HomeMy WebLinkAbout2005-25907 Reso
RESOLUTION NO. 2005-25907
A RESOLUTION OF THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH,
FLORIDA, APPROPRIATING FUNDS, IN THE
AMOUNT OF $1,152,260, FROM MIDDLE BEACH
QUALITY OF LIFE FUNDS, OF WHICH UP TO
$750,000 ARE ANTICIPATED TO BE REIMBURSED
BY MIAMI-DADE COUNTY GENERAL OBLIGATION
BOND FUNDS, FOR CONSTRUCTION OF THE 41sT
STREET BRIDGES PROJECT.
WHEREAS, In July 2000 the City authorized Consul-Tech Engineering
(CTE) to design the renovations of the two bridges on 41st Street crossing the
Biscayne and Indian Creek waterways; and
WHEREAS, the design was completed and approved by the Florida
Department of Transportation (FDOT) in 2002; and
WHEREAS, Invitation to Bid No. 22-03/04 was issued on March 16, 2004;
and
WHEREAS, a single bid was received on April 20, 2004, in the amount of
$969,845, from Ric-Man International, Inc; and
WHEREAS, the sole bid was well in excess of the 2002 engineer's cost
estimate of $621 ,567, and the available funding; and
WHEREAS, the Administration met with the sole bidder and the engineer
of record to review possible value engineering options and scope reduction that
might reduce cost; and
WHEREAS, the value engineering and scope reduction options explored
were not sufficient to bring down the cost materially; and
WHEREAS, the sole bidder informed the City that the original bid price
could no longer be honored, and issued a revised price of $1,274,000; and
WHEREAS, after the revised price was issued, the sole bidder informed
the City that it no longer wished to pursue the project; and
WHEREAS, after the City Manager rejected the bid, the Administration
sought to perform the project through one of the City's Job Order Contract (JOC)
contractors; and
WHEREAS, the Administration is currently in the final stages of pricing the
work through one of the City's JOC contractors; and
-
WHEREAS, negotiations are expected to yield a price of approximately
$1,300,000; and
WHEREAS, the Administration deems the JOC price to represent a fair
market value for this project; and
WHEREAS, the construction schedule has been coordinated with other
FDOT and City projects as well as other events of impact to traffic in the area;
and
WHEREAS, the Administration recommends appropriating the funds
outlined, in order to be ready to meet the time restrictions of the construction
schedule; and
WHEREAS, existing funds in the amount of $415,015 from the previous
appropriations for the project would be supplemented with a new appropriation in
the amount of $1,152,260, which includes a 15% project contingency of
$195,000, a JOe Program fee of $19,500, a CIP Office project management fee
of $52,775 and construction funding in the amount of $884,985; and
WHEREAS, the City is also eligible for funding in the amount of up to
$750,000 from the County G.O. Bond funds passed by the voters in November
2004; and
WHEREAS, when County G.O. Bond funds are received, they will be used
to reimburse the Quality of Life funds; and
WHEREAS, the Administration recommends approval of the appropriation,
in the amount of $1,152,260, to be funded from Middle Beach Quality of Life
funds, for construction of the 41st Street Bridges Project.
NOW THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND
CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the
Mayor and City Commission herein approve the appropriation of funds in the
amount of $1,152,260, from Middle Beach Quality of Life funds, of which up to
$750,000 are anticipated to be reimbursed by Miami-Dade County General
Obligation Bond funds, for construction of the 41st Street Bridges Project.
PASSED and ADOPTED this 18th day of May, 2005.
ATTEST:
David Dermer
.
.J.H:... ..
y '.
~"f~ 11~
Crfy,CLERK Robert Parcher
T:\AGEI'\IDA\2005\May1805\Regular\41 Street Bridges RESO.doc
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
~/
CITY OF MIAMI BEACH
COMMISSION ITEM SUMMARY
m
Condensed Title:
A Resolution of the Mayor and City Commission of the City of Miami Beach, Florida, appropriating
funds, in the amount of $1,152,260, for construction of the 41st Street Bridges project.
Issue:
Shall funding in the amount of $1,152,260, be appropriated for construction of the 41 SI Street
Bridges project?
Item Summarv/Recommendation:
In July 2000 the City hired Consul-Tech Engineering (CTE) to design the renovations of the two
bridges on 41 st Street crossing the Biscayne and Indian Creek waterways. The design was
completed and approved by the Florida Department of Transportation in 2002. At the time the
design work was completed, the project was not undertaken due to the lack of sufficient funding.
An invitation to bid was issued in March 2004. A single bid was received in April 2004, in the
amount of $969,845, which exceeded the engineer's original cost estimate and the available
funding. In an effort to bring the project into budget, the Administration met with the sole bidder
and CTE to review possible value engineering options that might reduce the cost, however, these
were not sufficient to bring the cost down materially. At the end of negotiations, which lasted
approximately six months, the sole bidder informed the City that the original bid could no longer
be honored, and issued a revised price of $1 ,274,000. At this time, the window of opportunity to
avoid the business peak season was not available anymore. The project construction had to be
postponed to early spring of 2005. The City Manager then exercised his authority pursuant to the
City Code, and rejected the sole bid received. The CIP Office then directed CTE to update its
cost estimate to reflect a price based on current market prices. CTE issued a revised cost
estimate of $1,045,213. The CIP Office is finalizing negotiations with one ofthe City's Job Order
Contract (JOC) contractors, which are expected to yield a price of approximately $1,300,000,
which is within 2.5% of the sole bidder's revised price. Despite the difference between the
revised estimate and the JOC price, City staff considers the JOC price to be an accurate
reflection of current market costs. The Administration recommends appropriating funds at this
time to meet the new proposed construction schedule for the Indian Creek and Biscayne Bridges
between mid July 2005 and mid January 2006 and avoid conflicts with other construction projects
and events in the area. This schedule will also avoid the next peak season activities. Existing
funds in the amount of $415,015 would be supplemented with a new appropriation in the amount
of $1,152,260, which includes a 15% project contingency of $195,000, a JOC Program fee of
$19,500, a CIP Office project management fee of $52,775 and construction in the amount of
$884,985. The County GO bonds will provide $750,000 which will be used to reimburse the
Quality of Life funds.
Advisory Board Recommendation:
I n/a
Financial Information:
Amount to be expended:
Source of
Funds:
Finance Dept.
AGENDA ITEM
DATE
R7-S-
$"' -rl7 -o~
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
www.miamibeachfl.gov
COMMISSION MEMORANDUM
From:
Mayor David Dermer and
Members of the City Commission
Jorge M. Gonzale7 1, n 0 (,
City Manager ~ ~ ~
Date: May 18, 2005
To:
Subject:
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, APPROPRIATING FUNDS, IN THE
AMOUNT OF $1,152,260, FROM MIDDLE BEACH QUALITY OF LIFE
FUNDS, OF WHICH UP TO $750,000 ARE ANTICIPATED TO BE
REIMBURSED BY MIAMI-DADE COUNTY GENERAL OBLIGATION BOND
FUNDS, FOR CONSTRUCTION OF THE 41sT STREET BRIDGES
PROJECT.
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
FUNDING:
Total remaining project costs are anticipated to be $1,567,275, inclusive of both soft and
hard costs. Of this amount, $415,015 of previously appropriated funds for this project
remains available. Funding for the current unfunded amount is available from Middle
Beach Quality of Life Funds. The City is also eligible for funding in the amount of up to
$750,000 from the County General Obligation (GO) Bond funds passed by the voters in
November 2004. When those funds are received, they will be used to reimburse the
Quality of Life funds. It should be noted that the County is considering deducting up to 1 %
of this amount to cover the administrative costs of their bond program.
ANALYSIS:
On June 4, 1997 the Mayor and City Commission, following a selection process, approved
a professional services agreement with Consul-Tech Engineering, Inc. (CTE), in the
amount of $413,222, for the design and construction administration services for the
renovation and beautification of the entire right-of-way of 41st Street from Alton Road to
Collins Avenue. This agreement anticipated that the complete renovation of the 41st Street
right-of-way would be undertaken, in a five-phase project, with a total project budget of $5
million.
Commission Memorandum
May 18, 2005
41st Street Bridges
Page 2 of 5
The originally proposed five phases consisted of the following:
Phase I
Phase II
Phase III
Phase IV
Phase V
Landscaping, irrigation & replacement of pavers.
Medians with irrigation, up-lighting and landscaping.
Improvement of Indian Creek and Biscayne Waterway bridges.
Improvement of side streets with lighting, landscaping and irrigation.
Improvement of 40th and 42nd Streets, landscaping and re-paving.
Subsequently, it was determined that anticipated revenues would be insufficient to fund
the debt service on the proposed $5 million loan, and the full proposed scope of the
project was not considered feasible. On March 12, 1998, the Finance and Citywide
Projects Committee recommended that only Phase I and Phase II ofthe originally planned
5 phases of the project be undertaken, at an estimated cost of$1 ,727,250. Following this
reduction in scope, the required design work was completed, and the construction of the
reduced scope streetscape project, was completed in 2001.
While renovation of the Biscayne Waterway and Indian Creek bridges was a part of the
original Master Plan as Phase III, it was removed from the project scope in March of 1998.
However, since the completion of the reduced scope 41st Street Beautification Project,
members of the 41st Street Merchants Association continued to request that the bridge
renovation portion of the project be done, because they considered the lack of a finished
look on the bridges made the street appear incomplete.
In July 2000 the City authorized CTE to proceed with design of the renovations of the two
bridges. Improvements to the Indian Creek Bridge consist of road resurfacing, sidewalk
widening, replacement of the existing concrete sidewalks with brick pavers, installation of
decorative handrails, installation of colorful decorative tiles along the side walls, structural
enhancements to meet new wind load requirements, flood lights to enhance the bridge's
exterior appearance, and colorful lighting fixtures on the deck of the bridge to replace the
existing standard fixtures. The smaller Biscayne Waterway Bridge will receive a reduced
level of improvement, consisting of decorative tile work and brick paver sidewalks. The
design was completed and approved by the Florida Department of Transportation (FDOT)
in 2002. At the time, CTE produced a construction cost estimate for the project in the
amount of $621,567. After the design was complete, the project was not undertaken due to
a lack of sufficient funding. The project was dormant during this period because of the
identified costs at the time and the funding issues.
After the City considered that new funding sources could be identified, an Invitation to Bid
was issued in March 2004, and a single bid was received in April 2004, in the amount of
$969,845, from Ric-Man, Inc., which was well in excess of the 2002 engineer's cost
estimate of $621,567, and the available funding. In an effort to bring the project into
budget, the Administration met with the sole bidder and the engineer of record to review
possible value engineering options and scope reduction that might reduce cost. However,
these were not sufficient to bring the cost down materially.
Commission Memorandum
May 18, 2005
4151 Street Bridges
Page 3 of 5
During negotiations, it was found that CTE's cost estimate had not taken into account
certain elements, including requirements for an off-duty police officer, increased traffic
controls required to work within the tight area of the bridge, and the cost of the contractor's
bond and insurance. These costs are not generally considered in consultant's estimates of
probable cost and some fall under the category of construction means and methods,
therefore they were not included in the original 2002 estimate and not recognized at the
time as potential additional costs to the project. Also not reflected in the cost estimate,
were significant increases in material cost from the time the estimate was produced to the
time of bidding in 2004.
The negotiations effort and the value engineering and scope reduction effort lasted
approximately six months and were unsuccessful. During that period several publicly
advertised meetings were held where different options and approaches to the project were
explored and for which different prices were submitted by the contractor for discussion. At
the end of this period, the sole bidder informed the City that the original bid price could no
longer be honored, and issued a revised price of $1,274,000. His justifications were related
to increases in cost due to time and some of the construction methods required to
complete the tasks. Under recommendation of the CIP Office and Procurement staff, I
exercised my authority under section 2-367 of the City Code, and rejected the sole bid
received.
The City's agreement with CTE was approved in 1997 under an old contract format and did
not include a provision to require the consultant to redesign the project to meet the
construction budget, as newer agreements do. In December 2004, after the negotiations
with Ric-Man were ended, CIP requested that CTE revise its estimate to reflect a price
based on current market values. By that time, due to requests from the community not to
be in construction during peak season, the window of opportunity to start construction was
missed and the project could not be implemented until early spring 2005 at the earliest.
CTE issued a revised cost estimate of $1,045,213, which places it reasonably close to the
revised cost submitted by the sole bid contractor.
The original agreement with CTE included design and construction administration services
for the five phases of the broader 41st Street beautification project, including the two
bridges. Certain additional services outside the original scope must be added to the
contract. Such services include revisions to the plans and specifications to reflect changes
required under the new building code, re-permitting the project through all applicable
regulatory agencies, updating the cost estimate, and an increase in the original
construction administration cost, commensurate with the revised project scope and current
billing rates. Certain credits, conversely, are also currently being negotiated. Such credits
arise from the elimination of Phases IV and V from the original scope of work of CTE's
contract. Phases IV and V are being completed separately through a combination of the
Bayshore Neighborhood Project, the Nautilus Neighborhood Project, and the 42nd Street
Streetscape Project. Some of these services have already been performed under the
existing agreement Purchase Order where funds are available in order to try and expedite
Commission Memorandum
May 18, 2005
41st Street Bridges
Page 4 of 5
the completion of the pricing process and initiate construction. CIP staff is currently
negotiating with CTE for the aforesaid additional services and reductions in scope, which
are expected to result in an overall reduction to the original contract amount. If required,
the Administration will bring an appropriate amendment to the City Commission for
approval.
Shortly after the revised construction cost estimate was issued by CTE, the CIP Office
began pricing the work through one of the City's Job Order Contractors (JOC). CIP staff is
currently in the final stages of pricing the work, and negotiations are expected to yield a
price of approximately $1 ,300,000. This price is within 2.5% ofthe price obtained from the
sole bidder approximately one year ago. A final cost has not been agreed upon, because
certain specifications related to the lighting fixtures, and decorative tiles are subject to HPB
review of alternates, and may affect the final price. It should be noted, however, that none
of these alternates are expected to affect the price significantly, and none would cause the
price to exceed $1,300,000 but rather may result in lower costs.
Despite the difference between the consultant's revised cost estimate and the actual price,
CI P staff deems the JOC price to represent a fair market value for this project, considering
those elements which are more closely related to the means and methods of construction,
rather than the design of the project. Such elements are typically not represented in any
cost estimate, and include the lack of a nearby staging area, requiring the contractor to
transport materials in smaller quantities at more frequent intervals, a requirement of the
FDOT, which limits working hours between 9:30am to 3:30pm, restricting work to only 6
hours per day, the intricacies of working on the outside walls ofthe bridge, requiring special
scaffolding, and protective measures required to prevent debris and materials from falling
into the waterway.
In 2002 the project received approval by the Historic Preservation Board (HPB), however,
this approval expired in May 2003, due to a lack of construction activity and staff could
have had extended for one year but did not. The project has now been rescheduled for
review by the HPB on June 16,2005. In conversations with Planning Department staff CIP
does not expect the Board to make any comments or request changes that will impact the
current project costs or schedule. Any comments that are made will be quickly addressed
by the consultant and reviewed with the JOC contractor in order to bring the project to
construction. The current contract documents have been reviewed for permitting, and are
100% complete.
Construction ofthe Indian Creek Bridge includes widening ofthe sidewalk, and milling and
resurfacing of the road surface, requiring temporary lane closures during non-peak traffic
hours. In contrast, the Biscayne Waterway Bridge will have a lesser impact to traffic, as it
does not include sidewalk widening or road resurfacing. The construction schedule has
been coordinated with other FDOT and City projects as well as other events of impact to
traffic in the area, such as the work projected next spring for the 63rd Street f1yover. The
JOC contractor has estimated that they could substantially complete the Indian Creek
Bridge within four months and the Biscayne Waterway Bridge within two months. This
Commission Memorandum
Mar 18, 2005
415 Street Bridges
Page 5 of 5
would assure that the most disruptive construction within the Indian Creek Bridge will occur
within the six month period of mid July 2005 to mid January 2006 to avoid overlapping with
other projects and events. The less disruptive Biscayne Waterway bridge may fall within
this period, or, should a delay in construction occur, it may fall outside the six-month time
window and overlap with other projects, which is not expected to pose a problem, due to its
minimal impact on traffic. This schedule also takes into consideration the community's
concerns about construction during peak season and will avoid the heaviest period of
activity in the area. The Administration recommends appropriating the funds outlined,
despite HPB approval not yet being obtained in order to be ready to move forward as soon
as the HPB order is issued, in order to meet the six-month construction time window.
Existing funds in the amount of $415,015 from the previous appropriations for the project
would be supplemented with a new appropriation in the amount of $1,152,260, which
includes a 15% project contingency of $195,000, a JOC Program fee of $19,500, a CIP
Office project management fee of $52,775 and construction funding in the amount of
$884,985. The Administration recommends approval of the appropriation, in the amount of
$1,152,260, to be funded from Middle Beach Quality of Life funds. The City is also eligible
for funding in the amount of up to $750,000 from the County G.O. Bond funds passed by
the voters in November 2004. When those funds are received, they will be used to
reimburse the Quality of Life funds. It should be noted that the County is considering
deducting up to 1 % of this amount to cover the administrative costs of their bond program.
It also must be noted that when negotiations are completed with the consultant on the
additional services and expected credits the remaining amount will be used for
reimbursement to the Quality of Life accounts.
JMG/RCM/TH/JEC/KLM/MB
T:\AGENDA\2005\May1805\Regular\41 Street Bridges MEMO.doc