Loading...
LTC 028-2008 63rd Street Bridge Rehabilitation ProjectR~~'~I~,~~( ' 1~J 1 I ~~V 1 ~ ~ 2008 ,~aP~ 25 PM ~~ 59 OFFICE OF THE CITY MANAGER C1TY CL~.tE`S ~'~ ~~ ~~~:. NO. LTC # o2s-loos LETTER TO COMMISSION TO: Mayor Matti H. Bower and Members of the City Commission FROM: Jorge M. Gonzalez, City Mana `~J~-- DATE: January 25, 2008 SUBJECT: 63rd Street Bridge Rehabilitation Project The purpose of this Letter to Commission (LTC) is to provide you with an update on the 63rd Street Bridge Rehabilitation Project. As we informed you in the December 7, 2007 (LTC), the span and tailock gear reducers purchased by the Contractor failed the Federal Highway Administration's (FHWA) minimum 30 year life expectancy requirement and material testing. In order to mitigate this issue, the Contractor is operating the bridge with temporary gear reducers until the new FHWA-approved reducers are manufactured and installed. The new gear reducers are scheduled to be installed in June 2008, after the end of the school year. In the interim, the temporary gear reducers are required to undergo a routine maintenance afterthe initial six (6) month "break-in" period. On January 27, 2008 through February 6, 2008 the Contractor will be performing this routine maintenance work on the span and tailock gear reducers. This work will occur only during the evening hours from 9pm to Gam, during week nights only so as to minimize impacts to traffic. All six lanes of vehicular traffic will be shut down during the maintenance work, and a scheduled detour route will be provided (see attached map). Although the Contractor will be working on all lanes of the bridge, they will ensure that they are able to open one lane of traffic for emergency vehicles and public safety vehicles only. The Maintenance of Traffic (MOT) plan, which takes into account the scheduled detours, will include the utilization of electronic message boards that will notify the public about the detour. The proposed electronic message board locations are listed below. A police detail will be assisting the Contractorwith the execution of the MOT plan each night. Electronic Message Board Locations: • Indian Creek Drive, south of Abbott Street • Indian Creek Drive, adjacent to Brittany Park and south of the parking area • Julia Tuttle Causeway, east-bound before the off-ramp • Alton Road, northbound before 63rd Street Work should not interfere with the Miami International Boat Show, which begins staging on February 7, 2008 and opens to the public from February 14-18, 2008. City staff will be closely coordinating all activities with FDOT and their Contractor during this short maintenance period. Please feel free to contact me if you have any questions or concerns. Attachment: 1. Scheduled Detour Map RCM/FFT6/FV/cl F:\WORK\$ALL\(1) EMPLOYEE FOLDERS\CHRISTINE LEDUC\Transportation\LTC\63rd St. Bridge_rev5.doc Routine Maintenance Detour Map for 63rd Street Bridge City of Miami Beach - GIS -January 2008