LTC 263-2004 41st Street Bridge Renovation Project
CITY OF MIAMI BEACH
Office of the City Manager
Letter to Commission No. 263-2004
m
-
To:
Mayor David Dermer and
Members of the City Commission
From: Jorge M. Gonzalez '\'v--O'
City Manager . i
I
~'
Date: October 7,2004
Subject: 41ST STREET BRIDGE RENOVATION PROJECT
A Master Plan for the beautification of the entire right-of-way of 41 st Street was prepared by
Curtis and Rogers Design Studio, Inc., and Savino and Miller Design Studio in September
1995, following an extensive community planning process. On May 1, 1996, the Mayor
and City Commission adopted a resolution appropriating $5 million for the 41 sl Street
Beautification Project. At that time, it was anticipated that the City would obtain a loan to
complete the project from a local bank, pledging 50% of the annual allocation for Middle
Beach from the 1 % Resort Tax. These funds were expected to be sufficient to repay the
loan, with interest, over a 6 year term.
On June 4, 1997, the Mayor and City Commission, following a selection process, approved
a professional services Agreement with Consul-Tech Engineering, Inc. (CTE), in the
amount of $413,222, for the design and construction administration of the project to
renovate and beautify the Right-of-Way of 41 sl Street from Alton Road to Collins Avenue.
This Agreement anticipated that the complete renovation of the 41 st Street right-of-way
would be undertaken, in a 5-phase project, with a total project budget of $5 million. The
originally proposed five phases consisted of the following improvements:
Phase I
Phase II
Phase III
Phase IV
Phase V
Landscaping, irrigation & replacement of pavers on both sides of 41 sl Street
Medians with irrigation, up-lighting and landscaping on 41st Street.
Improvement of Indian Creek and Biscayne Waterway bridges.
Improvement of side streets with lighting, landscaping and irrigation.
Improvement of 40th and 42nd Streets, landscaping and repaving.
Subsequently, it was determined that collections from the Resort Tax were insufficient to
fund the anticipated debt service on the proposed $5 million loan, and the full proposed
scope of the project was not considered feasible. Therefore, the scope of work was
revised. On March 12, 1998, the Finance and Citywide Projects Committee recommended
that only Phase I and Phase II of the originally planned 5 phases of the project be
undertaken, at an estimated cost of $1,727,250. Following this reduction in scope, the
Agreement with CTE was renegotiated to a level commensurate with the reduced project
scope. The required design work was completed, and the construction of the reduced
scope streetscape project, including the revised landscaping, irrigation, median
construction, and paver installation along 41st stis~~.fIt(0~)lJtdii~R6~~0 Pine Tree Drive,
this work was completed in 2001.
68 :~ Wd 8- DO ~o
03^1303tj
While renovation of the Biscayne Waterway and Indian Creek bridges was a part of the
original Master Plan as Phase III, it was removed from the project scope in March of 1998.
However, since the completion of the reduced scope 41st Street Beautification Project,
members of the 41st Street Merchants Association have continued to request that the
bridge renovation portion of the project be done, because they consider that the lack of a
finished look on the bridges makes the street appear incomplete.
In July of 2000, CTE was authorized to undertake the design of the bridge renovations with
a target budget of $600,000. Their design was completed and approved by FDOT in 2002.
A condition established by FDOT of the approval is that construction activities must be
accomplished between April15lh and November 15th. This requirement was imposed to
avoid impacting traffic flow during the peak tourist months.
At the time the design work was completed, the bridge renovation project could not be
undertaken due to the lack of sufficient funding. In FY 2003-04, a source of funding was
identified, sufficient to meet the construction cost estimate prepared by the consulting
engineers and an Invitation to Bid was issued by the Procurement Department on March
15, 2004.
On the bid closing date, April 20, 2004, a single bid was received for the project in the
amount of $969,845, from Ric-Man International, Inc. Since this bid is substantially in
excess of the Consultant's construction cost estimate of $621,467, and the available
budget allocation of $622,961, the Administration is not able to recommend that a contract
be awarded.
In an effort to bring the project within the available budget, the Administration met with the
sole bidder to review possible value engineering changes that might reduce the
construction cost. Some cost reducing suggestions were identified; such as: using a
different type of railing, using alternate vendors for the light fixtures, ceramic tile and
pavers, however, these were not sufficient to bring the project costs down materially. As a
result of these meetings, the contractor was also asked to provide a price for constructing
each of the bridges separately.
The sole bidder was asked to prepare a proposal to renovate the Indian Creek Bridge this
year, and to complete the Biscayne Waterway Bridge next year. The contractor proposed
a price that would lock in the cost for both bridges at today's prices. The proposal quoted
the price for the Indian Creek Bridge at $786,000, and the price forthe Biscayne Waterway
Bridge at $243,000, provided construction on the second bridge could begin within 9
months of the first. The construction cost of both would total: $1,029,000. Adding
Construction Administration and contingency, a budget of $1.29 Million would be required,
an increase of $668,000 over the existing allocation.
In order to determine if the bid price received was valid, and in an attempt to locate a less
expensive alternative, a JOC contractor was requested to price the project. The proposal
received from the JOC contractor was $1.18 Million, a price even higher than that received
from the bidder. Receipt of this high price at least validated the bid price as being in a
market range, and cast doubt on the Consultant's estimate of $621 ,467.
The City's Agreement with CTE was entered in 1997 and does not include a provision to
require the consultant to redesign the project to meet the actual construction cost, as
newer agreements do. The Consultant has been asked to provide a price proposal for the
Additional Services necessary to perform a value engineering review, to propose
approaches that may lower the construction cost of the project. CTE is preparing a
proposal for services, in the interim, they provided these recommendations: Reject the bid
received and re-advertise the project with more notice, making a strong effort to generate
interest in bidding among as many contractors as possible, and repackage the project by
dividing it into two parts with one bridge in each part.
Staff has evaluated the options and recommend the following, in order of preference:
1 Follow the consultant's recommendation. Reject the bid, re-advertise the project
aggressively, and request separate prices for each bridge. This may encourage
competition among competitive bidders, and would possibly give the City the option of
improving one bridge with available funding. The down side to this option is that it will take
an additional two to three months to re-advertise and re-bid the project before the outcome
is known, and there is no guarantee that a more competitive price will be obtained
2. Improve both bridges using the current sole bidder. If sufficient additional
funds can be identified, the City can proceed with the bidder to undertake the work at the
bid price of $969,845, less the value engineering items identified and agreed upon.
Additional funds of $551 ,251 will be required.
3, Appropriate additional funding to improve the Indian Creek Bridge only. CIP
has not obtained a price for this option alone, however based on the price given for
separating the bridges above, the Indian Creek Bridge alone would require additional
funding of approximately $321,124, if the sole bidder is willing to honor it.
4. Appropriate additional funding to improve one bridge now, the other one next
year, CIP requested the bidderto prepare a proposal to renovate the Indian Creek Bridge
this year, and the Biscayne Waterway Bridge next year, locking in the cost for both bridges
at today's price. The price for the Indian Creek Bridge is: $786,000, the price for the
renovation of the Biscayne Waterway Bridge beginning within 9 months ofthe NTP on the
Indian Creek Bridge is $243,000, for a total construction cost of $1,029,000. Adding
Construction Administration and contingency, the City would need $1.247 Million, an
increase of $625,298 over the existing allocation.
Recommendation: Staff recommends that the City reject the existing bid, re-advertise
aggressively, and reissue the invitation to bid the project. It should be noted that additional
funding will be needed for this project, to offset the cost of additional consulting services, to
provide a contingency reserve, for construction administration and to provide for an
additional cost increment over the original budget allocation. Staff intends to move forward
with this ion and place it on an upcoming Commission Agenda for your consideration.
331 Htl $,),.01318 All3
JM JEC\MB ZO :~ Wd 9-130 ~O
a3^1303~