2020 50,000 35,044 14,955
Closed #2 COLLINS PARK Parks Parks &Recreation 1 05-28-2020 557,287 557,287
Closed #13 NORTH SHORE GENERATOR Parks Property Management 1 06-30-2020 524,999 503,861 21,138
Closed #18 SCOTT RAKOW GENERATOR Parks Property Management 1 06-30-2020 729,719 729,717
Closed #18 SCOTT RAKOW POOL Parks Parks &Recreation 1 07-06-2020 977,105 977,104
Closed #47 71 ST.ENTRANCE READERS Public Safety Police 1 07-12-2020 31,582 31,582
Closed #47 JULIA TUTTLE CSWY READERS Public Safety Police 1 09-21-2020 89,186 89,185 1
Closed #57 LUMMUS PARK/OCEAN DRIVE CAMERAS Public Safety Police 1 02-28-2021 824,845 824,845
Closed #4 FAIRWAY PARK FENCE Parks Parks &Recreation 1 03-10-2021 209,999 205,917 4,082
Closed #40 41 STREET LIGHTING UPGRADES Infrastructure Public Works Department 1 03-13-2021 102,999 99,173 3,825
Closed #56 CAMERAS-BEACHWALK Public Safety Police 1 04-02-2021 693,219 693,218
Closed #24 MIDDLE BEACH BEACHWALK PH3 Parks Capital Improvement Projects 1 12-27-2021 4,214,179 4,214,178
Closed #42 NAUTILUS TRAFFIC CALMING Infrastructure Transportation 1 01-14-2022 739,499 712,631 26,867
Closed #18 SCOTT RAKOW GYM FLOORS Parks Parks &Recreation 1 01-21-2022 322,451 322,451
Closed #12N.BEACH OCEANSIDE BEACHWALK Parks Capital Improvement Projects 1 06-06-2022 1,999,999 1,999,999
Closed #SO DADE BLVD.CORRIDOR CAMERAS Public Safety Police 1 08-03-2022 165,674 131,420 34,254
Closed #9 MSD PLAYGROUND AND SIDEWALKS Parks Parks &Recreation 1 08-05-2022 553,999 528,513 25,485
Closed #18 SCOTT RAKOW OTHER FLOORS Parks Parks &Recreation 1 10-28-2022 203,798 203,798
Closed #52 FLAMINGO PARK LED LIGHTING Public Safety Parks &Recreation 1 11-14-2022 1,044,143 1,044,143
Closed #SO 71 STREET CORRIDOR CAMERAS Public Safety Police 1 12-22-2022 211,999 85,307 126,692
Closed #53 CONVENTION CENTER BOLLARDS Public Safety Public Works Department 1 09-07-2023 783,128 782,013 1,115
Closed #53 SOUNDSCAPE PARK BOLLARDS Public Safety Public Works Department 1 12-01-2023 225,198 223,665 1,533
Closed #53 SOUTH POINTE PARK BOLLARDS Public Safety Public Works Department 1 12-11-2023 391,668 335,362 56,306
CITY OF MIAMI BEACH 11/14/2025 -2:52 PM
G.O.BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Date 1'Count %Count $Budget $Encumbered $Spent %Spent $Available
Closed #34 ABOVE GROUND IMPROV-INDIAN CRK Infrastructure Public Works Department 1 03-30-2024 1,112,000 1,111,636 363
Closed #37 SIDEWALKS -TRANCHE 1 Infrastructure Public Works Department 1 12-31-2024 3,960,066 3,960,060 5
Closed #38 STREETS -TRANCHE 1 Infrastructure Public Works Department 1 12-31-2024 5,800,000 5,800,000
Closed #13 N.S.PLAYGROUND Parks Parks &Recreation 1 01-31-2025 794,999 512,455 282,544
Closed #9 MSD PARK LIGHTING Parks Parks &Recreation 1 05-08-2025 127,999 127,999
Closed Sum $38,534,009 $37,615,080 $918,907
Closed Count 50 54%
Complete #49 PUBLIC SAFETY RADIO SYSTEM Public Safety Fire 1 04-30-2022 9,700,000 1,167,519 8,525,827 6,653
Complete #10 MAURICE GIBB PARK Parks Capital Improvement Projects 1 04-21-2025 5,251,274 574,394 4,673,833 3,046
Complete #42 PALM VIEW TRAFFIC CALMING Infrastructure Transportation 1 09-30-2025 86,349 46,427 39,922
Complete #48 REAL TIME INTELLIGENCE CENTER Public Safety Property Management 1 09-30-2025 701,460 692,603 8,856
Complete #19 SOUNDSCAPE PARK:SOUND SYSTEM Parks Property Management 1 09-30-2025 1,600,000 923,035 676,964
Complete #52 FLA.PARK LED LIGHTING -FIELDS Public Safety Capital Improvement Projects 1 11-20-2025 1,655,856 335,000 574,819 746,037
Complete #15 PAR 3 /BAYSHORE PARK Parks Capital Improvement Projects 1 11-26-2025 20,166,104 20,098,218 67,885
Complete Sum $40,058,194 $2,077,811 $36,422,542 $1,557,835
Complete Count 8 9%
Construction #57 COLLINS AVE/WASH AVE CAMERAS Public Safety Police 1 11-30-2025 665,154 112,198 550,157 2,799
Construction #7 LA GORCE PARK Parks Parks &Recreation 1 12-01-2025 150,000 129,593 18,206 2,200
Construction #39 SEAWALLS/SHORELINES -TRANCHE 1 Infrastructure Public Works Department 1 12-30-2025 4,999,998 68,018 4,931,974 5
Construction #5 FLAMINGO PARK SOFTBALL FIELD Parks Capital Improvement Projects 1 02-17-2026 5,872,892 4,338,034 1,534,857
Construction #5 FLAMINGO PARK LODGE Parks Capital Improvement Projects 1 03-01-2026 1,116,674 752,549 355,962 8,162
Construction #43 23 ST.STREETSCAPE IMPROVEMENTS Infrastructure Capital Improvement Projects 1 04-02-2026 2,832,152 1,623,879 1,057,906 150,367
Construction #33 TREE PLANTING -TRANCHE 1 Infrastructure Environmental 1 04-30-2026 2,770,000 2,533,347 236,652
Construction #47 OTHER READERS CITYWIDE Public Safety Police 1 06-01-2026 1,390,000 287,030 959,960 143,009
Construction #55 STREET LIGHTING -TRANCHE 1 Public Safety Public Works Department 1 07-24-2026 3,499,999 1,816,595 756,910 926,493
Construction #50 ALTON RD.CORRIDOR CAMERAS Public Safety Police 1 07-31-2026 211,999 58,507 113,025 40,466
Construction #23 PEDESTRIAN BRIDGE Parks Capital Improvement Projects 1 02-27-2027 8,999,999 7,160,982 1,838,409 606
Construction Sum $32,508,867 $16,347,385 $14,650,713 $1,510,759
Construction Count 11 12%
Design #48 POLICE HQ FACILITY -TRANCHE 1 Public Safety Property Management 1,2 12-31-2025 5,871,811 157,694 2,052,944 3,661,172
Design #5 FLAMINGO PARK MASTER PLAN Parks Capital Improvement Projects 1 08-23-2026 8,160,431 224,909 2,187,728 5,747,794
Design #43 CHASE AVE/34 ST SHARED USE PATH Infrastructure Capital Improvement Projects 1 11-23-2026 829,998 36,078 484,329 309,591
Design #8 LUMMUS PARK Parks Capital Improvement Projects 1 11-26-2026 4,736,999 677,750 522,777 3,536,471
Design #25 WATERWAY RESTORATION Parks Capital Improvement Projects 1,2 03-11-2027 499,999 298,328 121,756 79,915
Design #54 MARINE PATROL FACILITY Public Safety Capital Improvement Projects 1,2 06-17-2027 1,999,998 234,960 612,633 1,152,405
Design #27 LOG CABIN Parks Capital Improvement Projects 1 06-25-2027 1,075,999 149,446 40,857 885,696
Design #42 NORMANDY ISLE TRAFFIC CALMING Infrastructure Transportation 1 07-10-2027 293,999 17,747 254,989 21,263
Design #42 BAYSHORE TRAFFIC CALMING -T1 Infrastructure Transportation 1 07-10-2027 380,148 11,838 340,157 28,153
Design #50 41 ST.CORRIDOR CAMERAS Public Safety Capital Improvement Projects 1 06-09-2028 235,324 21,575 213,748
Design #45 FIRE STATION #1 Public Safety Capital Improvement Projects 1,2 07-03-2028 5,746,057 1,797,899 3,470,427 477,730
Design #1 72 ST COMMUNITY COMPLEX Parks Capital Improvement Projects 1,2 07-24-2028 10,800,000 3,281,919 5,877,853 1,640,227
Design #40 41 ST CORRIDOR IMPROVEMENTS Infrastructure Capital Improvement Projects 1,2 08-08-2028 2,819,595 903,490 1,805,056 111,048
Design #31 OCEAN DRIVE CORRIDOR Infrastructure Capital Improvement Projects 1,2 04-22-2029 1,548,999 648,638 800,360 100,000
Design Sum $44,999,357 $8,440,696 $18,593,441 $17,965,213
Design Count 14 15%
CITY OF MIAMI BEACH 11/14/2025-2:52 PM
G.O.BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Tranche Anticipated End Date 1'Count %Count $Budget $Encumbered $Spent %Spent $Available
Planning #36 WASHINGTON AVE.CORRIDOR Infrastructure Public Works Department 1,2 01-31-2026 b 397,616 225,900 171,716
Planning #5 FLAMINGO YOUTH CENTER FACILITY Parks Capital Improvement Projects 1,2 03-13-2028 250,000 167,701 33,880 48,418
Planning #23 BAY GARDEN MANOR LINK Parks Capital Improvement Projects 1,2 12-22-2028 269,999 24,400 224,907 20,692
Planning #23 BAYVIEW TERRACE LINK Parks Capital Improvement Projects 1,2 02-15-2029 169,999 23,209 146,637 152
Planning #23 SOUTH BAY CLUB LINK Parks Capital Improvement Projects 1,2 04-26-2029 559,998 12,458 370,381 177,159
Planning #46 OCEAN RESCUE NOBE FACILITY Public Safety Capital Improvement Projects 1,2 01-09-2031 999,999 34,986 330,358 634,654
Planning #29 WEST LOTS -TRANCHE 1 Parks Parks &Recreation 1 (blank)1,000,000 1,000,000
Planning Sum $3,647,611 $262,754 $1,332,063 $2,052,791
Planning Count 7 8%
Pending #30 SKATE PARK Parks Parks &Recreation 1,2 (blank)532,999 49,708 39,726 443,565
Pending #18 SCOTT RAKOW ICE RINK FLOORS Parks Parks &Recreation 1 (blank)413,640 413,640
Pending Sum $946,639 $49,708 $39,726 $857,205
Pending Count 2 2%
Tranche 1 Total 92 100%160,694,677 27,178,354 108,653,565 24,862,710
Construction #33 TREE PLANTING -TRANCHE 2 Infrastructure Environmental 2 10-01-2029 2,229,999 27,807 52,818 2,149,374
Construction #37 SIDEWALKS -TRANCHE 2 Infrastructure Public Works Department 2 10-01-2029 3,500,000 620,031 1,610,088 1,269,879
Construction #38 STREETS -TRANCHE 2 Infrastructure Public Works Department 2 10-01-2029 8,600,000 495,920 2,079,438 6,024,640
Construction #39 SEAWALLS/SHORELINES -TRANCHE 2 Infrastructure Public Works Department 2 10-01-2029 4,999,999 544,063 1,237,619 3,218,316
Construction Sum $19,329,998 $1,687,821 $4,979,963 $12,662,209
Construction Count 4 80%
Design #42 BAYSHORE TRAFFIC CALMING -T2 Infrastructure Transportation 2 04-01-2027 500,000 2,589 497,411
Design Sum $500,000 $0 $2,589 $497,411
Design Count 1 20%
Tranche 2 Total 5 100%19,829,998 1,687,821 4,982,552 13,159,620
Grand Total 97 $180,524,675 $28,866,175 $113,636,117 $38,022,330
"b"Represents the estimated end date of the current phase.
CITY OF MIAMI BEACH 11/14/2025 -2:52 PM
EXHIBIT C
2025 /2026 CONSTRUCTION COMMENCEMENTS
2018 GOB PROGRAM
Project Name Dept 2024 2025 2026
PARKS
01 Q2 Q3 Q4 Q1 02 03 Q4 Q1 02 03 Q4
Pedestrian Bridge
Flamingo Pk Softball Field
MSD Park Lighting (complete)
La Goree Park
Flamingo Park Butterfly Garden
Flamingo Park Baseball Stadium
Log Cabin
Normandy Isle Traffic Calming
South Pointe Park
INFRASTRUCTURE
CIP
CIP
Parks
Parks
CIP
CIP
CIP
Transp/CIP
Parks
23rd St Streetscape
Chase Ave Shared Use Path
Bayshore Traffic Calming
41st Street Corridor Improvements
PUBLIC SAFETY
CIP
Transp/CIP
Transp/CIP
CIP
Street Lighting
Flamingo Park LED Lighting (Fields)
Marine Patrol Facility
LEGEND
PWD
CIP
CIP
Expected construction commencement (as reported in Feb 2024 or later)
Actual construction commencement
Current expected construction commencement (no change from last meeting)
Current expected construction commencement (changed from last meeting)
Bold Text Indicates projects that have commenced in the 2025 calendar year
Red Text Indicates projects that have changed from last meeting
Blue Text Indicates new project (added after last meeting)
EXHIBIT D
G.O.BOND ARTS AND CULTURE PROJECT LIST BY PHASE
Active Phase Project Name Department Tranche Anticipated End Date 1'Count %Count $Budget $Encumbered $Spent %Spent $Available
Closed 05 COLONY ELECTRICAL IMPROVEMENTS Facilities Management 1 01-05-2024 134,200 128,355 5,845
Closed 14 MB BANDSHELL CANOPY PROJECTION MAPPING Grant -Facilities Management 1 01-30-2024 153,000 153,000
Closed 07 ART DECO LADDER/ROOF ACCESS Facilities Management 1 05-10-2024 15,600 1,946 13,654
Closed 01 BASS AUTOMATIC SHADE SYSTEM Facilities Management 1 06-18-2024 230,600 127,711 102,889
Closed 01 BASS LIGHTING IMPROVEMENTS Facilities Management 1 01-30-2025 463,000 389,058 73,942
Closed 17 NORTH SHORE ARTISTIC PLAYGROUND Parks &Recreation 1 01-31-2025 206,179 202,579 3,600
Closed 03 WF HOUSING {COLLINS PARK)Grant -CIP 1 05-08-2025 4,000,000 4,000,000
Closed 01 BASS WI-Fl ACCESS POINTS Facilities Management 1 05-30-2025 190,310 173,757 16,553
Closed 05 COLONY FF&E Facilities Management 1 12-09-2025 32,102 32,102
Closed Count 9 19%
Complete 20 MB CLASSICAL MUSIC FESTIVAL Loan 1 02-29-2024 1,500,000 1,500,000
Complete 01 BASS MECHANICAL IMPROVEMENTS Facilities Management 1 01-30-2025 290,500 9,815 139,176 141,510
Complete 18 AQUATIC SCULPTURE PARK-PH.1 Grant -Facilities Management 1 10-31-2025 1,589,237 1,429,657 159,580
Complete Sum 3,379,737 9,815 3,068,833 301,089
Complete Count 3 6%
Construction 01 BASS FIRE ALARM SYSTEM Facilities Management 1 11-28-2025 2,305,900 11,463 653,472 1,640,965
Construction 17 LA GORCE ARTISTIC PLAYGROUND Parks &Recreation 1 12-02-2025 705,821 586,015 118,685 1,121
Construction 05 COLONY TECHNOLOGY IMPROV.Grant -Facilities Management 1 12-31-2025 2,594,000 1,505,038 1,088,962
Construction 09 HOLOCAUST MEMORIAL MB Grant -Facilities Management 1 12-31-2025 7,150,000 1,659,564 5,490,436
Construction 07 ART DECO LIGHTING Facilities Management 1 01-14-2026 156,000 142,221 1,154 12,625
Construction 19 COLLINS PARK ROTUNDA Capital Improvement Projects 1 02-27-2026 4,140,000 1,498,390 2,447,464 194,146
Construction 05 COLONY SECURITY &COMM.SYSTEMS Facilities Management 1 03-03-2026 286,900 26,386 2,121 258,394
Construction 05 COLONY BLDG.IMPROVEMENTS Facilities Management 1,2 04-06-2026 1,052,798 136,738 235,494 680,566
Construction 01 BASS MISCELLANEOUS IMPROVEMENTS Facilities Management 1 05-13-2026 833,000 62,506 419,391 351,103
Construction 12 HISPANIC COMMUNITY CNTR.Grant -Facilities Management 1 06-30-2026 767,000 556,233 210,767
Construction 08 NEW WORLD SYMPHONY Grant -Facilities Management 1 10-09-2026 5,700,000 2,551,941 3,148,059
Construction Sum 25,691,419 2,463,718 10,150,558 13,077,143
Construction Count 11 23%
Design 16 JEWISH MUSEUM OF FLORIDA Grant -Facilities Management 1 07-01-2026 750,000 750,000
Design 17 S.POINTE ARTISTIC PLAYGROUND Parks &Recreation 1 07-01-2026 1,126,000 9,554 1,116,446
Design 18 AQUATIC SCULPTURE PARK-PH.2 Grant -Facilities Management 1 07-03-2026 2,328,316 742,015 1,586,301
Design 11 NBOC CATERING KITCHEN EXPANSION Facilities Management 1 07-07-2026 392,900 156,316 13,971 222,613
Design 11 NBOC COMMUNITY ROOM FURNITURE Facilities Management 1 08-07-2026 b 78,600 68,204 1,504 8,892
Design 11 NBOC SOUND SYSTEM &ACOUSTICS Facilities Management 1 10-07-2026 408,300 84,404 54,755 269,141
Design 02 MCB ELECTRICAL IMPROVEMENTS Facilities Management 1 02-26-2027 393,500 7,305 386,195
Design 02 MCB ELEVATOR MODERNIZATION Facilities Management 1 02-26-2027 524,800 1,119 523,681
Design 02 MCB FF&E Facilities Management 1 02-26-2027 719,100 13,350 705,750
Design 02 MCB MECHANICAL IMPROVEMENTS Facilities Management 1 02-26-2027 900,000 16,709 883,291
Design 02 MCB MISCELLANEOUS IMPROVEMENTS Facilities Management 1 02-26-2027 1,944,600 36,102 1,908,498
Design 02 MCB TECH.IMPROVEMENTS Grant -Facilities Management 1 02-26-2027 7,518,000 923,402 6,594,598
Design 07 ART DECO MUSEUM EXPANSION Capital Improvement Projects 1 08-21-2027 1,248,400 358,519 148,026 741,856
Design 06 MIAMI BEACH BOTANICAL GARDEN Capital Improvement Projects 1 05-14-2028 6,270,000 52,258 374,978 5,842,764
Design 14 MB BANDSHELL BUILDING IMPROVEMENTS Capital Improvement Projects 1 05-26-2028 3,617,000 305,956 102,165 3,208,879
Design 11 NBOC STRUCTURAL REPAIRS Facilities Management 1 {blank)2,470,789 310,284 259,780 1,900,725
Design 15 THE WOLFSONIAN Grant -Facilities Management 1,2 {blank)1,500,000 333,526 1,166,474
Design Sum 32,190,305 1,335,941 3,038,259 27,816,105
Design Count 17 35%
CITY OF MIAMI BEACH 11/14/2025-2.30 PM
G.O.BOND ARTS AND CULTURE PROJECT LIST BY PHASE
Active Phase Project Name Department Tranche Anticipated End Date 1'Count %Count $Budget $Encumbered $Spent %Spent $Available
Planning 10 BYRON CARLYLE THEATER Facilities Management 1,2 12-31-2025 b 10,590,000 77,134 10,512,866
Planning 13 COLLINS PARK CULTURAL CNTR.Facilities Management 1 12-31-2025 b 7,670,000 65,466 7,604,534
Planning 01 BASS MUSEUM MULTIPURPOSE ADDITION Capital Improvement Projects 1,2 09-21-2029 6,675,690 52,047 619,057 6,004,586
Planning 04 FILLMORE {JACKIE GLEASON)Facilities Management 1,2 {blank)12,406,000 90,357 12,315,643
Planning Sum 37,341,690 52,047 852,014 36,437,629
Planning Count 4 8%
Pending 11 NBOC DOORS &WINDOWS SEAL Facilities Management 1 (blank)161,800 3,662 1,890 156,248
Pending 11 NBOC PAINTING Facilities Management 1 {blank)141,400 5,008 66,300 70,093
Pending 17 OTHERARTISTIC PLAYGROUNDS Parks &Recreation 1 {blank)1,797,000 1,797,000
Pending 18 AQUATIC SCULPTURE PARK-PH.3 Grant -Facilities Management 1 {blank)1,082,447 1,082,447
Pending Sum 3,182,647 8,670 68,189 3,105,788
Pending Count 4 8%
48 100%$107,210,789 $3,870,191 $22,386,362 21%$80,954,236
"b"Represents anticipitated end date of current phase
CITY OF MIAMI BEACH 11/14/2025-2.30 PM
EXHIBIT E
2025/2026 CONSTRUCTION COMMENCEMENTS
ARTS &CULTURE GOB PROGRAM
Project Name Dept 2024 2025 2026
Holocaust Memorial
Bass Technology -Wifi
Reefline (Ph.1 Fabrication)
La Goree Park-~
Colony Bldg.Improvements~~-----
Colony Security/Comm.System~-~---~
NBOC Kitchen
NBOC Furniture
NBOC Sound/Acoustics
NBOC Structural Repairs
Jewish Museum
S.Pointe Park Artistic Playground
LEGEND
Grant
Fae.
Grant
Parks
Fae.
Fae.
Fae.
Fae.
Fae.
Fae.
Grant
Parks
Q2 03 Q4 01 02 03 Q4
Expected construction commencement as reported in May 2024 (or later}
Actual construction commencement
Current expected construction commencement (no change from last meeting}
Current expected construction commencement (changed from last meeting}
Bold Text Indicates projects that have commenced in the 2025 calendar year
Red Text Indicates projects that have changed from last meeting
Blue Text Indicates new project (added after last meeting}