2000-23909 RESO
RESOLUTION NO. 2000-23909
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, APPROVING THE
ISSUANCE OF A CHANGE ORDER, IN THE AMOUNT NOT TO
EXCEED $105,347.50, TO MASTEC NORTH AMERICA, PURSUANT
TO STANDING ORDER NO. 14133 FOR THE COMPLETION OF
THE IMPROVEMENTS TO THE 77TH STREET BEAUTIFICATION
PROJECT; AND APPROPRIATING THE NECESSARY FUNDING
FOR THE AFOREST A TED PURPOSE FROM THE GENERAL FUND
UNDESIGNATED FUND BALANCE TO BE REIMBURSED FROM
THE FIRST SERIES OF THE $92 MILLION GENERAL
OBLIGA TION BONDS AND COMMUNITY DEVELOPMENT BLOCK
GRANT FUNDS.
WHEREAS, pursuant to Bid No. 18-99/00, for the 7ih Street Streetscape Improvements
Project, the Mayor and City Commission approved the award of a contract with Mastec North America
for the Project on December 15, 1999; and
WHEREAS, an appropriation and standing order was established for this purpose; and
WHEREAS, the approval of the attached Change Order, in the amount not to exceed
$105,347.50, will allow the City to achieve the Project's intent; and
WHEREAS, funding to pay for the attached Change Order is available from undesignated
General Fund balance, to be reimbursed from the first series of the $92M General Obligation Bonds and
Community Development Block Grant funds.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission hereby approve the issuance of a Change Order, in the amount not to exceed $105,347.50,
to Mastec North America for the completion of the improvements to the 77th Street Beautification
Project; and appropriating the necessary funding for the aforestated purpose from the General Fund
undesignated fund balance to be reimbursed from the first series of the $92 Million General Obligation
Bonds (Biscayne Elementary School Circulation Improvements: Municipal Mobility Plan Project #4)
and Community Development Block Grant funds.
PASSED and ADOPTED this 10th day of May, 2000 ~ft
MAY!/
AWST: 'J,
~-t{L~l~' ~'cu- c.(L-----
CITY CLERK
APPROVED 1>$ TO
FORM & LA.NGUf~,GE
& FOR EXECUTiON
/ltflili!~L- ~
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
COMMISSION MEMORANDUM NO. 357-00
TO:
Mayor Neisen O. Kasdin and
Members of the City Commission
DATE: May 10,2000
FROM:
Lawrence A. Levy It. /'
City Manager Wv
SUBJECT:
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, APPROVING THE ISSUANCE OF A
CHANGE ORDER IN THE AMOUNT NOT TO EXCEED $105,347.50 TO
MASTEC NORTH AMERICA, PURSUANT TO STANDING ORDER NO.
14133 FOR THE COMPLETION OF THE IMPROVEMENTS TO THE 77TH
STREET BEAUTIFICATION PROJECT; AND APPROPRIATING THE
NECESSARY FUNDING FOR THE AFORESTATED PURPOSES FROM
THE GENERAL FUND UNDESIGNATED FUND BALANCE TO BE
REIMBURSED FROM THE $92 MILLION GENERAL OBLIGATION
BONDS AND COMMUNITY DEVELOPMENT BLOCK GRANT FUNDS.
ADMINISTRA TIVE RECOMMENDATION
Adopt the Resolution.
FUNDING
$ 69,097.50: Funds are available from the FY 97/98 CDBG for North Beach Streetscapes
$ 36,250.00: Funds are available from the General Fund undesignated fund balance, to be
reimbursed from the first series of the $92M General Obligation Bonds (Biscayne
Elementary School Circulation Improvements: Municipal Mobility Plan Project #4)
$105,347.50 Total amount of available funding
ANAL YSIS
On December 15, 1999 the City Commission approved the award of a contract to Mastec North
America in the amount of $221,700, pursuant to Bid No. 18-99/00 for the 77th Street Streetscape
Improvements. At the time of award, the construction documents were based on available funds at
the time of design. Therefore, design was limited and the project was value engineered to a degree
that many desirable elements, such as replacement of sidewalks, curbs, and gutters, were omitted.
Community input, as well as Planning Department's review and comments, has created a need to
expand the original scope of work to include these desired enhancements.
AGENDAITEM~.
DATE 5-ID-00
ANAL YSIS (Continued)
Recently, additional funds have been identified which may be applied to the desired enhancements
for the 7ih Street Streetscape Project. These enhancements include new sidewalk, curb and gutter
throughout the project limits, additional landscape and irrigation and a brick paved crosswalk.
The Construction Management Division has requested a Change Order proposal from the contractor,
Mastec North America, to reflect a total value necessary to incorporate the additional scope of work.
Change Order No. I in the amount not to exceed $105,347.50, will be funded from the General Fund
undesignated fund balance, to be reimbursed from the first series of the $92M General Obligation
Bonds and Community Development Block Grant funds. The City's consultant, Bermello, Ajamil
& Partners, Inc., has evaluated this Change Order and agrees with the cost estimate submitted.
The City Commission should adopt the Resolution.
~~~~~~~~~;: