2000-23450 RESO
RESOLUTION NO. 2000-23'450
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING
THE MAYOR AND CITY CLERK TO EXECUTE AN AMENDMENT TO
THE CURRENT AGREEMENT WITH REG ARCHITECTS, INC., TO
PROVIDE ARCHITECTURAL /ENGINEERING SERVICES FOR TEN (10)
PARK PROJECTS, AS PROPOSED IN THE CITY'S PARKS MASTER PLAN
AND APPROVED BY THE MAYOR AND CITY COMMISSION;
ESTABLISHING A REDUCED OVERALL FEE OF 7.5% (FROM THE
PREVIOUSLY APPROVED RATE OF 8.0%) OF CONSTRUCTION COST;
APPROPRIATING THE AMOUNT OF $191,252 (COMPRISED OF $166,252
FOR THE ADDITIONAL ARCHITECTURAL/ENGINEERING SERVICES
NECESSARY TO COMPLETE THE PARKS, AS SPECIFIED IN THE 1999
GENERAL OBLIGATION BOND PROGRAM), AND AN AMOUNT NOT TO
EXCEED $25,000 FOR SURVEYING, TESTING AND OTHER
REIMBURSABLE EXPENSES WITH FUNDING AVAILABLE FROM THE
CITY'S GENERAL FUND UNDESIGNATED FUND BALANCE, TO BE
REIMBURSED FROM THE FUTURE GENERAL OBLIGATION (G.O.)
BOND ISSUE.
WHEREAS, on July 16, 1997, the Mayor and City Commission approved a Professional
Services Agreement with the firm of REG Architects, Inc. (the Agreement), for the architectural
design and development of construction documents for various parks included in the City's $15
Million General Obligation Parks Improvements Bond Program; and
WHEREAS, on May 20,1998, the Mayor and City Commission approved the schematic
plans for these park facilities, pursuant to the Master Plan; and
WHEREAS, REG Architects, Inc. prepared preliminary cost estimates; developed a draft
construction schedule, and the Administration was authorized to proceed with construction
documents; and
WHEREAS, on November 2, 1999, the voters of Miami Beach approved the issuance of an
approximately $92 Million General Obligation (GO) Bonds (the Bonds); and
WHEREAS, included in the $92 Million was $24,830,000 for parks and beaches; and
WHEREAS, ten (10) of the eleven (II) projects currently under contract with REG
Architects, Inc. are included in the parks and beaches program; and
WHEREAS, these projects include Crespi; Fairway; Stillwater; Tatum; LaGorce; Fisher;
Muss; Island View; South Shore Community Center; and Palm Island Park; Washington Avenue
Park is not addressed because it is fully funded from another source; and
WHEREAS, the improvements proposed for these parks under the Bonds include, but are
not limited to, new decorative perimeter fencing, security and sports lighting, sport courts and multi-
purpose recreation room; and
WHEREAS, these improvements were determined as a combined result of work originally
identified in the Parks Master Plan as necessary, but not funded in the initial $15 Million Parks
Improvement Bond Program; and
WHEREAS, REG Architects, Inc. currently has approved projects, totaling $2,451,566 in
construction, and approved architectural/engineering fees of $209,863, (representing an 8% of
construction cost fee); and
WHEREAS, the new construction dollars recommended to be added to the Agreement is
$2,563,299, for a new total of$5,014,865; and
WHEREAS, in response to the request for a lower fee percentage, REG Architects, Inc. has
agreed to an overall fee of7.5%; and
WHEREAS, the new fee total is $376,115, rather than the original fee of$401,189, which
equates to an overall reduction and savings to the City of $25,074; and
WHEREAS, REG Architects, Inc. has requested an amount not to exceed $10,000 for
reimbursables, that will be paid only on the cost of actual invoices, and $15,000, for additional
surveys and testing, if needed, and paid only with supporting invoices; and
WHEREAS, accordingly the Administration recommends a Third Amendment to the REG
Architects' contract be approved by the Mayor and City Commission and executed by the Mayor and
City Clerk.
NOW THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission herein approve and authorize the Mayor and City Clerk to execute an Amendment to
the current Agreement with REG Architects, Inc., to provide Architectural/Engineering Services for
ten (10) Parks projects, as proposed in the Parks Master Plan and approved by the Mayor and
Commission; establishing a reduced overall fee of 7.5% (from the previously approved rate of 8.0%)
of construction cost; appropriating the amount of$191,252 (comprised of$166,252 for additional
architectural/engineering services necessary to complete the parks, as specified in the 1999 General
Obligation Bond Program), and an amount not to exceed $25,000 for surveying, testing and other
reimbursable expenses with funding available from the City's General Fund Undesignated Fund
Balance, to be reimbursed from the future General Obligation (G.O.) Bond Issue.
PASSED and ADOPTED this 12th day of January, 2000.
f/I
MAYOR
ATTEST:
t/lwr -Pat~
CITY CLERK
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
T:\AGENDA \2000IJAN1200\CONSEN1\REGAG99.RES
1fj~
C AIforney
\~iOO
ATTACHMENT A
January 5, 1999
I :45 p.m.
BERMELLO, AJAMIL& PARTNERS, INC. (7.0% Fee)
Park Previously Approved Previously Approved Total Const. Dollars Difference A&E Fee
Const. Dollars Basic A&E fees Including GO Bond 1999
Lummus $ 840,242 $ 1,797,242 $ 957,000
North Shore $3,972,181 $ 6,297,181 $2,325,000
N.Shore Open Space $1,743,000 $ 2,008,500 $ 265,500
Pinetree $ 215,569 $ 294,069 $ 78,500
Parks Maint. Yard $ 324,106 $ 839,700 $ 515,594
S. Pointe Park $ 913,034 $ 2,680,034 $1,767,000
TOTAL $8,008,132 $531,235 $13,916,726 $ 5,908,594 $442,936
* T1F Funding
Flamingo
Nonnandy Isle
Scott Rakow Youth Ctr
CARR SMITH CORRADINO (9% Fee)
$2,288,075
$2,126,875
$2,852,774
TOTAL
*$87,000 from SNPB
$7,267,724
$780,503
$ 4,781,075*
$ 2,376,875
$ 2,980,274
$10,138,224
$2,493,000*
$ 250,000
$ 127,500
$ 2,870,500 $131,937
REG ARCHITECTS (7.5% Fee)
Crespi $ 210,048 $ 345,048 $ 135,000
Fairway $ 891,188 $1,108,688 $ 217,500
Stillwater $ 300,266 $ 444,266 $ 144,000
Tatum $ 245,683 $ 380,683 $ 135,000
LaGorce $ 91,808 $ 134,308 $ 42,500
Fisher $ 92,347 $ 227,347 $ 135,000
Muss $ 176,387 $ 241,387 $ 65,000
Island View $ 199,747 $ 334,747 $ 135,000
S. Shore Comm. Ctr. $ 0.00 $1,185,000 $1,185,000
Palm Island $ 244,092 $ 309,092 $ 65,000
Washington $ 0.00 $ 304,299* $ 304,299*
TOTAL $2,451,566 $209,863 $5,014,865 $ 2,563,299 $166,252
*Comprised ofTlF and SNPB Funding
PROJECTS RECOMMENDED TO BE INCLUDED IN THE
AGREEMENT AMMENDMENT WITH REG ARCHITECTS. INC.
PARKS and BEACHES
Crespi Park
Project Description: New restroom, renovate basketball court, park furnishings, playground,
landscaping and irrigation. 1999 GO Bond components include new basketball court and security
lighting, and perimeter aluminum picket fencing.
Status: Funding sources: $210,048 from the Parks Bond; and $150,000 from the 1999 GO Bond
for a total of $360,048. Park renovations completed on June 1999 as part of the $15 Million Parks
Bond. Total project cost $210,048. Improvements completed included new restrooms, renovation
of basketball court, playground, park furnishings, landscaping and irrigation. 1999 GO Bond
proposed improvements to include decorative perimeter aluminum picket fencing, basketball court
and security lighting and a multi-purpose room. 1999 GO Bond Funding: $150,000.
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG'S contract, April 2000 completion of construction
documents, specifications and permitting process, June 2000 bidding and award of contract,
construction July-November 2000. Estimated costs include: construction budget $135,000, NE fees
$10,800 (8% of construction budget) and estimated cost of permitting, testing and administration
$4,200.
Stillwater Park
Project Description: New recreation building, renovation of basketball court, playground, limited
security lighting, landscaping and irrigation. 1999 GO Bond components include court and security
lighting, and perimeter aluminum picket fencing.
Status: Park renovations completed on June 1999 as part of the $15 Million Parks Bond. Total
project cost $300,266. Improvements completed included a new recreation building, renovated
basketball court, site furnishings, new playground, landscaping and irrigation. 1999 GO Bond
proposed improvements to include decorative perimeter aluminum picket fencing, enhanced security
lighting and court lighting. 1999 GO Bond Funding: $160,000.
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
.
Timetable: December 1999 amend REG contract, March 2000 completion of construction
documents, specifications and permitting process, May 2000 bidding and award of contract,
Construction June-September 2000. Estimated costs include: construction budget $144,000, NE
fees of $11,500 (8% of construction budget) and estimated cost of permitting, testing and
administration $4,500.
Tatum Park
Project Description: New building, basketball court renovations, landscaping and irrigation, limited
security lighting and entry gate. 1999 GO Bond components include court and security lighting and
perimeter aluminum picket fencing.
Status: Park renovations to be completed in December 1999 as part of the $15 Million Parks Bond
Total project cost $245,683. Improvements included a new recreation building, refurbished basketball
court, landscaping, limited security lighting and irrigation. 1999 GO Bond proposed improvements
to include decorative perimeter aluminum picket fencing, additional security lighting and court
lighting. 1999 GO Bond Funding: $150,000
~"~-~',---.....-.:;-"
, .
Recommendation: Authorize the Administration to amend the contract with kEG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG'S contract, April 2000 completion of construction
documents, specifications and permitting process, June 2000 bidding and award of contract,
construction July-November 2000. Estimated costs include: construction budget $135,000, NE fees
$10,800 (8% of construction budget) and estimated cost of permitting, testing and administration
$4,200.
Fairway Park
Project Description: Addition of perimeter aluminum picket fencing.
Status: Construction documents 90% complete for improvements under the $15 Mil Parks Bond.
Estimated construction cost for this phase is $791,188. Current improvements include a new
recreation building, basketball and tennis courts renovations, ball field lighting, a new playground, site
furnishings, landscaping and irrigation. Additional 1999 GO Bond proposed improvements include
decorative perimeter aluminum picket fencing, additional sport court and security lighting and a multi-
purpose room. 1999 GO Bond Funding: $250,000
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG'S contract, April 2000 completion of construction
documents and specifications and permitting process, June 2000 bidding and award of contract,
construction July 2000-January 2001. Estimated costs include: construction budget $217,500, NE
fees $17,400 (8% of construction budget) and estimated cost of permitting, testing and administration
$15,100.
Fisher Park
Project Description: Addition of enhanced security lighting and perimeter aluminum picket fencing.
Status: Park renovations completed on 10/99 as part of the $15 Mil Parks Bond. Total project cost
$99,347. Completed improvements include a new playground, landscaping, site . furnishings,
pedestrian walkways, limited security lighting and irrigation. 1999 GO Bond proposed improvements
to include decorative perimeter aluminum picket fencing, enhanced security lighting, a shade
pavilion and parking pavers. New Bond Funding: $150,000
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG's contract, April 2000 completion of construction
documents, specifications and permitting process, June 2000 bidding and award of contract,
construction 7/00 - 11/00. Estimated costs include: construction budget $135,000, NE fees $10,800
(8% of construction budget) and estimated cost of permitting, testing and administration $4,200.
La Gorce
Project Description: Completed improvements included a new playground, security lighting,
pedestrian walkways, landscaping and irrigation. 1999 GO Bond components include security
lighting and perimeter aluminum picket fencing.
Status: Park renovations completed on 6/99 as part of the $15 Million Parks Bond. Total project cost
$91,808. Improvements completed were a new playground, landscaping, security lighting, pedestrian
walkways and irrigation. 1999 GO Bond proposed improvements to include decorative perimeter
aluminum picket fencing, a shade pavilion, enhanced security lighting and parking pavers. 1999 GO
Bond Funding: $50,000
, ,
Recommendation: Authorize the Admir.b~,ation to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG's contract, April 2000 completion of construction
documents and specifications and permitting process, June 2000 bidding and award of contract,
construction 7/00 - 11/00. Estimated costs include: construction budget $42,500, NE fees $3,400
(8% of construction budget) and estimated cost of permitting, testing and administration 54,100.
Muss Park
Project Description: Renovate recreation building, playground, landscape and irrgation. 1999 GO
Bond components include additional playground equipment, perimeter aluminum picket fencing, and
security lighting.
Status: Construction documents 90% complete for improvements under the $15 Million Parks Bond.
Total project cost $176,387. Current improvements consist of renovation of recreation building,
additional playground equipment, landscaping and irrigation. 1999 GO Bond proposed improvements
to include decorative perimeter aluminum picket fencing and enhanced security lighting. 1999 GO
Bond Funding: $75,000
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG contract, April 2000 completion of construction documents
and specifications and permitting process, June 2000 bidding and award of contract, construction
7/00 - 11/00. Estimated costs include: construction budget $65,000, NE fees $5,200 (8% of
construction budget) and estimated cost of permitting, testing and administration $4,800.
South Shore Community Center
Project Description: Renovation and reconstruction of complete facility, with new landscaping,
irrigation, signage, and playground.
Status: This project was originally included in the group of parks awarded to REG Architects but was
subsequently put on hold due to lack of funding. 1999 GO Bond proposed improvements include
renovation and reconstruction of complete facility, new landscaping, irrigation, signage and
playground. 1999 GO Bond Funding: $1,350,000
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans and specifications to complete the park as described above.
Timetable: December 1999 amend REG's contract, 7/00 completion of construction documents,
specifications and permitting process, 9/00 bidding and award of contract, construction 10/00 - 9/01.
Estimated costs include: construction budget $1,200,000, NE fees $96,000 (8% of construction
budget) and estimated cost of permitting, testing and administration $54,000.
Island View Park
Project Description: Playground surface, landscaping, irrigation and site furnishings. 1999 GO Bond
components include security lighting, perimeter aluminum picket fencing, and shade pavilion.
Status: Park renovations completed on 10/99 as part of the $15 Million Parks Bond. Total project
cost $199,747. Improvements completed included playground enhancements, park furnishings,
landscaping and irrigation. 1999 GO Bond proposed improvements to include decorative perimeter
aluminum picket fencing, additional security lighting and a shade pavilion. 1999 GO Bond
Funding: $150,000.
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans & specifications to complete the park as described above.
. .
Timetable: December 1999 amend REG'S contract. April 2000 completion of construction
documents & specifications and permitting process, June 2000 bidding and award of contract,
constructon 7/00 - 11/00. Estimated costs include: construction budget $135,000, NE fees $10,800
(8% of construction budget) and estimated cost of permitting, testing and administration $4,200.
Palm Island
Project Description: Repair existing shade pavilion, new basketball court, new playground
equipment, accessible routes. 1999 GO Bond components include court and security lighting, and
refurbishment of tennis courts.
Status: Park renovations completed on 6/99 as part of the $15 Million Parks Bond. Total project cost
$244,092. Improvements completed included renovations to existing shade pavilion, new playground,
new basketball court, landscaping, irrigation, park furnishings and pedestrian walkways. 1999 GO
Bond proposed improvements to include sport court lighting, additional security lighting, and
refurbishment of tennis courts. 1999 GO Bond Funding: $75,000
Recommendation: Authorize the Administration to amend the contract with REG Architects to
prepare plans & specifications to complete the park as described above.
Timetable: December 1999 amend REG contract, April 2000 completion of construction documents
& specifications and penmitting process, June 2000 bidding and award of contract, construction 7100
- 11/00. Estimated costs include: construction budget $65,000, NE fees $5,200 (8% of construction
budget) and estimated cost of permitting, testing and administration $4,800.
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
http:\\ci.miami-beach.ft.us
COMMISSION MEMORANDUM NO. 2G .00
TO:
Mayor Neisen O. Kasdin and
Members of the City Commission
Lawrence A. Levy W
City Manager
DATE: January 12, 2000
FROM:
SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, AUTHORIZING THE MAYOR AND
CITY CLERK TO EXECUTE AN AMENDMENT TO THE CURRENT
AGREEMENT WITH REG ARCHITECTS, INC., TO PROVIDE
ARCHITECTURAL /ENGINEERING SERVICES FOR TEN (10) PARK
PROJECTS AS PROPOSED IN THE CITY'S PARKS MASTER PLAN AND
APPROVED BY THE MAYOR AND CITY COMMISSION ESTABLISHING
A REVISED OVERALL FEE OF 7.5% FROM THE PREVIOUSLY
APPROVED RATE OF 8.0% OF CONSTRUCTION COST;
APPROPRIATING THE AMOUNT OF $191,252 COMPRISED OF $166,252
FOR THE ADDITIONAL ARCHlTECTURAL/ENGINEERING SERVICES
NECESSARY TO COMPLETE THE PARKS AS SPECIFIED IN THE 1999
GENERAL OBLIGATION BOND PROGRAM, AND AN AMOUNT NOT TO
EXCEED $25,000 FOR SURVEYING, TESTING AND OTHER
REIMBURSABLE EXPENSES WITH FUNDING AVAILABLE FROM THE
CITY'S GENERAL FUND UNDESIGNATED FUND BALANCE TO BE
REIMBURSED FROM THE FUTURE GENERAL OBLIGATION (G.O.)
BOND ISSUE.
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
ANALYSIS:
On July 16, 1997, the City Commission approved a professional services agreement with the firm
of REG Architects, Inc., for the design services, construction and bidding documents, construction
observation, project administration, scheduling and cost estimating necessary for the
reconstruction/renovations of Crespi, Fairway, Stillwater, Tatum, LaGorce, Fisher, Muss, Island
View, South Shore Community Center, Palm Island and Washington Parks. The rate of8% of the
construction cost of each project was negotiated as a fee for the above referenced professional
services. Additionally, a "not to exceed" reimbursable amount of $10,000 was agreed upon to be
paid based on actual invoices. The professional services agreement with REG Architects, Inc., also
anticipated the possibility of additional funding and included a section that permitted the addition
of work to this firm.
AGENDA ITEM
DATE
C.1~
1-1L.-DD
On November 2, 1999, the voters of Miami Beach approved the issuance of an approximate $92
Million General Obligation (GO) Bonds. Included in the $92 Million was $24,830,000 for Parks and
Beaches. Ten (10) of the eleven (11) projects currently included in the REG Architects, Inc., are
also included in the Parks and Beaches program. These include Crespi, Fairway, Stillwater, Tatum,
LaGorce, Fisher, Muss, Island View, South Shore Community Center and Palm Island Parks.
Washington Avenue Park in not addressed because it is fully funded from another source. The
improvements proposed for these parks under the $92 Million General Obligation (GO) Bonds
include new decorative perimeter fencing, security and sports lighting, sport courts and multi-purpose
recreation rooms. These improvements were determined as a combined result of work originally
identified in the Parks Master Plan as necessary but not funded in the initial $15 million Parks
Improvement Bond program and community input obtained during the recent neighborhoods
meetings process held prior to the November voter approval.
On November 17,1999, the City Commission referred the $92 Million General Obligation Bond
Issue to a joint meeting of the Finance and Citywide Projects Committee, the Neighborhoods
Committee and the GO Bond Project Oversight Committee. This referral included a recommendation
that agreements currently in effect with the three firms responsible for the professional architecturaV
engineering services for the parks be amended to enable the process to proceed efficiently both in
terms oftime and resources. Please see the attached copy of the parks improvements recommended
to be included in the REG, Architects, Inc. amended agreement as they were referred to the joint
meeting held on November 17, 1999.
On December 8, 1999, a joint meeting of the Neighborhoods Committee, Finance and Citywide
Projects Committee and the GO Bond Project Oversight Committee was held. A presentation was
made by the Administration setting forth the concept of amending the existing professional services
agreements with each of the fIrms currently working on park projects. An extensive discussion
transpired concerning the benefits of such an action, the past performance of each firm, the amount
of fees paid to each of the firms to date and the possibility of the firms to handle the additional
workload. The final recommendation of the Committees was to amend the contracts subject to
renegotiated lower fees. On December 15, 1999, the City Commission unanimously accepted this
report.
City staffmet with representatives of REG Architects, Inc., to discuss a lower fee schedule and are
pleased to report REG has agreed to adjust their percentage for their entire professional services
agreement including both the work already completed, that in progress and the new work to be done,
REG Architects, Inc., currently has approved projects totaling $2,451,566 in construction and
approved architectural/engineering fees of $209,863, an 8% fee. The new construction dollars
recommended to be added to the REG Architects, Inc., agreement is $2,563,299 for a new grand total
of$5,014,865. In response to the request for a lower fee percentage REG Architects, Inc., has agreed
to an overall fee of 7.5% for their total agreement of $5,014,865. The new fee total at 7.5% is
$376,115 rather than the 8% fee of$401,189, which equates to an overall reduction and savings to
the City of $25,074. Additionally, for the new work REG Architects, Inc., has requested an amount
not to exceed $10,000 for reimbursables that will be paid only on the cost of actual invoices and
$15,000 for additional surveys and testing if needed and paid only with supporting invoices. As a
point of information the result of this negotiation process was reported to the GO Bond Project
Oversight Committee at its January 10, 2000 meeting.
Approval of this Resolution will enable the parks projects currently underway to be proceed
expeditiously in a fiscally prudent manner.
L$J:M
Attachment
T:\AGENDA\2000\JAN 1200\CONSENliREGAG99.MEM
~
...,
AMENDMENT No.2
TO AGREEMENT BETWEEN
CITY OF MIAMI BEACH, FLORIDA
AND
REG ARCHITECTS, INC.
ARCHlTECTURALIENGINEERING SERVICES FOR THE ADDITIONAL SERVICES
NECESSARY TO COMPLETE THE PARKS MASTER PLAN BOND PROGRAM
SITES
This AMENDMENT NO.2, dated as of f). I I ,2000, to that certain Agreement, dated July
16, 1997, by and between the CITY OF MIAMI BEACH, FLORIDA (City) and REG
ARCHITECTS, INC. (Consultant) for the Parks Master Plan Bond Program Sites.
WHEREAS, the Agreement provides for the provision of architectural/engineering services for
eleven (11) Parks Projects included in the Parks Master Plan Bond Program; and
WHEREAS, the Administration recommends that the foregoing Amendment No.2 be executed
for the additional architectural/engineering services necessary to complete the Projects, as specified
in the 1999 General Obligation Bond Program.
I. ABOVE RECITALS
The above recitals are true and correct and incorporated as a part of this Amendment No.2.
2. MODIFICATION
The Agreement is amended to add those additional services, as specified in Exhibit A and
Attachment A., respectively, both attached hereto and incorporated herein.
3. OTHER PROVISIONS
All other provisions of the Agreement, as amended, are unchanged.
4. RATIFICATION
The City and Consultant ratify the terms of the Agreement, as modified by this
Amendment No.2.
Page 1 of2
.,/
....
IN WITNESS WHEREOF, The parties hereto have caused this Amendment No.2 to be
executed in their names by their duly authorized officials as of the date first set forth above.
CITY OF MIAMI BEACH
By YJ1Jj
MJ.~bR
~
~ 9hf1-1P'/)
,.,.'_ /_z,
ATTEST:
~f~
APPROVED AS TO
FORM & lANGUAGE
& FOR EXECUTION
t!y-r!C)()
CITY CLERK
,
Date
CONSULTANT
REG ARCHITECT , INC.
By
/21e# 67,u~t.e~... All<,
Print Name
ATTEST:
~(~~m1tJ
.~ ,
,~
EXHIBIT A
Additional Scope of Work:
Consultant shall provide Additional Services with regard to design; construction and bidding
documents; construction observation; project administration; scheduling and cost estimating,
necessary for the additional construction dollars approved under the 1999 General Obligation Bond
Program for reconstruction/renovation of Crespi; Fairway; Stillwater; Tatum; La Gorce; Fisher;
Muss; Island View; South Shore Community Center; Palm Island; and Washington Parks (See also
Attachment A).
Fee:
Consultant herein agrees to lower Consultant's Fee Schedule, as set forth in the Agreement, and to
include the Additional Services competed herein, to 7.5% of the total Construction Cost, estimated
at $5,014,865.
Reimbursable Expenses:
The City herein authorizes Consultant an additional $10,000 for Reimbursable Expenses that will
be paid only on the cost of actual invoices, and $15,000 for additional surveys and testing, if needed
and paid only with supporting invoices.