HomeMy WebLinkAboutResolution 2026-34114RESOLUTION NO. 2026-34114
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, ADOPTING THE SECOND
AMENDMENT TO THE CAPITAL BUDGET FOR FISCAL YEAR 2026 AS
SET FORTH IN ATTACHMENTS A, "PROJECTS"; B, "SOURCE OF
FUNDS"; AND C "PROGRAMS."
WHEREAS, on September 30, 2025, the final Capital Improvement Plan (CIP) for
Fiscal Years 2026 — 2030 and the final Capital Budget for FY 2026 was adopted via
Resolution No. 2025-33948; and
WHEREAS, on December 17, 2025, the First Amendment to the Capital Budget
for FY 2026 was adopted via Resolution No. 2025-34040; and
WHEREAS, it is recommended by the Administration that the FY 2026 Capital
Budget be amended to increase appropriations by $6,782,000.00 and re -align
$6,173,873.71 between existing projects as highlighted in Attachments A, "Projects"; B,
"Source of Funds"; and C, "Programs."
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that following a duly noticed
public hearing on February 5, 2026, the Mayor and City Commission hereby adopt the
Second Amendment to the Capital Budget for Fiscal Year 2026 as set forth in
Attachments A, "Projects"; B, "Source of Funds"; and C, "Programs."
PASSED AND ADOPTED this 5th day of February 2026.
ATTEST:
FEB 0 9 2026 Steven Meiner, Mayor
Y
Rafael E. Granado, City Clerk
y; APPROVED AS TO
ORPOUTED = FORM & LANGUAGE
11 `. ;`�' & FOR EXECUTION
i1z1/zoz4
City Attomey Date
FY 2026 CAPITAL
A
BUDGET
PROJECTSATTACHMENT
AMENDED
.
Amended
Revised
Capital Project Name
FY 2026
Amended 2/5/2026
FY 2026
Capital Budget
Capital Budget
WASTEWATER STATIONS REHABILITATION (Project #
$ 43,717,282.01
(4,829,873.71)
$ 38,887,408.30
20619)
FDOTALTON ROAD UTILITIES RELOCATION (Project #
20,137,625.02
4,291,410.87
24,429,035.89
20527)
WATER & WASTEWATER MAINS AND REHABILITATION
(Project # 28520)
81,172,674.82
538,462.84
81,711,137.66
FIRE ADMIN BUILDING UPS SYSTEM RENEWAL (Project #
63823)
39,000.00
66,000.00
105,000.00
FAIRWAY PARK IMPROVEMENTS (Project # 20237)
3,593,177.74
(1,344,000.00)
2,249,177.74
NORMANDY ISLE PARK TURF INSTALLATION (Project #
20300)
308,477.36
1,344,000.00
1,652,477.36
SOUTHGATE TOWERS BAYWALK (Project # NEW)
-
195,000.00
195,000.00
7605 COLLINS MARINE SCIENCE CENTER ACQUISITION
(Project# 68831)
6,521,000.00
6,521,000.00
Totalrrr
00
Note:
1.) $4,829,873.71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following projects:
a. FDOT Alton Road Utilities Relocation (Project# 20527) - $4,291,410.87
b. Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538,462.84
2.) $1,344,000 of funding will be transferred from the Fairway Park Impro\tements project (#20237) to the following project:
a. Normandy Isle Park Turf Installation (Project# 20300) - $1,344,000
SOURCEATTACHMENT B
FY 2026 CAPITAL BUDGET
AMENDED .
Amended
Funding Source FY2026
Capital Budget
Amended2/5/2026
Revised
FY2026
Capital Budget
Resiliency Fund
$ 7,478,030.00
$ -
$ 7,478,030.00
Capital Renewal & Replacement
5,936,384.00
5,936,384.00
Tree Preservation Trust Fund
110,000.00
110,000.00
North Beach Public Benefits
147,343.00
147,343.00
7th Street Garage
1,020,000.00
1,020,000.00
Art in Public Places
75,000.00
75,000.00
Fees In Lieu of Parking
2,022,197.00
2,022,197.00
Concurrency Management & Mobility Fee
1,258,773.00
1,258,773.00
ConcurrencyMitigation Fund
(161,000.00)
(161,000.00)
RDA City Center Renewal & Replacement
360,627.00
360,627.00
Local Option Gas Tax
(800,000.00)
(800,000.00)
Capital Projects Financed By Other Funds
1,062,872.00
1,062,872.00
Pay As You Go - Capital Fund
25,254,398.00
6,521,000.00
31,775,398.00
Capital Reserve
4,705,928.00
195,000.00
4,900,928.00
Resort Tax - South Beach
2,335,336.00
-
2,335,336.00
Resort Tax - Mid Beach
3,170,115.00
3,170,115.00
Resort Tax - North Beach
3,488,264.00
3,488,264.00
2015 Resort Tax Revenue Bonds
2,613,583.00
2,613,583.00
RDASeries 2015A
1,004,788.00
1,004,788.00
City Center RDA Capital Fund
1,022,374.00
1,022,374.00
1999 GO Bonds Neighborhood Improvements
465.00
465.00
2003 GO Bonds Fire Safety
22,946.00
22,946.00
2003 GO Bonds Parks & Rec
13,011.00
13,011.00
2003 GO Bonds Neighborhoods
16,885.00
16,885.00
South Pointe Capital
2,776.00
2,776.00
2019 GO Bonds — Neighborhoods & Infrastructure
76,748.00
76,748.00
2023AArt, Cultural, & Facilities GOB Tax -Exempt
1,845,789.00
1,845,789.00
2023B Art, Cultural, & Facilities GOB Taxable
400,000.00
400,000.00
2025 Water & Sewer Bonds
584,798.54
584,798.54
Water & Sewer Capital Projects funded from Operations
18,124,757.46
18,124,757.46
2017 Water & Sewer Bonds
3,717,721.00
3,717,721.00
Water & Sewer Bond Series 2010
835.00
835.00
Water & Sewer Impact Fees
353,777.00
353,777.00
Gulf Breeze 2006
5,227.00
5,227.00
2000 Water & Sewer Bonds
21,610.00
21,610.00
Stormwater Projects - MDC ILA
288,952.00
288,952.00
Storm Water Capital not Bonds
1,297,300.00
1,297,300.00
Convention Center Operating Fund
11,308,739.00
11,308,739.00
Convention Center Renewal & Replacement
1,453,000.00
1,453,000.00
RDA Garages
500,000.00
500,000.00
Penn Garage Fund
900,000.00
900,000.00
RDACollins Garage Operations
500,000.00
500,000.00
1988 Debt Service Construction
122,430.00
122,430.00
2010 Parking Bonds
545,935.00
545,935.00
2015 Parking Revenue Bonds
113,256.00
113,256.00
Parking Capital not Bonds
28,674,438.00
28,674,438.00
Fleet Management
9,587,800.00
9,587,800.00
Communications 39,000.00 66,000.00 105,000.00
Total Appropriation as of r 142,623,208.00 $ 6,782,000.00 $ 149,405,208.00
Note:
1.) $4,829,873.71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following
projects:
a. FDOT Alton Road Utilities Relocation (Project# 20527) - $4,291,410.87
b. Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538,462.84
2.) $1,344,000 of funding will be transferred from the Fairway Park Improvements project(#20237) to the following project:
a. Normandy Isle Park Turf Installation (Project# 20300) - $1,344,000
FY ATTACHMENT C
PROGRAMS
Amended
Revised
Program Area FY 2026
Amended 2/5/2026
FY 2026
Capital Budget
Capital Budget
Art in Public Places
$ 75,000.00
$ -
$ 75,000.00
Bridges
600,000.00
600,000.00
Community Centers
2,995,789.00
2,995,789.00
Convention Center
16,380,110.00
16,380,110.00
Cultural Services
400,000.00
400,000.00
Environmental
470,000.00
-
470,000.00
Equipment
12,844,291.00
66,000.00
12,910,291.00
General Public Buildings
24,474,860.00
6,521,000.00
30,995,860.00
Golf Courses
3,494,000.00
-
3,494,000.00
Monuments
133,000.00
-
133,000.00
Parking
11,808,236.00
-
11,808,236.00
Parks
27,629,840.00
-
27,629,840.00
Seawalls
8,322,374.00
-
8,322,374.00
Streets/Sidewalks/Streets capes Improvements
5,094,163.00
-
5,094,163.00
Trans it/ Transportation
387,773.00
195,000.00
582,773.00
Utilities 27,513,772.00 - 27,513,772.00
Total Appropriation r 142,623,208.00 $ 6,782,000.00 $ 149,405,208.00
Note:
1.) $4,829,873.71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following
projects:
a. FDOT Alton Road Utilities Relocation (Project# 20527) - $4,291,410.87
b. Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538,462.84
2.) $1,344,000 of funding will be transferred from the Fairway Park Improvements project (#20237) to the following project:
a. Normandy Isle Park Turf Installation (Project# 20300) - $1,344,000
ORDINANCE NO. 2016-4065
AN ORDINANCE OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, AMENDING APPENDIX A,
ENTITLED "FEE SCHEDULE," TO CHAPTER 98 OF THE MIAMI
BEACH CITY CODE, ENTITLED "STREETS AND SIDEWALKS,"
AMENDING ARTICLE III, ENTITLED "EXCAVATIONS," AMENDING
DIVISION 2, ENTITLED "PERMIT," AMENDING SECTION 98-92,
ENTITLED "APPLICATION; AMOUNT OF DEPOSIT; USE OF DEPOSIT
TO REPLACE SURFACE; PERMIT FEE," BY AMENDING THE FEES
AND HOURS REGARDING PERMITS FOR BLOCKING OF RIGHT-OF-
WAY FOR MAJOR THOROUGHFARES; PROVIDING FOR
CODIFICATION, REPEALER, SEVERABILITY, AND AN EFFECTIVE
DATE.
WHEREAS, at the May 13, 2016 Neighborhood/Community Affairs Committee (NCAC)
meeting, the Committee recommended in favor of staff's recommendation for adjustments to the
rush hour times during which lane closures along major thoroughfares would not be permitted;
and
WHEREAS, at the same meeting, the NCAC recommended in favor staff's
recommendations to pursue adjustments to the Fee Schedule for lane closures along major
thoroughfares, and
WHEREAS, the recommendation of the NCAC for restrictions to the closure times at
major thoroughfares was approved by the City Commission at its September 27, 2016 meeting,
pursuant to Resolution No. 2016-29583, which authorized such amendments to the City of
Miami Beach City Code and the Citywide Procedure regarding the Traffic Flow Mitigation Plan
(See Exhibit A); and
WHEREAS, the City Administration has worked on refinements to the existing fee
structure for work along Major Thoroughfares that will help reduce traffic congestion, and
WHEREAS, the amendments set forth below are necessary to accomplish the above
objectives
NOW, THEREFORE, BE IT ORDAINED BY THE MAYOR AND CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA:
SECTION 1. Appendix A, entitled "Fee Schedule," to Chapter 98 of the Miami Beach
City Code, entitled "Streets and Sidewalks," Article III, entitled "Excavations," Division 2, entitled
"Permit," Section 98-92, entitled "Application; Amount of Deposit; Use of Deposit to Replace
Surface; Permit Fee," is hereby amended as follows:
APPENDIX A- FEE SCHEDULE
Section this Code
Description
Amount (OFEli^^nGe-20 2_
Ordinance 2016-
Effective Dec. 24, 2016)
98-92 (c)
(1)
Street Excavation Permit
(17)
Blocking of right-of-way (GF@ses only)
Note: For aFteFffial Feadw Major
Thoroughfares, full day permit is defined as s+x
#peers five hours and thirty minutes between
10:00 a.m. and 3:30 p.m.
pursuant to Resolution No. 2016-29583
Cranes
Standard review (full day permit)
• Local road
320.43
• Collector road
427.24
• Artprial read -Major Thoroughfares
534.05 1000.00
Priority review (same day permit review)
• Local road
384.51
• Collector road
512.27
• Arterial read Major Thoroughfares
b49-861000.00
Consecutive multi -day additional fee (per day)
For Local and Collector Roads
54.96
Consecutive multi -day additional fee (per day)
1000.00
For Major Thoroughfares
Partial day permit (4 hours or less)
• Local road
159.69
• Collector road
213.62
Blocking right-of-way (all others) for Local and
Collector Roads: The greater of $0.25 per L.F. per
day or $0.03 per S.F. per day)
Blocking right-of-way (all others) for Maior
Thoroughfares: The greater of $2.50 per L.F. per
day or $0.30 per S.F. per day)
SECTION 2. REPEALER.
All ordinances or parts of ordinances in conflict herewith be and the same are
hereby repealed.
SECTION 3. SEVERABILITY.
If any section, subsection, clause or provision of this Ordinance is held invalid,
the remainder shall not be affected by such invalidity.
SECTION 4. CODIFICATION.
It is the intention of the Mayor and City Commission of the city of Miami Beach,
and it is hereby ordained that the provisions of this ordinance shall become and be
made part of the Miami Beach City Code. The sections of this ordinance may be
renumbered or relettered to accomplish such intention, and the word 'ordinance" may
be changed to "section," "article," or other appropriate word.
SECTION 5. EFFECTIVE DATE.
This Ordinance shall take effect ten days following adoption.
PASSED AND ADOPTED this H day of Imber 2016.
ATTEST:
Rafael E. Granado, City Clerk `
Underline denotes additions
Stfikethrough denotes deletions
(Sponsored by Commissioner John Elizabeth Aleman)
APPROVED AS TO
FORM & LANGUAGE
& FOR EX UTION
`:Q.,� ( t 1 n (I :�
City AttorneyDate
T:\AGENDA\2016\October\Transportation\Ordinance on ROW Fees\Ordinance Ammending Appendix A (Permit
Fees) Section 98-92(c)(17) RESO.doc
MIAMI BEACH
COMMISSION MEMORANDUM
TO: Honorable Mayor and Members of the City Commission
FROM: Jimmy L. Morales, City Manager
DATE: December 14, 2016
10:25 a.m. Second Reading Public Hearing
SUBJECT: AN ORDINANCE OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI
BEACH, FLORIDA, AMENDING APPENDIX A, ENTITLED "FEE SCHEDULE," TO
CHAPTER 98 OF THE MIAMI BEACH CITY CODE, ENTITLED "STREETS AND
SIDEWALKS," AMENDING ARTICLE III, ENTITLED "EXCAVATIONS," AMENDING
DIVISION 2, ENTITLED "PERMIT,' AMENDING SECTION 98-92, ENTITLED
"APPLICATION; AMOUNT OF DEPOSIT; USE OF DEPOSIT TO REPLACE SURFACE;
PERMIT FEE," BY AMENDING THE FEES AND HOURS REGARDING PERMITS FOR
BLOCKING OF RIGHT-OF-WAY FOR MAJOR THOROUGHFARES; PROVIDING FOR
CODIFICATION, REPEALER, SEVERABILITY, AND AN EFFECTIVE DATE.
RECOMMENDATION
The Administration recommends that the City Commission approve the amendment to the attached
Ordinance on Second Reading.
ANALYSIS
In February 2016, the City hosted a Commission Workshop on Traffic Management to discuss various
initiatives to manage traffic congestion and improve mobility in the City. One of the initiatives identified
at the workshop was the implementation of further restrictions to public right-of-way closure times and
adjustments to the permit fees for lane closures along major corridors. In January 2015, the Citywide
Procedure for Traffic Flow Mitigation was implemented to ensure the maximization of traffic flow along
major thoroughfares, especially during rush hours Monday through Friday. As per the procedure,
weekday rush hours are defined as 7:00 AM to 9:00 AM and 4:00 PM to 7:00 PM. No lane closures are
permitted during these hours with the exception of emergency projects of an engineering nature.
Based on the characteristics of traffic circulation in the City, at the May 13, 2016
Neighborhood/Community Affair Committee (NCAC) meeting, staff recommended adjustments to the
rush hour times to reduce conflicts with commuter traffic. The Committee approved staff's
recommendation to further extend restrictions for closure of public right-of-way along major
thoroughfares from 7:00 AM to 10:00 AM and from 3:30 PM to 7:00 PM and to increase fees for lane
closures along major thoroughfares. The classification of major thoroughfare shall be exclusive to the
following roadways pursuant to the Citywide Procedure for Traffic Flow Mitigation:
• Alton Road
• 5th Street
• West Avenue
• 16th Street
• Collins Avenue
Page 594 of 1191
• 17th Street
• Indian Creek
• Dade Boulevard
• Pine Tree/La Gorce Drive
• 41st Street
• Abbott Avenue/Harding Avenue
• 71st Street
• Washington Avenue
• 63rd Street
The recommendation of the NCAC for further restrictions to the closure times along major
thoroughfares was approved by Resolution of the City Commission at its September 27, 2016 meeting.
The current fee schedule (Appendix A of Section 98-92 of City Code) provides no incentive for
contractors to identify creative constructability solutions or accelerate schedules to create less
disruption on traffic. Based on this review, at the May 13, 2016 NCAC meeting, staff recommended that
an increase to the existing fee schedule for closures along major thoroughfares be considered. The NCAC
approved staff's recommendation for a more aggressive fee schedule.
The advantage of increasing the fee schedule for closures along major thoroughfares is that it will
motivate contractors to conduct more work from the minor streets when feasible or work at night. Work
requiring lane closures related to City Projects during the prohibited hours would be subject to City
Commission approval. All emergency utility work requiring lane closures, by the City or utility companies,
shall be reviewed and approved by the City's Public Works Director. Currently, the State of Florida
exempts utility franchises from any permitting fees. As such, utility companies shall be exempted from
any City Right -of -Way fees; however, these companies will have to comply with the restricted hours of
work unless emergency work is approved by the City. Additionally, Florida Department of Transportation
(FDOT) is exempt from any City Right -of -Way permit fees for any work on roadways under its
jurisdiction. Further, FDOT is not required to comply with the City's established lane closure restriction
hours; however, the City and FDOT have been working collaboratively to minimize any roadwork
requiring lane closures along major thoroughfares during the restricted times approved by the City
Commission.
Staff proposes that the existing fee schedules be changed as reflected in the following table:
98(c) (1) Street excavation permit:
50 lineal feet or less
$362.95
Each additional lineal foot
$3.05
(2) Sidewalk repair permit:
50 lineal feet or less
$298.65
Each additional lineal foot
$3.05
(3) Sidewalk construction permit:
50 lineal feet or less
$298.65
Each additional lineal foot
$3.05
(4) Paving or resurfacing of parkway or shoulder area permit:
25 lineal feet or less
$298.65
Each additional lineal foot
$6.48
(5) Landscaping, per tree $103.70
(6) Landscaping, bedding $103.70
(7) Building line and grade survey permit:
Page 595 of 1191
,)u uneai reet or less )3bZ.yb
Each additional lineal foot $7.25
(8) Driveway construction permit, each driveway $129.62
(9) Flume excavation permit, each excavation $298.65
Utility placement permit, poles, splice pits, manholes, hand holes, catch basins,
{10) $298.65
pedestals, vaults and auger holes
Plus, for each additional, per block on same permit $14.51
Underground utility service connection right-of-way excavation permit, each
(11) water, gas, electric, telephone, cable, television or sanitary sewer connection from $298.65
base building line to the utility located within the public right-of-way
(12) Groundwater monitoring wells, each well $298.65
(13) Permit renewal fee: 90-day extension of permit fee expiration date $129.62
After -the -fact permit fee. For any work described in (1) through (12), (16) and
(14) (17) herein, performed without proper permits and inspections, quadruple the
fees
Reinspection fees. When additional inspection is required for work previously
(15) inspected and rejected by the department of public works, a reinspection fee will $114.07
be required, for each reinspection
(16) Dewatering permit fee $362.95
Blocking of right-of-way (Cranes only)
(17) Note: For aFteFial Feadw moior thoroughfaresfull day permit is defined as 94
houfs five hours and thirty minutes between 10:00 a.m.
and 3:30 p.m.
Cranes
Standard review (full day permit)
• Local road
$320.43
• Collector road
$427.24
feed Major Thoroughfares
534.95
Priority review (same day permit review)
• Local road
$384.51
• Collector road
$512.27
• Arterial Fead-Major Thoroughfares ;, „n'n- r
Consecutive multi -day additional fee (per day) For Local and Collector Roads $54.96
Consecutive multi -day additional fee (per day) For Maior Thoroughfares $1,000.00
Partial day permit (4 hours or less)
• Local road $159.69
• Collector road $213.62
Blocking right-of-way (all others) for Local and Collector Roods: The greater of
$0.25 per L.F. per day or $0.03 per S.F. per day)
Blocking right-of-way (all others) for Major Thoroughfares: The greater of $2.50
per L.F. per day or $0.30 per S.F. per day)
(18) Revocable permit
Page 596 of 1191
Application fee, involving city property
Mailing fee, per address within 375 feet
(19) Coastal review
(20) Sewer capacity certification letter application
$4,148.00
$0.51
$918.78
$155.55
Staff performed a high-level analysis of the potential effects of the proposed adjustments to current
Right -of -Way closure fees based on historical permit data. Based on this research, it was found that 85%
of all crane permits are two (2) days or less in duration while the 85th percentile duration of all other
right-of-way permits is approximately 24 days. Under the current fee structure, a typical 2-day closure of
a single travel lane for a length of 100' along a major thoroughfare for crane installation/operation would
cost $624.96 for both days. Under the proposed ordinance, the cost for the same closure would
be $1,610 per day (for total cost of $3,220 for a typical 2-day crane permit). Similarly, under the existing
fee structure, a typical 24-day closure of a lane on a major thoroughfare would have a cost of $36 per
day (for a total cost of $864 for a typical 24-day lane closure permit). Under the proposed Ordinance, the
cost for the same lane closure would be $360 per day (for a total cost of $8,640 for a typical 24-day lane
closure permit).
The table below provides a cost comparison between the amounts that an applicant would have to pay
for a typical 2-day crane permit and typical 24-day lane closure permit, respectively, under the current
fee structure as compared to the proposed fee structure. It is worth noting that under the current fee
structure, for a typical 2-day crane permit, the additional cost per day is $54.96.
Current Fee
Current Total Fee
Proposed Fee
Proposed Total Fee
($/day)
($)
($/day)
($)
Crane Permit
$570/day
$624.96 for 2-days
$1,610/day
$3,220 for 2-days
Lane Closure
$36/day
$864 for 24-days
$360/day
$8,640 for 24-days
Permit
Page 597 of 1191
KEY INTENDED OUTCOMES SUPPORTED
Ensure Comprehensive Mobility Addressing All Modes Throughout The City
FINANCIAL INFORMATION
The proposed Ordinance Amendment is not anticipated to have a financial impact and can be
enforced through existing resources.
Legislative Tracking
Transportation
Sponsor
Commissioner John Elizabeth Aleman
ATTACHMENTS:
Description
o Ordinance
Page 598 of 1191
Resolutions - R7 B
MIAMI BEACH
COMMISSION MEMORANDUM
TO Honorable Mayor and Members of the City Commission
FROM: Eric Carpenter, City Manager
DATE: February 5, 2026 2:01 p m. Public Hearing
TITLE: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH. FLORIDA. ADOPTING THE SECOND AMENDMENT TO THE
CAPITAL BUDGET FOR FISCAL YEAR 2026 AS SET FORTH IN ATTACHMENTS
A, "PROJECTS B. "SOURCE OF FUNDS AND C -PROGRAMS "
RECOMMENDATION
The Administration recommends that the Mayor and City Commission adopt the attached
Resolution
BACKGROUND/HISTORY
Planning for capital improvements is an ongoing process: as needs change within the City of
Miami Beach (the 'City"), capital programs and priorities must be adjusted accordingly. The
Capital Improvement Plan ("CIP") serves as the primary policy and planning tool for systematically
identifying, prioritizing, and assigning funds to critical City capital improvement projects.
The City's CIP and Capital Budget development process begins in the winter when all
departments are asked to prepare updates and requests on their department's ongoing and new
proposed capital projects. Individual departments prepare submittals identifying potential funding
sources and requesting commitment of funds for their respective projects.
The CIP is updated annually and submitted to the Mayor and City Commission for adoption. The
Fiscal Years ("FY") 2026 — 2030 CIP and FY 2026 Capital Budget were adopted on September
30, 2025 by Resolution No. 2025-33948.
The First Amendment to the FY 2026 Capital Budget was adopted on December 17, 2025 by
Resolution No. 2025-34040.
ANALYSIS
SECOND AMENDMENT TO THE FY 2026 CAPITAL BUDGET
The proposed Second Amendment to the FY 2026 Capital Budget reflects an overall increase of
$6,782,000.00 and the re -alignment of $6,173,873.71 for the following capital projects:
1. FDOT Alton Road Utilities Relocation (#20527): The Florida Department of
Transportation (FDOT) is undertaking major roadway and drainage improvements
along the southern segment of Alton Road/SR 907, from Michigan Avenue to 43"
Street, and subsequent phases will address the middle and northern segments, from
431,' Street to 63'° Street.
As part of this initiative, the City must execute a Utility Work by Highway Contractor
Agreement (UWHCA) to relocate City -owned water and sewer utilities impacted by
1125 of 2180
FDOT's state roadway projects. This work is critical to ensure uninterrupted utility
services and to avoid costly delays or conflicts during FDOT's construction activities.
Due to significant increases in construction costs and the addition of a force main to
the project scope, additional funding is required. Without this additional funding, the
City risks project delays, potential service disruptions, and increased costs if work is
deferred.
Funding for this proposed amendment would come from the Series 2025 Water &
Sewer Bonds Funds (Fund 417) and the Water and Sewer Capital Projects funded
from Operations Funds (Fund 418) which were previously appropriated to the following
project that is no longer required due to additional federal grant funding that was
received from the U.S. Department of Housing and Urban Development for Sewer
Pump Station #28.
• Wastewater Stations Rehabilitation (20619):
o Fund 417 - $1,930,749.02
o Fund 418 - $2,360,661.85
Prior Appropriations
$20,137,625.02
February 5, 2026 Budget Amendment
4,291,410.87
Proposed Total Appropriations
$24,429,035.89
2. Water and Wastewater Mains and Rehabilitation (#28520): The City of Miami
Beach is undertaking a critical infrastructure project to replace the existing 16-inch
cast-iron sanitary sewer force main serving Pump Station 19 (PS 19). This
replacement became imperative following a rupture on October 14, 2022, at the
intersection of 691" Street and Indian Creek Drive, where the force main connects to
the City's larger sewer transmission system. Emergency repairs were completed to
restore service and prevent sanitary sewer overflow; however, subsequent evaluations
by the City Engineer and Public Works operations staff confirmed that the force main
was significantly deteriorated and beyond its intended service life, making additional
failures highly likely without full replacement.
During construction, the contractor encountered unforeseen site conditions that were
not reflected in the original plans. These included:
• Installation of a concrete support pad for the tap -in connection
• Additional dewatering requirements
• Emergency backfilling and excavation to reopen traffic lanes during permit
review
• Unmapped Florida Power & Light (FPL) utility lines
• Immediate repair of two damaged stormwater pipes
Addressing these conditions requires a construction change order to procure
additional materials and services. As a result, additional funding is necessary to
accommodate these unforeseen conditions and ensure successful completion of this
high -priority project.
This project is essential to eliminate the risk of future force main failures, which pose
serious public health and environmental concerns. Force main breaks can result in
sanitary sewer overflows, roadway closures, and restrictions on water -based
recreational activities until water quality is restored. Such events disrupt residents,
commuters, and businesses, and create significant community impacts associated
1126 of 2180
with emergency construction activities and sewer hauling operations. Replacing this
critical segment is necessary to ensure the long-term reliability and resilience of the
City's wastewater transmission system.
Funding for this proposed amendment would come from the Series 2025 Water &
Sewer Bonds Funds (Fund 417) which was previously appropriated to the following
project that is no longer required due to additional federal grant funding from the U.S.
Department of Housing and Urban Development that was received for the Miami
Beach Sewer Pump Station #28.
• Wastewater Stations Rehabilitation (#20619) - $538,462.84
Prior Appropriations
$81,172,674.82
February 5, 2026 Budget Amendment
538,462.84
Proposed Total Appropriations
$81,711,137.66
3. Normandy Isle Park Turf Installation (#20300): The City of Miami Beach plans to
deliver a high -quality, industry -standard, artificial turf playfield along with concrete
pads for existing bleachers at Normandy Isle Park. Additional improvements include a
chilled water fountain with the necessary electrical system, as well as extra concrete
pads and bleachers to enhance user experience and accommodate increased
demand.
These upgrades are critical to improving customer satisfaction and ensuring safe,
reliable recreational facilities. Normandy Isle Park is one of the City's most heavily
used fields within the City hosting hundreds of users daily, which has resulted in
significant wear and tear. The current field is in substandard condition with bald spots
and deteriorated turf due to the high volume of activities.
Installing artificial turf will:
• Increase public access and usability of the field
• Support program expansion for Parks & Recreation activities
• Enhance safety and playability for all users
The Parks & Recreation Department faces an ongoing shortage of quality fields, and
Normandy Isle Park is a high -priority location for safety and community use. Timely
approval of this funding will allow the City to address these deficiencies and deliver a
durable, modem playfield that meets the needs of residents and program participants.
Funding for this proposed amendment would come from the Capital Pay -As -You -Go
Funds (Fund 302), which was previously appropriated to the following project that
remains necessary but is currently on hold due to a shift in park project priorities within
the Parks & Recreation Department.
• Fairway Park Improvements (#20237) - $1,344,000
Prior Appropriations
$308,477.36
February 5, 2026 Budget Amendment
1,344,000.00
Proposed Total Appropriations
$1,652,477.36
1127 of 2180
4. Fire Administrative Building Uninterruptible Power Supply System Renewal
(#63823): The City of Miami Beach plans to do a complete overhaul of the electrical
system powering the Fire Station 2 datacenter, which is now approximately 20 years
old and has reached the end of its service life.
Originally, the Facilities and Fleet Management Department secured $39,000 through
the FY 2026 Capital Budget for a standard battery replacement. In May 2024, the
project was transferred to the Information Technology Department for implementation.
During the process of obtaining updated estimates, the electrician concluded that due
to the age and condition of the equipment, all components must be replaced to prevent
system failure. This revised scope requires an additional $66,000 and includes the
replacement of all electrical components, power distribution systems, and battery
cabinets to ensure reliable and uninterrupted operation of critical public safety
systems.
Funding for this proposed amendment would come from funding that is set aside for
renewal and replacement that is available for appropriation in the Information
Technology Fund (Fund 550).
Prior Appropriations
$39,000.00
February 5, 2026 Budget Amendment
66,000.00
Proposed Total Appropriations
$105,000.00
5. Southgate Towers Baywalk (#NEW): As part of the development and improvements
at 910 West Avenue (Southgate Towers), the property owner agreed to grant an
easement for a public baywalk along the upland portion at the rear of the site. The
baywalk has since been constructed and is open for public use; however, the property
owner must be reimbursed for the cost of installing the glass railing, which was a
required component of the baywalk improvements.
On December 17, 2025, the Mayor and City Commission, via Resolution No. 2025-
34051, approved an Easement Agreement with Southgate Towers, LLC, granting the
City this perpetual easement and authorizing the reimbursement of $195,000 for the
installation of the glass railing, subject to appropriation and approval through an
amendment to the FY 2026 Capital Budget.
Funding for this proposed amendment would come from fund balance that is available
for appropriation in the Capital Reserve Fund (Fund 304).
Prior Appropriations
$0.00
February 5, 2026 Budget Amendment
195,000.00
Proposed Total Appropriations
$195,000.00
6. 7605 Collins Marine Science Center Acquisition (#68831): On December 17, 2025,
the Mayor and City Commission adopted Resolution No. 2025-34050, approving the
acquisition of the property located at 7605 Collins Avenue for general municipal
purposes from the Building Department.
Acquiring 7605 Collins Avenue is a high -priority initiative that aligns with the City's
goals of securing strategic assets for municipal purposes. Ownership of this property
1128 of 2180
provides flexibility for future City operations and helps preserve critical real estate in a
highly desirable area.
The total cost of the property acquisition from the Building Department is $6,521,000.
This funding ensures the City can secure the property for municipal use, consistent
with the Commission's directive to advance strategic property acquisitions that support
long-term operational and community needs.
Funding for this proposed amendment would come from fund balance that is available
for appropriation in the Capital Pay -As -You -Go Fund (Fund 302) based on the
recommended transfer of FY 2025 surplus from the General Fund that is proposed as
part of the companion operating budget amendment item on today's City Commission
agenda.
Prior Appropriations
$0.00
February 5, 2026 Budget Amendment
6,521,000.00
Proposed Total Appropriations
$6,521,000.00
FISCAL IMPACT STATEMENT
See detailed information provided above.
Does this Ordinance require a Business Impact Estimate?
(FOR ORDINANCES ONLY)
If applicable, the Business Impact Estimate (BIE) was published on:
See BIE at: https://www.miamibeachfl.gov/city-hall/city-clerk/meeting-notices/
FINANCIAL INFORMATION
See detailed information provided above.
CONCLUSION
The City Administration recommends that the Mayor and City Commission adopt the Second
Amendment to the Capital Budget for FY 2026 described herein and further detailed in
Attachments A-C of the accompanying Resolution.
EC/JDG/TOS
Applicable Area
Citywide
Is this a "Residents Right to Know" item,
pursuant to City Code Section 2-17?
Yes
Is this item related to a G.O. Bond
Project?
No
Was this Agenda Item initially requested by a lobbyist which, as defined in Code Sec. 2-481,
includes a principal engaged in lobbying? No
1129 of 2180
If so, specify the name of lobbyist(s) and principal(s):
Department
Management and Budget
Sponsor(s)
Co-sponsors)
Condensed Title
2:01 p.m. PH, Adopt 2nd Amendment to the FY 2026 Capital Budget. OMB
Previous Action (For City Clerk Use Only)
1130 of 2180
A
IFY 2026 CAPITAL BUDGET
PROJECTSATTACHMENT
AMENDED 2/5/2026
Amended
Revised
Capital Project Name FY 2026
Amended 2/5/2026
FY 2026
Capital Budget
Capital Budget
WASTEWATER STATIONS REHABILITATION (Project #
$ 43,717,282.01
(4,829.873.71)
$ 38,887,408.30
20619)
FDOT ALTON ROAD UTILITIES RELOCATION (Project #
20,137,625 02
4,291,410 87
24,429,035.89
20527)
WATER & WASTEWATER MAINS AND REHABILITATION
81,172,674.82
538.462.84
81,711,137.66
(Project # 28520)
FIRE ADMIN BUILDING UPS SYSTEM RENEWAL (Project #
39 000.00
66 000 00
105,000.00
63823)
FAIRWAY PARK IMPROVEMENTS (Project # 20237)
3,593,177 74
(1,344,000,00)
2,249,177.74
NORMANDY ISLE PARK TURF INSTALLATION (Project #
20300)
308A77 36
1,344.000-00
1,652,477.36
SOUTHGATE TOWERS BAYWALK (Project # NEW)
195.000.00
195,000.00
7605 COLLINS MARINE SCIENCE CENTER ACQUISITION
(Project # 68831)
6,521,000.00
6.521.000.00
6,782.000.00
S 155,750,236.95
Note.
1 ) $4,829,873.71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following projects
a- FDOT Alton Road Utilities Relocation (Project# 20527) - $4.291,410.87
b. Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538.462.84
2.) $1.344,000 of funding will be transferred from the Fairway Park Improvements project (#20237) to the following project:
a. Normandy Isle Park Turf Installation (Project# 20300) - $1.344,000
1131 of 2180
FY ATTACHMENT
SOURCE
AMENDED
Fundirig Source
8
OF FUNDS
t .
Amended
FY 2026
Capital Budget
Amended 2572026
devised
FY 2026
Capital Budget
Resiliency Fund
$ 1478,030 00
$
$ 7,478,030 00
Capital Renewal & Replacement
5,936 384 00
5.936,384 00
Tree Preservation Trust Fund
110 000 00
110.00000
North Beach Public Benefits
147 343 00
147,343 00
7th Street Garage
1.020.000 00
1.020 000 00
Art in Public Places
75 000 00
75,000 00
Fees In Lieu of Parking
2,022,197 00
2 022,197.00
Concurrency Management & Mob" Fee
1,258, 773 00
1,258,773.00
Concurrency Mtigation Fund
(16100o 00)
If 6 t 000 00)
RDA City Center Renewal & Replacement
360,627 00
360.62700
Local Option Gas Tax
(800 000 00)
(800 000 00)
Capital Projects Financed By Other Funds
1.062,872 00
1,062.872 00
Pay As You Go - Capital Fund
25,254,398 00
6.521,000 00
31,775,398 00
Capital Reserve
4,705 928 00
195,000 00
4,900.928 00
Resort Tax - South Beach
2 335,336 00
-
2,335 336 00
Resort Tax - Md Beach
3,170 115 00
3,170 11500
Resort Tax North Beach
3 488,264 00
3 488 264 00
2015 Resort Tax Revenue Bonds
2.613,583 00
2,613,583 00
RDA Serves 2015A
1004,78800
1,004,78800
City Center RDA Capital Fund
1.022.374 00
1.022 374 00
1999 GO Bonds Neighborhood Improvements
465 00
46500
2003 GO Bonds Fire Safety
22.946 00
22.946-00
2003 GO Bonds Parks & Rec
13 011 00
13 011 00
2003 GO Bonds Neighborhoods
16 885 00
16.885 00
South Pointe Capital
2.77600
2,77600
2019 GO Bonds - Neighborhoods & Infrastructure
76,748 00
76,748 00
2023AArt, Cultural, & Facilities GOB Tax -Exempt
1,845,789 00
1.845 789 00
20238 Art, Cultural & Facilities GOB Taxable
400.00000
400,000 00
2025 Water & Sewer Bonds
584.798 54
584 798 54
Water & Sewer Capital Projects funded from Operations
16 124,757 46
18,124,757 46
2017 Water & Sewer Bonds
3.717,721 00
3.717,721_00
Water & Sewer Bond Serves 2010
83500
835 00
Water & Sewer Impact Fees
353,777 00
353,777 00
Coif Breeze 2006
5.22700
5,22700
2000 Water & Sewer Bonds
21 610 00
21.61000
Stormwater Projects - hW ILA
288 952 00
288,952 00
Storm Water Capital not Bonds
1,297,300 00
1,297,300.00
Convention Center Operating Fund
11,308,739 00
11,308.739 00
Convention Center Renewal & Replacement
1,45300000
-
145300000
RDA Garages
500.000 00
500,000 00
Penn Garage Fund
900.000 00
900.00000
RDA Collins Garage Operations
500,000 00
500.000 00
1988 Debt Service Construction
122,43000
122,43000
2010 Parking Bonds
545,935 00
545.935 00
2015 Parking Revenue Bonds
113.256 00
113,256 00
Parking Capital not Bonds
28,674 438 00
28,674 438 00
Fleet Wriagement
9.587.800 00
9.587 800 00
Communications
39,00000 1
66.000 00
105.000 00
Total Appropi tation as of i is it S 6,782,000.00 $ 149,405,208.00
Note
1 ) $4,829.873 71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following
projects
a FDOT Alton Road Utilities Relocation (Project# 20527) - $4.291 410 87
b Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538 462 84
2 ) $1,344.000 of funding will be transferred from the Fairway Park Improvements project (1120237) to the following project
a Normandy Isle Park Turf Installation (Project# 203001 - $1 344 000
1132 of 2180
ATTACHMENT C
BUDGET
PROGRAMS
Amended
Program Area FY 2026
Capital Budget
Amended 2/5/2026
Revised
FY 2026
Capital Budget
Art in Public Places
S 75.000 00
S -
$ 75,000 00
Bridges
600.000,00
600,000.00
Community Centers
2,995.789 00
2,995.789 00
Convention Center
16,380,110.00
16,380,110.00
Cultural Seances
400.000.00
400.000 00
Environmental
470,000.00
-
470,000 00
Equipment
12,844,291.00
66.000.00
12,910,291.00
General Public Buildings
24,474,860 00
6,521,000.00
30.995.860,00
Golf Courses
3,494,000.00
3,494,000.00
Monuments
133,000 00
133,000 00
Parking
11,808,236.00
11,808,236,00
Parks
27,629,840.00
27,629,840 00
Seawalls
8,322.374,00
8.322,374 00
Streets /Sidewalks%Streets capes Improvements
5,094,163 00
-
5,094,163.00
Transit/ Transportation
387.773 00
195,000.00
582,773.00
Ublibes
27,513,772.00
27,513,772 00
AppropriationTotal r 0: rr S 6,782.000 00 S 149.405.208.00
Note
1.) $4,829,873.71 of funding will be transferred from the Wastewater Stations Rehabilitation project (#20619) to the following
projects
a. FDOT Alton Road Utilities Relocation (Project# 20527) - $4,291,410.87
b Water & Wastewater Mains and Rehabilitation (Project# 28520) - $538,462.84
2.) $1.344,000 of funding will be transferred from the Fairway Park Improvements project (#20237) to the following project:
a Normandy Isle Park Turf Installation (Project# 20300) - $1,3",000
1133 of 2180