RESOLUTION NO. 2000-23441
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, APPROVING THE
ISSUANCE OF A CHANGE ORDER, IN THE AMOUNT NOT TO
EXCEED $60,000, TO VILA & SON LANDSCAPING
CORPORATION, PURSUANT TO STANDING ORDER NO. 12672
FOR THE COMPLETION OF THE IMPROVEMENTS TO THE 41ST
BEAUTIFICATION PROJECT, PHASE I.
WHEREAS, pursuant to Bid No. 79-97/98, for the 41 st Street Beautification Project,
Phase I (the Project), the Mayor and City Commission approved the award of a contract with
Vila and Son Landscaping for the Project on July 15,1999; and
WHEREAS, an appropriation and standing order was established for this purpose;
and
WHEREAS, the approval of the attached Change Order, in the amount not to exceed
$60,000, will allow the City to achieve the Project's intent; and
WHEREAS, funding to pay for the attached Change Order is available in the
appropriated Quality of Life Account No. 366.2104.069358.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and
City Commission hereby approve the issuance of a Change Order, in the amount not to
exceed $60,000, to Vila & Son Landscaping Corporation for the completion of the
improvements to the 4151 Street Beautification Project, Phase I.
PASSED AND ADOPTED THIS 12th day of January
,2000
APPROVED AS TO
FORM & LANGUAGE
ATT~r' k (). . & FOR EXECUTION
~ll~ 0 ttt,tcb
'=~}!o~~:;;~'M"_W~'''''_~ ~
~
MA YOR
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
COMMISSION MEMORANDUM NO. <2.D-O 0
Mayor Neisen o. Kasdin and
Members of the City Commission
FROM: Lawrence A. Levy ~
City Manager
DATE: January 12,2000
TO:
SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, APPROVING THE ISSUANCE OF A
CHANGE ORDER IN THE AMOUNT NOT TO EXCEED $60,000, TO VILA
& SON LANDSCAPING CORPORATION, PURSUANT TO STANDING
ORDER NO. 12672 FOR THE COMPLETION OF THE IMPROVEMENTS
TO THE 41ST BEAUTIFICATION PROJECT, PHASE I.
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
FUNDING:
$60,000: Funds are available from the proceeds of the Colonial Bank loan for the 41'1 Street
Beautification Project and are within the project budget - Account No. 366.2104.069358
ANALYSIS:
On May 1, 1996, the City Commission adopted a Resolution appropriating $5 million for the 41 sl
Street Beautification Project (the "Project). The Finance and Citywide Projects Committee reviewed
the plan at their meeting of March 12, 1998, and recommended that Phase I and II of the Project be
implemented and that the appropriation be reduced to $1,727,250.
The cost of the Project was estimated at $1,727,250 which provided $1,527,250 for the construction
of Phase I and II, and $200,000 for architectural and engineering fees. The source of funding for the
Project is an appropriation of 50% of the Middle Beach share of the 1 % Resort Tax (Quality of Life
Funds).
Agenda Item
C-Il
l-\2-00
Date
Page 2 of2
On July 15, 1998, the City Commission awarded a contract to Vila & Son Landscaping Corp. for
the Phase I improvements which included landscaping, irrigation, uplighting, and the replacement
of brick pavers and Chattahoochee with new concrete pavers throughout the existing sidewalks from
Alton Road to the Indian Creek Waterway Bridge. Change Order Nos. 1-6 were administratively
approved through a $70,000 contingency fund previously allocated to Phase I of the Project.
Change Order No.7 in the amount not to exceed $60,000, will be reduced from portions allocated
for Phase II improvements that will not be constructed. This Change Order is for the removal and
replacement of concrete base along the sidewalks from Alton Road to the Biscayne Waterway Bridge
to allow the proper installation of the new concrete pavers. The existing conditions do not allow for
the removal of the Chattahoochee without destroying the underlying concrete base. Alternate
methods of installation were compared and it was concluded that replacing the existing concrete base
is the most cost effective method of installation to achieve the project's intent. The new concrete
base will accommodate the installation of the proposed concrete pavers and allow for the pavers to
match existing elevations. The City's consultants and the Middle Beach Partnership have evaluated
this Change Order and agree with the cost estimate submitted.
The City Commission should adopt the Resolution.