Loading...
HomeMy WebLinkAbout2005-25808 Reso RESOLUTION NO. 2005-25808 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROPRIATING FUNDS, IN THE AMOUNT OF $313,042, FROM GULF BREEZE LOAN INTEREST, AND APPROPRIATING FUNDS, IN THE AMOUNT OF $768,244, FROM TWO- PERCENT RESORT TAX FUNDS, FOR A TOTAL APPROPRIATION OF $1,081,286; SAID APPROPRIATIONS PROVIDING FOR PAYMENT OF THE FOLLOWING MATTERS RELATIVE TO THE MIAMI BEACH GOLF COURSE CLUBHOUSE, MAINTENANCE YARD BUILDING, AND RESTROOM SHELTERS PROJECT: A CHANGE ORDER, IN THE AMOUNT OF $600,000, FOR REMOVAL OF UNSUITABLE SOIL; ADDITIONAL CHANGE ORDERS, IN THE AMOUNT OF $278,405; SUPPLEMENTAL CONTINGENCY, IN THE AMOUNT OF $100,000; REGULATORY REQUIREMENTS, IN THE AMOUNT OF $40,000; ADDITIONAL ART IN PUBLIC PLACES FEE OF $4,176; AND CAPITAL IMPROVEMENT PROJECTS OFFICE FEE OF $58,705. WHEREAS, on September 11, 2002 the Mayor and City Commission approved the award of a contract to TRAN Construction Inc. (TRAN), in the amount of $2,669,000, for the construction of the Miami Beach Golf Course Clubhouse, Maintenance Yard Building, and Restroom Shelters pursuant to Invitation to Bid No. 54-01/02 (the Project); and WHEREAS, site work at the clubhouse began shortly after issuance of the notice to proceed on January 11, 2003; and WHEREAS, soil tests taken on February 3, 2003 revealed that the building pad failed to achieve the minimum compaction required to support the weight of the future clubhouse building; and WHEREAS, the soils report produced during the design phase of the Project revealed the presence of organic soils within the construction area; and WHEREAS, such soil report recommended the removal and replacement of the muck with adequate soils; and WHEREAS, on February 18, 2003 TRAN stated its position that, as the soil report was not furnished as part of the contract documents, and that any work required to remove the unsuitable soil would be performed as a change order; and WHEREAS, on the same day, the City responded with its position, that the soil report was clearly referenced in the plans and the specifications, and that it would be TRAN's responsibility to remove the unsuitable soil accordingly; and WHEREAS, Section 34 of the Construction Contract with TRAN, entitled "Continuing the Work", obligates the Contractor to adhere to the Project schedule during all disputes or disagreements with the City, including disputes and disagreements concerning requests for change order; and WHEREAS, TRAN proceeded to remove the unsuitable soil, but began submitting requests for change orders (RCO's) totaling $1,066,307; and WHEREAS, the City's preliminary review of the RCO's and supporting documentation was issued on July 30, 2003, revealing numerous discrepancies found in the information provided by the RCO documents submitted by TRAN; and WHEREAS, as a result of several meetings with City staff, on January 15, 2004, TRAN consolidated all of the previously submitted RCO's into a single request reflecting a reduced amount of $890,343.45; and WHEREAS, on February 24, 2004, the City issued findings that the amount requested could not be supported by the City's calculations and site observations, and the documents provided by TRAN; and WHEREAS, in March of 2004, the City and TRAN entered into the contractual procedure for resolution of disputes, and began a search for a mutually acceptable mediator; and WHEREAS, through this effort, a non-binding agreement was reached by all parties that, if hereby approved by the City Commission, would approve a Change Order, in the amount of $500,000, for the de-mucking work, and an additional $100,000 for general conditions incurred during the extended Project timeline, which includes a time extension for the de-mucking work, and for all additional work on the Project; and WHEREAS, upon review of all the facts, City staff hereby recommends approval of a change order to TRAN, in the amount of $600,000; and WHEREAS, in addition to the aforestated requested change order, unforeseen site conditions, design enhancements requested by the City, possible errors and omissions, and regulatory requirements will require additional change orders in excess of the original Project contingency to complete the Project; and WHEREAS, it is foreseen that an additional $278,405 will be required to pay for additional change orders on the Project; and WHEREAS, additional change orders are likely to occur during final inspection and close-out as a result of regulatory agencies' review and requirements; and WHEREAS, it is recommended that an additional sum of $100,000 be set aside as a contingency to fund these anticipated final changes and additions; and WHEREAS, the Florida Department of Environmental Protection (DEP) has required that the City undertake further remedial action prior to the installation a new stormwater drainage well that is part of the Project; and WHEREAS, the total estimated cost to produce the documentation required by the DEP, and to perform the required remediation is $40,000; and WHEREAS, City Code Section 82, Article VII, requires that an adjustment to the appropriation of Art In Public Places (AIPP) funds be made for construction costs associated with City requested changes in scope requiring additional appropriations in excess of $200,000; and WHEREAS, the corresponding AIPP fee for this appropriation is $4,176; and WHEREAS, operating expenses for the Capital Improvement Projects (CIP) Office are funded through an appropriation of 4.8% of any project that is managed by CIP; and WHEREAS, the corresponding CIP Office fee for this appropriation is $58,705; and WHEREAS, the total supplemental funding to provide for change orders, additional services, additional AIPP fees, and CIP Office fees to complete the Project is $1,081,286; and WHEREAS, it is recommended that $313,042 be appropriated from Gulf Breeze Loan Interest and $768,244 be appropriated from Two-Percent Resort Tax funds. NOW THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission herein appropriate funding in the amount of $313,042, from Gulf Breeze Loan Interest, and appropriate funds, in the amount of $768,244, from Two-Percent Resort Tax Funds, for a total appropriation of $1,081,286; said appropriations providing for payment of the following matters relative to the Miami Beach Golf Course Clubhouse, Maintenance Yard Building, and Restroom Shelters Project: a Change Order, in the amount of $600,000, for removal of unsuitable soil; additional change orders, in the amount of $278,405; supplemental contingency, in the amount of $100,000; regulatory requirements, in the amount of $40,000; additional Art In!Ubli Places Fee of $4,176; and Capital Improvement Projects Office Fee of $58,705. \ J I PASSED and ADOPTED this 2nd day of February, 200 ATTEST: ~L&.-iL ITY CLERK T:\AGENDA\2005IFeb0205\RegularIBayshore Clubhouse Change Orders - 02-02-05 RESO.doc '~J CITY OF MIAMI BEACH CITY COMMISSION ITEM SUMMARY m Condensed Title: A resolution appropriating funds in the amount of $313,042 from gulf breeze loan interest, and appropriating funds in the amount of $768,244 from two percent resort tax, for a total appropriation of $1,081,286 to supplement the Miami Beach Golf Course Clubhouse Project contingency, to provide for change orders, additional services, AIPP fees and CIP Office fees to complete the Miami Beach Golf Course Clubhouse Proiect. Issue: Shortly after construction of the Clubhouse began in January of 2003, the contractor found presence of unsuitable soils that needed to be removed. TRAN stated its position, that a soils report was not furnished as part of the contract documents, and that any work required to remove the unsuitable soils would be performed as a change order. The City responded, that the soils report was clearly referenced in the plans and the specifications, and that it would be TRAN's responsibility to remove the unsuitable soils accordingly. The construction contract obligates the Contractor to adhere to the Project schedule during all disputes or disagreements with the City. Therefore, TRAN continued with the work, and submitted a series of requests for change order (RCO's) for this work, totaling $1,066,307. The City performed a detailed review of all de- mucking submittals and the supporting documentation and found that the amount requested could not be supported by the City's calculations, observations and records provided by TRAN. Given these irreconcilable differences, in March of 2004 the City and TRAN entered into the contractual procedure for resolution of disputes, and took the matter before a mutually acceptable mediator. Through this effort, a non-binding agreement was reached by all parties that, if approved by the City Commission, would provide TRAN a Change Order in the amount of $500,000 for the de-mucking work, and an additional $100,000 for general conditions incurred during the extended Project timeline, which includes a time extension for the de-mucking work, and for all additional work on the Project. Construction of the clubhouse is currently proceeding and is expected to be substantially completed by the summer of 2005. Unforeseen site conditions, design enhancements requested by the City, possible errors and omissions, and regulatory requirements will require additional change orders in the amount of $278,405. An additional contingency of $100,000 should be set aside to fund anticipated final changes and additions to complete the Project. The Florida Department of Environmental Protection (DEP) has required that the City undertake further remedial action prior to the installation a new stormwater drainage well that is part of the Project. The total estimated cost to produce the documentation required by the DEP, and to perform the remediation is $40,000. City Code Section 82, Article VII, requires an adjustment to the appropriation of Art In Public Places (AIPP) funds. The corresponding AIPP fee for this appropriation is $4,176. Operating expenses for the Capital Improvement Projects (CIP) Office are funded through an appropriation of 4.8% of any project managed by CIP. The corresponding CIP Office fee is $58,705. The total supplemental funding to provide for change orders, additional services, and comolete the Proiect is $1,081,286. Item Summa /Recommendation: Approve the resolution. Adviso Board Recommendation: On Janua 27, 2005 the Finance and Cit Financial Information: Source of Funds: Gulf Breeze Loan Interest Resort Tax I Finance Dept. AGENDA ITEM DATE R1G- J.-~-OS CITY OF MIAMI BEACH CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH. FLORIDA 33139 www.miamibeachfl.gov To: From: Subject: COMMISSION MEMORANDUM Mayor David Dermer and Date: February 2, 2005 Members of the City Commission Jorge M. Gonzalez 1 ~~ City Manager () 0 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROPRIATING FUNDS IN THE AMOUNT OF $313,042 FROM GULF BREEZE LOAN INTEREST, AND APPROPRIATING FUNDS IN THE AMOUNT OF $768,244 FROM TWO PERCENT RESORT TAX, FOR A TOTAL APPROPRIATION OF $1,081,286 TO SUPPLEMENT THE MIAMI BEACH GOLF COURSE CLUBHOUSE PROJECT CONTINGENCY, TO PROVIDE FOR CHANGE ORDERS, ADDITIONAL SERVICES, AIPP FEES AND CIP OFFICE FEES TO COMPLETE THE MIAMI BEACH GOLF COURSE CLUBHOUSE PROJECT. ADMINISTRATION RECOMMENDATION Approve the resolution. FUNDING Total appropriation of $1 ,081 ,286 will be partially funded from Gulf Breeze Loan Interest funds, in the amount of $313,042, and partially from Two Percent Resort Tax, in the amount of $768,244. BACKGROUND On September 11 , 2002 the Mayor and City Commission approved the award of a contract to TRAN Construction Inc., (TRAN) in the amount of $2,669,000 for the construction of the Miami Beach Golf Course Clubhouse, Maintenance Yard Building, and Restroom Shelters, (The Project). The contractual duration of the project was separated in two independent timelines: one for the clubhouse and restrooms, and another for the maintenance yard building. The City issued a notice to proceed to TRAN for the clubhouse building on January 11,2003, which established a substantial completion date of October 7,2003, with a contractual duration of 269 calendar days to achieve substantial completion. A notice to proceed was issued for the maintenance yard building on April 3, 2003, which established a substantial completion date of August 31, 2003, with a contractual duration of 150 calendar days to achieve substantial completion. City Commission Memorandum February 2, 2005 Miami Beach Golf Course Clubhouse Project Page 2 of 6 Site work at the clubhouse began shortly after issuance of the notice to proceed, and TRAN began preparing the soil layer that supports the weight of the building (commonly referred to as the "building pad"). Soil tests taken on February 3, 2003 revealed that the building pad failed to achieve the minimum compaction required to support the weight of the future clubhouse building. The City immediately informed TRAN that the existing unsuitable organic soils (commonly referred to as 'muck') under the footprint of the building would have to be removed in accordance with the requirements of the soils report produced for the Project. The soils report produced during the design phase of the Project, was used by REG Architects ("REG") to design the foundations and structure of the building. The report revealed the presence of organic soils within the construction area, and recommended the removal and replacement of the muck with adequate soils. Since organic soils compress when subjected to pressure, the weight of the building may place enough pressure on the muck to cause the building to sink, and potentially cause extensive damage to the structure. On February 18, 2003 TRAN stated its position that the soils report was not furnished as part of the contract documents, and that any work required to remove the unsuitable soils would be performed as a change order. On the same day, the City responded with its position that the soils report was clearly referenced in the plans and the specifications, and that it would be TRAN's responsibility to remove the unsuitable soils accordingly. Section 34 of the construction contract, entitled "Continuing the Work" obligates the Contractor to adhere to the Project schedule during all disputes or disagreements with the City, including disputes and disagreements concerning requests for change order. Therefore, TRAN continued with the work, and proceeded to remove the unsuitable soils. The de-mucking work continued through March, April and May of 2003. As the de-mucking work continued, TRAN began submitting requests for change order (RCO's) for this work, which totaled $1,066,307. The City's preliminary review of the RCO's and supporting documentation was issued on July 30, 2003 (copy of letter is attached as Exhibit 1), revealing numerous discrepancies found in the information provided by the RCO documents. During the several months following, the City performed a detailed review of all de-mucking submittals and the supporting documentation. As a result of several meetings with City staff, on January 15, 2004 TRAN consolidated all of the previously submitted RCO's into a single request reflecting a reduced amount of $890,343.45 (copy of the RCO is attached as Exhibit 2). On February 24, 2004, the City issued findings that the amount requested could not be supported by the City's calculations, observations and even the records provided by TRAN (copy of letter is attached as Exhibit 3). The City's analysis focused on three main areas of disagreement: 1) The volume of material both excavated and brought to the site greatly exceeded the City's estimates, 2) The unit price per cubic yard of material exceeded the fair market values researched by the City, and 3) A substantial portion of the work for which TRAN sought compensation was, in the City's opinion, part of the contract. Given these irreconcilable differences, in March of 2004 the City and TRAN entered into the contractual City Commission Memorandum February 2, 2005 Miami Beach Golf Course Clubhouse Project Page 3 of 6 procedure for resolution of disputes, and began a search for a mutually acceptable mediator. Representatives of the CIP Office, the City Attorney's Office, TRAN and its legal counsel met on June 28, 2004, September 30, 2004 and again on October 21, 2004 in the presence of a mediator, to review all of the documentation and negotiate a fair and equitable change order amount. Since TRAN has not been compensated for any portion of the de-mucking work, TRAN has only made a partial payment to its sub-contractor, Alpine Construction, who in turn has not paid its sub-contractor, Talavera Trucking & Equipment Corporation, the firm that performed the de-mucking work. Either prior to, or during, the contractual mediation process, Talavera Trucking filed a formal claim for payment against Alpine Construction for payment with the Circuit Court. In order to assist with attaining a positive outcome, the parties at mediation agreed that all affected parties should be present. Therefore, Talavera Trucking & Equipment Corp. was invited to participate in the final mediation process. Through this effort, a non-binding agreement was reached by all parties that, if approved by the City Commission, would provide TRAN a Change Order in the amount of $500,000 forthe de-mucking work, and an additional $100,000 for general conditions incurred during the extended Project timeline, which includes a time extension for the de-mucking work, and for all additional work on the Project. Upon review of all the facts, City staff recommends approval of a change order to TRAN Construction Inc., in the amount of $600,000. Construction of the clubhouse is currently proceeding and is expected to be substantially completed in the summer of 2005. Change orders that have been negotiated and approved in the amount of $342,320 include unforeseen site conditions in the amount of $146,619, design enhancements requested by the City in the amount of $111,855, possible errors and omissions in the amount of $22,994, and regulatory requirements in the amount of $60,852. It is estimated that the percent of change orders as compared to the total cost for this Project will be approximately 41 % including the de-mucking work, and 19% without. These ratios exceed the usual amount of 10% to 15% in change orders for projects of similar size, scope and contingency allocation. Other foreseeable change orders, in the amount of $155,096 are currently being negotiated, and have not been approved (a summary of all approved and foreseen change orders is attached as Exhibit 4). In addition, as commonly experienced on numerous vertical construction Projects, additional change orders are likely to occur during final inspection and close-out, as a result of regulatory agencies' review and requirements. It is recommended that an additional sum of $100,000 be set aside as a contingency to fund these anticipated final changes and additions. The total amount needed to provide for approved and foreseen change orders, and to provide a contingency for additional change orders is $597,416. Of this amount, $219,011 is funded through the existing project contingency. The additional $378,405 is needed to supplement the project contingency and complete the Project. Unforeseen conditions encountered during construction include the removal of an abandoned kerosene underground tank, removal of wood piles that supported the old City Commission Memorandum February 2, 2005 Miami Beach Golf Course Clubhouse Project Page 4 of 6 clubhouse, unexpected utility locations, and a change in the location of FP&L's electrical connection point. Design enhancements include the addition of fiber optic conduits to link all buildings across the golf course; additional data, power and cable outlets; addition of a fence to screen the maintenance building from the golf course; and an upgraded electrical system to supply power to portable A/C units for a new patio enclosure that will expand the under-roof dining occupancy from 80 to 144. Possible errors and omissions include the omission of a sales counter at the pro-shop; omission of scupper drains on the clubhouse roof; and the omission of a roofing membrane specification for the wash station building. The Architect's failure to include the soils report as part of the bid documents, has also been identified as a possible error and omission. Regulatory requirements include the relocation of the wash station building outside a contaminated area; additional drainage pipe and manholes to relocate a drainage well outside the contaminated area; additional fire sprinklers and strobes; and water quality sampling required during installation of the drainage well at the clubhouse. These regulatory requirements were not included in the original permit set that TRAN priced. REG's fees for construction administration services total $58,625 and are based upon twenty five (25%) percent of the lump sum consulting services contract with the City. While REG originally estimated a thirteen (13)-month duration for the Project, it is now expected that the actual duration of the project will be 26 months. Throughout the extended construction time, REG has continued to provide services on the Project. On December 13, 2004 REG requested compensation in the amount of $197,940 (copy of REG's letter is attached as Exhibit 5), of which $148,575 are for additional services rendered during the extended period of time. City staff found that a portion of REG's request may be legitimate, however, other factors which must be considered include design errors and omissions, excessive unforeseen conditions, and REG's potential liability in its role in the de-mucking issue, and REG's failure to include the soils report as part of the bid documents submitted, and in not fully assisting the City in the resolution of this dispute. Therefore, City staff has informed REG that their request for additional services is premature, and will not be considered until after the completion of the Project. At that time the City will fully evaluate REG's performance on the Project, establish a value to the aforesaid responsibility, and initiate negotiations towards resolution of the matter. The Florida Department of Environmental Protection (DEP) has required that the City undertake further remedial action prior to the installation a new stormwater drainage well that is part of the Project. Construction of the maintenance building is currently being delayed pending resolution of this issue. The total estimated cost to produce the documentation required by the DEP and to perform the required remediation is $40,000. Performance of this work will allow the Contractor to proceed with the installation of the well, and complete construction of the maintenance yard. City Code Section 82, Article VII, requires that an adjustment to the appropriation of Art in Public Places (AIPP) funds be made for construction costs associated with City requested scope changes requiring additional appropriations in excess of $200,000. The corresponding AIPP fee for this appropriation is $4,176. City Commission Memorandum February 2, 2005 Miami Beach Golf Course Clubhouse Project Page 5 of 6 Operating expenses for the Capital Improvement Projects (CIP) Office are funded through an appropriation of 4.8% of any project that is managed by CIP. The corresponding CIP Office fee for this appropriation is $58,705. This Project is part of a larger, multi-year, multi-phase project which includes the construction of the Miami Beach Golf Course. As such, it shares portions of its funding with previous phases, as well as other related projects, including the Normandy Shores Golf Course, Normandy Shores Clubhouse, and FP&L Utility Under-grounding from 20th to 40th Street. The totality of all these projects encompasses numerous accounts and involve multiple City Departments over several years. The Administration has performed a reconciliation of some of the accounts related to these projects, but has not exhausted its efforts. The amount presented here represents the greatest possible amount of additional funding that may be needed to complete the project, and since completion is nearing, the Administration recommends appropriation of $1,081,286 to complete the project, providing for change orders, additional services, regulatory requirements, AIPP fees and CIP Office fees, as summarized in the table below. If, after the reconciliation effort is completed, it is found that less funding than requested is needed, the remaining funding will be returned to the original funding sources. ALLOCATION TOTAL AMOUNT $ 600,000 $ 278,405 $ 100,000 $ 40,000 $ 4,176 $ 58,705 $1,081,286 In addition to the construction issues described above, there have been extensive environmental remediation activities at the site which resulted from requirements and directives issued by the Department of Environmental Regulation & Management (DERM). These activities involved identification and removal of several areas within the property that were contaminated by the continuous disposal of agricultural materials onto the soils by the former golf course management firm. The environmental remediation effort also included further removal of soils necessary to perform the underground installations and excavations for structural foundations for the maintenance building which is part of the scope of the TRAN Project. Because of the involvement of several departments and because events related to the City's procurement and financial systems, a shortfall in the available funding to complete payment on the subject activities has been identified. The amount of the shortfall is currently estimated at $530,000 which is still being evaluated and researched. A Commission Memorandum and Resolution with full explanations will be City Commission Memorandum February 2, 2005 Miami Beach Golf Course Clubhouse Project Page 6 of 6 submitted to the City Commission for action by the Public Works Department at the February 23, 2005 meeting. It is referred to in this memo because of discussions that ensued on this matter at the Finance and Citywide Committee of January 27,2005 On January 12, 2005 the City Commission approved a referral of the Miami Beach Golf Club Clubhouse Project appropriation item to the Finance and Citywide Projects Committee. At the January 27,2005 meeting, the Administration presented a request for additional funding, in the amount of $1 ,081 ,286 to complete the Project and included the details and support material for the request. The item on the de-mucking non-binding agreement resulting from the mediation was discussed at length. The members of the Committee asked for more details on reasons why the City was recommending the subject amount of $500,000 and the process which the City followed in arriving at such amount. Members were particularly concerned with a previous analysis performed by CIP staff that had stated TRAN was perhaps entitled to a much lower amount and how the parties had moved towards the presented agreement value. Discussions were somewhat limited by established confidentiality clauses present in the mediation process and both TRAN's attorney and the City's attorney expressed concern about proper presentation of the facts without impacting the confidentiality clause. In the end, the members of the Committee voted to refer the item to the full Commission and directed all parties to be present at the February 2, 2005 meeting to discuss all aspects and details of the issue. T:\AGENDA\2005IFeb0205IRegular\Bayshore Clubhouse Change Orders - 02-02-5 Memo.doc EXHIBIT 1 CITY COMMISSION MEMORANDUM FEBRUARY 2, 2005 MIAMI BEACH GOLF COURSE CLUBHOUSE CITY OF MIAMI BEACH CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH. FLORIDA 33139 www.miamibeachfl.gov CAPITAL IMPROVEMENT PROJECTS OFFICE Telephone 305 673-7071 Facsimile 305 673-7073 July 30,2003 Henry T. Louden, President TRAN Construction 420 Lincoln Road, M-1 Miami Beach, Florida 33139 VIA FACSIMILE (305) 673-5428 AND US MAIL Re: Review of RCO's Related to Site Excavation Work at Bayshore Clubhouse Dear Mr. Louden, Over the past several months, TRAN Construction has submitted to the City a total of eighteen Requests for Change Order (RCO's) related to de-mucking work for the Bayshore Clubhouse, amounting to over $1 million. As agreed upon during a meeting held on July 24th, 2003 with TRAN Construction, the City, the Program Manager, and the Consultant, the following is a detailed list of issues pertaining to these RCO's. 1. There is a large discrepancy in the volume of fill (both removed and brought to the site), between the amount alleged by TRAN Construction through its RCO's and any reasonable estimate of the City. In attempting to verify the amounts presented by TRAN Construction, the City estimated the volume of fill, utilizing the following assumptions: a. The footprint of the building, including the terrace area, was squared off resulting in a larger surface area than the actual contour of the building and terrace areas combined; b. A soil swell factor of 20% was used to account for the increase in voids between undisturbed material and hauled material; and c. The volume calculation was based on an average depth of excavation of ten feet below existing grade throughout the entire area. The following is a breakdown of the process used by the City to calculate the estimated volume of excavated muck, as well as the volume of required fill: a. The building footprint of 9,864 ft2 was squared off, resulting in a rectangular footprint measuring 200ft x 75 ft, or 15,000 ft2. Note that this area is larger than the sum of the actual building and terrace; b. The over-excavation area of 6 feet was added to the perimeter of the rectangular footprint, resulting in an area of 212ft x 87ft, or 18,444 ft2; c. The total area of 18,444 ft2 was multiplied by the average depth of 10ft to obtain a total volume of 184,440 ft3, equivalent to 6,831 Yds ; and Review of ReO's Related to De-Mucking Work July 25, 2003 Page 2 of 4 d. Applying a swell factor of 20% results in a total volume of 8,197 Yds3. TRAN Construction has submitted RCO's alleging that 20,592 Yds3 were removed from the site, and that 17,370 Yds3 were brought to the site. Both of these amounts are more than double the City's estimated volume of 8,197 Yds3. 2. As backup material for justification of the RCO's, TRAN Construction has submitted approximately 2,300 hauling tickets from Talavera Trucking. The following is a list of issues related to these tickets: a. Although most tickets do not reflect the capacity of the truck, some indicate that 18 Yd3 trucks were used. Assuming that all trucks had a capacity of 18 Yds3, then there should be 1144 tickets for the alleged volume of material removed and 965 tickets for the alleged material brought to the site for structural back fill. None of the tickets indicate if material was being hauled in or out of the site. b. None of the hauling tickets were signed by TRAN Construction's superintendent, as required by contract, and as previously requested by the City. c. There are several instances where truck tickets indicate a specific truck and driver made 7, 8 or 9 trips on the same day. Given the time it takes to fill an 18 Yd3 truck, drive to the designated site, unload the material and drive back to the site to repeat the process, it is highly questionable that this could be accomplished. d. The job site addresses listed on some tickets does not reflect the address for the Bayshore Clubhouse site. Hauling tickets pertaining to other jOb sites will not be considered as legitimate. e. TRAN Construction submitted photocopied tickets, several of which were found to be reduced in size and submitted in duplicate. Duplicate tickets will not be considered as legitimate. 3. The unit costs per cubic yard of material hauled significantly exceeds current industry rates. The following is a comparison between the hauling unit costs in the RCO's and current industry rates that would be acceptable to the City: UNIT COSTS IN ReO's a. Hauling and disposal of Muck = b. Purchase and hauling of Structural Fill = c. Purchase and hauling of Limerock = $15.01 Yd3 $24.20 Yd3 $19.58 Yd3 CURRENT INDUSTRY UNIT COSTS a. Hauling and disposal of Muck = b. Purchase and hauling of Structural Fill = c. Purchase and hauling of Limerock = $12.00 Yd3 $ 8.54 Yd3 $ 9.54 Yd3 Review of ReO's Related to De-Mucking Work July 25, 2003 Page 3 of 4 4. The RCO's include hourly costs for operation of heavy equipment. It was foreseeable that the extent of de-mucking work would require heavy equipment to be kept on site for an extended period of time, therefore, it is inappropriate to bill for this equipment by the hour. The City believes that at a minimum, a weekly rate should be used. Upon receipt from TRAN Construction of equipment designations, we will provide data on acceptable industry standard rates. 5. There are discrepancies between the amount of hours billed for equipment, and the observed, or possible use of equipment. a. RCO number 18 requests an allowance for 8 weeks of de-watering. The program manager inspector, and related logs indicate that the equipment was only used for a period of 4 weeks. b. ReO number 17 for the period 2-20-03 thru 03-01-03, a period of (7)- working days, requests an allowance of 188.5 hours for a bulldozer. The program manager inspector, and related logs, which were validated by TRAN Construction's superintendent, indicate (2)-bulldozers for a period of (5)-days for that period of time. Therefore, each dozer would have had to perform 19-hours per day. 6. We reiterate our statement of financial responsibility in that the City agrees to compensate TRAN Construction for all excavation below the 6-foot depth of muck indicated in the soils report. The contract documents, including plans and specifications, contained directions for the contractor to consult the soils report. Such directions include the following: a. Sheet S-3 of the Bid Set specifically states that "All Site Preparation and Excavation work is to be performed in strict accordance with the Report on Soils and Foundation Investigation Prepared by Law Engineering and Environmental Services Inc., dated April 16, 2001 and that the building Site should be excavated to the depth and extent indicated in the soils report." b. Technical Specifications, Division 2, Section 1.6 B. (Page 02260-2) states that "Project Site Information: A geotechnical report has been prepared for this Project". c. Division 1 of the Contract Documents also states that "the contractor by virtue of signing the Agreement, acknowledges that it has satisfied itself as to the nature and extent of soil (surface and underground) and water conditions on the project site." Based on the above provisions contained in the contract documents, it was the contractor's responsibility to obtain and review the soils report prior to bidding and commencing any work on the building pad. 7. During a meeting held on July 24th, 2003, TRAN Construction stated that daily reports detailing construction activities throughout the de-mucking work period, were available for review. Immediately after the meeting, the City through its Program Manager, URS, Review of RGO's Related to De-Mucking Work July 25, 2003 Page 4 of 4 requested a copy of such reports. An inspector was sent to the jobsite trailer to pick up the reports, where he was advised they were not available. The same inspector later visited TRAN Construction's offices, where again he was advised the reports were not available. As of July 29, 2003, TRAN Construction has only submitted a portion of the daily reports. The nature and extent of questionable and irregular information evidenced in the previously submitted documents is more consistent with fraudulent practice than mere oversight. Therefore, as the necessary documents are gathered and prepared by TRAN Construction for re-submittal to the City, close attention should be paid to each of the above items. Once we receive a revised submittal, we will review it promptly. Sincerely, ~av{O bt0 Mauro Burgio; .E. Senior Capital rojects Coordinator Enclosure - Ordinance No. 2003-3398 c: Tim Hemstreet, Director Rhonda Montoya Hasan, Senior Assistant City Attorney Jorge E. Chartrand, Assistant Director Todd Osborn, URS Colin Price, REG h {.,c Lof>'f F:\CAPt\$aJl\Mauro\LellersITran on De-Mucking ReO's - REVJ.doc EXHIBIT 2 CITY COMMISSION MEMORANDUM FEBRUARY 2, 2005 MIAMI BEACH GOLF COURSE CLUBHOUSE ATTN: PROJ: NATALIE HOSEIN - URS BAYSHORE CLUBHOUSE MIAMI GOLF CLUB HOUSE (JJ THAN CONSTRUCTION PHONE#: FAX#: PCO#: 305-884-8900 305-884-2665 19 DATE: REVISION: TRAN #: 1/15/2004 3 3671 QTY I UNIT DIVISION 2 CC DESCRIPTION I SUB UNIT PRICE TOTAL SITEWORK ..I. FROM 2/24/03 - 7/10/03 COSTS FROM ALPINE FOR REMOVAL, DEMUCKING, NEW L1MEROCK, NEW SHOTROCK & EQUIPMENT TIME SEE ATTACHED I I I ALPINE I $ 773,165.80 $ 773,165.80 THIS RCO REQUIRED A PROJECT TIME EXTENSION OF 97 WORKING DAYS THE ADD'L COSTS FOR LIMEROCK FILL REQUIRED AT THE PATIO, PLANTERS & TERRACE ARE NOT INCLUDED SEE REVISED RCO II 49 FOR ADD'L INFO 1 LS 20000 SUBTOTAL FOR SUB AMOUNTS GC FEE ON SUB AMOUNTS SUBTOTAL ON SUB AMOUNTS GC AMOUNTS FROM ABOVE 14000 GC SUPERVISION $ SUBTOTAL GC AMOUNTS GC FEE ON TRAN AMOUNTS SUBTOTAL FOR TRAN AMOUNTS SUBTOTAL FOR TRAN & SUB AMOUNTS 10200 BOND 10300 BUILDERS' RISK INSURANCE SUBTOTAL 10600 PERMIT, PROCESSING & CC FEES TOTAL COSTS PLEASE CALL WI ANY QUESTION77REG RDING T 'PROPOSAL. SUBMITTED BY: ~ 711 "/ 1/15/2004 HENRY T. LOUDEN 1//1 1/ I DATE TRAN CONSTRUCTION, INC. P <r ( 48.89 $ 773,165.80 7.50% $ 57,987.44 $ 831,153.24 $ - X 776 HRS $ 37,938.64 97 WORKING DAYS $ 37,938.64 10.00% $ 3,793.86 $ 41,732.50 $ 872,885.74 $ 17,457.71 $ - $ 890,343.45 $ - $ 890,343.45 50 50 NATALIE HOSEIN - URS DATE 420 LINCOLN ROAD. SUITE M-1 MIAMI BEACH. FL 33139 PHONE 305-673-5427; FAX 305-673-5428 3671 Reo's 1-20.xls - Reo (19) R(3) - 1/16/2004 - PAGE1 OF 1 December 16,2003 Tran Construction LLC 420 Uncoln Road Miami Beach, Florida RE: Bayshore Golf Course 2301 Alton Road, Miami Beach, Florida Alpine Construction Management Corp and Talavera Trucking & Equipment Corp. Dear Mr. Louden: Attached please find the letter dated December 15, 2003 from Talavera Trucking & Equipment Corp. indicating the cost breakdown of the above the referenced project As per our previous billing, please notice that Mr. Talavera has deducted $3,000.00 for the removal of the initial building pad. ALPINE Below please find our billing breakdown; CDNmWCI10N MANAGEMENT CORP. Total amount billed by Talavera Trucking $702,878.00 I Alpine's Overhead & Profit S 70.287.80 Total amount billed to Tran Construction S773 165.80 If you have any questions, please do not hesitate to contact our firm at 305-263-6883. I t] i "'. ;. )' MPHL---~ 7005. N. '''1'~rw~y Drive; Unit 305, Miami, Florida 33155 . ol'Iie<: (3!l'1) 263-,6tlll3. Fi'x (305) 263-6884 . . . , ' , fl I i I I I to~ L)J~LSNOJ a~Id1Y tgggC96S0C XYd Tt:.G to/ST/TO TALAVERA TRUCKING & EQUIPMENT CORP. 4341 S.W. 95"' Coun Miami, Florida 33165 Phone: (786) 402-3511 F 8.A; (305) 553-7492 December 15, 2003 Alpine Construction Management Corp. 7005 N. Waterway Drive, Suite 305 Miami, Florida 33155 RE: Baysbore Golf Course 2301 Alton Road, Miami Beach, Florida Dear Mr. Quero: As per your request enclose please find the break down of actual cost of my billing for the Bayshore Golf Course de-mucking and back filling of the clubhouse building pad. Equipment RentaJ - Please refer previous billing. $213,224.00 Dispose of Material, 1168 loads $105,120.00 Hauling and Dispose $116,800.00 Note; the above prices included charges imposed by Dade County Dump Sites. Location and prices have been provided previously with billing as per your request. Back Filling Material Shot Rockfill, 367 loads Material Cost Hauling Cost $ 40,958.00 $ 50,792.00 Lime rock fill 566 load Material cost Hauling cost $ 51,958.00 L60.128.00 co IP1 TALA VERA TRUCKING & EQUIPMENT CORP. 4341 S. W. 951b Court Miami., Florida 33165 Phone: (786) 402.3511 Fill(: (305) 553.7492 SUBTOTAL $638,980.00 $ 63.898.00 $702,878.00 OH&P@lO% GRAND TOTAL Note: Hauling charges included, labor burden @ 31 % and fuel cost. Please be aware I have remove $3,000.00 charges for removing the initial pad fill from the previous invoices. Should you have any questions, please do not hesitate to contact our finn. Sincerely, i'~ TRUCKING & EQUIPMENT CORP. .l:Jml.lS'Io:) q"'T ,i"Hi tAQQrQ~enr vv~ T~:77 ~nieT/Tn EXHIBIT 3 CITY COMMISSION MEMORANDUM FEBRUARY 2, 2005 MIAMI BEACH GOLF COURSE CLUBHOUSE PI~~....,. FILE COpy CITY OF MIAMI BEACH CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH. FLORIDA 33139 www.miamibeachtl.gov CAPITAl IMPROVEMENT PROJECTS OFFICE Telephone 305 673.7071 Facsimile 305 673.7073 February 24, 2004 Henry T. Louden, President TRAN Construction 420 Lincoln Road, M-1 Miami Beach, Florida 33139 VIA HAND DELIVERY AND US MAIL Re: Bavshore Clubhouse - De-muckinq Dear Mr. Louden, This letter is in response to Tran Construction's (TRAN) request for the City to review proposed change order (PCO) no. 19 dated January 15. 2004. TRAN's request is based on additional information that was provided to the City on January 16. 2004. The information provided on that date, a complete set of 15 soil boring reports, is a highly critical component of TRAN's proposed change order. Over the past few weeks, the City has taken an extensive and exhaustive look at the totality of TRAN's request to arrive at a proposed solution that is fair and consistent with the contract. The City offers the following regarding PCO no. 19: To determine the fair and reasonable value of the work performed, the following items need to be established: 1. Volume of the excavation. 2. Fair market value per cubic yard of material handled. 3. Portion of the work in TRAN's contract vs. work that warrants additional compensation. The City has researched each of the above 3 items extensively, including the highly critical information noted above and recently provided to the City. Volume of the Excavation In support of its PCO, TRAN provided a complete set of 15 soil boring reports from tests performed on site after completion of the building pad. (Note: TRAN was in possession of these reports since September 2003, and with the exception of a select few borings, did not provide this information to the City until January 16, 2004). It should be noted that 12 of the 15 borings performed by All State Engineering, were taken from atop the building pad, at elevation 8.0, which is approximately 5 feet higher than the Bayshore Clubhouse - De-mucking February 24, 2004 Page 2 of 6 existing grade elevation of 3.0. Hence, the first 5 feet of all the borings starting with the letters A and B represent the building pad, which is included in TRAN's contract for construction of the Clubhouse. Since the excavation that is the subject of the pca preceded the building pad chronologically, the volume analysis must begin at the existing grade line at elevation 3.0. The City's determinations as to the depth of excavation are based on the findings of the original soil boring tests performed by MACTEC (formerly LawGibb Group) dated April of 2001, in conjunction with information contained in the 15 soil boring tests performed in September 2003 by All State Engineering under contract with TRAN. For the purposes of this analysis, the primary indicator used to determine depth of excavation is the standard penetration number, designated as "N". N is the number of blows required to drive the soil sampler through a one-foot depth of soil, and it is commonly used to correlate several physical parameters of soils. The compression strength of soil, is one such parameter that can be correlated with the standard penetration number, N. A high N value is an indicator of a dense soil, while a low N value is an indicator of a loose soil (see table in exhibit "A"). An N value of 10 or less is generally associated with granular soils that are loose. The presence of loose soil is an indication that the soil has not been compacted. An N value of 30 or more is generally associated with granular soils that are dense, and may indicate either a naturally dense soil, or a soil that has been compacted. Section 02220-3.05-C of the specifications for the Bayshore Clubhouse requires that each layer of fill under the slab of the building be compacted to 98% of its maximum density. In a soil boring, such degree of compaction would be reflected as high N values, consistent with dense soil. It appears that TRAN complied with the requirement to compact the fill, given its use of a vibratory roller and de-watering techniques to achieve the right conditions for compaction, which are also reflected in passing results of density tests. The test borings performed by All State Engineering indicate that the 5.0-foot building pad is generally well compacted, exhibiting N values generally above 30. The layer of soil directly below the building pad is also generally composed of well compacted material. This layer varies in thickn'ess from 3 to 9 feet, and has an average thickness of 6.0-feet. Below this layer, there is a clear transition from dense soil to medium-loose soil. The medium-loose soil in this layer is evidenced by N values lower than 20. Such low N values indicate that the soils in this layer have not been compacted. The transition line between the dense soil layer and the medium-loose soil layer (density transition line) as indicated by the N values in All State Engineering's report, does not always coincide with transition line (descriptive transition line) between what the testing company referenced as "fill" and "beach sand". For 9 of the 15 borings, the density transition line is higher than the descriptive transition line, while for the remaining 6 borings, the two lines coincide (see exhibit "B"). It is unknown why All State Engineering chose to describe certain soils encountered generally 6' to 14' below grade as "fill"; since the native soil's composition at the same Bayshore Clubhouse - De-mucking February 24, 2004 Page 3 of 6 general depth, pre-construction, coincides with the composition of the soil described as "fill". The original soil report by MACTEC describes the layer of soil at these depths as: "medium dense, gray, fine sand with shell and limestone fragments", while the All State Engineering report describes the layer at the same depth as: "FiII- Tan lime rock & lime sand". It should be noted that, other than the color, the composition of this layer of soil as described in the pre-construction and post-construction borings is essentially the same. Hence, the variation in standard penetration number, N, offers a better indicator of depth of excavation than the soil description. When compacting select fills such as the ones used on this project, the roller is typically operated between soil layers of one foot or more, while still acl1ieving a desired level of compaction. This is because the layer of soil influenced by the roller extends two feet or more under the surface of the soil being compacted (see exhibit "A"). The density transition line is not an accurate indicator of the actual depth of excavation: rather it represents the depth to which the soil has been influenced by compaction. The depth of excavation is typically two to three feet above the depth of influence, because the first lift of compaction influences the native soil underneath. For the purpose of this analysis, the depth of excavation, (excavation line) is estimated as a line located only one-foot above the density transition line. Exhibit "8" illustrates how the depth of excavation was determined for each boring location. A plan view representation of the soil borings, shown on Page 1 of Exhibit "C", reveals that it is possible to draw three distinct cross-sectional lines. These resulting cross-sections: A- A, 8-8, and C-C shown in Exhibit "c" reveal a detailed profile of the excavation at each of these locations. The cross-sectional area of each section is computed, and used to calculate the total volume of excavation. Page 6 of Exhibit "c" illustrates how the total volume is calculated. Note that additional cross-sections, D-D and E-E were created for purposes of calculating the total volume. These are not based on post-construction soil boring data, because there are no such borings available at these locations; however, there are pre-construction borings at both of these locations, which revealed a depth of unsuitable soil of four feet. This data was utilized to create sections D-D and E-E, which show the entire cross-section excavated down to the maximum depth of unsuitable soil. The results of the cross-sectional analysis of the excavation based on the soil borings yields a total excavation volume of 3,869 Cubic Yards. Fair Market Value per Cubic Yard of Material Handled Even a small variation in the unit price per cubic yard of material results in significant variation of the total dollar amount, therefore it is important to determine a fair unit price. The unit prices listed in TRAN's change order request include a 10% markup for Talavera Trucking (TRAN's subcontractor's subcontractor), plus an additional 1 0% markup for Alpine Construction (TRAN's subcontractor), plus an additional 7.5% markup forTRAN, resulting in a total markup of 30% over the original price. Please note that sections 38.2 through Bayshore Clubhouse - De-mucking February 24, 2004 Page 4 of 6 38.4 of the contract between TRAN and the City for this project only allow a 10% markup for one subcontractor and a 7.5% markup for TRAN. The City obtained quotes from two independent local trucking companies to purchase and deliver identical materials to the Bayshore clubhouse site, and to remove and dispose of unsuitable material from the site. The vendors' quotes were consistent with each other and when averaged resulted in the following unit prices: Unit price per cubic yard of muck hauled & disposed = $5.60 Unit price per cubic yard of shot rock purchased and delivered = $10.25 Unit price per cubic yard of limerock purchased and delivered = $11.33 For the purpose of this report, a 10% subcontractor markup was added to the above unit prices, and a 7.5% markup was added to allow for TRAN's overhead and profit, resulting in the following unit prices: Unit price per cubic yard of muck hauled & disposed = $6.62 Unit price per cubic yard of shot rock purchased and delivered = $12.12 Unit price per cubic yard of Iimerock purchased and delivered = $13.39 For the purposes of determining a fair compensation per cubic yard of material handled, the City would be willing to use the above unit prices, where applicable. TRAN's proposed change order includes a charge of $213,224 for rental and operation of equipment needed to remove muck and to place and compact fill material. To evaluate the fairness of these equipment charges, the lump sum cost was translated to a unit cost per cubic yard, and then compared to a fair market value estimated using the current R.S. Means Building Construction Cost Data book as shown in the attached spreadsheet (see exhibit "0"). The equipment charge per cubic yard of material in TRAN's change order request is $5.64 per cubic yard. As part of establishing its means and methods of construction, TRAN may decide to utilize multiple pieces of equipment to get the job done, however, for the purpose of estimating the equipment charges, it is noted that each cubic yard of muck needs to be handled by only one piece of equipment: an excavator or trackhoe of some type to remove the material from the ground and place it in the truck. In addition, it is noted that each cubic yard offill needs to be handled by only two pieces of equipment: an excavator or trackhoe to remove it from the truck and place it in the ground, and a roller to compact the material. Fair market values for equipment were calculated in accordance with these assumptions (see exhibit "0" for a detailed calculation). The estimated unit costs are as follows: Equipment unit cost for unsuitable material excavated = $2.31/ CuYd Equipment unit cost for clean fill placed and compacted = $3.08/ CuYd For the purposes of determining a fair compensation for equipment costs per cubic yard of material handled, the City would be willing to use the above unit prices, where applicable. Bayshore Clubhouse - De-mucking February 24, 2004 Page 5of6 Portion of Work in TRAN's Contract vs. Work that Warrants Additional Compensation As stated on page 3 of the City's letter dated July 30,2003, the City agrees to compensate TRAN Construction for all excavation below the 6-foot depth of muck indicated in the soils report. The contract documents, including plans and specifications, contained directions for the contractor to consult the soils report. Such directions include the following: a. Sheet S-3 of the Bid Set specifically states that "All Site Preparation and Excavation work is to be performed in strict accordance with the Report on Soils and Foundation Investigation Prepared by Law Engineering and Environmental Services -lnc., dated April 16, 2001 and that the building Site should be excavated to the depth and extent indicated in the soils report." b. Technical Specifications, Division 2, Section 1.6 B. (Page 02260-2) states that "Project Site Information: A geotechnical report has been prepared for this Project". c. Division 1 of the Contract Documents also states that "the contractor by virtue of signing the Agreement, acknowledges that it has satisfied itself as to the nature and extent of soil (surface and underground) and water conditions on the project site." Based on the above provisions contained in the contract documents, it was the contractor's responsibility to obtain and review the soils report prior to bidding and commencing work. The total calculated excavation volume of 3,869 cubic yards consists of 3,580 cubic yards excavated above a 6-foot depth, and 289 cubic yards excavated below a 6-foot depth. The compensation to TRAN summarized in Exhibit "0" takes into account a swell factor of 35%, resulting in a total volume of 390 cubic yards. This amount is multiplied times the revised unit prices as presented above, resulting in a total fee of $9,41 0.12. The City is therefore prepared to issue TRAN a change order in this amount. Sl~:'g~,o Mauro Burgio, E. Senior Capital rojects Coordinator Enclosures: Exhibit "A" - Excerpts from the Book "Construction of Fills" Exhibit "B" - Marked up Soil Boring Logs Highlighting Density Transition Lines Exhibit "C" - Soil Boring Plan View, Cross Sections, and Volume Calculations Exhibit "0" - Spreadsheet Summarizing Unit Costs and Compensation c: Tim Hemstreet, Director Rhonda Montoya Hasan, Senior Assistant City Attorney Jorge E. Chartrand, Assistant Director BByshore Clubhouse - De-mucking February 24, 2004 Page 6 of 6 Todd Osborn, URS Grace Escalante, URS Colin Price, REG F:lCAPllSalllMaurolLetterslTran on De-Mucking RCO's - Determination.doc BAYSHORE CLUBHOUSE EXHIBIT "A" TABU '.1 IIow Counf/ltelallw Denllty .e1at1On1hlp of Sandi (Fallty h11ab1e) Relative Density Percent Range 0-10 10-40 40-70 70-95 Over 95 Designation Number of Blows per Foot N 0-4 4-10 10-30 30-50 Ovef 50 Very loose Loose Medium Dense Very dense 104 FILLS AND FILL COMPAClION TAII.I6.1 LIt TIlIcllrlel-. and Compac:1Dn lor \oWIoIa loll ~ Uti Thickness (in,) 3-5 4-7 5-8 Soil Types Fat cloys Lean cloys Silts TAlB 8-15 Suggested Compactor> Sheepsfoot roller Sheepsfoot roller Pneumatic (rubber-tired) 0( tomping- type roller PneumotIc. wobble-....neel roller: smooth drum roller; 0( smooth vibratory roller Smooth drum vibratOI)' roller Select "liS 24(+) o For moredetolledond~ocMceregadlng selecrionaC<lfl'1)OCIoB. _olagonlzoltons hove devtsed chats and lobIGI that list prcJ)IlrtIes and conslIucllon chaocterlstlcs fa soils clossltled according to the lklined System, 0 system containing 17 categorles of soils. Note, Asstoted ecwl..1t Is not within the scopeotthls book logo Inlo details 01 soil closslncatlon. For those unlomlllaWlth the UnllIed System. I '8COlTVTllII1d thalyau learn the S'/S1em. a retain a soils specialist to GI- tabllsh the carect ClasI/ncaltan(s) Ier the soI/(s) a Interest, !he Inlamatton may be bXld In Means and R:l'chEw (1963. p. 119). 1llt1. and ~e (I96Q p. 206). and In other standa'd texl$ under the~- imate heading OIClassllIcatlon of Soils. In Chapter \1 a ptop05OIls modeler thee.ocJUsNe Ul80fthe Burmls- ler s\lSfem of soli ctossItIcailcn but only tlmB WIN felf It this recarnnendaNon win __ be adopted, It It Is., 9JlPElCI it will be 0 graclJollralSlllOn rather than on abupt change. Inasmuch os most prOC11t1oners ae familia (a>d comfortable) with other systems, Source: Construction of Fills. 2nd Edition, by Edward J. Monahan. 1994 John Wiley & Sons, NY, M o o N .... 0::: ~ w ~ ~ :::! w ~ b: w "'( C/) ~ t5 -z l:! ~ c2 <.) ~ "'" ~ C/)~ 00:: ...J CO )... ...Jo ltl <w U) ~Q !@ C/) > 1i t') ~ Q ~Q. ltl a:: J: Q~ Ou CO"'" j:;: t') W zli:: ~ -C/) ..... li::z p:: u- -- :Jz <c ~ ::E~ Q ~o (.) J: lIJ' "'" CJ) 8CJ) It Q.~ .$ OJ () w CJ') :::> o J: aJ :J ..J ~ .u= l::P :>1- 1:- "co..... ... J: . :(xC) owa. UJ o i= <( Q. ..... !eo ~ . ~ ~.... Ol~ N >< $ ~ ~"' ,,- 1'0 m $ Cl ~ ~" .... - <D m $ ~ ~.... "'~ (j) m $ ~ ,....., ~::.. $~ ~;". .... - "f.,:" m $ ~ ~ " !::..:::. ~;, .., - -~ ID w C/) :J o J: co :J ...J U ~ ~"' " - SN <( w ""' !eo ~ () Cl <c OJ o z w ~ W ...J S M > LlJ ..J LlJ~ ~C! 0'" 0:: . u..> ~LlJ ..J LlJW :::>~ ..JO ;;0:: 'u.. z~ ~z CtI~ fil~ z~ ~Ct1 0::0 WW ~~ w- 0:5 enu <z Zo 0- -~ ~< <> en >< <u Cl ux Z 0:: Xw ii W LlJu.. 0 CtI u..0 CtI ~ Ox Cl :::> X~ z z ~a. cr a.w Cl LlJO W ~ 0 t LlJ Z (3 \.~ z LlJ LlJ ~ < ~ ID en S ..J ..J < 0 z :::> 0 u.. :.:: u :::> 0:: ~ en LlJ u.. Cl CtI 0 Z ~ cr :::> x 0 z ~ a. lD Cl LlJ ai' ! r lD (3 , ~ ~~ d. ::t U Cli LlJ ~ U . < ~ b (") :I' ..... W ....J <( () rn W. N en 9 . ::>~Cl O-a.. J:fQ a:lJ: ::>x ...JW o w 0:: o J: en ~ a:l u.zf- 00 00(/)111--' zl=!!;f- L1. Q<(u.wd f->zlflJ) O<(J:'o> wOf-~ CD Co? t;J:;; '" M )( > I L1.Z ~ 00 Cl II ' 5~ztLiti: ...,_1= > e W 0 _ u<-Ltcn WOli!Cllll ClJX W~ XW ~"""" 0::>< Wa.. >~ - ""N JI 0:: ....0 .. J: W_ ...JLt'.l <("jj" 0- (/)~ <( J: z o I- () UJ rJ) 0 it C9 z '<t 0 0 Ll) l"'l <l:enl- 0 ..J 0 a. - e.> N ::::> (!)z~ al a:: ~~I- W ...... u.. 0 0 Cl-Z al 0 ::!ZO :?: N a. ::::>-e.> w ..J 0 al I- ir I- a.. W a.. en <( w c5 I- W <( l- e l- e.> en <l: ..... :?: aJ ..J ..J > <( al > en al C9 en z w C9 ir z C9 1i 0 ..... E>NIOllna .:10 3E>03 Z al ..... <l: 0 z aJ J: al 0 --------------------- e.> C9 i= 3NIl NOU.V^V::lX3-l::l3^0 w Z e.> ::::> ~ ::::> (c ..J e.> a:: <( ::::> I- ~ :?: II) z w z en 0 0 :Ii:: l- e.> , a:: II) w <( 0 a:: :> :?: a.. a.. W I I I I I I I I I I I I I I I ...J 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 s. x W en co '" c.o L() v ('f) N ..- ..... N (\') v L.() to r-.. m w= C"') (I) () . ::);..e> 0-0.. IEQ co:!: ::)x ...JUJ U W 0:: o I CJ') >- <t 0 CO <: ll. C ;~ o ...J :::l al u.. o ll. o I- ~ L() ea z o 15~~ "~' zi=g;f-u. Q-tU.UJd f->z~(/) u<CIo ..- UJuf- '..... lQ ~:> '" U'l )( > I U.z ~ 00 " ' Z-of-f- O<zUJu, ... ri=>!2UJO- u-t~u.(/) UJu~o"'" (/))( <ci'" xUJ Co N ~ ~[ " z o i= <( ~ U )( UJ ...l -t f- o f- M' N 11- . 0:: .....0 ..I W_ ...JIJ') <t..... UJ' (1);0- l:D I l:D Z o .- () UJ (/) M 0 0 N 0:: ~ CO W 0 ea CJ 0 ::E N W ...J I- a: ll. w ll. en <: w U I- W r-- <: I- ea I- U en <: ...J ::E ...J >- <: CJ >- en CJ Cl co en z ea w Cl a: z Cl a: 0 z CJ <: 0 z J: CJ 0 U Cl B w Z :::l ~ :::l ...J U 0:: <: :::l l- I ~ ::E en z w z en 0 0 ~ I- U 0:: , en w <: 0 0:: ::E ll. 0.. > I I I I I I I I I I I I I I I I UJ .....J 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 X S8 UJ 0') CO I"- <0 Lt') V ('f) N ..- ..- N ('f) -q- u:> cp ~ CO o <( a. (!) z Ci ...J ~ en u.. o a. o I- T'"' III -0 I U Z o ~ u w en ;". l") N 0 0 N 0::: .... w 0 en 0 ~ N N w = III I- 0::: a. W a. en <( w c.5 S W l- t) en <( en ...J ~ N ...J >- <( en >- en en C) en z w C) cr z (!) cr 0 '<:t Z 0 en aJ <( z :r en 0 t) C) i= w z t) ~ ~ ~ ...J t) 0::: <( ~ l- =? ~ en z w z en 0 0 ~ l- t) 0::: , en w <( 0 0::: ;> ~ a. a. W I I I I I I I I I I I I I I I I ~ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 X s. W (J) CO t--. CO LO ~ C") N ~ ~ '" C") "<t L() CO ,..... CO BA YSHORE CLUBHOUSE EXHIBIT "C" PG.5 A2 , To , , , 0 T w, "'" C), 01 a:, w, ~, I~I ;?;:, i=r w, ~, ~, ,e, 91 :1 lZ, -', ~, 1=1 ~: ~: <, ~, ." I~I 0', -, BUILDING PAD IN <, '~I u.1 wi ~, :<, ~: ,0, 0, ell 0, >, TRAN'S ,w, B5 UJlo, w, 1\, CONTRACT ><, tl~, ", WI 8' x, "I, 'w' fE' I w' "I, a:, , , , , , a:, ~, , , , , 1 ~, 01 I , , , , 0' , I , , ELEV. 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 o -1.0 -2.0 -3.0 -4.0 -5.0 -6.0 -7.0 -8.0 L__________ , I , , , 1-__________ , , -----~ 1-__________ , t' MUCK ' , , ~I - - - -2'- +- ~ - - - - - - - - .f.O~:_ + + - - - - -:- ....1-' -;, - - - - - - - - - --, I I I I ---I--.I--f _ I "--- ~ I_ I I I I I I I I I I I , I, -----~~~-----------++--___l--~__________ I J I I I I I I I I I I I I -----~~~-----------++-----I--~---------- : : : TOTAL EXCAVATION =1 296 SO.FT. I :: :: -----~~~----- --+~-----I--~---------- I I I I I I I I I I I I I I --- - - T-t-'"I"'- - - - - -- - - -- - T ~- - - - -1- - r--- - _ _ _ _ _ __ I I I I I I I I I I I I I I I I I I I I I )( - MARKS N.VALUE CHANGE o - POST DE MUCKING BORINGS BY ALL STATE, SEPTEMBER 2003 . - PRE.CONSTRUCTION BORINGS BY MACTEC, APRIL 2001 SECTION D-D ELEV. 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 o -1.0 -2.0 -3.0 -4.0 -5.0 -6.0 -7.0 -8.0 X.SECTION OF EXCAVATION WITHIN FIRST 6.0-FEET . 296 SO.FT. I L x-seCTION OF EXCAVATION BEYOND 6,Q-FEET :: o SO.FT ~ I 0 , T "" "" a:, ", ~I ~, ~I ZI ZI <,;' :5' :5' >' Il' Il' BUILOING PAD IN "" ~, ..., ~, 0, 0, TRAN'S 0, 81 w, w, CONTRACT w, 8' '" 8, w' :il, w, , , I I , I I , , , ~-------- I , -----~ ~-------- -----l~L--_---~~L-J--------l-~L-------- 2'-1 : : 80': : 1-2' --+----I I---+-_ I --+-- , I I I 'I f I I I I I -----~-~--------~-~--------~--~-------- I I I I I I I I I I I f -----~-~--------~-~--------~--~-------- : TottAL EXCAVATION" I 328 sa.FT. I :: :: -----~-~--- ~-~--------~--~-------- I I I I I I I I I I I I -----~-~--------~-~--------r--~-------_ I I I I I I I I I I I I I I 'I I I . - PRE-CONSTRUCTlON BORINGS BY MACTEC. APRIL 2001 SECTION E-E X.SECTlON OF EXCAVATION WITHIN FIRST 6.Q-FEET :: 328 SOH. I L X.SECTIQN OF EXCAVATION BEYOND 6.0.FEET III o SQ.FT ~ > u> ~u > Q >~o u> z U " " cou W ~f-f- >~co 0 W ~IL.I.L. W t.> II " Z W II (0 (0 < COf-f- W ~ ..JW~ S:u..u.. :) 15Eig T ...I W II (0 U) 0 OIDW ~ ..JW~ > f-<ID :) 15Eig ...I 0 OIDW > f-<ID w ~ > > W u u a .... II) (") II) .., > ~ "!. (.) >>> .... .... (.)(.)(.) co " " 0 cnocn .... .... .... colDlD N N " CG..II!. N .... .., .., u. u. U U N <( 0 0 u. <( " .... 0 u > " "" co u> <D ..; 0 ID '" '" .... NU "'0 .. " " "1. ~ ~ '" ~~ .c b b +N f- " ~ " II) .... .... b ~+> Qc C ~ >< .:.; >< t .... ",>u 515 - ... - >< 0 10 10 >< oUo co .... .~+ :)w - ,... w '" w .... ~ - ilN '" It) ~IN +",> ~~ ~ +N > +N :) "" 0 a> ..J >+u CW 0 ~ co w (.)>co ...I "" '" (.)ID ......... 0 - .......... ID - ~u+ WW II > " W II W II "'It)> ..J~ .. ...I .. ~ .. ~ .. --~ () 11.:) .c c( .c :) .c :) .c ~..J ..J I- ..J ..J ..J ..J ..J +....:to c(o 0 0 0 0 0 0 0 >-+~ 0> > I- > > > > > U> + ~U> ~""u ....:~O'J >> + .... +.... (]) UU CO >>+ >",,01 UU> Ua>.... ~oU a>~ ~ II II ....""'" ~ u +:LO riJ ~f- f- a ~u. u. > + u>> ll') W II '" '" NUU ~ ..JW~ c:o~o :) 4:EiO -l I- ..J " II " 0 OIDw 01-1- > l-4:m wu.u. ~",,,, >w~ <EiO U ...J XIDW () >> () W<ID Uu WWW 0", ~::!;~ >;!U1 ~ :):)::> Q U II II ...J...J ...J b 000 U "'1-1- c( >>> 0 ~U.LL :E ..J...J...J ll') W II (0 CD <<c( ~ ..JW~ :E 1-1-1- ::l <>0 :::I 000 W ..J I-O..J II) 1-1-1- en 0 OIDW :::> > 1-<10 0 I CD :::> 0 0 ..J U w= >> o::~ Q Uu b ~o M 01- z ~" II JI W I- e ",1-1- ~!!! cou.u. ..- to W II (0 CD >- I . ~ ..JW~ W ~X(!) ::l <>0 ..J :ewe.. ..J f-O..J <t: 0 OIDW > f-<1Il U CJ) BAYSHORECLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 West 78" Street., 33016. Tel; (305) - 888-3373 Fax: (305) 888.7443 TEST BORING REPORT Client Tran Construction Order No 03.716 Address 420 Lincoln Road Ste#M-l., Miami, Florida 33139 Report No Project Proposed Property Hole No A.1 Address 2301 Alton Road" Miami Beach, Florida Date 07/31/03 Location 50'-0" N, of the SW comer of proposed building inside footing Driller MP & L T I Depth Description of Materials Sample Hammer Blows on IlN" Hammer (feet) - Number Sampler- Blows on Casing j 1 From 0'-0" to 0'-6" B,Fill- Tan lime rock & lime sand 38 45 1 2 From 0'-6" to 4'-0" B.Fill- Dark brown silty sand with 0'2' 48 50 93 3 Lime stone 51 60 BvIL.DIN Gr P,A,b L.Dlrl(,. II\IC:-ll..~"'!;. r\J Pi 4 2'4' 72 75 132 Go ..-l' .......... ,~. -, ~ 5 From 4'-0" to12'~_g,:)B.Fill- Tan lime rock & lime sand 60 42 " 6 {;'tIS,. ~vc--'--- 4'"6' -- --40 33 82 -- - r-- 7 31 30 /SI i2KAvA 8 6'8' I 25 20 55 1'1Q'" I 9 21 22 I - , 10 8'10' 20 16 42 , ~2 - '3 11 12 10 INRuE/JC. f- 12 10'12' 6 4 16 :-''f 13 From 12'~?.:.l0 20'-0" Grey medium beach sand 7 18 -$ 14 12'14' 17 18 35 -t;; 1- 15 18 19 16 14'16' 20 '" 39 , 1::1 ~ 17 19 18 i 18 16'18' 20 18 38 '0 11,8'20' - 19 18 19 .- -. 20 20 22 39 ri) - 21 End of Boring @ 20'.0' - - 22 20'22' 23 \--- 24 22'24' .- 25 (\ ') - , " 1/ ..-. Water level. 4 -0 below surface at 07/31/03 date "+ ~' I~ /tJ'7 ~ r/, /:---~Z'~-~ . ASEEM QUADRl, P.E. #51481 As a mutual protection to clients, the public and ourselves, all reports are submitted as the confidential property of clients, and authorization for publication of statements conclusions or c:xtract from or regarding is served pending our written .approval )<' lJ.J BAYSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING lABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRIlliNG . ENVIRONMENTAL SERVICES 2380 West 78" Street., 33016, Tel: (305) - 888.3373 Fax: (305) 888.7443 TEST BORING REPORT Client Tran Construction Order No Address 420 Lincoln Road Ste#M-1., Miami, Florida 33139 Report No Project Proposed Property Hole No Address 2301 Alton Road., Miami Beach, Florida Date location 15'-0" S. of the NW corner of proposed building Driller Depth Description of Materials Sample Hammer Blows on UN" :[E 1/. (feet) Number Sampler - g '~ ~ From 0'.0" to 3'-6" 9,Fifl- Tan)ime rock & lime sand 1-. 2 , 6,0 , 3 ::::.CJ 4 From 3'-6" to 6'-0" B,Fill- o.a!~ bro.wn medium 5 Sand with lime stone c.'tI~JT. ,,{.:.;.,..~.- 6 ----. 2.0 I.: [ij From 6'-0" to 14~0~'rTan lime rock & lime sand I ~ I _ \.1>, .\..,.L t,,.,,.;l J {j( /.01 I _ 2.~1 10 I - :J"-Jto{.),J",'L~t,,,;... HH1 (,I ,'-;r 0<:. 0,,:;,;....J ~r-:I- :./,3.10.',0 ]1~ -C,.,J <:",,.,,e '''.....f::>\"Jor. J~ -' - U"'.I ~.;'l l('..r~1 i(,,~ .~ ':,. ~ ~,o ]4 r....L,.,,\ ~J:17 ,-"-', 6.0 ] 5 From 14'-0:>to 20'.0" Grey medium beach sand L ,0 '_./ ]6 '.0 ]7 ]8 19 20 2] 'f.:J ,;. a End of Boring @ 20'.0" 22 23 24 25 Water level: 4'-0" below surface at 07/31/03 date 11S 16 0'2' 17 16 16 14 '~'4' 15, 14 15 13 4'6'---rs- .-- 18 I 20 2S I 6'8' I 24 25 8'10' I~: ~~ 8 6 10'12' S 6 4 4 12'14' 4 3 lS 16 14'16' 1~ 18 32 ,0 18 17 I 16'18' lS I 16 32 16 I 15 18'20' 14 13 29 20'22' 22'24' - 03-716 A-2 07/31/03 MP & lT 33 I Hammer Blows on Casing 1 'f,VIl:..!> INc:'- PA-!::> 29 fN c::NTr:kC t--~- 49 I IS XCAV'>11. ,) '-f' '~ 36 r ,.JH Ellct' 28 11 8 I I ,- '3 As a mutual protection to cHcnts, the public and ourseJves. all reports are submined as the confidential property of clients, and authorization for publication of statements conclusions or extract from OT regarding is served pending OUT ~'Tinen approval BAYSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 West 78" Street., 33016. Tel: (305) - 888.3373 Fax: (305) 888.7443 TEST BORING REPORT !.f Client Tran Construction Order No 03.716 Address 420 Lincoln Road Ste#M-l" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B.1 Address 2301 Alton Road" Miami Beach, Florida Date 09/10/03 Location As marked on plan Driller MP & LT I Depth Description of Materials Sample Hammer Blows on UN" Hammer (feet) - Number Sampler Blows on .'J Casing 1 From 0'-0' to 4'-0" B,Fill. Tan lime sand with limestone 15 14 I 29 i .0 2 From 4'-0" 8'-0" B.FiII. Dark brown silty sand with lime 0'2' 15 17 PM .:J 1>" IC-i:l I rJE:, 3 Stone fragments 18 19 I .::J IN::::L~ IN 4 2'4' 20 27 39 c:;o.J'IOt-< :r ..;:) 5 42 55 .0 -,-- E )i16T. 6(.}d.E".. .. ,- --.-- .. ,.----.-. -_.~-- u ______. _". . r-'- 1-- I 6 I 4'61 60 62 115 I~ J ~ 70 82 ::J "!.' I 6'8' 81 I 75 1163 0 9 From 8'-0' to _l~.Fili- Tan lime rock & iime sand 24 20 g' [)(c..( vA ~ 1 Of' ,Q 10 8'10' 14 13 34 ::> 11 12 10 0 12 10'12' 10 18 20 0 ,,~ 13 18 16 .0 '"jFL c.JE).I('",.. 14 12'14' 13 13 29 0 From 14'~~24'-0" Grey medium beach sand - ---_.... 15 6 5 0 16 14'16' 5 " 11' V IV 0 17 6 6 18 16'18' 8 8 14 19 10 16 20 18'20' 16. 18 32 21 18 17 22 20'22' 17 15 34 l 22'24' I' I 23 15 16 I 24 15 14 31 25 I From 24'.0" to 25'.0" Tan & gray coral rock I 28 I 32 26 I End of Boring @ 25'-0" 24'26' I I '11 I I Water level: 5'-6" below surface ~<,~- '. , (/ . , ~ ~ - - I ~ c{ ,;;;..- 8 1 6 .~ " ~, ," - , -? :S. , 6. ., -r, eI at date 09/1 0/03 ( 0. .~ "1 ~/2.... :.J WASEEM QD.WRl, P.E. #51481 A_".8 ,"'If'l.,,] .........'...I"h....n t.... .~I;......... .h_ _..l..l~~ __.I _..___1____ _" u_ BAYSHORECLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPEc;lON SERVICES. CHEMISTS. DRILLING - ENVIRONMENTAL SERVICES 2380 West 78"> Street., 33016. Tel: (305) - 888-3373 Fax: (305) 888.7443 TEST BORING REPORT & Client Tran Construction Order No 03.716 Address 420 Lincoln Road Ste#M-1" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No 8.2 Address 2301 Aiton Road., Miami Beach, Florida Date 09/10/03 Location As marked on plan I Driller MP & L T I Depth Description of Materials Sample Hammer 810ws on "N" Hammer - ~ Number Sampler (feet) Blows on .0 Casing 1 From 0'-0" to 4'-0" 8. FiII- Tan lime sand with limestone 15 16 5' bJI~~ -00 2 From 4'-0" B'-O" S,Fill- Dark brown medium sand with 0'2' 16 17 32 00 3 Lime stone 18 20 .::1 It! C::t-.'T(i 4 2'4' 27 25 47 0 5 25 47 r I .::> - E'w::r: <E;{J...\:;C - --- --, --.. 6 4'6' 55 60 102 , T- o I 7 62 64 8 -- 6'B' 50 4B 114 I I I 6 I ~XCAv~ 9 I From 8'-0" to<~B.Fil/- Tan lime sand & lime rock 40 37 10 8'10' 2Z 18 ,59 -- ~ - t - 11 16 15 12 10'12' 14 III "'29"- 0 , rJ FL.u9Vc..E 13 LU ~ I 14 12'14' 7 8 12 15 -, 7 10 ]6 , From ~~.:9to 25'.0" Grey medium beach sand 14'16' 1~ ,~ 24 /0 17 - ~ 15 17 18 16'18' 17 18 34 ]9 1B 17 20 18'20' 18 19 35 2] 20 20 22 20'22' 21 22 41 23 22 21 I 24 22'24' 20 20 41 25 End of Boring @ 25'-0" 16 14 , I I i (,. "lit. r E( J G. ~'- 2_ 1.0 o II~ ,.:1 ',0 :.0 !. I: l,O >0 Water level: 5'.6" below surface at date 09/10/03 /'/ '; c-' f (Cd. J t.'t- " ~---e"1E! , WASEEMQUADRl,P.E.#514817-/2-J 3 -A.s a muwaJ proleClJon 10 clients, the public and ourselves, all reports are 5 C as the confidential prorerTy 07 clients. and authorization for publr~tjon of statements conclusions or extraCT from or regardmg is served pending OUT written approvaJ BAYSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRilLING . ENVIRONMENTAL SERVICES 2380 Wesl71l" Streel., 33016, Tel: (305)-888-3373 Fax: (305)888.7443 TEST BORING REPORT o Client Tran Construction Order No 03-716 Address 420 Lincoln Road Ste#M.1" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No 8-4 Address 2301 Alton Road., Miami Beach, Florida Date 09/10/03 Location As marked on plan Driller MP & LT I Depth Description of Materials Sample Hammer Blows on "N" Hammer I. (feet) Number Jampler Blows on .0 Casing 1 From 0'.0" to 4'.0" B.Fil/- Tan lime sand & lime rock 6 8 I t .0 2 0'2' 7 5 15 3u1(..l)IN& .0 3 4 4 I' Nc..l.vIx~ I,.) 0 U:l..nf',^ (" 4 2'4' 3 3 7 ,- a 5 From 4'.0" to 8'.0" BFil/- Dark brown medium sand 18 20 .:.;:> E.lC 1<;::T_ 6J>.c.e- 6 I With lime stone 4'6' I 28 I 32 I 48 , I 0 7 40 42 3 €)(cA#T r B ,....", .~ 38 62 t 00 I 'fU I -- -. 9 From B'.O" to 13'.0")B,Fiii- Tan lime sand & lime rock 16 1 14 IN Fi.JE:'-)J ~ ;:J I / 10 8'10' 8 6 22 I ::> 11 6 5 0 12 10'12' 6 8 11 I 13 I 12 6 >0 - 14 From 13'.0'1025'.0" Grey medium beach sand 12'14' 5 5 11 " 15 10 13 I ]6 14'16' 15 16 28 I ]7 16 17 18 16'18' 17 18 34 I 19 18 19 20 '18'20' 18 19 37 21 20 18 22 20'22' 18 17 36 23 17 16 24 22'24' 16 15 32 25 End of Boring @ 25'-0" . .' 14 It ,0 , .. - /; '. 1 ^, ..:; - ~ Lf' - ~ '+ b /1 1 i.,;) ..:>tJ , (. ra ). o ~o Water level. 5 6 below surface at date 09/10/03 / ~/A ,- ~ /2t2' :..,0. ' /t:z..c...:~~'I7" ..-- 7' '/ '<----..:3 WASEEM QUA.DRl, PE #5]481 A.s a murual protection to clients, the public and ourselves, aJl reportS submitted as the confdentizl prOperty of clients, and authorization for publication of statements conclusions or e~"tract from or regardmg IS served pending Our wrinen approval BAYSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 West 78. Street., 33016, rei: (305) - 888.3373 Fax: (305) 888.7443 TEST BORING REPORT Client Tran Construction I Order No 03-716 Address 420 Lincoln Road Ste#M-1., Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B.5 Address 2301 Alton Road., Miami Beach, Florida Date 09/10/03 Location As marked on plan Driller MP & L T ;/. 8 ,0 =l ,0 6, ,:;} - .:J ::>. L(, ::I ~ ...,). 0 2_ ,:;} 1 2 3 4 5 S 7 8 I 9 10 11 12 13 ]4 ]5 16 17 'to ]8 19 20 21 22 '.J o (0 ? 0 ~.o f; ~.o 1_0 , .0 23 24 25 Depth I (feet) Description of Materials I From 0'-0" to 4'-0' B,Fill. Tan lime sand & lime rock From 4'-0" to B'-O' B,Fill- Dark brown medium silty 0,<<;1". 6-f~\~ Sand with lime stone -. 0'2' 2'4' 4'S' S'8' I 8'10' 10'12' 12'14' 14"16'1 16'18' 18'20' 20'22' ,'---";'" From 8'.0" tQ..1~Tan lime rock & lime sand .r--..... Fro~to 2~'-0" Grey medium beach sand ;' ,,, End of Boring @ 2S'.0" 22'24' I -----'-- Water level: S~-6" pe/ow surface at date 09/10103 Sample Number Hammer Blows on Sampler I Hammer Blows on Casing .f 6' BUlL-I:> ~ roM:> 't'tCl. M:-t;; 'N La.Jr~~ :: .--+ . I I 4/ t;XCAV.t'Od ! 157 I Jr~ f---- -- 11 I I "N" 28 16 23 ?7 .., 41 :: I ~~ ' I r /" __ ._ . '~~?v-e"",.,.?!? C" l- -.,5 , rWASEEM QlJ.WRl, r.E. 1$51481 , As a mutuel proteco8n to clients, the publlc and ourselves, all reports are 5ubmmel! as the confldentJaJ property of .:J:er.ts, and authonzatlOn for publication of starements conciusions or extract from or regardmg is served pendmg uur v.rrittcn Z,'JpiOV;,iJ 13 14 14 15 15 16 j8 20 I t: r:; I 82 I 71 I 40 I .22 1-16 22 8 S 5 I 4 15 12 2 4 8 11 12 12 13 --tJ- 14 22 20 20 21 20 20 20 18 18 17 16 16 14 13 I. 14 P Depth (feet) iL c> '1 _? 1 r 2 .j. .:J 3 (-.0 4 ;:, ..7 5 ~..o 2.0 6 7 !.o 8 0 9 I ,;:) 10 2,::; 11 ~~ 12 .0 13 J,;;.. '0.0 14 ;0 , 15 ~.o 16 ',0 J 7 18 19 20 21 22 23 BAYSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 West 78" Street., 33016, Tei: (305)- 888.3373 Fax: (305) 888-74<43 TEST BORING REPORT Client Tran Construction Address 420 Lincoln Road Sie#M-1., Miami Beach, Florida 33139 Project Proposed Property Address 2301 Alton Road., Miami Beach, Florida Location As marked on plan Description of Materials Order No Report No Hole No Date Driller 03-716 8.6 09/10/03 MP & L T Sample Hammer 810ws on "N" Number Sampler Hammer Blows on Casing From 0'.0" to 4'-0" S,Fill- Tan lime sand & lime sione 18 23 25 25 33 50 78 52 60 35 27 18 16 _. _____n_u_ _.._ 12'14' 8 3 4 5 12 21 20 18 16 20'22' /15 22'24' 14 i 13 , //7.r... ~~./ , \., ;L--' ~::o.-______ ..-'1:---=z:/ f ' / -z..... ~.5 /WASEEM Q[JADRI, P.E. #51481 As a mutual protection fO clients, the public and oW"seJves. all reports are !ubmined a:; :hf confideni.jiil property of clients, and authorization for Dublic8tlon of~afem~nts cnnc:ll1c:innt: f'lT ~Ytr::lr-f frnfY1 nr r~..~rAin.,;c c~~p'" ...~...A';.... ,.",.. u...;...__ ..__~_.._! 0'2' 2'4' From 4'.0" to 8'-0" 9,Fi/l- Dark brown medium silty .-----:-.. .,.--.---- c'l(I<:.T. 6fA\:C" -- Sand with lime stone . 4'6' 6'8' From 8-0" t6'13'-S" S,Fill- Tan lime rock & lime sand "- 8'10' 10'12' From 13'-6" "-...-"'/ 25'-0" Grey medium beach sand 14'16' 16'18' 18'20' 24 25 End of Boring @ 25'-0" Water level: 5'-6" below surface at date 09/10/03 20 24 24 27 47 - -....---... 54 71 65 42 30 20 16 15 3 4 43 I 5 BUlL. D' ) (..... i'AU ,,.lCL --1.- f/' Cbr I'r rf. (', 'r" 49 I I I 97 /123/ I I 1/ exc.{v~f/orJ 77 _1 38 II\JFLuE.ijC. 23 6 B 7 10 22 18 16 15 14 13 15 19 42 32 28 BAYSHORECLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 West 78" Street., 33016, Tel; (305) - 888.3373 Fax: (305) 888-7443 TEST BORING REPORT Client Tran Construction Order No 03-716 Address 420 Lincoln Road Ste#M-1" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B-7 Address 2301 Aiton Road., Miami Beach, Fiorida Date 09/10/03 Location As marked on plan Driller MP & LT ~ ,.., Depth Description of Materia!s ~ Sample Hammer Blow.; on UN" Hammer I. (re-et) Number Sampler Blows on . .0 Casing 1 From 0'.0' to 4'-0' B,Fill- Tan lime sand & lime stone 15 14 t .0 2 0'2' 15 17 29 0 :5' gulL [;f 1.16- I 3 I 18 20 ~ /f'1(' l c tx:. .0 4 2'4' 20 21 40 /1\1 c::Jr.fT~ ~ 0 I 5 From 4'.0" to 8'.0" B.Fill- Dark brown medium silty 29 42 r I .:=> C)< l"Si. c:;: A v<:::' - - -.-- 1-----......... ! 6 Sand wilh lime stone I 4'6' 50 75 92/ . I ~I I 7 80 92 I I 8 6'B' 90 I 71 182 I I I 9 I From 8'-0" [0 13.6" B,rifj. I an lime rock & lime sand 30 I 24 I I I ' 44 I J-' bxl:J.V1Lroo 10 8'10' 20 16 11 is 13 25_ -,,J,J.J- 12 10'12' 12 12 d _._- 13 12 11 ':) I From 13'.6" to 24'.0" Grey medium beach sand 12'14'- ------- -.--.-,. --- ... 14 10 6 21 15 5 5 16 14'16' 5 5 10 17 5 6 '- 18 16'18' 8 11 I 14 19 13 16 20 18'20' 16 17 32 21 17 18 22 20'22' 17 18 35 23 18 19 24 22'24' , 20 I 21 39 I 25 From 24'-0" 10 25'-0" Tan & Grey coral rock i 32 35 J 26 End of Boring @ 25'-0" 24'26' I I r? Water level: 5'-6" below surface ~/~- . /LOJ ~.__/iu-~ - at date 09/10/03 ..- .. , _.(!. If: ::.-- '! 7- b. q, :? ~ ". 1.0 o I. :) t.o ~ ) .0 " .0 .0 ,/' --...... =z-/ r. / 2:...' '7 r WASEEM QUADRI, P.E. #514~lr Ac .. ,....,,,"'....f ..r"........;......_ ~"" ,..1:..._.... .\.... _..).,1;.. __..l _..___1-.__ _H __ ___ ___ __.. "__.. .. 1"- y ~ N BAYSHORECLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. DRILLING. ENVIRONMENTAL SERVICES 2380 W!st 78~ Street.. 33016, rei: (305)- 888.3373 Far: (305) 888.7443 TEST BORING REPORT -:;{ Client Tran Construction Order No 03-716 Address 420 Lincoln Road Ste#M-1, Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B.8 Address 2301 Aiton Road" Miami Beach, Florida Date 09/11103 Locatien As marked on plan Driller MP & LT I Depth Descn~tion of Materials Sample Hammer Blows en IIN" Hammer ! (feet) Number Sampler Blows on 0 Casing 1 From 0'-0" to 4'-0" B,Fill- Tan lime sand & lime stone 15 20 1 ~ NG 2 0'2' 23 24 43 6' WILl:>I " 3 25 30 r11t> II'lCL Ak ~ ,,1 (::#TCP 4 2'4' 28 25 58 Cl I 5 I From 4'-0" to 8'-0" B,Fill- Dark brown silty sand with I 40 67 I - P . .,___~___.o E'I'<=:T". C";-('f.'U,-:-- '-135-- -j41 ~- "I 6 Lime stone 4'6' 80 7 88 77 I 8 I 6'8' 60 42 137 I ~ I 9 From 8'-0" t~B.Fill- Ian lime rock & lime sand 30 21 7' c;XCAv1fio I 10 8'10' 15 15 37 11 14 12 12 10'12' 12 10 24 , 13 ----... 11 12 IN rWl<-tJC i;'" , Fro~o 25'-0" Grey medium beach sand - J4 12'14' 4 4 16 15 4 5 16 i41161 4 5 9 '7 --- J7 5 6 18 16'18' ~ 7 12 v 19 7 10 20 18'20' 16 18 26 21 18 20 22 20'22' 23 22 43 23 21 20 24 22'24' 20 , 18 40 25 End of Boring @ 25'-0" ! 17 15 I I ! '(; Water level: 6'-0" below surface @: ~.I', , .l/:' I - "t..'" at date 09/11/03 f U~~.~~ . ' WASEEM QUADRI, P.E. #51481 As a mutual rotectiotJ ro clients, the public and oursctves. all rc orts are ubmined as the coniidenria! ro e I of cJicr.~Cj_ and authorizati n ? '. .;> ..::> _0 .:/ o .0 .J t..::> to _0 <:) ,a ( p p P PIT) for p:Jbli~atjon of staremcnts conclusions or extrac: from or regarding IS served pending our wntten approval o =1> :oJ ~ \ 10 ~ iLfM 14 15 ]6 17 ]8 19 20 2] 22 23 24 25 BAYSHORE CLUBHOUSE EXHIBIT ..~" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. DRILLING. ENVlRONMENTAL SERVICES 2380 West 78" Street., 33016, Tel: (305) - 888.3373 Fax: (305) 888-7443 TEST BORING REPORT Client Tran Construction Address 420 Lincoin Road Ste#M-l" Miami Beach, Florida 33139 Project Proposed Property Address '2301 Alton Road., Miami Beach, Fiorida Location As marked on plan Depth (feet) Description of Materials Sample Hammer Blows on "N" Number - Sampler I Hammer Blows on Casing 13 13 12 10 11 10 9 22'24', 9 L 10 I 9;i !~ ~~---~ ~1p -r;::; 2- ~ ~ /WASEEM QUADRI, P,E. #51481 1 2 3 4 5 6 7 8 From 0'-0" to 4'-0" a,Fill. Tan lime sand & lime stone 20 0'2' 30 32 2'4' 31 35 4'6' 60 72 ""nl 80 00 42 8'10' 22 15 1012' 13 12 12'14' 13 11 14'16' 14 From 4'-0" to 8'-0" a.Fill. Dark brown medium silty Sand with lime slone E~s,. GC.A~ 9 /"--., I From 8'.0' iO,1~'~)a,Fiii- Tan iime rock & lime sand From(~)o 25'-0" Grey medium beach sand 16'18' 18'20' 20'22' End of Boring @ 25'.0" Water level: 6'-0' below surface at date 09/11/03 NC)TE: ~ LOJN Pe?.:>rt I~ 8-4 UJc:... Order No Report No Hole No Date Driller 37 35 30 30 48 71 75 71 30 18 13 '12 13 12 13 14 14 12 12 11 10 9 8 8 03-716 B-9 09/11/03 MP & L T 57 S I 3u11..P1t ::;... ij\-b IIJC(ubE,D 11'1 (':::)(oTTPj., r-\ ~ ,~ 61 /105 /155 I I I 6' ~'IC A ,J1 TI;xl 52 26 l' (NF~tJC - 26 27 27 I 22 20 17 As a mutual protection to clients, the public and ourselves, aU reports are submitted as th,e contidenticJ properTy of dients, and authorization for publication ot statcmcots conclusions or extract from aT regarding is served pending our -written apprc\1liil BA YSHORE CLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. ORILLlNG . ENVIRONMENTAL SERVICES 2380 West 78'> Slreel., 33016. Tel: (305) - 888-3373 Fax: (305) 888.7443 TEST BORING REPORT Client Tran Construction Order No 03-716 Address 420 Lincoln Road Ste#M-1" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B.10 Address 2301 Alion Road" Miami Beach, Florida Date 09/11/03 Location As marked on plan Driller MP & LT 1 2 3 4 5 I From 4'-0" to 6'-0" B.Fill. Dark brown silty sand with I I. E'(I';;i1-.6i?A-le- 6 Lime stone t=i=J From 6'-0" t~~.a,Fill- Tan lime rock & lime sand I 9 I 10 11 12 '/ /:~ 15 16 17 18 19 20 21 22 23 24 25 End of Boring @ 25'-0" Water level: 6'-0" below surface \ Depth (feet) Description of Materials Sample Number Hammer Blows on Sampler 10 12 13 15 25 60 66 71 30 12 15 16 42 -e. 58 70 / 54 33 12 6 4 45 10 12 11 23 30 102 1141 I .. <-- 53 12 55 24 I 29 27 22 22 I Hammer Blows on Casing t S'3uILDIN ~ PAb I t-lCLV I::>c-t:> IN C o~"'RJ c--r 14'EL~t ....,.,._~.... --L 'NFWENG~ I "N' 22'24' I ! 10 ,1 ,/ //1) l' (U6------~t1" q //2- -3 /WASEE!\1 QUADRI, P,t. #51481 As a mutual protection to clients. the public and ourselves, all report! are submincd ~ r)-ye confidential property of ciienrs, and authorization fOT pubhcarion of statements conclusions or eXlract from or regardmg JS served pendmg nur wrinen appro\af at From 0'.0" to 4'-0" B.FiJl. Tan lime sand & lime stone 0'2' 2'4' 4'6' 6'8' .. .. --... 8'10' 10'12' ,~ Frol11~o 25'-0" Grey medium beach sand 12'14' 14'16' /16'18' 18'20' 20'22' date 09/11/03 '..20..'. , 8 6 ~ o I 10 11 12 13 13 15 14 15 14 12 11 12 12 10 BAYSHORECLUBHOUSE EXHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS. INSPECTION SERVICES. CHEMISTS. DRILLING . ENVIRONMENTAL SERVICES 2380 Wes178~ Street., 33016. Tel: (305) - 888.3373 Fax: (305) 888.7443 TEST BORING REPORT Client Tran Construction Order No 03-716 Acldress 420 Lincoln Road Ste#M-1" Miami Beach, Florida 33139 Report No Project Proposed Property Hole No B.11 Ad dress 2301 Alton Road., Miami Beach, Florida Date 09/11/03 Location As marked on plan Driller MP & L T Depth Description of Materials (feet) Sample Number Hammer Blows on Sampler 1 From 0'-0' to 4'-0" B.Fill- Tan lime sand & lime stone 2 3 0'2' 12 15 18 17 17 18 "N" Hammer Blows on Casing 33/ ~13vfL DltJ \"1\-tJ '''ICL '=>€!) '..... _\ 4 2'4' 18 20 36 IN CONTt2J11 5 From 4'.0" to 8'-0" B,Fill. Dark brown silty sand with 23 25 6 I Lime stone ex, r;,T_ 6i:A.cc ..-- "--'. 3'8' ..... -. --r I 4'6' 25 50 . 7 40 71 8 i I 6'8' 70 , 50 I 141 , I I 9 From 8'-0" toJ4'-0~BlFill. White line rock & lime sand I 23 20 138 I i 10 8'10' 18 16 g I EYe).. viti, 11 16 20 I 12 110'12' 27 30 I 47 13 31 35 ."- f-.-- L.__ . ...... 14 .'---. 12'14' 30 20 65 IN F'lu(;N6 ~ f- 15 From,~'25'-0" Grey beach sand 14 10 16 14'16' 11 10 ~. LI ]7 10 12 18 16'18' 12 I 14 24 19 14 15 20 18'20' 15 16 3D 21 16 17 22 20'22' 17 16 34 23 16 15 24 22'24' 14 13 29 25 End of Boring @ 25'-0" 1 <~ 12 i: 'w .IN J ~ ~,.. (~~, _ J '::~-~-r::>/ q ~ J U ~ v] ASEEM QUAl.JRT, P .E, f;5] 481 As a mutual protection to dients, me pubiic and ourselves, ali reports are submjned as thr conildenti3.1 property of clienrs, and authorization for publication ofsratements conclusions or extract from" or regarding is served pending eu:" wrinen a~pTOvaJ Water level: 6'-0" below surface at date 09/11/03 :,P,3~i, 2003 3:39AM all 'late er,gineerirg BAY~I:I~I$~cE~Htl~~'~: All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. CRIWNG. ENVIRONMENTAL SERVICES 2380 Wnt 78" SlIItt, 33018. T.,: (3D" - 888.3373 Fax: (305) 888-7443 Client Tran Construction Add".. 420 Lincoln Road" Ste#M.1., Miami, Florida 33139 I Project Proposed Property ~ Addr... 2301 Alton Road" Miami Beach, Florida ~ L.ocatlon North side of planter area "_}~::r I "K_" of ...". -. M From 0'.0' to 6'.0" 8.Fill- Tan lime sand & lime rock td H--1 I 6 I I 7 8 9 \ "" 10 I R=1 13 14 15 16 17 ] 8 19 20 21 22 23 24 25 End of Boring @ 25'-0" Water level: 0'-6" below surface at 09/25/03 date (I 20 15 13 11 8 10 12 13 13 12 4'6' 11 10 23 .. --- -a----7+- 4 3 7 8 10 13 14 16 16 18 18 17 17 16 15 16 16 17 17 18 18 19 17 18 18 20 25 30 31 30 30 29 28 29 30 31 (t.p~~ /~ 2 9-;J jYIASEEM QUADRI, P.E. #51481 TEST BORING REPORT Ssrr.ple Number 6'8' From 8'.0" to 20'.0' Grey medium beach sand 8'10' 10'12' 12'14' 14'16' 16'18' 18'20' From 20'-0" to 25'.0" Tan sandy coral rock 20'22' 22'24' Order No Report No HOle No Date Driller Hemmer BloWl on Sampler 0'2' 2'4' 03.711 r- ! 6' 8/J/L.1)/J (; X-1 ~Irl 09/25/03 (. ~~,~a" MP&L.T , - , l , 'IN" Hammer z.!. Blows on i Casing 28 I '1 E-XCAV, no"J 22 , 11 Ir~FLvEr cE' r 18 32 34 32 36 36 61 57 As ft l1,utuu1 protection to cli~l1ts, the public ftnd ourselves. nil repons ore S1.Ibl11itt:d as the cuntldentJal proJ'crtrofcljcnts. IInd aUlhoriT.wtion filT puhlicft!l~n ofstutcmc:nts conclu~jun' 0: ~xtrs~t from or rCi3rding t!li served pendinG our writt.n approval ~€P, 30, 2003 BAYSHOREC~BHOUSE !fe.5"T';-T EXHrBlT "B" All State Engineeri~g & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES. CHEMISTS. DRilliNG . ENVIRONMENTAL SERVICES 2380 WI117P Strut, 3301 S. T II : 13D5) - 888-3373 fax: (305) 888.1443 3:39f.M ail qate enginEering TEST BORING REPORT '-I Clillnt Tran Construction Order No 03.718 ~ Addrell 420 Lincoln Road., Ste#M-1" Miami, Florida 33139 Report No 5' bvlLC,r.t ProJlct Proposed Property Hol, No X.2 fkt> Addr... 2301 Alton Road" Miami Beach, Florida Dlte 09/25/03 1,1 c: LJ...i 1) , Location Center of planter area Driller MP & LT J, I i , I Depth DHcrlptJon 01 Malari"1 Sam pl. Hammer BloWl on uN" Hammer j (feet) Number Simpler Blows on Z- - t- Casing - . '~I From 0'-0" to 8'.0" 8,Fill. Tan lime sand & lime rock 10 12 I 1 - 2 0'2' 16 18 28 .:/ 3 20 22 '" -- 4 2'4' 20 18 42 '1't'lLA ATlOr~ 5 18 18 -~ ',? 6 4'6' 16 13 32 " 7 13 12 .- --6'8'- -Tio", -"'0-" '24 ---.._~._- 8 I~.F L.uul - ...- From 8'-0" to 20'.0" Grey medium beach sand 6 --.....-. . --.'. 1-. 9 5 /" HR 8'10' 4 5 9 11 5 6 I tij 10'12' 6 7 12 8 10 hH 12'14' 10 12 20 15 I 12 14 16 14'16' 16 18 30 RR 18 19 18 16'18' 19 20 38 19 21 20 20 18'20' 18 18 38 21 From 20'-0' to 25'-0" Tan sandy coral rock 29 31 22 20'22' 31 30 62 23 30 32 24 22'24' 32 34 64 25 End of Boring @ 25'-0' 31 30 " Water level: 0'-4" below surface (?ptC ~ f":-) .l.p 'f, 1-9- ~ J at 09/25/03 date I"'ASEEM QUADRl, P.E. #5148] " -. 6 ra.I o rt y' As II nlutunl pr~t=Cliol' to clicn'~. the puhlic. and Ourselves., f1fl rcpons 3re sLJhlnltted as the confidential propc:rly of elitmes. and authorization tin (mhllClltJOI1 of sLAlcmcl1t!i cOl1clusions or ex.lrm:i ttom or regRrdh'B III served pending our 'WTJtten appro\'.' ~:p ,20, 2003 3:39AM BAYSMq~E~UpHOUSE JlI (j":b' I " r I:XHIBIT "B" All State Engineering & Testing Consultants, Inc. TESTING LABORATORIES. ENGINEERS . INSPECTION SERVICES, CHEMISTS. ORILUNO. ENVIRONMENTAL SERVICES 2380 WI.tT", 5trl".. 33018. Tel: (305)- 1...3373 FIX: (305) 888-7443 al' qate ergineering" TEST BORING REPORT r Client Tran Con.truetlon Order No 03-716 Add rell 420 Lincoln Road., Ste#M.1., Miami, Florida 33139 Report No GI~,UIL proj.ct Proposed Property Hole No X.3 y~.i) ) Addr... 2301 Alton Road., Miami Beach, Florida Oa_ 09/25/03 i II( Uk Loca~on North side of planter area Drill.r MP&LT I Depth DelcrlpUon 01 Mat.rial. Sample Hammer BloWl on UN" Hammer (feet) Number Sampler Blows on 2.' I - -" Casino ... 1 ' From 0'.0' to 10'-0' 8,FilJ. Tan lime sand & lime rock 10 11 2 0'2' 10 9 21 5' EX( :.+VAlicN 3 9 11 ._-_. ---.. 4 2'4' 10 8 21 llJFuJt "'Ct 5 9 8 ! 6 I 4'6' 9 8 17 7 8 8 8 6'8' 7 5 15 9 5 3 10 8'10' 3 3 6 11 From 10'.0" to 12'-0" Gre medium silty beach sand 3 3 12 With some fine mangrove roots 10'12' 2 2 5 13 From 12'-0" to 22'.0" Grey medium beach sand 5 15 14 12'14' 16 18 31 15 17 18 16 14'16' 17 18 35 17 18 20 I 18 16'18' , t--2O 18 40 19 1a- 17 20 18'20' 18 19 35 21 19 18 22 20'22' 20 21 38 23 From 22'.0" to 25'.0" Tan sandy coral rock 28 30 24 22'24' 32 35 62 I 25 End of Boring @ 25'-0" 35 34 Water level: 0'.14" below surface m$ 0~(j'l1;1) at 09/25/03 date jWASEEM QUADRI, P.E. #)1481 -r l:b. , .-.: ~ ... L As" """".1 prolecli"" to elienll, Ihe p"bli\ and ourselv... /III reports are .ubm'lIed .. the em,lid.null property l,fclicnl.. and .uthorlll"o" for puhlicn1ipl1 ofs1ltt'lTIcnb cOlu.:luSIOfl5 or e.'(tn'tct frUIll or rcgardin~ is ierved p~ndJn' uur written approval 8 l!l ill .. ., .. ... N N '" ..; z U> '" '" :! :> '" .. .. 0 N ..- C '" ~ I U> N .., ;;; N II ~ ID :> " " " ., z 0 0 1!i 0 ~ ~ ~ w >- >- , , , w u U U ... ~ ., ~ ~- ~ Z N o_ il! ;;; U> ~ .. . . . ..,.., ~ ...., $ M::1 ~ ...., 0.., ~ ..,.. :;; m": .. ..,...: :;; 0( -~ _M N _M ... M ~ ~ ~ ~ ~ 0 ... 0- l!i;;; .. 1El;;; .. 8;;; ;;; :> ~ .. '" 00 ;;; ;;;Sl ;;; ;;;Sl ;;; z '" M~ il! ~ .. " on .. w .. N ill _ N .., Mill ~ u ..'" mm U> ii' ~ill S!' ~ill .., ~ill 0 N III 0- ~ ~ ~ ~ ~ w ., 0( ID "N '" _N M _N ~ ..'" on mm U> ..,m --' ~ill '" ~ill M ~ill 0 0( .. N N ... M ~ ~ .. .. 0 ... z il! 0- U>N '" .., .. :> _U> .. :ril<l :!l Nl<l '" l! '" _0 ;;; ;;;Sl :;:: ;;;Sl .. .t> '" M~ . 0( !2 :; w ~ z 0: --' w ;oi\l a; mo '" 00 g .. U NN .. _N ii' ~ill .. :!lill iii ~ill m 0- ~ ;;; ~ ~ ;; w '" 0( '" -0 a; "'0 m 00 g U>N NN .. _N --' ~ill .. :!lill N ~ill m ;0 ~ ~ ~ .. ~ ;; W- 0 z ... 0: ... .. 0- 8:11 N i!l:ll !\l ~ill 18 s :> U> '" ;;Sl ;;;:;i ;;:;i ... '" ;; ;; ;;; . ~ !2 i:! " ~ ~ w :Ii;! S!' ill;! M 8;! ;! u on ii' ~::l U> ..,on '" -on U> .. ;; -~ ;; -~ ;; 0- .. ~ ~ w ., ~ ~ ~ .. 2 ... 'le.. ~ !; w .. .. '" .. .. !:: z .. gill g 'lez '" w w 0 g~ g " 2 .. 0:2 0: 0: -:ar:: !!: '" ..!!O .. "'0- 0: .. U:> U 0:> 0 i~ w x :>0 :> XO X 2 u IIw II .,w ., ...w :; .. w .. ill 8 ::! w N ~ ., a; '" Sl c .. N :; ~ W .. '" u ..; on .. ii: ~ ~ .. 0- W .. ID Z w II :> " " " " Ii; ~ 0 1!i ... ~ ~ ~ g " >- >- >- 0: , , , .. u u u .. oU iF ~ &1 0 w 0 ~ z .., ~ .. !; . . . .. N_ .., ~8 .. i!l8 .. "'.., .. N .. ... illlll :i N .., .. M M :! ;0 -~ -~ ~ .. ~ .. w 0 " ... ~ > 0- on M Iii '" :> .. '" '" " " Sl Sl :il '" ; ~ " w on ~ .. :!l .. ~ ~ ., N W ill ~ ... ~ ~ 0 :> 0 .., on :: .. N --' ..: N ;0 .. .. .. 0 .. >-- >- : 0- i!i g ~ :> ~ '" :;i .. .. '" u ~ " z " ;c ~ u :> on M 0: 15 .. N .. N W ill 0 .. ;; ;;; 0 :> C '" g 0 .. '" ~ ~ N ;0 .. ;; 0 - .. >- z : 0- ~ M ~ :> 0 2 '" :il ;; ;; 0 '" u " " :; Z ~ ;c g 0: ~ .. ;! .. - N W ~ 0 .. .. ;; 0 :> 0 ... .. ... >-- .. 0 ... 2 ~ 'le.. .. 0 w .. " 'le'Z ... !:: z ... gill g " w w 0 uw u " '", ~ .. ~~ '" 011 0 ~ " 2 0:0- 0: u:> u 0:> ia w "0 " XO II u :Ow II .,w ., ...w :; ~ .. ~ ~ .. ~6 . 0 \! u N'" ;: .. ~<<i_ Z N" .. ...., .. " " " " .. i z w wO l :;w m 0-'" a; :; 5!i 0 @:! i:i w - g ~lU .. 0:; N N .. ..::> ..; .. "'... f:i 00 "' u> 0 00 ... WlU ~ ,.:; " 55 ... .. '" z uu 0 0 ..... u u .. 00 Z 0--0-- ::> w .. => o X ID " ... u ~ p o .. x ili ~ ~ b w ... o ~ X ~ ii: w ~ II ~ o o ! u ili => u '" w 0- 0-- lI> o U 0-- Z w II 0- S o w 0: :c ~ ~ o w ~ II " lI> W s ~~ >- >->- . . , u uu ~ ;1:1; .... N g~ on on on PI NN ..,M ~ ~~ ."."."." ." " 't:!"'''CI1:I." ~ " >->>->- >- >->->->-> >- >- ::) ::l ::l ::l . >- ::::I ::;J ::l :l :l , . ouuo u . uuuuu u u u ----- s~r;;le ill " .., NNf'-.<<l1l'l :; " .. M CON....~ M .. Sl;;SlSl N SlSl..lllSl .., ..; III 0 .. .. 0 .. '" .. " " >- >- 8 . . u u ~ ! !. N e I- e . ~ ~ . ~ i i .!! i i 0 0- 0 0- 0 ,:: . ~ u ...'" ~ . ~ U D at! " u 5 "'~ ~ 'E . . ~ ;; g . 5~8 ,. . 0-- j;~h 1i '" ! ~!i..~ 1i '" ! :!",ij l!l 0 0 8il~ h~~ 0 u ! 15 u .~ u ~ i?:' II~I~ ~ >- .u< .. ..~o cJ ... w =~8 z ,.... - '" 5 '" u Kjj Ot W 0-- ii: II l lI> jj 62~ 0- 0 ~~~ :; D u 0 .. ... . . . 0 . l!''''< w 85l5': w z ~~!:l~ z ~ w ~!:i _NN II 0 00.. 0- 00_..- ::txuj " 5188 ... :; 5l:1l88 o 0 .. ..'" ~ N.... ill NN......- ~~~ ~~~ ~~~~ ::I ..,.., --' .E.E14 NNN ... SNNN W 000 il: 000 _Nn EXHIBIT 4 CITY COMMISSION MEMORANDUM FEBRUARY 2, 2005 MIAMI BEACH GOLF COURSE CLUBHOUSE Change Order Summary ~ CITY OF MIAMI BEACH MIAMI BEACH GOL.F COURSE CLUBHOUSE / MAINTENANCE YARD / RESTROOMS - UPDATED: 12/20/04 ORIGINAL. CONTRACT AMOUNT: $ 2,669,000.00 SCOPE OF WORK PROPOSED AMOUNT APPROVED AMOUNT CHANGE ORDER NO.1 3 Additional Branch Circuit Feeders as a result of relocation RR $ 3,436,16 $ 2,401,35 of wash station, 4 Relocate fence for handicapped par\(ing and reinstall after ORC $ 304,66 $ 304,66 removal bv CMB crew to Dlace aSDhalt. 6 Relocate fence to allow more par\(ing, ORC $ 312,63 $ 312,63 APPROVED: 03/25/03 SUBTOTAL.: $ 3,019.04 0,11% CUMULATIVE SUBTOTAL: $ 3,019.04 REVISED CONTRACT SUM: $ 2,672,019.04 CHANGE ORDER NO.2 Extension of service entrance lateral and addition of 600- 1 amp disconnet as a result of relocation of pad mounted ORC $ 42,207,73 $ 16,409,05 transformer at Clubhouse. 10 T emnorarv Cart Path UN $ 11,979,93 $ 11,752,95 14 Additional circuit and breaker for securitv oanel EO $ 194.29 $ 194.29 APPROVED: 05/01/03 SUBTOTAL: $ 30,356.29 1,25% CUMULATIVE SUBTOTAL: $ 33,375.33 REVISED CONTRACT SUM: $ 2,702,375.33 CHANGE ORDER NO.3 2 Electrical War\( for transformer at Maintenance Site ORC $ 5,631,95 $ 5,631.95 12 Survey for centerline of Alton/23rd and layout clubhouse ORC $ 1,001,36 $ 966.65 buildina for the 2nd time, 15 Broken lniaation Pioe and North Restroom Lavout. UN $ 661.72 $ 671.64 26 Temllllrarv fence - Maintenance Site UN $ 635,15 $ 635,15 32 Relocate Range Ught Feeders UN $ 3,546,33 $ 3,495.42 APPROVED: 06/04103 SUBTOTAL: $ 11,821.21 1,69% CUMULATIVE SUBTOTAL: $ 45,196.54 REVISED CONTRACT SUM: $ 2,714,196.54 CHANGE ORDER NO.4 22 I Soils engineer observation during de-mucking war\( I UN I 1$ 3,42527 I $ 3,425.27 APPROVED: 06/30/03 SUBTOTAL: $ 3,425.27 1,62% CUMULATIVE SUBTOTAL: $ 48,621.81 REVISED CONTRACT SUM: $ 2,717,621.81 UN - Unforeseen Condition EO - AlE Error / Omission RR - Regulatory Requirement ORC - Owner Reauested Chanae 12/21/2004 Page 1014 SCOPE OF WORK COMMENT PROPOSED AMOUNT APPROVED AMOUNT CHANGE ORDER NO.5 11 Removal of Trees within Clubhouse site, UN $ 2,019.60 $ 2,019.60 25 Relocate trees at service drivewav at Clubhouse UN $ 2,670.30 $ 2,670.30 26 Relocation of ilTljlation lines/sprinkler heads at Clubhouse UN $ 6,694,13 $ 6,228,12 26A Relocalion of high voltage wire, and control cable for UN $ 3,762,20 $ 3,762,20 inieation system at Clubhouse 36 Relocate teleDhone stubout at Buildina A, UN $ 475.31 $ 475,31 APPROVED: 07/04/03 SUBTOTAL: $ 15,155,53 2.39% CUMULATIVE SUBTOTAL: $ 63,777.34 REVISED CONTRACT SUM: $ 2,732,777.34 CHANGE ORDER NO.6 29A Excavate and compact pad at south area for 36" slab - UN $ 4,435.02 $ 4.370,75 Maintenance Buildina. Raise pad north side to correct elevation issues, Option A 29B use fill material, Option B use concrete - Maintenance UN $ 3,088,85 $ 2,556,95 Buildina, 310 Demuck-FiII and Remove Grade Beams at Storage Bin. - UN M&E $ 5,540,61 $ 5,540.61 Maintenance Buildina, 30A Demuck wash station - Maintenance Buildine, UN M&E $ 12,066,98 $ 12,066.98 31B Adiust catch basin elevations - Maintenance Building, UN M&E $ 4,125,03 $ 4,125,03 APPROVED: 11/13/03 SUBTOTAL: $ 28,660.32 3,46% CUMULATIVE SUBTOTAL: $ 92,437.66 REVISED CONTRACT SUM: $ 2,761,437.66 CHANGE ORDER NO.7 27 Concrete Dad for transformer - Maintenance Buildina, aRC $ 10,355.10 $ 10.355,10 33 Credit for Kitchen EauiDment. ORC $ (16,405.68 $ 116,405,68) 35 Credit for Retainina Wall, ORC $ (21,953,30 $ (21.953,30) 46 Concrete Dad for transformer at Clubhouse ORC $ 13,559,56 $ 13,559.56 46A Credit for In Contract Concrete pad for transformer at ORC $ (200,00) ($200,00) clubhouse site, 50 Renlacement of damaoed visaueen RR $ 508,53 $ 508.53 51 Water supply relocation due to relocation of wash station RR $ 2,725,93 $ 2,725,93 buildina 31A South Entry Ramp - Cutlimerock to required elevation and UN $ 3,256.61 $ 3,256,61 recomoact to receive new asohalt. APPROVED: 11/13/03 SUBTOTAL: $ (8,153.25) 3,16% CUMULATIVE SUBTOTAL: $ 84,284.41 REVISED CONTRACT SUM: $ 2,753,284.41 CHANGE ORDER NO.8 53 Location of Bell South Conduits at Site B, aRC $ 200,00 $ 200,00 57 Tank Remediation bv ATC at Clubhouse UN $ 16,735,88 $ 16,735,88 57 Fence at Site B ORC $ 15359,77 $15,359,77 17A Removal of Concrete and Wood Piles at Clubhouse UN $ 40 303.47 $ 27,230,48 APPROVED: 12/19/03 SUBTOTAL: $ 59,526.13 5,39% CUMULATIVE SUBTOTAL: $ 143,810.54 REVISED CONTRACT SUM: $ 2,812,810.54 UN - Unforeseen Condition EO . AlE Error I Omission RR. Regulatory Requirement ORC . Owner Reouested Chance 12/21/2004 Paae 2 of.c SCOPE OF WORK COMMENT PROPOSED AMOUNT APPROVED AMOUNT CHANGE ORDER NO.9 34 Stvrofoam blockout for BuildinQs Band C RR $ 24,591,46 $ 21,718.22 48 New Roof at Can Wash EO $ 9,757,72 $ 8.344.69 52 Chemical Storaoe Buildino Additions ORC $ 20,512,86 $ 7,154,16 54 Additional reinforcing bars at foundation for wash station - EO $ 4,968,73 $ 2,742,28 SiteB 55 Security for FT AA ORC $ 4,327.70 $ 4,249,36 56 Connect Water Service at Buildino B UN $ 28,230,46 $ 28.320,46 60 Electrical for Pro-Shop Counter EO $ 1,148,04 $ 1,148,04 61 Provide Emntv Conduits under Pro-Shoo slab for IT. EO $ 3,313,63 $ 3,486,08 62 Relocate Irrination Line at Footer at Site B Wash Station UN $ 389,70 $ 389.70 63 Securitv Svstem Credit ORC $ (3,261 ,56 $ (3,261.56) 64 Relocate Ranoe Lioht Feeders UN $ 9,872,54 $ 6,255,46 APPROVED: 02127/04 SUBTOTAL: S 80,546.89 8.41% CUMULATIVE SUBTOTAL: S 224,357.43 REVISED CONTRACT SUM: S 2,893,357.43 CHANGE ORDER NO. 10 71 Wash Station Reinforcino Steel Reolacement I RR $ 3,570,88 $ 3,570,88 72 New Column C-10 oer Structural Enoineer I EO $ 1,480,63 $ 1,480,63 73 Additional Condensate Hood per Shop Drawings by ! ORC $ 1,281,98 $ 1.281,98 Kitchen Consultant 76 Relayment of Wash Station Building due to existing footers UN M&E $ 433.51 $ 433,51 found durino excavation 79 New Panel in Phone Room ORC $ 4,200.54 $ 4.200,54 81 New 3/4 conduit for orinder ORC $ 1,740,03 $ 1,740,03 APPROVED: 05126/04 SUBTOTAL: S 12,707.57 8,88% CUMULATIVE SUBTOTAL: S 237,065.00 REVISED CONTRACT SUM: S 2,906,065.00 CHANGE ORDER NO. 11 59 Phone Data Conduits BuildinQ A&B ORC $ 52,427,71 $ 52,000.00 80 Additional electricallTV outlets oer REG fURS drawinns, ORC PARKS $ 10,762,32 $ 10,762.32 84 Secondarv (inside) windows in kitchen ORC $ 5,080,37 $ 5,080.37 87 Exterior Soot lioht for tower ORC $ 925,36 $ 925,36 APPROVED: 08116104 SUBTOTAL: S 68,768.05 11,46% CUMULATIVE SUBTOTAL: $ 305,833.05 REVISED CONTRACT SUM: S 2,974,833.05 CHANGE ORDER NO. 12 66 Additional drainage pipe installation to connect to new well RR $ 28.673,09 $ 28,673,09 location at Site B 67 Additional work at CB at site A next to curb EO $ 1,524.13 $ 1,524,13 68 Provide scupper drains on Clubhouse roof - and EO $ 4,074,21 $ 4,074,21 associated stone work. 85 Provide additional sprinkler heads in lockers area as RR $ 1,253,99 $ 1,253,99 directed bv Fire Inspector 94 Reolace and add door locks at restrooms ORC $ 961,52 $ 961,52 APPROVED: 10/01/04 SUBTOTAL: S 36,486.94 12,83% CUMULATIVE SUBTOTAL: S 342,319.99 REVISED CONTRACT SUM: S 3,011,319.99 UN - Unfor.seen Condition EO . AlE Error / Omission RR. Regulatory Requirement nAr: . nwn.r ~.nll.ctNt Chann~ 12/21/2004 PaQ~ 3 of 4 COMMENT PROPOSED AMOUNT SCOPE OF WORK APPROVED AMOUNT SUMMARY UNFORESEEN CONDITIONS OWNER REQUESTED CHANGES REGULATORY REQUIREMENTS AlE ERRORS AND OMISSIONS UN ORC RR EO 5,5% 4,2% 2,3% 0,9% TOTAL 12,8% ADDITIONAL FORESEEABLE CHANGE ORDERS TO FINISH (SEE DETAIL BELOW) CUMULATIVE CHANGE ORDERS TO FINISH 19% FINAL CONTRACT AMOUNT TO FINISH $ 146,618,58 $ 111,855,07 $ 60,851,99 $ 22,994,35 $ 342,319.99 $ 155,095,60 $ 497,415,59 $ 3,166,415,59 PROPOSED CHANGE ORDER NO. 13 65 Pro-shoo Counter EO $ 15,609,50 $ 13,528,65 83 Install 3-2" conduits from Phone Room to new hand hole for ORC $ 12,097,04 $ 10,336,78 future Cartbam 90 Terrace Awnina Endosure ORC OTHER $ 5,187,06 $ 5,187.06 91 Additional testing & sampling of drainage well for RR $ 6,363,22 $ 6,363,22 Clubhouse 92 Dumoster floor drain EO $ 3,026,37 $ 2,532.72 95 C-South restroom DOwer suoolv UN $ 33,000.00 $ 26,935.00 96 Revised floorina finishes ORC $ 1,801.46 $ 1,801,46 97 Uoarade to wood lockers aRC PARKS $ 13,256,73 $ 13,256,73 98 Stainless steel wall flashina in kitchen aRC $ 1,728,05 $ 1,728,05 99 FP&L-reauired handhole for C-north restroom EO $ 610,83 $ 610,83 101 Address letterina for restrooms - required bv Fire deot RR $ 483,57 $ 483.57 APPROVED: SUBTOTAL: $ 82,764.07 15.93% CUMULATIVE SUBTOTAL: $ 425,084.06 REVISED CONTRACT SUM: $ 3,094,084.06 PENDING CHANGE ORDER REQUESTS 43 Pennit Exoediter ORC $ 1,096.50 $ 1,260,98 86 Paint purchased for original color scheme but no used, C RR $ 778,84 North Washroom, 88 Reoair to Sanitarv Line Broken bv Gas Comoanv UN $ 280,41 110 Wash Station Self Cleanino Sum" aRC $ 2,208,00 Read, Wash Station Recvdina System ORC $ 4.521,00 31C Provide additionallimerock at oar1<ing lot area - buildina B M&E $ 16.678,86 $ 13,855,85 102 Brackets & substrate forcranite counter EO $ 1,176,04 103 Cost increase far well casino RR $ 2,750,41 104 1" asnhalt resurfacinn far nar1<ina lot - Clubhouse aRC PARKS $ 22,808.81 $ 22,808,81 Reqd, Electrical service ground wire - required by Building RR $ - Deaartment 108 5-foot extension of wash station slab EO $ 2,730,82 107 Water service to temDorarv dubhouse UN $ 1,192,40 $ 1,192.40 108 Air line to wash station aRC $ 4,072.76 109 Credit for electric hand drvers EO $ (50500 $ (505,00\ 111 Electrical items for terrace AlC units aRC OTHER '$ 12,541,68 $ 12,541,68 APPROVED: POTENTIAL SUBTOTAL: $ 72,331.53 $ 51,154.72 18.6% POTENTIAL CUMULATIVE SUBTOTAL: $ 497,415.59 .$ 476,238.78 POTENTIAL FINAL CONTRACT SUM: $ 3,166,415.59 22,5% De-mucking 41,1% POTENTIAL CUMULATIVE SUBTOTAL: $ 1,097,415.59 POTENTIAL FINAL CONTRACT SUM: $ 4,263,831.18 UN - Unforeseen Condition EO - AlE Error I Omission RR. Regulatory Requirement ORC . Owner Reauested Chanae $ 600,000,00 12/21/2004 Paae 4 of 4 EXHIBIT 5 CITY COMMISSION MEMORANDUM FEBRUARY 2, 2005 MIAMI BEACH GOLF COURSE CLUBHOUSE DEC-14-2004 10: 54 REG ARCH !TEeTS 561 659 5546 P. 02/03 REG ARCH IT E C T S,\ IN C . A It CHI T E C T U II a* J NT B:a 10 It DB S I.G"'" * P LAN 1\1'. 11\1' G December 13, 2004 Mauro Burgio Capital Improvement Division City of Miami Beach 777 17111 Street, Suite 201 Miami Beach, FL33139 Re; Bayshore Golf Clubhouse, Additional Services REG Job No: 98042 Dear Mauro, In our correspondence dated August 23, 2004, with regard to extension of time for Construction Administration services we make mention of the contraCt duration and the amounts of monies incurred on this project every month this project bas been extended. The construction conunenced on November 19,2002 and the construction duration for the Clubhouse and related facilities allowed for 400 days (13 months). Please keep in mind, REG Architects, IDc, allowed eleven (II) months in their contract and twice a month "ire \'isits to respond to constrnction meeting minutes, RFI's, construction observation, review shop drawings/samples, punch list items, etc. Our budget was $4,517.00 per month for thirteen (13) months = $58,731.25. We anticipate (so we are told) the project wiJl be completed at the end of February 200.5 which ill the tOla] of twenty-seven (27) month construction period. From August 2004 until FebrullIY 2005 we will have a field representative from our West Palm Beach office atteud site meetings at lea.lit twice (2) a month together with Jesse Guerra. The following is an anticipated c.,timate of additional services through completion ofmis project; February 2005. BondlEscrow Release Balance Due for Original Construction Administration SubTotal lime Extension November 2003 Though February 2005 Additional Services (To Be ADproVed) Total Fees Due $ 20,000.00 S 29.36S.~3 $ 49,.365.63 $ 134,074.50 $ ]4.500.00 $ 197,940.13 no SOUTH DIXIE HIGHWAY, STilL HI WIUT PALM BBACH, FL '3401 .HO"'8, 561 Ut..,., . PAX, 561 ,,,..... 1I'1I'1I'.IlI!GAIlCH.COM AA-OIOZ"1 DEC-14-2004 10:54 REG ARCH !TECTS 561 659 5546 P.03/03 Baysnoft Golf Clubhouse REG Project No: 98042 Dc:cember 14, 2004 Page 2 We hope that a partial payment of $49,365.63 would be made to REG in lieu of the total outstanding amount. We realize that the total amount indicated is yet to be approved. but keep in mind that these added services are a remit of extei1ded construction administration services work performed by us. Cc: Rick Gonzalez. AlA. REO Architects Tim Hemstreet, City of Miami Beach Jorge Chartrand, City of Miami Beach 120 SOUTH DIXIB HIGH1VAV. 'TE. 211 "'1l'T PALM, BEACH ~"O' 'HONE: 561 6J'.Z.J'~ . PAX: 5'1 "I.IJ41 "'^TLlIIIRBGARCH.COM o\A-'OU."7 TOTR.. P. 03