HomeMy WebLinkAbout3. Meeting Minutes_01-22-26
General Obligation Bond Oversight Committee
City of Miami Beach
MEETING MINUTES No. 59
January 22, 2026
Members Present: Members via Zoom (not part of quorum):
Karen Rivo, Chair Isaac Kessler
Dana Martorella
Daniel Veitia
Jason Koslowe
Kate Mosley
Margalit Edelman
Non-Voting Members Present:
Adam Kravitz
Jack Benveniste
Donald Goldberg
David Sexton
Staff Present: Guests Present:
Thais Vieira, Liaison Brandi Reddick
Anthony Scallo Casey Steadman
Bryan Niedelson Cesar Sepulveda
Daniel Alzuri David Philips
David Gomez Rebecca Stanier
Francisco Brignoni Ximena Caminos
Frank Garcia
Ghassan Choueiry
Heather Shaw
Jani Singer
Jose Gonzalez
John Rebar
Kristy Bada
Mohsen Abu Shaaban
Maria Cerna
Pilar Caurin
Roland Aragunde
Meeting Start Time: 4:00 pm
General Notes: These meeting minutes are condensed and seek to capture the overall intent of discussions as
interpreted by the meeting coordinator. Each paragraph indicates the time on the audio recording where the
discussion commenced during the meeting. For more detail on the discussion, please refer to the audio recording
in its entirety. All current and past meeting materials including agendas, handouts, minutes, presentations, and
audio recordings are available by visiting: www.GOMBInfo.com/OversightCommittee/Meeting Records.
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 2 of 9
I. Roll Call and Introductions
(Refer to the Meeting Audio Recording on the G.O. Bond Website.)
00:30 Chair Karen Rivo called the meeting to order. Roll call was completed. She highlighted that
there was still one open position that is yet to be filled for North Beach.
II. Committee Business
Selection of Vice Chair
03:42 Jason Koslowe was unanimously selected as the Vice Chair.
2026 Calendar
(Refer to page 2 of the Agenda & Handouts Packet on the G.O. Bond website.)
04:17 Draft 2026 Calendar was shared with the Committee. The calendar is subject to change
pending the finalization of the Commission Committee calendars, which have not yet been set.
Adoption of Meeting Minutes from 11-20-25
Motion:
08:06 Jason Koslowe made a motion to approve the minutes as presented. Daniel Veitia
seconded the motion. Motion passed unanimously.
III. “Stop the Pause” Policy
8:29 Chair Karen Rivo introduced the item and reminded the Committee of the two prior motions
to extend the “Stop the Pause” Ordinance to G.O. Bond projects. She then introduced Rob
Rosenwald from the City Attorney’s Office, along with Commissioner Alex Fernandez’s aide, Kara
Petrella, who presented the item.
9:11 Kara stated that the original Ordinance, which was sponsored by Commissioner Fernandez
and adopted by the City Commission in September of 2024, was established to safeguard critical
infrastructure projects, such as stormwater, water and sewer upgrades, from the costly delays
and political shifts that previously stalled vital work in areas like Palm and Hibiscus Islands and
West Avenue. By implementing a higher Commission voting threshold required to halt active
construction, it aimed to ensure fiscal responsibility and maintain community resiliency against
rising costs.
The proposed amendment expands this protection to include all projects that are within the
City’s 5-year capital plan, which encompasses all General Obligation (G.O.) Bond projects.
Commissioner Fernandez has requested the Committee’s feedback and formal support for this
Ordinance update.
12:21 Rob Rosenwald clarified that the voting formula remains consistent with the original policy:
at 60% plan completion, a 5/7th vote of the city commission is required to pause a project. Once
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 3 of 9
a project reaches 90% completion or permits have been issued, the threshold increases to a 6/7th
vote.
13:14 Chair Karen Rivo asked for clarification regarding the unforeseen site conditions clause.
In response, it was explained that this refers to unexpected discoveries during the course of a
project, such as that could drastically change project costs, and in such cases, the voting threshold
would remain a simple majority (4/7th) rather than the supermajority.
14:31 Chair Karen Rivo inquired about the specific project markers used by the city. Thais Vieira
stated that the standard deliverables are 30%, 60%, and 90% (permitting stage), with 100% being
ready for construction.
15:10 Chair Karen Rivo suggested a chart showing how many projects are in each of these design
stages.
Discussion continued.
23:23 Rob Rosenwald informed the Committee that the ordinance has two public hearings, and
the first is scheduled for February 5, 2026, where it will be open for public comment.
Motion:
24:05 The Committee made a motion to support the proposed amendment to the "Stop the
Pause" policy as proposed.
Motion made by: Daniel Veitia
Motion seconded by: Dana Martorella
Motion passed 6-0
2018 G.O. Bonds
IV. Program General Status Update
(Refer to pages 3-13 of the Agenda & Handouts Packet on the G.O. Bond website.)
25:20 Thais Vieira provided a general update about the 2018 G.O. Bonds. She reported that the
La Gorce Park Playground project has been completed. Currently, 98% of all active tranche
projects are either completed or underway. Since the last meeting, about $6 million has been
spent, bringing the total expenditure to almost $120 million.
26:33 Regarding sub-projects, Thais Vieira reported that 98% (90 out of 92) of all tranche 1 (T1)
subprojects are either complete or active, while 69% of the total value of all T1 Projects are
complete or under construction. Currently, 48% of the projects are complete, 21% in
construction, 28% in design, 2% in planning and 1% pending. Regarding tranche 2, there has been
no change since the last meeting, and progress will remain the same until the Bayshore Traffic
Calming Project moves into construction.
27:25 Regarding 2026 construction commencements, Thais Vieira reported no changes from the
last meeting.
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 4 of 9
2018 Bonds Projects Update
(Refer to pages 14-25 of the Agenda & Handouts Packet on the G.O. Bond website.)
Fire Station 1
28:48 David Gomez reported that, at the December meeting, the Commission approved
construction of the fire station at the South Shore Community Center site. Amended contracts
for the Design Consultant and the Construction Manager at Risk firm are currently being prepared
and will be presented to the City Commission for approval at the February 25 meeting. In parallel,
staff will seek approval from the Historic Preservation Board (HPB) in February, as the previous
approval was rescinded when the project site was relocated to Flamingo Park.
Bayshore Park
38:28 Chair Karen Rivo thanked the City for sending the notice to the community regarding the
work that is in progress.
40:20 David Gomez reported that the project is substantially complete, though some items
remain pending and a few issues need to be addressed.
The crosswalks on Prairie Avenue and 28th Street have been marked in advance of the Bayshore
Traffic Calming Project. Work continues on the crosswalk near the high school, which presents
challenges due to the swale that must be crossed without impeding drainage.
Most of the equipment for the lake ozone and circulation system has been installed, with the
final section expected to be completed within the next two weeks.
Additionally, a new walkway has been designed to improve access between the playground and
the path near the banyan tree. The team is working to ensure the design meets all ADA
requirements so it can be implemented promptly.
42:03 John Rebar provided an update on operational matters. He noted that signage is being
installed in strategic locations throughout the park to help visitors navigate and identify parking
areas, particularly since Google has not yet updated the address and recent changes. New
maintenance contracts are being finalized to preserve the park’s design and ensure continuity. In
addition, a designated rental zone has been established for event bookings.
A separate proposal to add pickleball courts is being sponsored by a Commissioner and will be
explored at Committee.
Discussion continued.
49:10 Jason Koslowe recommended that the City consider adopting a conservancy model to
manage this unique park asset, providing consistent governance and securing long-term capital
funding. In response, John Rebar noted that the concept has been discussed previously and is
currently under consideration.
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 5 of 9
51:42 Donald Goldberg expressed concern about adding pickeball courts to this park, since it was
envisioned to be a passive park.
West Lot - Tranche 1 / Log Cabin
52:18 John Rebar reported there isn’t much to report since his last update on this item. There is
a pending item at the Land Use & Sustainable Committee (LUSC). Since then, another
Commissioner has submitted a nearly identical referral to develop the lots into city parks,
meaning two separate recreational proposals will eventually be considered.
53:13 Regarding Log Cabin, there is a separate referral to discuss moving the Log Cabin to the
original location within the West Lots, which could significantly impact the proposed recreational
designs.
53:42 Thais Vieira reminded the Committee that a while back, the LUSC directed the
administration to conduct community surveys, community picnic, and report back on the
findings.
54:20 John Rebar further explained that since the lots are too small for regulation soccer or
baseball fields, the City is exploring options like padel courts, pickleball courts, micro-soccer
fields, and community gardens.
54:41 Daniel Veitia shared that during the recent community picnic, he observed many attendees
who were not Miami Beach residents and were advocating for soccer uses. He emphasized that
while community input is important, the City must also rely on the Parks Department’s expertise
in understanding program demand, such as which activities are sold out or have long waiting lists.
John Rebar confirmed that final proposals will not be based solely on community feedback but
will also consider the practical ability to adjust programs across locations to meet overall
demand.
Tree Planting - Tranche 1
56:23 Amy Knowles reported on a new campaign that was launched on January 12, called “Let
Us Throw You Some Shade”, which aims to proactively gather resident input on tree planting
locations through March 31. The goal is to plant approximately 250 trees during the summer and
early fall rainy season. A GIS dashboard is being used to track requests in real-time, with 25
submissions already received as of the meeting date.
59:57 Chair Karen Rivo asked whether the proposed tree plantings would occur on public or
private property. Amy Knowles clarified that the trees are being planted on the public swale area
in front of homes, though residents are required to maintain them.
1:00:41 Adam Kravitz raised concerns about mature, non-native species, that are currently
damaging sidewalks and interfering with overhead wires, asking about the city's position on
replacing them with native species. In response, the staff stated that the City generally attempts
to maintain mature trees as long as they are healthy, only removing them if they become
hazardous.
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 6 of 9
Pedestrian Bridge
1:07:00 David Gomez reported that the Pedestrian Bridge project experienced a significant delay
after the developer’s contractor struck an unidentified FPL duct bank while performing test piles
for the foundation. In response to questions about the cause, it was clarified that although the
lines had been previously located, the actual infrastructure was found to be approximately nine
feet north of the marked position.
If a foundation redesign becomes necessary, it could result in a six-month delay for design and
permitting before construction can resume. Any major design changes would likely require the
project to go through the entire permitting process again.
Despite these challenges, staff affirmed that the project remains feasible, as the bridge can be
constructed over the existing utilities once the plans are adjusted.
41st Street Corridor Improvement
1:09:33 David Gomez reported that the 41st Street project is currently addressing FDOT
comments following the 90% plan submittal, which included several design variances to
accommodate non-compliant existing conditions. The City anticipates receiving the permit within
30 days and plans to advertise the project for bidding in February, with a contract award expected
three to four months thereafter.
In response to a question about narrow sidewalks, Gomez explained that the project will improve
pedestrian comfort by adjusting the placement of trees and signage; however, most sidewalk
widths will remain unchanged due to roadway constraints.
Flamingo Park
1:16:42 Bryan Niedelson provided an update on active projects within Flamingo Park:
Lodge: construction is nearly complete. The team is closing out permits and preparing to turn
the building over.
Baseball Stadium: CIP is working with procurement to issue an Invitation to Bid (ITB) to secure
a contractor, while a separate solicitation is being prepared for the design of the Baseball
Field.
Softball Field: construction is nearing completion, with Substantial Completion expected in
approximately six weeks, followed by about a month of punch list work.
Butterfly Garden: the design is being revised again to integrate it with the temporary daycare
facility, which has returned to the site after previously being removed.
V. Public Comment
No one from the public requested to speak.
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 7 of 9
2018 G.O. Bonds for Arts &Culture
VI. Arts & Culture General Status Update
(Refer to pages 26-32 of the Agenda & Handouts Packet on the G.O. Bond website.)
1:21:36 Thais Vieira reported that the total number of sub-projects has decreased from 48 to 43.
This change is due to the Miami City Ballet sub-projects, which were originally planned to be
executed by the City, being consolidated into a single grant to Miami City Ballet, which will now
oversee the project’s execution.
She also reported that approximately $3.3 million has been spent since the last update.
Additionally, the commencement of construction for the sub-projects at the North Beach
Oceanfront Center (NBOC) has been rescheduled to Q2 2026 to allow for better coordination
with the facility’s programming.
1:23:17 Daniel Veitia asked whether the funding challenges due to the structural unforeseen
repairs have been resolved. Thais Vieira reported that the first phase of the structural repairs has
been funded. The second phase will be funded through the capital budget process for next fiscal
year.
1:23:49 Daniel Veitia inquired about the timeline for removing scaffolding. Daniel Alzuri
responded that it is difficult to provide a definitive date at this stage. As structural repairs
progress, additional issues are expected to be uncovered, which will likely require relocating the
scaffolding to different sections as work continues.
VII. 2022 Bonds Projects Update
(Refer to pages 33-40 of the Agenda & Handouts Packet on the G.O. Bond website.)
Byron Carlyle Theater
1:24:49 Daniel Alzuri reported that the Request for Qualifications (RFQ) for the design team has
been issued. Responses are expected in February.
It was announced that a Town Hall meeting hosted by Commissioner Suarez is scheduled for
January 27 at 7 pm (both in-person and online) to discuss the project's history and objectives.
The Wolfsonian
1:29:22 Daniel Alzuri reported that the preliminary designs for The Wolfsonian have been
completed and underwent a round of review with FIU’s design committee. It was mentioned that
a value engineering process is currently underway, though it was clarified that the project's core
functionality and ability to host events should remain intact. The team expects to submit the
package to the Historic Preservation Board (HPB) by March or April, with a hearing anticipated in
June or July.
Thais Vieira reminded the committee that this is a grant-funded project supported by G.O. Bond
funds and county grants, but it also requires significant fundraising. In response to a committee
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 8 of 9
member's question about the fundraising timeline, it was stated that the process will likely take
about a year and will begin once HPB approval is secured.
Casey Steadman, representing the Wolfsonian, clarified that the specific fundraising goal is $4.5
million, which will run concurrently with the development of final drawings.
Holocaust Memorial MB
1:32:23 Daniel Alzuri reported that work on the Holocaust Memorial is currently being finalized
and is anticipated to reach completion in February. Reopening is expected in March. The grant
funding will remain active for approximately three to four months following the reopening to
allow for the reconciliation of project costs.
Colony Theater
1:33:16 Daniel Alzuri reported that the Colony Theater project is progressing in two distinct
phases. The first phase involves a technology improvement grant for production systems, which
experienced a significant delay due to a critical network failure in the production backbone. To
address this setback, the team re-sequenced the work to restore the local network first. The
project is now expected to be completed by June or July, with the grant closing out in August.
Several City-controlled subprojects (CR&R) have already been completed, including electrical
work, FF&E, painting, and awning installation. The installation of front-facing windows is
currently in progress and is expected to be finished within the next few weeks. Staff confirmed
that this work is being carefully coordinated with performance schedules to minimize any
disruption. In addition, preparations for “Tranche 2” of the CR&R work - which will encompass a
more comprehensive interior renovation - are now underway.
Miami Beach Botanical Garden
1:35:39 Mohsen Abu Shaaban reported that, following meetings with staff and board members
to clarify operational requirements, a master plan was developed to enhance the site’s
functionality. Due to budget constraints, the team prioritized specific items that could be
accommodated within the available funds. Conceptual designs for these short-term
improvements have now been completed.
A significant portion of the budget must be dedicated to a mandatory water management system
to meet code requirements. A new canopy will be installed at the main entrance to increase
visibility, as visitors often fail to notice the garden. The scope of work also includes renovation of
the Banyan Rooms, with the installation of acoustic separators to sub-divide the space for smaller
groups; restrooms renovation; kitchen renovation; expanding pathways; and upgrading signage.
Collins Park Rotunda
1:39:32 David Gomez reported that the restoration of the concrete artistic panels is now
complete. The process involved removing panels with significant spalling and deteriorated
G.O. Bond Oversight Committee
Meeting Minutes No. 59
January 22, 2026
Page 9 of 9
connectors, restoring them with new corrosion-resistant anchors, and re-waterproofing the
building structure. He added that the contractor was able to successfully preserve all original
pieces during the removal process. Overall project substantial completion is expected within 30-
60 days.
VIII. Community Outreach
(Refer to pages 41-42 of the Agenda & Handouts Packet on the G.O. Bond website).
1:40:52 Thais Vieira reported that while the La Gorce Park Artistic Playground was completed in
November, the date for the official grand opening is yet to be determined.
1:41:58 In response to a question from Daniel Veitia, David Gomez reported that the Bandshell
project remains in the design phase, with current plans encompassing a scope larger than the
current budget allows. It was clarified that the city is designing the entire project but has split it
into two phases to ensure work can begin on Phase 1. The design and permitting process will
likely take eight to nine months, with a submittal to the Historic Preservation Board (HPB),
expected later this year. Maria Cerna added that a capital budget request for approximately $1.9
million is being submitted to cover the funding gap; if approved, the city would be able to proceed
with both phases simultaneously. Daniel Alzuri noted that proceeding with a phased design now
prevents a loss of construction momentum while waiting for a final answer on the additional
funding.
IX. Public Comment
1:44:25 Ximena Caminos reported that the Reefline project has established a partnership with
Divers Paradise to provide three to four boat trips per week for snorkeling and diving. In response
to safety concerns regarding residents swimming to the site from the shore, it was clarified that
anyone choosing to do so should use a dive flag for visibility and safety.
Brandi Reddick reported that they have received the first Ecological Impact Study by the
University of Miami, which shows the fish population at the site has grown by the hundreds. It
was further mentioned that the first set of test corals are currently thriving, with an additional
12 corals scheduled to be planted during the first week of February 2026.
X. Adjournment
1:50:36 Meeting adjourned.