2001-24265 RESO
RESOLUTION NO. 2001-24265
A RESOLUTION OF THE MAYOR AND CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA,
AUTHORIZING THE ADMINISTRATION TO ISSUE A
REQUEST FOR PROPOSALS (RFP) FOR A CITYWIDE
PARKING DEMAND ANALYSIS.
WHEREAS, the Mayor and Commission authorized the Administration to issue a Request
for Proposals (RFP) for proposals for a Citywide parking demand analysis; and
WHEREAS, at the October 18, 2000 City Commission meeting, the Mayor and City
Commission approved a referral to the Joint Land Use and Finance Committee to seek input and
recommendations regarding the potential identification of parking projects; and
WHEREAS, the Joint Land Use and Finance Committee and the Transportation and Parking
Committee have met and discussed several potential projects at various levels of development; and
WHEREAS, in order to determine the viability of each project, both Committees have
endorsed the undertaking of a parking demand analysis to project the future parking demand; and
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission herein authorize the Administration to issue a Request for Proposals (RFP) for a
Citywide parking demand analysis.
PASSED AND ADOPTED this 21st day of February. 2001.
1/1J!
MAYOR
ATTEST:
~rf~
CITY CLERK
JMG/CMC/SF
T:\AGENDA 12001 \FEB21 01 ICONSEN1\PDEMAND.RES
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
1.--' y- dl
-
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
http:\\cLmiami-beach.f1.us
COMMISSION MEMORANDUM NO. 'i1 3'-0/
TO:
Mayor Neisen O. Kasdin and
Members of the City Commission
DATE: February 21, 2001
o~
SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, AUTHORIZING THE
ADMINISTRATION TO ISSUE A REQUEST FOR PROPOSALS (RFP) FOR
PROPOSALS FOR A CITYWIDE PARKING DEMAND ANALYSIS.
FROM:
Jorge M. Gonzalez
City Manager
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
ANALYSIS:
On October 18, 2000, the Mayor and City Commission approved a referral to the Joint Land Use and
Finance Committee to seek input and recommendations regarding the potential identification of
parking projects to be funded by Parking Revenue Bond Funds. The potential development of a 13th
Street Garage was specifically referred to the Transportation and Parking Committee and the Joint
Land Use and Finance Committee for their respective review and/or recommendation. On
November 27, 2000, the Joint Land Use and Finance and Citywide Projects Committee met and
endorsed the Administration's recommendation to (1) purchase additional parking meter housings
and (2) appropriate more funding for parking surface lot renovations. A third project was discussed
which included a list of 11 alternative projects that involve potential land acquisition for parking
expansion and/or parking garage developments. As a result of the committees' discussion, the
following projects were to be considered for potential parking expansion and/or parking garage
developments, including:
. North Beach Lot by Normandy Fountain - site acquisition
. 17th Street and Washington Avenue
. 17th Street and Convention Center Drive (TOP A lot)
. Convention Center - Preferred Lot
. 13th Street Surface Lot - Potential Garage
. Hotel Corridor Garage
. Cultural Campus Garage
. Cejas lot - 420 Lincoln Road, Public-Private Venture
. Intermodal Facility
AGENDA ITEM
e7K.
~h~.I- 01
DATE
February 21,2001
Commission Memorandum
Parking Demand Analysis
Page 2
As part of the presentation to the joint Committees, the Administration recommended that the City
conduct a citywide parking study, incorporating the aforementioned sites/projects. The Committee
requested that the Administration seek additional information relative to the timeframe and estimated
cost involved in conducting a citywide parking study. Preliminarily, various parking consultants
have indicated a citywide parking study would require a 4-6 month time frame at an estimated cost
of approximately $60,000. In accordance with the Committee direction, attached for
Committee/Commission approval is a draft scope of services to be included in an RFP to conduct
a citywide parking study.
On December 4, 2000, the Transportation and Parking Committee endorsed the Administration
recommendations as stated above. The South Pointe Advisory Committee has also discussed
addressing parking needs for the South Pointe Area. Therefore, in order to determine the priority
focus and viability of each project, the Administration recommends the undertaking of a parking
demand analysis to project the future parking demand together with the performance of a feasibility
study.
The Scope of Services encompasses a study area bounded by South Point Drive on the south, 87th
Terrace on the north, Biscayne Bay on the west, and the Atlantic Ocean on the east. For ease of
compilation and reference, the study areas will be subdivided and prioritized into the following
geographical areas; however, it is essential that abutting areas be taken into account to accurately
reflect the overall needs of the district:
a. North Beach - 63rd Street to 87th Terrace.
b. South Point - South Point Drive to 5th Street
c. South Beach - 5th Street to 17th Street
d. Hotel Corridor/South - Collins/J ames Avenue between 17th Street and 23rd Street,
including Cultural Campus area.
e. Hotel CorridorlNorth - Collins AvenuelIndian Creek between 23rd Street and 41st
Street.
f. Middle Beach - 41st to 63rd Street.
The citywide parking study will address the following tasks:
1. Physical Inventory and Analysis - Physical inventory and analysis includes a
snapshot review of current citywide parking operations and characteristics and then
explores changes to that system in response to growth and operational changes. Data
collection activities include review and gathering of inventory and use data, financial
information on the parking system, maps, previously prepared reports, user surveys
and drawings.
2. Projection of Future Parking Demand and Need - Projection of future parking
demand and need will occur simultaneously with the assessment of existing parking
conditions. Three development scenarios will be evaluated, existing, year 2006, and
year 2011. The parking model will project the demand for a series of alternatives
that represent various outcomes of proposed development projects.
February 21.2001
Commission Memorandum
Parking Demand Analysis
Page 3
3. Cost and Feasibility Analysis - Cost and feasibility analysis will be conducted as part
of this task. If the parking model and analysis completed to this point indicates that
additional parking structures are needed, the successful proposer will complete a
parking structure feasibility study. This evaluation will determine the most feasible
and sustainable parking expansion in order to preserve the functional integrity ofthe
existing parking system or, if expansion of the parking system is recommended, the
location and configuration offeasible new facilities.
4. Public Involvement - Public involvement will be a critical element to the success of
the parking improvement plan. As discussed in the RFP, the following meetings or
presentations will be conducted:
Project initiation: an opportunity for public input and comment at the initial
stages of the project
Preliminary study findings
Study findings
Planning board, Joint Land Use and Finance Committee, Transportation and
Parking Committee, and City Commission, and other Committees as deemed
appropriate.
As the study is conducted, the Transportation and Parking Committee will review elements of the
study and provide advice prior to submission of the final report to the City Commission.
CONCLUSION:
Due to the competing demands and as endorsed by the Joint Land Use and Finance Committee,
Transportation & Parking Committee and South Pointe Advisory Board, it is recommended that the
City undertake a parking demand and feasibility study to project future parking demand and viable
parking developments. It is recommended that the City Commission adopt the attached resolution
authorizing the issuance of an RFP for a Parking Demand Analysis to be conducted in accordance
with the attached scope of services. This Parking Demand Analysis of the entire City will
complement the rate analysis recently performed by HNTB and will assist in identifying the priority
needs for the City.
JMG/c~~ar~
T:IAGENDA 1200 1 \FEB2\ 01 \CONSEN1\PDEMAND.CM
ATTACHMENT FOR PARKING DEMAND ANALYSIS
COMMISSION MEMORANDUM
EVALUATION COMMITTEE
The City Commission shall consider the City Manager's recommendation(s) in light of the
recommendation(s) and evaluation of the Evaluation Committee and, if appropriate, approve the
City Manager's recommendation(s). The City Commission may reject the City Manager's
recommendation(s) and select another response or responses. In any case, the City Commission
shall select the response or responses acceptance of which the City Commission deems to be in the
best interest of the City. The City Commission may also reject all responses.
Negotiations between the selected respondent and the City Manager take place to arrive at a contract.
If the City Commission has so directed, the City Manager may proceed to negotiate a contract with
a respondent other that the top-ranked respondent if the negotiations with the top-ranked respondent
fail to produce a mutually acceptable contract within a reasonable period of time.
A proposed contract or contracts are presented to the City Commission for approval, modification
and approval, or rejection.
If and when a contract or contracts acceptable to the respective parties is approved by the City
Commission, the Mayor and City Clerk sign the contract(s) after the selected respondent(s) has (or
have) done so.
Important Note:
By submitting a response, all respondents shall be deemed to understand and agree that no property
interest or legal right of any kind shall be created at any point during the aforesaid
evaluation/selection process until and unless a contract has been agreed to and signed by both
parties.
2
ATTACHMENT FOR PARKING DEMAND ANALYSIS
COMMISSION MEMORANDUM
EV ALUA nON CRITERIA
The proposer must have a verifiable proven record of providing Parking Demand Analysis' services
and must have not fewer than three (3) years of experience, providing successful services for
municipal parking departments, parking authorities and/or parking system, including hospitals and/or
colleges/universities.
An Evaluation Committee, appointed by the City Manager, shall meet to evaluate each response in
accordance with the requirements of the RFP. If further information is desired, respondents may be
requested to make additional written submissions or oral presentations to the Evaluation Committee.
The Evaluation Committee shall recommend to the City Manager the response or responses
acceptance of which the Evaluation Committee deems to be in the best interest ofthe City.
The Evaluation Committee shall base its recommendations on the following factors:
1. Firm's Qualifications and Experience
2. Experience and Qualifications of Project Team
3. Project Manager's Experience
4. Previous Similar Projects
5. Methodology and Approach
6. References Provided by Prior Project Owners
After considering the recommendation(s) of the Evaluation Committee, the City Manager shall
recommend to the City Commission the response or responses acceptance of which the City
Manager deems to be in the best interest of the City.
1
ATTACHMENT A
SCOPE OF SERVICES
Study Area
The study area is bounded by South Point Drive on the south, 87th Terrace on the north, Biscayne Bay on the west,
and the Atlantic Ocean on the east. For ease of compilation and reference, the study areas should be subdivided
and prioritized into the following geographical areas; however, it is essential that abutting areas be taken into
account to accurately reflect the overall needs of the district:
a. North Beach - 63rd Street to 87th Terrace.
b. South Point - South Point Drive to 5th Street
c. South Beach - 5th Street to 17th Street
d. Hotel Corridor/South - Collins/James Avenue between 17th Street and 23rd Street, including Cultural
Campus area.
e. Hotel CorridorlNorth - Collins A venue/Indian Creek between 23rd Street and 41 st Street.
f. Middle Beach - 41 st to 63rd Street.
The following Scope of Services has been developed specifically for the City of Miami Beach Parking Study based
on the tasks listed in the RFP. The City reserves the right to prioritize the sequencing of tasks and by area. The
citywide parking study will address the following tasks:
1. Physical Inventory and Analysis
2. Projection of Future Parking Demand and Need
3. Cost and Feasibility Analysis
4. Public Involvement
Task One
Physical inventory and analysis includes a snapshot review of current citywide parking operations and
characteristics and then explores changes to that system in response to growth and operational changes. Data
collection activities include review and gathering of inventory and use data, financial information on the parking
system, maps, previously prepared reports, user surveys and drawings. The successful proposer will gather and
document the existing public (City, County, and State) and private parking inventories and space use. This data
will be collected through aerial photography and in-field verification.
The parking date collection will be conducted during typical weekday peak periods and over one weekend to
identify the change in parking characteristics the outlined areas experience on a day-to-day basis. Parking space
inventory and use will be documented on a block-by-block and sub-area basis and the current parking rates charged
for all City (on-street as well as off-street) and other private parking facilities, by location, will also be identified.
Previously prepared documents, such as the Municipal Mobility Plan, South Beach Master plan, City of Miami
Beach Parking Rate Analysis, Lockheed IMS Parking Study, and a variety of applicable resources will be reviewed
and incorporated, as appropriate, into the parking study. The successful proposer will do the work with the City
to identify the type of financial parking system data required.
The conduct of business owner, employee, and patron surveys, as well as windshield surveys are recommended (see
example survey forms in the appendix) to assist in confirming peak period parking during the day, by walk distance
and from month to month. As identified in the RFP, several development and redevelopment projects are expected
to significantly alter the parking demand as well as supply. Particularly, new hotel construction and hotel
renovation projects, which include new up-scale inventory, may alter historical parking patterns and trends and
should be incorporated in the demand and supply assessment. To most precisely estimate, or model, anticipated
changes in parking demand, an accurate assessment of existing parking demand is critical. Therefore, a
comprehensive peak period parking space use (occupance) and supply (inventory) for a typical weekday/night and
weekend day/night is recommended for public on and off-street parking facilities and other private off-street
facilities.
The parking system use data will be obtained (aerial photography and in-field verification) during the following
four time periods to accurately reflect changing parking conditions throughout a typical day as outlined above:
Prior to 9:00 am
Peak mid-day period, from II :OOam to 2:00 pm
Late afternoon/early evening peak from 5:00 to 8:00 pm
Late night/early morning peak from II :00 pm to 2:00 am.
An inventory of existing buildings and the estimated number of users present on a typical weekday, by block, will
be necessary to determine parking generation rates by employ type, such as retail, hotel, entertainment, commercial,
governmental, and private office. However, the model is only as accurate as the data on which it is based.
The successful proposer will undertake a comprehensive parking system modeling effort to predict parking demand
and then compare the demand to the existing supply in the following areas:
On-street
- Private off-street
- Public off-street
Data collected will be analyzed and a parking model will be developed for use in evaluating peak parking demand
as a function of the number of employees, by type of employment, by block and sub-area. Employees not only
generate their own demand but also are the reason visitors, patrons, and others visit the employment centers,
whether retail, hotel, entertainment, commercial, governmental or office establishments. Resources including: the
Miami Beach Chamber of Commerce, the City's Economic Development Department, Planning Department, and
Public Works Department, and a number of the City's Committees, including, the Joint Finance and Land Use
Committee, Business Resolution Task Force, and Transportation and Parking Committee, are available and must
be consulted for data and input.
The employment base will be reviewed and adjusted to represent current conditions as closely as possible through
review of city assessor data, city employment statistics, principle shopping district data, and hotel
guest/tourist/entertainment use. Employment data is the input into the parking model while parking demand is
the calculated output. The parking demand output will then be compared against occupancy City data to determine
if the model is accurately reflecting current parking demand. If it does not match current conditions within
acceptable tolerance levels, then the model will need to be recalibrated through a review of the model's
assumptions. Some additional data collection may be required to modify the assumptions.
As mentioned, existing parking shortages and surpluses need to be identified on a block-by-block basis as well as
by sub-area. Prior to recommending system expansion, modifications to parking management operations will be
reviewed to determine if operational changes can alleviate the parking shortages by more efficient use of both the
private and public parking system. An alternative analysis will be developed concurrently that projects the impacts
that the proposed new developments and redevelopments projects have on the parking supply and demand.
Task Two
Projection of future parking demand and need will occur simultaneously with the assessment of existing parking
conditions. Three development scenarios will be evaluated, existing, year 2006, and year 2011. The parking model
will project the demand for a series of alternatives that represent various outcomes of proposed development
projects. The parking assessment scenarios will be evaluated in several categories including:
- Projects under construction
- Projects programmed for construction
- Potential proj ects
The parking model will be used to estimate future parking demand associated with the development projects. These
projects will be converted from square feet of building or land use to estimates of all parking generators, including
employees, visitors, tourists, etc., related to the development. This will enable the successful proposer to develop
several probable scenarios simultaneously to determine the most likely one for implementation. The projects
identified and evaluated will include not only the increase in parking demand from new developments and
redevelopment projects, but also any losses or additions to the private or public parking system. The results will
identify parking shortages or surpluses by block and by sub-area. This information will be reviewed to provide
compatibility and consistency with any system expansion, recommended to meet parking shortages identified in
the existing conditions analysis.
Task Three
Cost and feasibility analysis will be conducted as part of this task. If the parking model and analysis completed
to this point indicates that additional parking structures are needed, the successful proposer will complete a parking
structure feasibility study. This evaluation will determine the most feasible and sustainable parking expansion in
order to preserve the functional integrity of the existing parking system or, if expansion ofthe parking system is
recommended, the location and configuration of feasible new facilities.
The successful proposer's approach to parking facility and structure site feasibility studies should involve the
analysis of alternative sites interwoven with functional and aesthetic considerations. Often preliminary design
analysis must often be performed to properly assess the suitability of alternate sites. The successful proposer
should analyze the potential placement of a building on the site, vehicular access points, adjacent roadway capacity
and on-site vehicular and pedestrian circulation opportunities and constraints. Site availability constraints
considered by the successful proposer include site cost, public policy and regulations, highest and best use analysis,
zoning restrictions, property easements and the character ofthe surrounding development.
The study will also address physical constraints such as existing site development demolition, drainage and utilities,
excavation needs, other geotechnical requirements, surrounding elevations, space for construction staging, traffic
management during construction and a minimum site footprint for efficient functional design of the parking
structure.
The successful proposer's evaluation of potential parking expansion site alternatives must reflect the needs of the
City. The successful proposer will assist in evaluating each site in the most objective manner possible, weighting
those criteria that are most important to the City. Tasks that may be appropriate for a new parking structure
include:
- Confirmation ofthe need to expand the parking system
Review of existing vehicular and pedestrian access and circulation patterns for their relationship to existing
and proposed facility sites
- Determination of whether any existing facilities can be expanded to meet area parking needs
Identification of possible sites for new parking facilities
- Development of conceptual designs, sections, cost estimates, elevations, functional layout and circulation and
massing studies will be developed for the recommended alternatives
Comparison of each alternative's relative costs, including geotechnical requirements
- Evaluation of various alternatives on the basis of criteria
Development of a recommended plan for improvements, including phasing of components corresponding
to projected needs
Positive and negative aspects of each alternative will be identified and a preferred altemative(s) recommended to
the City for comment. Construction and other related costs estimates will be based on typical parking related costs
in the area.
The information and recommendations resulting from the Task 3 analysis will be implemented into the financial
proforma analysis. This financial analysis will identify the parameters and recommended changes to the parking
system necessary to maintain a financially stable system while expanding the system to provide additional parking
for new parking demand associated with the current building program. The level of analysis conducted here in will
be suitable for presentation with the City Finance Director as well as bond council, if necessary.
A critical element of the study will be to identify funding mechanisms should the construction of one or more
parking structures be recommended. Common methods of financing include:
- Parking revenue bonds
Block grants
Tax increment finance districts
- Business improvement districts which are similar to parking assessment districts but used for a variety of
needs necessary to support businesses located in the business district
Special assessments against property owners which is not likely a suitable solution because of the limited
funds that can be generated and the small group of affected property owners
- General obligation bonding/tax levy
User's fees collected through the sale of permits, meters and fines
These recommendations will provide the City with a methodology for use in determining future rate changes as
conditions dictate. The financial analysis (expressed as proformas) should focus on the first five years, from 2001
to 2006, and estimate rate increases in five year intervals over a 25-year period.
Task Four
Public involvement will be a critical element to the success of the parking improvement plan. As discussed in the
RFQP, the following meetings or presentations will be conducted:
Project initiation: an opportunity for public input and comment at the initial stages of the project
- Preliminary study findings
- Study findings
Planning board, Joint Land Use and Finance Committee, Transportation and Parking Committee, and City
Commission, and other Committees as deemed appropriate.
Deliverable and Reports
Based on information in the RFP, the successful proposer should provide the listed deliverables:
- Workplan, including progress schedule (to be submitted before the kick-off meeting)
Technical memoranda for major tasks (see description below)
- Study report (see description below)
- Public participation document
All relevant files in electronic format
Fifty (50) copies of the plan, fully reproducible in black and white photo-copy format WordPerfect
- One (I) camera-ready copy and one hundred (100) copies ofthe final citywide parking plan with
updated files as described in the RFP
The City may desire, for purposes of alternative uses, postings on the City Web site, the successful proposer should
prepare a summary of parking operations and development recommendations. All geographical-based data will
be developed to be compatible with the City's current electronic mapping format. For the study a total of five
technical memoranda will be prepared as follows:
Technical Memorandum No. 1 will address the City's current parking operations with regard to existing
parking supply and occupancy. In addition, data related to the parking model and testing of the model will
be presented in this memo.
- Technical Memorandum No.2 will include an evaluation of the City's future parking needs and propose
the development of a parking plan to meet those needs for the next five years.
- Technical Memorandum No.3 will be an economic proforma for each of the previous memoranda
including estimates of the probable construction cost, operations and maintenance costs, debt retirement
costs, capitalized reserve, and net operating surplus or loss for at least three separate parking system
development scenarios.
Technical Memorandum No.5 (the public involvement plan) will be presented as a technical
memorandum.
The successful proposer should prepare a comprehensive report summarizing the data gathering and definition of
the issues identified in Tasks 1 through 4. The main objective of the report will be to:
- Describe the adequacy of the parking system to meet current lease commitments and parking demand
- Establish the need to expand the parking system to serve existing and/or future land use development.
The successful proposer will prepare estimates of future parking demand
- Graphically depict the recommended parking plan for the sub areas
. Discuss the potential of using new financial mechanisms that might be implemented by the City to assist
in financing the operations and/or expansion
- Depict a series of financial proformas illustrating cash flow assumptions used in the financial analysis.
Preparation of a financial proforma analysis of the parking system from 2001 through an established future year
analysis period. The fmancial analysis will be based on revenue and operating costs over the study analysis time
period and net funds available to offset the cost of parking improvements.
T:IAGENDA\2001 IFEB2101 ICONSEN1\PDEMAND.A IT