97-22562 RESO
RESOLUTION NO.
97-22562
A RESOLUTION OF THE MAYOR AND CITY COMMISSION APPROVING
AN AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
DUANY, PLATER-ZYBERK FOR THE ALTOS DEL MAR DESIGN
GUIDELINES IN AN AMOUNT NOT TO EXCEED $14,000.
WHEREAS, in November, 1993, the City Commission approved a
professional services agreement for the North Beach area with
Andres Duany and Elizabeth Plater-Zyberk Architects, Inc. ("DPZ");
and
WHEREAS, DPZ assisted in developing a preliminary set of
design guidelines for the Altos del Mar area of North Beach; and
WHEREAS, additional work by the consultant is necessary in
order to develop design guidelines for the single-family district
in Altos del Mar.
NOW, THEREFORE BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA that the Mayor and
City Commission approve an amendment to the Duany, Plater-Zyberk
agreement in an amount not to exceed $14,000.
PASSED and ADOPTED this 21st
~~+ YClAJw-
CITY CLERK
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
#6 ~~/L
Ity H may
/f)/I r!91
, Dcfte
FEE SCHEDULE FOR AMENDMENT TO
NORTH BEACH PROFESSIONAL SERVICES AGREEMENT
ANDRES DUANY & ELIZABETH PLATER-ZYBERK ARCHITECTS. INC. (DPZ)
The following hourly rates in effect for planning and consulting
services:*
Principal
Project Manager
Computer/Drafter
$175.00 per hour
$ 75.00 per hour
$ 45.00 per hour
*DPZ has agreed to maintain this fee schedule for the completion of
the assignment, though higher rates are currently' in
effect.
CITY OF
MIAMI
BEACH
~
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH FLORIDA 33139
COMMISSION MEMORANDUM NO. L:. <g 7 - q 1_
TO:
Mayor Seymour Gelber and
Memben of the City Commission
DATE: October 21, 1997
FROM:
')
.Jose Garcia_pedrosaj/1(1
City Manager . .. Ii
A RESOLUTION F ;HE MAYOR AND CITY COMMISSION APPROVING
AN AMENDMENT TO THE PROFESSIONAL SERVICES AGREEMENT WITH
DUANY, PLATER-ZYBERK FOR THE ALTOS DEL MAR DESIGN
GUIDELINES IN AN AMOUNT NOT TO EXCEED $14,000.
SUBJECT:
RECOMMENDATION:
Approve the Resolution.
BACKGROUND:
In November, 1993, two professional services agreements for the
North Beach area were approved:
(1) Duany, Plater-Zyberk (DPZ) in the amount of $33,000; and
(2) University of Miami School of Architecture for $17,000.
These efforts resulted in the preparation of a North Beach Master
Plan which included a series of recommended design guidelines.
The Altos del Mar neighborhood within North Beach consists of a
historic district which includes an area of single-family homes
along the ocean. Elizabeth Plater-Zyberk and her staff, along with
a committee consisting of the Planning and Zoning Director, Dean
Grandin, Architect Laurie Swedroe, Ronnie Singer, then Director of
North Beach Development Corporation, and Marla Dumas of the
Redevelopment Agency, have worked on developing a set of
preliminary design guidelines for this single-family area. The DPZ
contract has been fully expended; however, the firm continued to
assist and provided services totalling $6,800 toward this effort.
DATE
c..1~
\O-'2.\-q 1-
AGENDA ITEM
.
..
ANALYSIS:
At this time, in order to respond to the request for Altos del Mar
Design Guidelines from Commissioner Nancy Liebman, the
Administration has determined that an amendment to the original DPZ
agreement is necessary. With this amendment in place, the Altos
del Mar single-family design guidelines could be further refined
and appropriately prepared for incorporation into the Miami Beach
Zoning Ordinance. Assistance from Elizabeth Plater-Zyberk and her
staff for this particularly sensitive ocean front neighborhood will
help to ensure that future development is compatible with the
existing fabric and character of the area.
CONCLUSION:
Administration recommends that the Mayor and City Clerk be
authorized to execute a Resolution approving an amendment to the
Duany, Plater-Zyberk Professional Services Agreement in an amount
not to exceed $14,000 from unallocated bond funds.
JGP:HSM:MSD: jm
AMENDMENT TO NORTH BEACH PROFESSIONAL SERVICES AGREEMENT
ANDRES DUANY & ELIZABETH PLATER-ZYBERK ARCHITECTS. INC. (DPZ)
TASK 1
TASK 2
TASK 3
TASK 4
TASK 5
TASK 6
TASK 7
TASK 8
SCOPE OF SERVICES:
Initiate infor.ma1 meetings to
Administration, North Beach
(NBDC), and the Department of
Historic Preservation.
receive input from City
Development Corporation
Development, Design and
Review preliminary guidelines developed for the Altos del
Mar single-family district, revise as appropriate, and
present to the City Administration and NBDC.
Refine and adjust guidelines to produce written document.
Schedule presentation to City Commission for referral to
the Planning Board and the Land Use and Development
Committee.
Present guidelines to the Planning Board, Land Use and
Development Committee and NBDC.
Make final adjustments to guidelines and regulating plan.
Meet with City Commission to receive the Planning Board,
Land Use and Development Committee and the NBDC reports,
and for approval of guidelines and regulating plan.
Produce final guidelines and regulating plan in for.mat
for incorporation into Zoning Code.
AMENDMENT AMOUNT: NOT TO EXCEED $14,000 (Fee Schedule attached).
IN WITNESS WHEREOF, the parties hereto have caused this
Amendment to be executed by their appropriate officials, as of the
5th day of November , 1997.
ATTEST:
CI~! p~
ANDRES DUANY & ELIZABETH PLATER-
ZYBERK ARCHITECTS, INC.
Wi~ ~laUa -2t-l~OJtD AS TO
\/tCtPRESIDENT "'f:ORM- & LANGUAGE
& FOR EXECUTION
4!.~J/~
City Attorney
11{[,(l7
FEE SCHEDULE FOR AMENDMENT TO
NORTH BEACH PROFESSIONAL SERVICES AGREEMENT
ANDRES DUANY & ELIZABETH PLATER-ZYBERK ARCHITECTS. INC. (DPZ)
The following hourly rates in effect for planning and consulting
services:*
Principal
Project Manager
Computer/Drafter
$175.00 per hour
$ 75.00 per hour
$ 45.00 per hour
*DPZ has agreed to maintain this fee schedule for the completion of
the assignment, though higher rates are currently in
effect.