Loading...
352-2000 RDA RESOLUTION NO. 352-2000 A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE MIAMI BEACH REDEVELOPMENT AGENCY (RDA), AUTHORIZING APPROPRIATION OF FUNDS, IN THE AMOUNT OF $76,640, FOR AMENDMENT NO. 2 OF THE PROFESSIONAL SERVICES AGREEMENT FOR ARCHITECTURAL AND ENGINEERING SERVICES WITH ROBERT A. M. STERN ARCHITECTS (STERN), FOR THE CULTURAL CAMPUSIREGIONAL LIBRARY PROJECT, FOR ADDITIONAL SERVICES TO REDESIGN THE SERVICE AREAS OF THE PROPOSED LIBRARY BUILDING IN ORDER TO ACCOMODATE ANY FUTURE DEVELOPMENT OF THE KING PARCEL NORTH OF THE SITE. WHEREAS, on September 23, 1998, the Mayor and City Commission adopted Resolution No. 98-22904, authorizing the Mayor and City Clerk to execute an Agreement with the firm of Robert A. M. Stem Architects (Stem) for the Architectural and Engineering Design of a Regional Library; a Master Plan for Collins Park and the Cultural Campus Streetscape (the Project) (the Agreement); and WHEREAS, on January 6, 1999, the Mayor and City Commission, authorized appropriation of the funding necessary to implement the Agreement with Stem for the Project, and authorized Amendment No.1 to said Agreement; and WHEREAS, the Administration is requesting approval of Amendment No.2 to the Agreement, in the amount of $76,640, for the redesign of the back area of the library building and the relocation of mechanical and electrical equipment in the North parking lot; and WHEREAS,the Administration is requesting that the $76,640 be appropriated from RDA funds. NOW, THEREFORE, BE IT DULY RESOLVED BY THE CHAIRMAN AND MEMBERS OF THE MIAMI BEACH REDEVELOPMENT AGENCY (RDA), that the Chairman and Members of the Redevelopment Agency, authorize appropriation of funds, in the amount of $76,640, for Amendment No. 2 to the professional services Agreement for architectural and engineering services with Robert A. M. Stern Architects, for the Cultural CampuslRegional Library project, for additional services to redesign the service areas ofthe proposed library building in order to accomodate any future development of the King parcel North of the site. PASSED and ADOPTED this ~ day of June, 2000. ~ CHAT ~. AN A TfEST: JLlLLL{ K V [t( JLL~ SECRETARY APPROVED AS 'TO FORM & LANGUAGE & FOR EXECUTION F\WORK\$ALL\CHA TRAND\CUL TURALIRDARES03. WPD fi/r/IJ}p)Lp I if fi/ .'lel ment Agency f 0 . Gf'f'!'!rd C,.....f\.,,,! Sent By: BORRElLI&ASSOCIATES; 305 665 :;)972; Apr.7-QO 4:13PM; Page 2 BB f30RRELLl & ASSOCIATFS ^r.:hil<':l'l'!r~' ~\llIClllinLl LJnd.~c.;lIpe LJc:,ign III t c.; rill t' n" 513:l .1 WI, W. 'lolli, l I ,,1ft. SUII~ I n.l \tl~ml, ::I..;.(~~" Jjl~' (,II \) /It,.I. .~:i1 \ "" c (, 1111 , I I OrlQlhtl"t, ="111 ill I ~(;,,,.:,,-,, I:, 199~ April 7, 2000 (,1(17: ~ i:l . :i,'~.1 ~lr. Alex wmis, Pnncipal Robert A,M. Stern An.:hil~(.:t~ 460 West ]4'" Street New York, N~w YOI'!c 10001 RE: MiOlmi Beach LIbrary Cnnstrut:LiCJn Documeurs Revisions Additional Services (Revised. t'roooSllll Dell! Alex.: Pur~uanl to our previou!; di~cu!\,<;iolls l'eJeV:1llt I'~vlsions to the M13m.i Beach Library consU'ucuoa documents. reqllired to ac::ammodate RClll Blnomhc:rg' s development aireem~nts with tl'.~ City of7Vfiami Beach, we her~by submit our ~ Fee Pl'Opo:llll fo/' additional ~eI'VIC~S and requcst for lime: cxtenSiOl1 co illlplcmCl1l the desired chanycs The scope of additional work Includes allne::e,~!iary architecmraJ/englneering revisions to modify che existing ~ 99% compl~tc construction documcnrs for the project, generally cOllsistin~ of the followinR ~ope of '.I.'ork: A RCHITE CTURAL A E.:i I . 14e Saj'l1ty Plall Fir.t FloQr R~\'ist" blld-{,)f.hllllse ,'r~.. b~lwl'.(~n eridlinc~ (' ro H and I (() 2. <J. affecting the curr~nc luyuul uf the followillC ~pllt:C~: receiving area, el~ctriClllltIlLl ldel,:ummu!ll(.;~tiun:s ruurn.s. ~l4ir lIu,2. mechanical reom ilnd elevater machin~ room, udminiSlr:ltion, ref. manag~r, branch manager, janitor and storage. Rducut~ doors untl windows on building's NOrth wall, as required to re-align with abOVe! room changes. Rt:!vi~w changcs LO caress calculations & path of travel due Co new layout. Revise plJ:\ area ~orth of ;;rid line 1 and ca:;t or ~rri:'; lin\,; ~ LO rdk:::. nt;w si:e ch!ll1g~s, A I.S2 - Ule Safety Plan Second Floor Revis~ ba.:k'o[-hCJus~ an~1l between gridliD\:s C co H and I to 2.9. affectilli (he c~rrent layoullu rdl~l:L required chanli~s ;1._ a c()n~cqucnce of chang~s co tirst noar Jreil5. Reiocate doon and window1 on buildiog'~ ~\iort.1 wlill. tl~ n:quin.:J l() r-..:-aligC\ with aoovo room ;bnJ;e~. .40,2 . Sue Plan Dele~e parking areas I.Ino sit~ pe~LC, w..lls Re.Jocate FPL pad mounted transfo~r l:ntl \':hillc~ yard an~a. R~-IOl::;;lc dumpQtcr an:a. Re. contigmc hllrdllClipC ttrl;llll ilL Nonh tlnu Ea.st alley ways. r~emove current landscapell1ardscape graphics and <lnnotations from <1/1 rl!visiun are<lS, Layout and annotate new landscdpe/hard~('app' d!-''iign in all r~vlslon area;. ~ ""-_ ",-,. - """..... '...I -.' ... '-' ....................; . '-""-' ~o..i",V"I,-...... I ,--t\ '....-'''';-''';v I r-./\' v Sent By: BORAELLI&ASSOC!ATES; 305 1385 9972 i Apr-7-OO 4:13PM; Page 3/6 Mr. Alex Lllnis 1X~,-l1lb,. D, 199') April? 2000 Page 2. A. I.I - Fin' Flour Plan Revi.'\e back.of.hoWI~ ureu between iridlincs C to Hand l to :.Sl, ;lffccrin~ rht~ ~lIrrenl luycll~ or"the fclloWI:1g sp:lces: receiving a.rea. ele.:tric111 and tclecammunicati011S ruums, slair no.2. ~chanlca.l room :llld elevator machine room. adrnlnistration. r~r. rrutnllgcr, brand) mana~r. janilur :md storage. Relocale doors und windows on bulldill~' g North wall, as r=qui~d to re-olliin with above room (.;hanges. Revi.'\e plan area North uf grid line l and east of grid 1i1'\~ N 10 rcfl~l n~W !:lite chitnges. ,il.2 . Seco,uJ Floor Plan Revise back..of.houlie area between gridJines r. to H and I to '2..9, to reflect required changes as il coastlqu~nce of changes (0 first tloor areas, RdoC.11l'. doors and windows on bllilding' s ~(Jrth wall, as rec;uired to re-alig:t with above room changes. A '.3 . Roof PlQn l{~V1Ht: roof tlquipment layout tu cuonJinutd wilh floor plun I .H V AC t;hllngos .12.! . F{rrt Floor RefUct~d Ceillng pUzn Revise plan llrea between grid lines C to H ami llIJ 2.9. ~ff':l,;lCU by :,ll1n cnanscs (0 all the above listed spaces: A2.2 - S6COM Floor RljlecCed Ceiling fAwn Revise plan area between grid:ines C tu Hand Il0 2.9. to rcf1~ct reauired chansec; a.s a ::OlUequenc~ uf chaD~cs to first floer OlretlS. . 043.1 . First Floor Furniturt! Plan Revise plan area bt:l w~t:Q gridlincs C ro H and I to 2.9, atlect~d by plan chang~s to all the ahove listed S-pliCl:S: AJ.2 . Second Floor Furniturr Plan Rcvi~c pllm Lirc:a bclween gridlines C to I J and 1 to 2.~, to rer10ct :~uired ctumgcs Il,j 11 C()n5~quence of changes to fl rst floor areas. A4.2 - North and East Eltvtuions l<.cvisc eievations to reflect requir>:u t.:h:ingcs 8..'\ a consequence of first ar.d ,~<.:.:ond f1nnr r1an rev~sior.s. 115.1 . Building St!crwns R~vist: st:clion~ III rt:f1cCl challg~5 rhrough areas moJit'iL:d in plan .i1. indicated 'lbuve. /~ 9,7 - EnIarfll!d Stair Plans R(;vi~(; ~LIlir No.2 plan co reflecr changes in builcling plll.n as indicated above. ~ /2..5 & 12.6 -lnlfrior El_vatiolts Rt:vise interior I:lldvalions as required by builJing plan changes. ent By: BORRELLI&ASSOCIATES; 305 665 9972; Apr-7-0Q 4:14PM; Page 4/6 Mr. AlelC Lamis Ve':",1 Ill,... I D. 191') April 7. 2000 Pllg~ 1. 04.14.2. Finish Schedule Revise schedule as required by bUilding plan l:h,wg<.:::J. A 14..1 . Door Schidule R::vize ~chedulc a~ n~q\lir",d by building plan chur1gl;!~ A 14.4 - Window ScJl~dl.lle RevIse schedule as r~quir~d by buildillg plan changes. LANDSCAl'E ARCHITECTURAL LJ,/ . l.Jbrary u.ndscup~JHurd~'capt! Plan Kemo'Ve current landscape graphics and annotations from parking lotarea. Layout and annot.lte new Idndscapp. design along proposed access driveway. Revlso landscape design in .alley. east of Library to accommodate Jny relocated site elements. Remove current screen wall graphics and annotations (rom parking lot ,lrea. Rp.move current hardscape graphics and annotations (rom p.1rklng lot area. Layout and annotate new hardscape design for Library service area. Kl!mOVe current graphics and annotations (or backflow preventor, check valv~, transformer pad, chiller pad and dumpster from parking lot area. I_Jycut and annotate n~w locations for backflow preventor, chec~ valve. transformer !Jtfd, ch iller pad and dumpst0.r. 1.1.2. Wf3t PaI'king l..()llAJtd.fcap~//1ard.scap~ Plnn Remove current landscape graphics and annotations from west parking lot drp.t1. Add new parking garage layout to plan. Layout and annotate .new landscape design for parking gara~e planters <IS required. L2. 1 . PllJntioll ~tailJ l<E'move plants from plant list which were exclusive to Library parking lor dreas. Kevise pldnt list Quantitif!s {or plants not exclusive to Library parking tot areas, Add new plants to plant list as appropriatc (or new landscape designs along proposed <Ieee)) drivew.w and at parking gara~e planters. Crf!ate new planting d~rails (or parking garage planter3. L2.3 . Hardscap~ Details Remove screen WJll d('talls. Genllral. Coordin.ul~ all r~vi~i(Jns with in-house techniclll staff and engin~t:ring cunsulUint5, Attend review meetings with Owm:r and Library Statf to 5ecu~ llPprovuls ~nJ si)(n-<)ff of revised plan~. Schedule: Rf.::-{)(.sil5n un.d ,Ti.l{n-oJT 2 weekJ. implcm.mt YC!',Ji.\.jrm:: I 1f1m!th. Sent By: BORAELLI&ASSOCIATESj 305 665 9972; Apr.7.00 4:14PMj Page 5/6 Mr, Alex Lamis !)ec,mb<.. D, 1999 April 7,2000 Page 4. CIVIL ENGIN.tERIN(] Impact on civii ~ngin~ring cunstruL:tion docum~nts due to deletion of North Darkin~ arl::lS and thl; d(.;vc:opmc!1C of new huildjn~ adjacent to Library induutl Lhd fuLlowing: Sanitary S"wu Relocate sanitary sewer servlc~ for Llhrary to'iervlcc drlvl;W:lY area und~rnellf.h Lht: n~w North building, f)rainagf Relocate discharges from Lihrary to the South or East ali may be required, DC3j~ new extiltmtlon trench \11" dJ'llillUic well. betwccll Library a.ml m:w builuill~. ~ubjtlCllU l.tnu]y~is of ~oil test to determine feasibiliLy of the er..!.i.ltration system. WaiST Relocate water ~ervice fur Librolry to ~tlrvice r.l.riveway lU'ea to be provided underneath the new North building Relocate bo.ckflow pl'evel1l()l'~ to Eo.st ,iue uf ,erl/i\.'1: Llril/c, nrc Litle Relocate ti,'c line for r .ihTary 10 driv;,.way lIrt',a lu b~ provided 1I1werneath the llew North building. CoordiMlioll Coordinale revisions with at"chileet and other disciplill~S. STRUCTURAL E~G1NEERI~G Genital Revise location of ~talr No.2 to accommodate archiccctural plan chlln~elf u rc:quircd. RG'llnaIY71~ llntl reconfigure coLumn locations at back-of-house area (0 confonn with new architectural plan layout. Re-analyze and revise slabs. beams, columns and footings in.u~ impacted by plan ~hang~s. !-te-il.nalyze and revise as may be required. building wind system. Coordinate revi3ions with architect llnci other discipline:;. MEP/FP ENGINEERING Gel/uu'ol Coordinul.t: nwillilln,~ with urchit.ect and lItht:lT ui.~ciplim~,~. Relocate all mechanical, electrical and plulubing utility lines currencly indicatod in p<lrkiu!; arc",- North of Lihrury, Revise the following mechunicl1J, electncal, pLumbing and fire prutection drawings ItS miy be required. to implemenl architectural plan chanaes In hack-af-house area between gridlines C [0 Hand 1102.9.: ent By: BORRE~LI&ASSOCIATES; 305 665 9972; Apr-7-00 4:14PM; Page 6/8 Mr. All:x Lamis IXc..,llbcr [J, 1999 April 7, 2()()O Puge 5. IIV:\C - M-Zoo, M-lOI, yt.202, ~..1.301 ELECTRICAL - E-OOl, E-lO!. E.10:, E-103, E.104. E-10~, E.IC6. E.107, E-~08, E-201, E-21)2. E-203 PLUMBING. 1'-200, P-201. 1'-301 .FIRE PROTECTiON - FP-200, fP-201, FP-20'2 Our prupos"d Pees 10 ~rform the scrvic~s summarized above is El8hty Seven Thousand Five Hundred Sevtmly Dollars (S87J70.00) for additional sc:rvices, plus reimbursable expenses, payable on a monthly bllsis and calculatt:d 011 the hasis of the fol!owin~ estitnllted man hours and hourly r:ltes as (ollows: Principul Ar:;hil~ct 24 Project Maoagement 90 Architectw'ilJ Production $00 Civil Engineering 60 Structural Engineering 8~ MEPlFP Engineering I W Coal ElItimlt.tor ~ E!lUm.l~ HUUC!lltod AlE F~~ 895 ~ Hours @ S125.O/hr - S ",000,00 3,000.00 +fW Hnur~ @ $ 90.0/hr. ~ Hour~ @ $ 80.0/hr. 69 Huurs @:) 90.0/hr. te5 Hours @ S 90,OIhr. ~ Hours @ S 90.D/hr. 16 Hou:'S @ S 90. O/hr. -t-;M6 tIours . ~,.l('().OO H,100.00 - ....,800.00 40,000.00 . 5,676.00 5,400.00 - 9,458.00 7,650.00 - 12,600.00 10,800.00 - 1.6!.lO.OO 1.690.00 $ "'7,576.l:J6 76,640.00 A 1.';0. plea~c he advi5ed that due to the extent of the ch.mges required to the d::-uwings and oLhl:r project documents submitted 0.3 pllrt of our previous work. we will require an IiJdilionul 1.3 month perlod of time. allocated as tndicuted iLbuv~, in urd~r Lu imp!~rncnL tilllhc n:y,uin:u rt;yi:;iuns. If thii proposal meetll with yuur Cipproval. please nOtify us at YOUl ear1.iest convenience in order thul w~ may commence the implementation of lht: work.. If you have any questions regw'dillg this proposal or require any additionllJ in{omliltion regarding this maHer, please feel free to concact us. S incerel y, ~~ hime E. Borrelli, AL\ ~ ce. Jorge A. Borrelli JJ.YJ. Zcb~e Miami Beach Redevelopment Agency 1700 Convention Center Drive Miami Beach, Florida 33139 Telephone: (305) 673- 7295 Fax: (305) 673- 7772 REDEVELOPMENT AGENCY MEMORANDUM NO. 2000- 3<6 June 7, 2000 TO: Chairman and Members of the Miami Beach RedevelOpm~y Lawrence A. Levy 0. ' Executive DireY A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE MIAMI BEACH REDEVELOPMENT AGENCY (RDA), APPROPRIATING FUNDS, IN THE AMOUNT OF $76,640, FROM CITY CENTER TAX INCREMENT FUNDS FOR AMENDMENT NO.2 TO THE ARCHITECTURAL AND ENGINEERING DESIGN AGREEMENT WITH ROBERT A. M. STERN ARCHITECTS, FOR THE CULTURAL CAMPUSIREGIONAL LIBRARY PROJECT, FOR ADDITIONAL SERVICES TO REDESIGN THE SERVICE AREAS OF THE PROPOSED LIBRARY BUILDING IN ORDER TO ACCOMODA TE ANY FUTURE DEVELOPMENT OF THE KING PARCEL NORTH OF THE SITE. FROM: SUBJECT: ADMINISTRATION RECOMMENDATION: Adopt the Resolution. FUNDING: Funding is available from the City Center Redevelopment Agency (RDA). ANALYSIS: On September 23, 1998, the Mayor and City Commission adopted Resolution No. 98-22904, authorizing the Mayor and City Clerk to execute an agreement with the firm of Robert A. M. Stem Architects (Stem) for the architectural and engineering design of a Regional Library, a 400-space Parking Garage and a Master Plan for Park and Streetscape Improvements in the area surrounding Collins Park. SUUTIl f)UI~r: l?edevel()pment [)1~tr1ct Agenda Item ,.3 C G'-f-(J:) IDate On November 18, 1998, the Mayor and City Commission directed the Adminstration not to proceed with the design of a 400-space Parking Garage and to instead design two surface lots in those parcels. On January 6, 1999, the Mayor and City Commission, authorized appropriation of the funding necessary to implement the architectural and engineering design agreement with Stem for the Cultural Campus/Regional Library and authorized Amendment No.1 to said agreement which reflected the changes in scope. The Administration is now requesting approval of Amendment No.2, in the amount of $76,640, to the agreement with Stem, for the redesign of the back of the house area of the library building and the relocation of mechanical and electrical equipment in the North parking lot. This redesign is necessary in order to plan for the possibility of a future development of the parcel known as the King parcel North of the proposed library building. The scope of work includes interior changes to various areas of the building, relocation of cooling equipment, a transformer pad and a trash dumpster area on the site. It also encompasses relocation of domestic and fire water services and of the main sanitary sewer service to the building. Additionally, changes are required to the North facade and to mechanical, fire sprinkler and electrical distribution services within the building. The redesign is expected to last six weeks and will alow completion of the project documents in preparation for final City reviews and for construction bidding. The Chairman and Members of the Redevelopment Agency should adopt the resolution appropriating funding, in the amount of $76,640, for Amendment No.2, to the agreement with Robert A. M. Stem Architects, for the Regional Library redesign and the associated equipment and services relocations. ~~~=~~ Attachments