RESOLUTION NO. 2005-25954
A RESOLUTION OF THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH,
FLORIDA, APPROVING AMENDMENT NO. 5 IN
THE AMOUNT OF $53,795.25, TO THE
AGREEMENT BETWEEN THE CITY OF MIAMI
BEACH AND URS CORPORATION-SOUTHERN
FOR PROGRAM MANAGEMENT SERVICES,
DATED JUNE 27, 2001; SAID AMENDMENT
PROVIDING FOR ADDITIONAL PROGRAM
MANAGEMENT SERVICES.
WHEREAS, on June 27, 2001, the City Commission adopted Resolution
No. 2001-24499, approving an agreement with URS Corporation-Southern
(Consultant) for Program Management Services, to Manage Construction
Projects for Facilities and Parks (the Agreement); and
WHEREAS, since 2001, Consultant has been performing these services
for a variety of City parks and facilities projects, including the Scott Rakow Youth
Center, the Miami Beach Golf Course, the Regional Library and others; and
WHEREAS, over the past few months, the Capital Improvement Projects
(CIP) Office has experienced several vacancies in staffing the department; and
WHEREAS, the CIP Office project manager for several projects that fell
under the Agreement resigned from the City; and
WHEREAS, due to this staffing issue, on July 1, 2005, the CIP Office
amended the Consultant's Agreement to provide additional services on projects
falling under the Agreement for approximately two months, said amendment in
the amount of $24,589.34; and
WHEREAS, these additional services began in June 2005 and will expire
at the end of July 2005; and
WHEREAS, the vacancies in the CIP Office are being addressed through
on-going recruitment efforts; however, there are still a few projects that fall under
the Agreement that need to be closed out; and
WHEREAS, these include the Scott Rakow Youth Center (Phase I), the
Miami Beach Golf Course clubhouse and maintenance yard, and the Regional
Library; and
WHEREAS, while all of these facilities have received Temporary
Certificates of Occupancy (TCO's), allowing for general use, the projects still
have items that need to be closed out with the respective contractors; and
WHEREAS, the CIP Office has requested a proposal from Consultant for
additional services to provide project management staffing for the CIP Office; and
WHEREAS, the Consultant proposed an additional sixteen (16) weeks of
project manager staffing, for a total of $53,795.25; and
WHEREAS, this would provide the CIP Office with a senior project
manager, effective August 1, 2005 through the middle of November 2005; and
WHEREAS, after careful consideration, the CIP Office believes that this
time will be sufficient enough to complete the recruitment of additional staff, and
have the aforementioned projects closed out; and
WHEREAS, sufficient funds exist in the CIP Office operational budget to
fund this Amendment to the Agreement; and
WHEREAS, accordingly the Administration recommends the approval of
an Amendment No. 5 in the amount of $53,795.25, to the Agreement, for
program management services to provide project manager staffing.
NOW, THEREFORE BE IT DULY RESOLVED BY THE MAYOR AND
CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the
Mayor and City Commission approve Amendment No. 5 in the Amount Of
$53,795.25, to the Agreement between the City of Miami Beach and URS
Corporation-Southern for Program Management Services, dated June 27, 2001;
said Amendment providing for additional Program Management Services.
PASSED AND ADOPTED this 27th day
A~C PGlA-~
CITY CLERK
Robert Parcher
David Dermer
'--
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
~-i~~ft
_.
CITY OF MIAMI BEACH
COMMISSION ITEM SUMMARY
m
Condensed Title:
A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Approving An
Amendment In The Amount Of $53,795.25 To The Agreement Between The City Of Miami Beach And
URS Corporation-Southern For Proqram ManaQement Services.
Issue:
Shall the City Commission Approve An Amendment In The Amount Of $53,795.25 To The Agreement
Between The City Of Miami Beach And URS Corporation-Southern For Program Management Services?
Item Summa IRecommendation:
On June 27, 2001, the City Commission adopted Resolution 2001-24499, entering into a professional
services agreement with URS Corporation-Southern (URS) for Program Management Services, to manage
construction projects for Facilities and Parks.
Over the past few months, the CIP Office has experienced several vacancies in staffing the department.
The CIP Office project manager for several projects that fell under the URS agreement resigned from the
City. Due to this staffing issue, the CIP Office amended URS' agreement to provide additional services on
projects falling under the Program Management agreement for approximately two months. These
additional services will expire at the end of July 2005. The vacancies in the CIP Office are being
addressed through on-going recruitment efforts. However, there are still a few projects that fall under that
URS agreement that need to be closed out. These include the Scott Rakow Youth Center project (Phase
I), the Miami Beach Golf Course Clubhouse and Maintenance Yard, and the Regional Library project.
While all of these facilities have received Temporary Certificates of Occupancy (TCOs), allowing for
general use, the projects still have items that need to be closed out with the contractor.
The CIP Office has requested a proposal from URS for additional services to provide Project Manager
staffing for the CIP Office. URS proposed an additional 16 weeks of Project Manager staffing for a total of
$53,795.25. Effective August 1, 2005, this would provide the CIP Office with one URS Senior Project
Manager through the middle of November 2005.
The Administration recommends the approval of an amendment in the amount of $53,795.25 to the
Agreement between the City of Miami Beach and URS Corporation-Southern for Program Management
Services, to rovide Pro'ect Mana er staffin
Board Recommendation:
Financial Information:
Source of
Funds:
ved
I I
Finance Dept.
$53,795.25
Ci Clerk's Office Le islative Trackin
Kristin McKew, Acting Assistant Director
AGENDA ITEM
DATE
7A-
;..7-OS-
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH. FLORIDA 33139
www.miamibeachfl.gov
COMMISSION MEMORANDUM
From:
Mayor David Dermer and Date: July 27, 2005
Members of the City Commission
Jorge M. Gonzalez \ ~
City Manager I
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, APPROVING AN AMENDMENT IN THE
AMOUNT OF $53,795.25 TO THE AGREEMENT BETWEEN THE CITY OF
MIAMI BEACH AND URS CORPORATION-SOUTHERN FOR PROGRAM
MANAGEMENT SERVICES.
To:
Subject:
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
FUNDING:
Funds are available from the Capital Improvement Projects (CIP) Office operating budget.
ANALYSIS:
On June 27, 2001, the City Commission adopted Resolution 2001-24499, entering into a
professional services agreement with URS Corporation-Southern (URS) for Program
Management Services, to manage construction projects for Facilities and Parks. Since
2001, URS has been performing these services for a variety of Parks and Facilities
projects, including the Scott Rakow Youth Center project, the Miami Beach Golf Course
project, the Regional Library project and others.
Over the past few months, the CI P Office has experienced several vacancies in staffing the
department. The CIP Office project manager for several projects that fell under the URS
agreement resigned from the City. Due to this staffing issue, the CIP Office amended
URS' agreement to provide additional services on projects falling under the Program
Management agreement for approximately two months. These additional services will
expire at the end of July 2005.
The vacancies in the CIP Office are being addressed through on-going recruitment efforts.
However, there are still a few projects that fall under that URS agreement that need to be
closed out. These include the Scott Rakow Youth Center project (Phase I), the Miami
Beach Golf Course Clubhouse and Maintenance Yard, and the Regional Library project.
While all of these facilities have received Temporary Certificates of Occupancy (TCOs),
allowing for general use, the projects still have items that need to be closed out with the
contractor.
City Commission Memorandum
July 27, 2005
URS Additional Services
Page 2 of 2
The CIP Office has requested a proposal from URS for additional services to provide
Project Manager staffing for the CIP Office. URS proposed an additional 16 weeks of
Project Manager staffing for a total of $53,795.25 (Exhibit 1). Effective August 1, 2005, this
would provide the CIP Office with one URS Senior Project Manager through the middle of
November 2005. After careful consideration, the CIP Office believes that this time will be
sufficient enough to complete the recruitment of additional staff, and have the projects
mentioned above closed out. Sufficient funds exist in the CIP Office operational budget to
fund this amendment.
RECOMMENDATION:
The Administration recommends the approval of an amendment in the amount of
$53,795.25 to the Agreement between the City of Miami Beach and URS Corporation-
Southern for Program Management Services, to provide Project Manager staffing.
JMGrrH/JEC/klm
T:\AGENDA\2005\JuI2705\Consent\URS Additional Services.doc
Gy. k,; 91-1:- ,
~
---
URS
RECEiVED
7rr,S JUN 3 \ ~~ \ \: '0
.. .;,. ;.;: '... ;..CH
elT'!" Ur ill"" \. U'-"\llH
(""~;'_. t1:~11'-:"iT~ -' ",1 ,~';; ~.:.::.t_l
vH. PH\tJ,jic~_~ i~;
June 30, 2005
Jorge E. Chartrand
Acting Director
Capital Improvement Projects Office
City of Miami Beach
1700 Convention Center Drive
Miami Beach, Florida 33139
Re: Program Management Services Request
Additional Project Manager (16 Wks)
Dear Mr. Chartrand:
As discussed, URS Corporation is pleased to provide the City of Miami Beach an
Additional Services Fee proposal for a Senior Project Manager to assist with Planning,
Design and Construction Management Services as outlined bellow:
v
1) Senior Project Manager, Grace Escalante
2) 16 weeks at 32 hours per week (512 hrs at $105.07/hr.).
Subtotal
$53,795.25
Total Fee
$53,795.25
We appreciate the opportunity to provide this proposal to the City of Miami Beach. If
you have any questions, or require additional clarifications, feel free to contact me at the
phone numbers provided below.
Assistant Program Director
URS Corporation
7650 Corporate Center Drive, Suite 401
Miami, Florida 33126
Tel: 305.884.8900 Fax: 305.884.2665
Cell: 786.229.7398 Direct: 305.514.2472
P:IPM. CM\Miami Beach Parks & RecIProposals\6.30.0S Project Manager Add Serv_Rev2.docP:IPM. CM\Miarni Beach Parks & RecIProposals\6-30-0S Project Manager Add
Serv _ Rev2.doc